MONTHYEARNLS2012001, 10 CFR 50.55a Request Number RI-07, Revision 02012-01-16016 January 2012 10 CFR 50.55a Request Number RI-07, Revision 0 Project stage: Request ML12031A2482012-01-16016 January 2012 Completion of License Renewal Commitment NLS2009100-1 (Revision 1) Project stage: Other ML1204506862012-02-14014 February 2012 Acceptance Review Email, Relief Request RI-07 from ASME Code Requirements for Residual Heat Removal Shell Circumferential and Nozzle to Head Welds, Fourth 4th 10-Year Inservice Inspection Interval Project stage: Acceptance Review ML1213205752012-05-11011 May 2012 Request for Additional Information, Relief Request RI-07 from ASME Code Requirements for Residual Heat Removal Shell Circumferential and Nozzle to Head Welds, Fourth 4th 10-Year Inservice Inspection Interval Project stage: RAI ML1213205722012-05-11011 May 2012 Email, Request for Additional Information, Relief Request RI-07 from ASME Code Requirements for Residual Heat Removal Shell Circumferential and Nozzle to Head Welds, Fourth 4th 10-Year Inservice Inspection Interval Project stage: RAI ML12159A2992012-06-11011 June 2012 Request for Additional Information, Relief Request RI-07 from ASME Code Requirements for Residual Heat Removal Shell Circumferential and Nozzle to Head Welds, Fourth 4th 10-Year Inservice Inspection Interval Project stage: RAI NLS2012064, Response to Nuclear Regulatory Commission Request for Additional Information Request for Relief for the Fourth 10-Year Inservice Inspection Program2012-06-22022 June 2012 Response to Nuclear Regulatory Commission Request for Additional Information Request for Relief for the Fourth 10-Year Inservice Inspection Program Project stage: Request ML12313A1112013-01-22022 January 2013 Relief Request RI-07 from ASME Code Requirements for Residual Heat Removal Shell Circumferential and Nozzle to Head Welds, Fourth 4th 10-Year Inservice Inspection Interval Project stage: Approval 2012-05-11
[Table View] |
Text
From:
Wilkins, Lynnea Sent:
Friday, May 11, 2012 3:59 PM To:
McCutchen, Edward L.
Cc:
Burkhardt, Janet; Lent, Susan
Subject:
DRAFT RAIs Re: Cooper Relief Request RI-07 (ME7875)
Attachments:
ME7875 RAIs Email.docx Ed, By letter dated January 16, 2012 (ADAMS Accession No. ML12023A005), Nebraska Public Power District (NPPD), the licensee for Cooper Nuclear Station (Cooper) submitted for staff review and approval weld examination relief requests for the Cooper Fourth 10-Year Inservice (ISI) Inspection Interval (RI-07).
The NRC staff has reviewed your submittal and has determined that the information specified in the attached Request for Additional Information (RAI) is needed for the staff to complete its evaluation.
Please contact me if a clarifying teleconference is needed for the attached RAIs.
Thanks Lynnea Lynnea Wilkins, Project Manager Fort Calhoun Station, Unit 1 Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation US Nuclear Regulatory Commission Phone: 301-415-1377