ML12062A008

From kanterella
Jump to navigation Jump to search
Fitness for Duty Performance Data Report - Annual 2011
ML12062A008
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 02/29/2012
From: Thurman P
ZionSolutions
To:
Document Control Desk, NRC/FSME
References
ZS-2012-0098
Download: ML12062A008 (6)


Text

ZIONSOLUTIONSLW An EnergySolutions Company 10 CFR 50.75(f)(1)

February 29, 2012 ZS-2012-0098 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Zion Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-304

Subject:

Fitness for Duty Performance Data Report - Annual 2011 In accordance with 10 CFR 26.717(e), "Fitness-For-Duty Program Performance Data," and 10 CFR 26.203(e) "General Provisions," ZionSolutions LLC (ZS) is providing the compiled Fitness-For-Duty Program Performance Data for the Zion Nuclear Power Stations and the corporate support employees within the scope of the rule for the period January 1, 2011 through December 31, 2011.

There are no regulatory commitments contained in this letter.

If you have any questions regarding this submittal, please contact me at (224) 789-4041.

Respectfully, trick S. Thurman, Esq.

P (ice President Regulatory Affairs cc: John Hickman, U.S. NRC Senior Project Manager Service List

Attachment:

Fitness for Duty Performance Data - Personnel Subject to 10 CFR 26 101 Shiloh Boulevard, Zion - IL 60099 (224) 789-4016

  • Fax: (224) 789-4008
  • www.zionsolutionscompany.com

Zion Nuclear Power Station, Unit 1 and 2 License Transfer Service List cc:

Mr. Patrick T. Daly Mr. Kent McKenzie Senior VP and General Manager Emergency Management Coordinator ZionSolutions, LLC Lake County Emergency Management Agency 101 Shiloh Boulevard 1303 N. Milwaukee Avenue Zion, IL 60099 Libertyville, IL 60048-1308 Patrick Thurman, Esq. Regional Administrator VP Regulatory Affairs, Licensing and U.S. NRC, Region III Document Control 2443 Warrenville Road ZionSolutions, LLC Lisle, IL 60532-435.2ý 101 Shiloh Boulevard Zion, IL 60099 John E. Matthews Morgan, Lewis & Bockius LLP Gary Bouchard 1111 Pennsylvania Avenue, NW VP Engineering, Ops & Nuclear Security Washington, DC 20004 and Decommissioning Plant Manager 101 Shiloh Boulevard Zion, IL 60099 John Hess Executive VP and General Manager Commercial Services 1009 Commerce Park Drive, Ste. 100 Oak Ridge, TN 37830 Thomas Magette Senior VP Nuclear Regulatory Strategy 6350 Stevens Forest Road, Ste. 2000 Columbia, MD 21046 Russ Workman Deputy General Counsel Energy Solutions 423 West 300 South, Ste. 200 Salt Lake City, UT 84101 Illinois Department of Nuclear Safety Office of Nuclear Facility Safety 1035 Outer Park Drive Springfield, IL 62704

ATTACHMENT 2011 Fitness-For-Duty Performance Data - Personnel Subject to 10 CFR 26

Random Testing Rate ZionSolutions LLC (ZS) maintains separate testing pools for employees and contractors. For the period of January 1 through December 31, 2011, the company wide random testing rate for employees was greater than 50%.

Work Hours Control Waivers - Summary of Corrective Actions ZS issued no waivers.

Additional Information As shown on the attached schedule for ZionSolutions LLC's Fitness for Duty Program, the work force has been divided into three groups: Licensee Employees, Long-Term Contractor Personnel and Short-Term Contractor Personnel. For the reporting period in 2011, of the 243 tests conducted (101 pre-access, 5 for-cause post accident, 130 random and 7 follow-up) for Licensee Employees, there were 2 positive results. There were no Long-Term Contractor Personnel tested since none of these personnel had unescorted access. There were 444 tests conducted for the Short-Term Contractor Personnel (277 pre-access, 2 for-cause post accident, I for-cause observed behavior, 148 random and 16 follow-up) with 3 positive results.

FITNESS FOR DUTY PROGRAM PERFORMANCE DATA PERSONNEL SUBJECT TO 10CFR26 Zion Solutions 12/31/2011 Company 12 Month Ending ZION NUCLEAR POWER STATION Location Eileen Moore (224)789-4036 Contact Name Phone Cutoffs: Screen/Confirmation (ng/mI)

Marijuana 50/15 Amphetamine 1000/500 N/A N/A Cocaine 300/150 Phencyclidine 25/25 N/A N/A Opiates 2000/2000 Alcohol (%BAC) 0.04% N/A N/A Testing Results Licensee Long-Term Short-Term Employees Contractor Contractor Personnel Personnel Average Number with 170 0 209 Unescorted Access Categories Tested Positive Tested Positive Tested Positive Pre-Access 100 1 0 0 275 3 Pre-Access Random 1 0 0 0 2 0 For-Cause Post Accident 5 0 0 0 2 0 For-Cause Observed Behavior 0 0 0 0 1 0 Random 130 1 0 0 148 0 Follow-Up 7 0 0 0 16 0 Other 0 0 0 0 0 0 Total 243 2 0 0 444 3

BREAKDOWN OF CONFIRMED POSITIVE TESTS FOR SPECIFIC SUBSTANCES Marijuana Cocaine Opiates Amphetamines Phencyclidene Alcohol Creatinine Nitrites pH 50 1100 Licensee Employees 1 0 1 0 0 0 0 1 0 0 Long-Term Contractors 0 0 0 0 0 0 0 0 0 0 Short-Term Contractors 2 0 1 0 0 0 0 0 0 0 Total 3 0 2 0 0 0 0 1 0 0 Refusal 3X Adulterated Substituted To Test Dilute Specimen Specimen Licensee Employees 0 0 0 0 Long-Term Contractors 0 0 0 0 Short-Term Contractors 0 0 0 0 Total 0 0 0 0 Total Confirmed Positive Tests For All Specific Substances, Refusals, Dilutes, Substituted and Adulterated Specimens: 5