ML121320572

From kanterella
Jump to navigation Jump to search

Email, Request for Additional Information, Relief Request RI-07 from ASME Code Requirements for Residual Heat Removal Shell Circumferential and Nozzle to Head Welds, Fourth 4th 10-Year Inservice Inspection Interval
ML121320572
Person / Time
Site: Cooper Entergy icon.png
Issue date: 05/11/2012
From: Lynnea Wilkins
Plant Licensing Branch IV
To: Mccutchen E
Nebraska Public Power District (NPPD)
Wilkins, L E, NRR/DORL/LPL4, 415-1377
Shared Package
ML121320571 List:
References
TAC ME7875
Download: ML121320572 (1)


Text

From: Wilkins, Lynnea Sent: Friday, May 11, 2012 3:59 PM To: McCutchen, Edward L.

Cc: Burkhardt, Janet; Lent, Susan

Subject:

DRAFT RAIs Re: Cooper Relief Request RI-07 (ME7875)

Attachments: ME7875 RAIs Email.docx Ed, By letter dated January 16, 2012 (ADAMS Accession No. ML12023A005), Nebraska Public Power District (NPPD), the licensee for Cooper Nuclear Station (Cooper) submitted for staff review and approval weld examination relief requests for the Cooper Fourth 10-Year Inservice (ISI) Inspection Interval (RI-07).

The NRC staff has reviewed your submittal and has determined that the information specified in the attached Request for Additional Information (RAI) is needed for the staff to complete its evaluation.

Please contact me if a clarifying teleconference is needed for the attached RAIs.