MONTHYEARCNL-24-080, Response to Request for Additional Information Regarding Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (WBN-19-011)2024-11-20020 November 2024 Response to Request for Additional Information Regarding Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (WBN-19-011) IR 05000390/20240032024-11-13013 November 2024 Integrated Inspection Report 05000390/2024003, 05000391/2024003 & 07201048/2024001 CNL-24-021, Application to Revise Technical Specification Limiting Condition of Operation 3.5.2, ECCS – Operating, Note 1 to Include Residual Heat Removal Pump Flow Paths (SQN-TS-23-04 and WBN-TS-23-020)2024-11-12012 November 2024 Application to Revise Technical Specification Limiting Condition of Operation 3.5.2, ECCS – Operating, Note 1 to Include Residual Heat Removal Pump Flow Paths (SQN-TS-23-04 and WBN-TS-23-020) CNL-24-014, License Amendment Request to Revise the Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 Technical Specifications to Use Online Monitoring Methodology (SQN-TS-24-02 and WBN-TS-23-22)2024-11-0404 November 2024 License Amendment Request to Revise the Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 Technical Specifications to Use Online Monitoring Methodology (SQN-TS-24-02 and WBN-TS-23-22) CNL-24-064, Response to Request for Additional Information Regarding the Watts Bar Nuclear Plant, Unit 2 Steam Generator Tube Inspection Report for U2R52024-11-0404 November 2024 Response to Request for Additional Information Regarding the Watts Bar Nuclear Plant, Unit 2 Steam Generator Tube Inspection Report for U2R5 IR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter 05000391/LER-2024-003, Inoperability of Both Trains of Unit 2 Low Head Safety Injection2024-07-11011 July 2024 Inoperability of Both Trains of Unit 2 Low Head Safety Injection ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000391/LER-2024-002, Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO2024-05-0606 May 2024 Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements 05000391/LER-2024-001, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-03-27027 March 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation 2024-09-05
[Table view] |
Text
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 March 13, 2012 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Units 1 and 2 NRC Docket Nos. 50-390 and 50-391
Subject:
WATTS BAR NUCLEAR PLANT (WBN) UNITS 1 AND 2 - FIRE PROTECTION REPORT - REVISION OF COMMITMENTS
References:
- 1. TVA letter to NRC dated November 30, 2011, "Update to the Fire Protection Report"
- 2. TVA letter to NRC dated August 15, 2011, "Watts Bar Nuclear Plant (WBN) Unit 2 - Transmittal of Revised Unit 1 / Unit 2 As-Designed Fire Protection Report (TAC NO. ME3091)"
- 3. TVA letter to NRC dated December 18, 2010, "Watts Bar Nuclear Plant (WBN) Unit 2 - Fire Protection Program (TAC NO. ME0853) -
Submittal of Revised Fire Protection Report" The purpose of this letter is to clarify the actions being taken to address the commitment listed below which TVA made in Reference 1:
"TVA commits to provide an updated WBN, Unit 1 FPR within four months of the date of this letter."
In lieu of completing this commitment for the Unit 1 Fire Protection Report (FPR), TVA plans to fulfill the commitment made in References 2 and 3 to submit an as-constructed version of the Unit 1/Unit 2 FPR. This version of the FPR will reflect the updated Fire Hazards Analysis for WBN and will be applicable to both units. Once submitted, the Unit 1/Unit 2 FPR will supersede WBN's previous FPR and the commitments made in correspondence related to the FPR previously submitted by TVA. Based on this, the Unit 1/Unit 2 FPR will be baselined to Revision 0 when it is initially issued.
U.S. Nuclear Regulatory Commission Page 2 March 13, 2012 The commitment made in Reference 3 indicated the as-constructed FPR would be submitted by July 1, 2012. However, WBN is currently working to establish an estimated completion schedule for Unit 2 which will be finalized in the near future. This estimate will include a revised schedule for the submittal of the as-constructed FPR.
TVA will communicate the updated schedule for the as-constructed FPR to NRC as soon as it is available.
Currently, Section 1.1.2, "Licensing Basis Documents," of the Unit 1 Updated Final Safety Analysis Report (UFSAR) indicates that the FPR is incorporated by reference into the UFSAR. This is consistent with the following statement from Section 2.1, "Purpose and Scope," of Appendix FF, "Safety Evaluation Watts Bar Nuclear Plant Fire Protection Program," of Supplement Number 18 of NUREG 0847, "Safety Evaluation Report Related to the Operation of Watts Bar Nuclear Plant Units 1 and 2:"
"In its fire protection plan, the applicant has consolidated previous program commitments into a single document. This document is referenced by the Watts Bar Final Safety Analysis Report (FSAR) and will be updated in conjunction with the updates to the FSAR..."
Based on this, future revisions of the Unit 1/Unit 2 FPR will be submitted on a schedule consistent with the requirements of 10 CFR 50.71(e) or as required to support the licensing of Unit 2. In addition, the revisions for either unit will be designated with change indicators as required 10 CFR 50.71 (e)(5).
Listed in the enclosure is the new regulatory commitment contained in this letter. If you have any questions, please contact Gordon Arent at (423) 365-2004.
I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge. Executed on the 13th day of March 2012.
ull
?Respe
.J rZingue, Jr.
- eneral Manager, Engineering and Construction Wafts Bar Unit 2
Enclosure:
- 1. Regulatory Commitment cc: (see Page 3)
U.S. Nuclear Regulatory Commission Page 3 March 13, 2012 cc (Enclosure):
U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381
Enclosure Regulatory Commitment
- 1. The WBN Unit 2 estimated completion schedule will be finalized in the near future. This estimate will include a revised schedule for the submittal of the as-constructed FPR. TVA will communicate the updated schedule for the as-constructed FPR to NRC as soon as it is available.