MONTHYEARSBK-L-24030, 2023 Annual Environmental Operating Report2024-04-12012 April 2024 2023 Annual Environmental Operating Report SBK-L-23053, Radiological Emergency Plan (Ssrep), Revision 802023-06-22022 June 2023 Radiological Emergency Plan (Ssrep), Revision 80 SBK-L-23031, 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 2022 Annual Radioactive Effluent Release Report SBK-L-23044, 2022 Annual Radiological Environmental Operating Report2023-04-28028 April 2023 2022 Annual Radiological Environmental Operating Report SBK-L-23033, 2022 Annual Environmental Operating Report2023-04-11011 April 2023 2022 Annual Environmental Operating Report SBK-L-22093, 75 Day and 150 Day Submittal Letters2022-12-0101 December 2022 75 Day and 150 Day Submittal Letters SBK-L-22113, Radiological Emergency Plan (Ssrep), Revision 792022-11-16016 November 2022 Radiological Emergency Plan (Ssrep), Revision 79 SBK-L-22114, Independent Spent Fuel Storage Installation (Isfsi), Cask Registration2022-11-0909 November 2022 Independent Spent Fuel Storage Installation (Isfsi), Cask Registration SBK-L-22112, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2022-11-0303 November 2022 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration SBK-L-22094, Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2)2022-10-26026 October 2022 Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) SBK-L-22105, Supplement to 2021 Annual Radioactive Effluent Release Report2022-10-24024 October 2022 Supplement to 2021 Annual Radioactive Effluent Release Report SBK-L-22103, 5 to the Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan2022-10-12012 October 2022 5 to the Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan SBK-L-22102, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2022-10-0606 October 2022 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration SBK-L-22080, Submittal of 10 CFR 72.48 Report of Changes, Tests and Experiments for August 2020 to July 20222022-08-12012 August 2022 Submittal of 10 CFR 72.48 Report of Changes, Tests and Experiments for August 2020 to July 2022 SBK-L-22054, SBK-L-22054 - License Amendment Request 22-01, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-06-0909 June 2022 SBK-L-22054 - License Amendment Request 22-01, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections SBK-L-22044, 2021 Annual Radioactive Effluent Release Report2022-04-29029 April 2022 2021 Annual Radioactive Effluent Release Report SBK-L-22036, Steam Generator Tube Inspection Report2022-04-25025 April 2022 Steam Generator Tube Inspection Report SBK-L-22040, Radiological Emergency Plan (Ssrep), Revision 7822022-04-20020 April 2022 Radiological Emergency Plan (Ssrep), Revision 782 SBK-L-22024, Response to Request for Additional Information (Raj) Regarding License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2022-03-0707 March 2022 Response to Request for Additional Information (Raj) Regarding License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-22003, Inservice Inspection Examination Report2022-01-24024 January 2022 Inservice Inspection Examination Report SBK-L-21126, Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan2022-01-0404 January 2022 Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan SBK-L-21135, Submittal of Changes to the Seabrook Station Technical Specification Bases2021-12-29029 December 2021 Submittal of Changes to the Seabrook Station Technical Specification Bases SBK-L-21108, Core Operating Limits Report for Cycle 222021-11-0404 November 2021 Core Operating Limits Report for Cycle 22 SBK-L-21106, Transmittal of WCAP-18607-NP, Analysis of Capsule X from the NextEra Energy Seabrook Unit 1 Reactor Vessel Radiation Surveillance Program2021-09-30030 September 2021 Transmittal of WCAP-18607-NP, Analysis of Capsule X from the NextEra Energy Seabrook Unit 1 Reactor Vessel Radiation Surveillance Program SBK-L-21105, Withdrawal of Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink One-Time Allowed Outage Time (AOT) Extension2021-09-27027 September 2021 Withdrawal of Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink One-Time Allowed Outage Time (AOT) Extension SBK-L-21104, Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink Onetime Allowed Outage Time (AOT) Extension2021-09-25025 September 2021 Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink Onetime Allowed Outage Time (AOT) Extension SBK-L-21103, Request for Exercise of Enforcement Discretion2021-09-25025 September 2021 Request for Exercise of Enforcement Discretion SBK-L-21098, Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2021-09-22022 September 2021 Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-21083, NextEra Energy Seabrook, LLC - Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage2021-08-18018 August 2021 NextEra Energy Seabrook, LLC - Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage SBK-L-21067, License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2021-07-21021 July 2021 License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-21049, Revision to Updated Final Response to NRC Generic Letter 2004-022021-06-24024 June 2021 Revision to Updated Final Response to NRC Generic Letter 2004-02 SBK-L-21056, Response to Request for Additional Information Regarding Seabrook Steam Generator Tube Inspection Report Review References:2021-05-20020 May 2021 Response to Request for Additional Information Regarding Seabrook Steam Generator Tube Inspection Report Review References: SBK-L-21044, 2020 Annual Radiological Environmental Operating Report2021-04-30030 April 2021 2020 Annual Radiological Environmental Operating Report SBK-L-21045, Submittal of 2020 Annual Radioactive Effluent Release Report2021-04-30030 April 2021 Submittal of 2020 Annual Radioactive Effluent Release Report SBK-L-21042, Response to RIS 2021-01 Preparation and Scheduling of Operator Licensing Examinations2021-04-22022 April 2021 Response to RIS 2021-01 Preparation and Scheduling of Operator Licensing Examinations SBK-L-21033, Response to Request for Additional Information (RAI) Regarding License Amendment Request (LAR) 20-02, Resolve Non-Conservative Heat Flux Hot Channel Factor (Fo(Z)) Requirements2021-03-24024 March 2021 Response to Request for Additional Information (RAI) Regarding License Amendment Request (LAR) 20-02, Resolve Non-Conservative Heat Flux Hot Channel Factor (Fo(Z)) Requirements SBK-L-21023, Radiological Emergency Plan (Ssrep), Revision 772021-03-0404 March 2021 Radiological Emergency Plan (Ssrep), Revision 77 SBK-L-20154, Submittal of Changes to the Seabrook Station Technical Specification Bases2020-12-22022 December 2020 Submittal of Changes to the Seabrook Station Technical Specification Bases SBK-L-20149, Response to Request for Additional Information in Respect to One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-12-0808 December 2020 Response to Request for Additional Information in Respect to One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic SBK-L-20146, One-Time Exemption Request for the Biennial Emergency Preparedness Exercise Requirements of 10 CFR 50, Appendix E. IV.F.2.b and IV.F.2.c2020-12-0303 December 2020 One-Time Exemption Request for the Biennial Emergency Preparedness Exercise Requirements of 10 CFR 50, Appendix E. IV.F.2.b and IV.F.2.c SBK-L-20144, Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-23023 November 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic SBK-L-20143, Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-022020-11-19019 November 2020 Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-02 SBK-L-20132, Fourth Interval Inservice Testing (IST) Program2020-10-21021 October 2020 Fourth Interval Inservice Testing (IST) Program SBK-L-20127, Generator Tube Inspection Report2020-10-20020 October 2020 Generator Tube Inspection Report SBK-L-20117, Response to Request for Additional Information Regarding Technical Specification 3/4.8.1 for a One-Time Extension of Allowed Outage Time License Amendment Request2020-09-23023 September 2020 Response to Request for Additional Information Regarding Technical Specification 3/4.8.1 for a One-Time Extension of Allowed Outage Time License Amendment Request SBK-L-20103, Inservice Inspection Examination Report2020-07-27027 July 2020 Inservice Inspection Examination Report SBK-L-20068, License Amendment Request 20-01, One-Time Change to the Seabrook Technical Specifications A.C. Sources - Operating2020-07-13013 July 2020 License Amendment Request 20-01, One-Time Change to the Seabrook Technical Specifications A.C. Sources - Operating SBK-L-20092, Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-411 and TSTF-4182020-07-13013 July 2020 Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-411 and TSTF-418 SBK-L-20085, Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic2020-06-16016 June 2020 Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic SBK-L-20077, Core Operating Limits Report for Cycle 212020-06-0101 June 2020 Core Operating Limits Report for Cycle 21 2024-04-12
[Table view] |
Text
NEXTera T ENER f SEABROOK April 16, 2012 SBK-L- 12076 Docket No. 50-443 U.S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 Seabrook Station Confirmation of Information provided to NRC Staff Regarding Seabrook Station License Renewal Application
References:
- 1. NextEra Energy Seabrook, LLC letter SBK-L-10077, "Seabrook Station Application for Renewed Operating License," May 25, 2010. (Accession Number ML101590099)
- 2. Summary Of Telephone Conference Call Held On May 5, 2011, Between The U.S.
Nuclear Regulatory Commission And NextEra Energy Seabrook, LLC, Concerning Clarification Of Information Pertaining To The Seabrook Station License Renewal Application (Tac No. ME4028) (Accession Number ML11280A045)
- 3. Summary Of Telephone Conference Call Held On November 22, 2011, Between The U.S.
Nuclear Regulatory Commission And Nextera Energy Seabrook, LLC, Concerning The Response To The Request For Additional Information Pertaining To The Seabrook Station, License Renewal Application (TAC No. ME4028). (Accession Number ML11327A072)
- 4. NextEra Energy Seabrook, LLC letter SBK-L- 11069, "Seabrook Station Response to Request for Additional Information, NextEra Energy Seabrook License Renewal Application - Set 12 April 22, 2011. (Accession Number ML1 1 15Al 16)
- 5. NextEra Energy Seabrook, LLC letter SBK-L-11240, Seabrook Station Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs December 15, 2011 (Accession Number ML11354A235)
In Reference 1, NextEra Energy Seabrook, LLC (NextEra) submitted an application for a renewed facility operating license for Seabrook Station Unit 1 in accordance with the Code of Federal Regulations, Title 10, Parts 50, 51, and 54.
NextEra Energy Seabrook, LLC, P.O. Box 300, Lafayette Road, Seabrook, NH 03874
United States Nuclear Regulatory Commission SBK-L-12076 / Page 2 In References 2 and 3, the NRC requested clarification of information provided in the LRA in order to complete the review of NextEra's License Renewal Application (LRA). In References 4 and 5, NextEra provided responses to RAIs related to the License Renewal Application.
During the staff review of the responses it was determined that the information supplied by NextEra in the teleconference of May 5, 2011 (Reference 3) is required to be submitted under oath and affirmation as it will be relied upon by the staff for a determination in the Safety Evaluation Report. Enclosure 1 contains NextEra's response to the previous staff information request made in the May 5, 2011 teleconference, as modified by information provided to the staff related to action limits associated with the personnel airlock and equipment hatch (Reference 5).
There are no new or revised regulatory commitments contained in this letter.
If there are any questions or additional information is needed, please contact Mr. Richard R.
Cliche, License Renewal Project Manager, at (603) 773-7003.
If you have any questions regarding this correspondence, please contact Mr. Michael O'Keefe, Licensing Manager, at (603) 773-7745.
Sincerely, NextEra Energy Seabrook, LLC.
Paul 0. Freeman Site Vice President
Enclosure:
- Response to NRC Staff- Draft Requests for Additional Information Seabrook Station License Renewal Application
United States Nuclear Regulatory Commission SBK-L-12076 / Page 3 cc:
W.M. Dean, NRC Region I Administrator J. G. Lamb, NRC Project Manager, Project Directorate 1-2 W. J. Raymond, NRC Resident Inspector A.D. Cunanan, NRC Project Manager, License Renewal M. Wentzel, NRC Project Manager, License Renewal Mr. Christopher M. Pope Director Homeland Security and Emergency Management New Hampshire Department of Safety Division of Homeland Security and Emergency Management Bureau of Emergency Management 33 Hazen Drive Concord, NH 03305 John Giarrusso, Jr., Nuclear Preparedness Manager The Commonwealth of Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399
United States Nuclear Regulatory Commission SBK-L-12076 / Page 4 N~x~era ENERGY)
SEABROOK I, Paul 0. Freeman, Site Vice President of NextEra Energy Seabrook, LLC hereby affirm that the information and statements contained within are based on facts and circumstances which are true and accurate to the best of my knowledge and belief.
Sworn and Subscribed Before me this 7 yof a~od ,201 2 Paul 0. Freeman Site Vice President Notary Putic
Enclosure 1 to SBK-L-12076 Confirmation of Information provided to NRC Staff regarding Seabrook Station License Renewal Application
United States Nuclear Regulatory Commission 2 of 3 SBK-L-12076 /Enclosure 1 Request 1 LRA Section 4.6.1 In LRA Section 4.6.1, NextEra Energy Seabrook stated the following:
The Seabrook Station analyses confirmed the 40-year anticipated stress cycles listed below would satisfy the exemption criteria of NE 3221.5(d).
" Atmospheric-to-service pressure cycles (120 cycles)
" Temperature difference from Startup to Shutdown (120 cycles)
" Operating Basis Earthquake (500 cycles)
" LOCA (10 cycles)
However, in the UFSAR Section 3.8.1.3, NextEra Energy Seabrook states the following:
Cyclic Loading The various cycles loads were considered in the design. The following design conditions were considered in the fatigue analysis:
120 cycles start and shutdown 500 OBE cycles 100 SSE cycles 1 accident cycle (LOCA)
The staff asked for the following clarification:
- a. What is the difference between the startup and shutdown cycles presented in the LRA and in the UFSAR?
NextEra Enerul'y Seabrook Response:
The 120 cycles for plant startups and shutdowns is cited in the UFSAR Section 3.8.1.3 and was used to determine both the thermal and the pressure cycles of 120 used for the analysis of the containment liner. The pressure cycles referenced in LRA Section 4.6.1 are derived from the thermal cycles resulting from plant startups and shutdowns (also 120 cycles both in the LRA and in the UFSAR). In response to a subsequent question from the Staff NextEra revised LRA Table 4.3.1-2 to independently monitor the startup and shutdown cycles specified in the analysis of the Containment Liner, personnel hatch and equipment hatch.
'United States Nuclear Regulatory Commission 3 of 3 SBK-L-12076 /Enclosure 1
- b. Why did NextEra use 10 accident cycles (LOCA) in the TLAA?
NextEra Energy Seabrook Response:
Ten (10) accident cycles is used in the TLAA for conservatism. As stated in UFSAR Section 3.9(N). 1.1 and LRA Table 4.3.1-2 the Seabrook Station design basis load is 1 cycle (LOCA).
Request 2 LRA Section 4.6.2 In LRA Section 4.6.2, NextEra Energy Seabrook stated that, "The design of the containment penetrations did not involve cyclic evaluations and therefore are not considered TLAAs."
For the piping and electrical penetrations the staff reviewed UFSAR 3.8.2.4 titled "Design and Analysis Procedures," parts (d), (e), and (f) titled "High Energy Piping Penetrations," "Moderate Energy Piping Penetrations," and "Electrical Penetrations." The staff asked for clarification regarding no TLAAs for penetrations. Additionally, the staff asked for clarification on whether the mechanical piping that goes through the penetration are TLAAs.
NextEra Energy Seabrook Response:
United Engineers and Constructors, the Architect-Engineer for Seabrook Station, did not perform cyclic analyses for the containment penetrations. However, the mechanical piping that goes through the penetrations was analyzed in a simplified manner in the design process. When the non-Class 1 Seabrook Station piping was designed, the overall number of thermal and pressure cycles expected during the 40-year lifetime of these components was determined. The total number of cycles expected during 40 years was compared to cycle ranges specified in ASME Section III Class 2 and 3 design codes for consideration of allowable stress reduction. If the total number of cycles exceeded 7,000 cycles, a stress range reduction factor was applied to the allowable stress range for secondary stresses (expansion and displacement) to account for thermal cycling. This method is considered to be an implicit fatigue analysis because it is based upon a total number of cycles projected to occur in 40 years, but no explicit Cumulative Usage Factor (CUF) was computed. These TLAAs are addressed in LRA Section 4.3.7. Based on a previous staff question NextEra Energy Seabrook provided a revised LRA section 4.3.7 in response to RAI 4.3.7-lb dated April 22, 2011 (Reference 4).