Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 April 20,2012 Mr. Victor M. McCree, Regional Administrator U.S. Nuclear Regulatory Commission, Region ll Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257 Attn: Mr. Malcolm T. Widmann Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390
Subject:
Scheduling of Operator Licensing Examinations
References:
- 1.
Letter from TVA to NRC, "Response to NRC Regulatory lssue Summary 2010-08, "Preparation and Scheduling of Operator Licensing Examinations,'dated August 5, 2010
- 2.
Letter from TVA to NRC, "Response to NRC Regulatory lssue Summary 2011-04, "Preparation and Scheduling of Operator Licensing Examinations," dated July 8, 2011
- 3.
NRC Regulatory lssue Summary 2010-08, "Preparation and Scheduling of Operator Licensing Examinations," dated June 28, 2010
- 4.
NRC Regulatory lssue Summary 2011-04, "Preparation and Scheduling of Operator Licensing Examinations," dated May 25, 2011 In references 1 and 2, the Tennessee Valley Authority (T\\/A) provided proposed initial operator license examination schedules for Watts Bar Nuclear Plant for calendar year (CY) 2012-2015 and CY 2013-2016, respectively, as requested by the Nuclear Regulatory Commission (NRC) in references 3 and 4. In references 3 and 4, the NRC also stated that any schedule changes required should be addressed in a letter to the applicable NRC regional office. TVA requests the following changes to the initial license operator examinations proposed in reference 1 for Watts Bar Nuclear Plant.
U.S. Nuclear Regulatory Commission Page 2 April 20,2012 Initial Operator Licensing Examinations Proposed in References 1 and 2 Requested Changes to the Initial Operator Licensing Examinations Proposed in References 1 and 2 PlanU Station 2012 2013 Date Applicants Date Applicants Watts Bar 10t14 16 03/1 I 16 The Operator Training lnitial License Training (lLT) class 1211 examination is being delayed to ensure that the new Feedwater Digital Control System procedures being used during the examination will be approved and issued prior to submittal of our NRC examination. The Feedwater Digital Control System procedures will be approved and issued in October 2012 after the next Unit 1 refueling outage. ILT class 1306 is being moved to ensure at least 6 months between NRC examinations to ensure appropriate resources and oversight are provided to the project.
The number of anticipated license candidates is 16 per examination date. Therefore, TVA is requesting two weeks for each examination. There are no other changes to the previously requested initial license operator examination schedules for Watts Bar Nuclear Plant submitted in reference 2.
There are no regulatory commitments associated with this submittal. lf you have any questions related to this response, please contact Donna Guinn at (423) 365-1589 or Bill Thompson (423) 365-801 3.
Site Vice President Watts Bar Nuclear Plant NRC Senior Resident NRC Senior Resident f nspector - Watts Bar Unit 1 f nspector - Watts Bar Untt2 Plant/
Station 2012 2013 Date Applicants Date Applicants Watts Bar 11t5 16 6/3 16 cc:
U.S. Nuclear Regulatory Commission Page 3 April 20, 2012 DKG:JHH bcc:
J. R. Dalton D. E. Grissette D. K. Guinn W. L. Prevatt W. W. Thompson EDMS M:\\ln-Process Letters to NRC\\Change in Operator Exam Date\\License Exam Date Change - Rev 0 -
jhh.doc