MONTHYEARML23304A1422024-02-0101 February 2024 Issuance of Environmental Scoping Summary Report Associated with the U.S. Nuclear Regulatory Commission Staffs Review of the Oconee Nuclear Station, Units 1, 2, & 3, Subsequent License Renewal Application ML24005A2492024-01-24024 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000269/20243012024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000269/2024301, 05000270/2024301, and 05000287/2024301 ML23331A7982023-12-14014 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report (01R32) ML23262A9672023-12-13013 December 2023 Alternative to Use RR-22-0174, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section XI, Division 1 IR 05000269/20230032023-11-14014 November 2023 Integrated Inspection Report 05000269/2023003, 05000270/2023003, and 05000287/2023003; and IR 07200040/2023001; and Exercise of Enforcement Discretion ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 ML23219A1402023-10-10010 October 2023 Audit Report Proposed Alternative to Use ASME Code Case N-752, Risk Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems XI, Division 1 ML23269A1102023-10-0606 October 2023 Letter to Steven Snider-Revised Schedule for the Environmental Review of the Oconee Nuclear Station, Unit 1, 2, and 3, Subsequent License Renewal Application ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000269/20230112023-08-25025 August 2023 Comprehensive Engineering Team Inspection Report 05000269/2023011 and 05000270/2023011 and 05000287/2023011 IR 05000269/20230052023-08-25025 August 2023 Updated Inspection Plan for Oconee Nuclear Station Units 1, 2 and 3 (Report 05000269/2023005, 05000270/2023005, and 05000287/2023005) IR 05000269/20230022023-07-28028 July 2023 Integrated Inspection Report 05000269/2023002, 05000270/2023002 and 05000287/2023002 ML23208A0972023-07-27027 July 2023 Subsequent License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected IR 05000269/20230102023-07-19019 July 2023 Biennial Problem Identification and Resolution Inspection Report 05000269/2023010 and 05000270/2023010 and 05000287/2023010 and Notice of Violation ML23178A0682023-07-0303 July 2023 Audit Plan Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 & 3 Systems Section XI, Division 1 ML23132A2392023-06-0101 June 2023 Summary of the April 2023 Remote Environmental Audit Related to the Review of the Subsequent License Renewal Application ML23144A0192023-05-25025 May 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report (O3R31) IR 05000269/20230012023-05-12012 May 2023 Integrated Inspection Report 05000269/2023001 and 05000270/2023001 and 05000287/2023001 ML23121A0552023-05-0303 May 2023 Acknowledgement of Withdrawal Request to Revise TS 5.5.2 Containment Leakage Rate Testing Program ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23117A0432023-04-20020 April 2023 Framatome, Inc., Part 21 Notification of Existence of a Defect ML23075A0732023-04-0505 April 2023 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Supplement (EPID Number L-2021-SLE-0002) ML23045A1332023-03-15015 March 2023 Request for Scoping Comments Concerning the Supplemental Environmental Review of Oconee Nuclear Station, Units 1, 2, and 3, Subsequent License Renewal Application - Achp Letter ML23045A1402023-03-15015 March 2023 Request for Scoping Comments Concerning the Supplemental Environmental Review of Oconee Nuclear Station, Units 1, 2, and 3, Subsequent License Renewal Application - Shpo Letter ML23045A1432023-03-15015 March 2023 Request for Scoping Comments Concerning the Supplemental Environmental Review of Oconee Nuclear Station, Units 1, 2, and 3, Subsequent License Renewal Application - State Tribe Letter ML23069A1102023-03-10010 March 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility ML23061A1772023-03-0303 March 2023 Notification of Oconee Nuclear Station Comprehensive Engineering Team Inspection - NRC Inspection Report 05000269/2023011, 05000270/2023011 and 05000287/2023011 IR 05000269/20220062023-03-0101 March 2023 Annual Assessment Letter for Oconee Nuclear Nuclear Station, Units 1, 2 and 3 (NRC Inspection Report 05000269/2022006, 05000270/2022006, and 05000287/2022006) ML23039A1632023-02-0808 February 2023 Requalification Program Inspection ML23037A0772023-02-0606 February 2023 402 Cyber Notification and RFI Letter Final IR 05000269/20220042023-02-0202 February 2023 Integrated Inspection Report 05000269 2022004 and 05000270/2022004 and 05000287/2022004 ML22363A3942023-01-12012 January 2023 Subsequent License Renewal Environmental Report Supplement - Proposed Review Schedule ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22321A0492022-12-0808 December 2022 Issuance of Amendment Nos. 426, 428 and 427, Additional Mode Change Limitations Applicable to the Adoption of TSTF- 359, Revision 9, Increase Flexibility in Mode Restraints ML22329A1042022-11-29029 November 2022 Review of the Fall 2021 Steam Generator Tube Inspection Report ML22321A1582022-11-22022 November 2022 Summary of Conference Call Regarding the Fall 2022 Steam Generator Tube Inspections ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000269/20220032022-11-0707 November 2022 Integrated Inspection Station 05000269/2022003 and 05000270/2022003 and 05000287/2022003 ML22301A0112022-11-0303 November 2022 Request for Withholding Information from Public Disclosure Regarding the SLR Application - September 2, 2022 ML22298A0752022-10-27027 October 2022 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application Duke Energy Letter Dated July 25, 2022 ML22264A0322022-10-20020 October 2022 _Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Duke Energy Letter Dated July 8, 2022 IR 05000269/20220112022-09-26026 September 2022 NRC Inspection Report 05000269/2022011 and 05000270/2022011 and 05000287/2022011 ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports ML22222A0072022-09-14014 September 2022 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application ML22231B1362022-09-0101 September 2022 Review of the Draft Environmental Assessment and Findings of No Significant Impact for Catawba Nuclear Station, H.B. Robinson Steam Electric Plant, and Oconee Nuclear Station Independent Spent Fuel Storage Installation Decommissioning Fundi 2024-02-01
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 February 23, 2012 Mr. T. Preston Gillespie, Jr.
Site Vice President Duke Energy Carolinas, LLC Oconee Nuclear Station 7800 Rochester Highway Seneca, SC 29672
SUBJECT:
OCONEE NUCLEAR POWER STATION - NOTIFICATION OF NRC INSPECTION AND REQUEST FOR INFORMATION
Dear Mr. Gillespie:
On March 19, 2012, the NRC will begin the temporary instruction (TI) inspection, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks, (TI 2515-182) at your Oconee Nuclear Power Station. This on-site inspection is scheduled to be performed March 19-21, 2012.
In order to minimize the impact to your on-site resources, we have enclosed a list of documents pertinent to our inspection. The documents that are requested for this inspection include all relevant documents that will allow the inspector(s) to adequately complete Phase 1 of this inspection.
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Ms. Judy Smith of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector Alexandra Rogers at (404) 997-4657 or Alexandra.Rogers@nrc.gov.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document
DEC 2 Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/
adams.html (the Public Electronic Reading Room).
Sincerely,
/RA Louis Lake for/
Steven J. Vias, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 50-269, 50-270, 50-287 License No. DPR-38, DPR-47, DPR-55
Enclosure:
TEMPORARY INSTRUCTION (TI 2515-182) INSPECTION DOCUMENT REQUEST cc w/encl: (See page 3)
_ _______X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE /RA/ /RA L. Lake for/
NAME A. ROGERS S. VIAS DATE 2/ 23 /2012 2/ 23 /2012 E-MAIL COPY YES NO YES NO 3
DEC cc w/encl:
Division of Radiological Health Sandra Threatt, Manager TN Dept. of Environment & Conservation Nuclear Response and Emergency 401 Church Street Environmental Surveillance Nashville, TN 37243-1532 Bureau of Land and Waste Management Department of Health and Environmental Charles J. Thomas Control Fleet Licensing Manager Electronic Mail Distribution Duke Energy Carolinas, LLC Electronic Mail Distribution Scott L. Batson Station Manager David A. Baxter Oconee Nuclear Station Vice President, Nuclear Engineering Duke Energy Carolinas, LLC General Office Electronic Mail Distribution Duke Energy Carolinas, LLC Electronic Mail Distribution Senior Resident Inspector U.S. Nuclear Regulatory Commission David A. Cummings Oconee Nuclear Station Associate General Counsel U.S. Nuclear Regulatory Commission Duke Energy Corporation 7812B Rochester Hwy Electronic Mail Distribution Seneca, SC 29672 Judy E. Smith Terry L. Patterson Licensing Administrator Safety Assurance Manager Oconee Nuclear Station Duke Energy Carolinas, LLC Duke Energy Carolinas, LLC Electronic Mail Distribution Electronic Mail Distribution Charles Brinkman Kent Alter Director Regulatory Compliance Manager Washington Operations Oconee Nuclear Station Westinghouse Electric Company, LLC Duke Energy Carolinas, LLC Electronic Mail Distribution Electronic Mail Distribution Tom D. Ray Lara S. Nichols Engineering Manager Vice President-Legal Oconee Nuclear Station Duke Energy Corporation Duke Energy Carolinas, LLC Electronic Mail Distribution Electronic Mail Distribution Luellen B. Jones County Supervisor of Oconee County Fleet Licensing Engineer 415 S. Pine Street Duke Energy Carolinas, LLC Walhalla, SC 29691-2145 Electronic Mail Distribution W. Lee Cox, III M. Christopher Nolan Section Chief Fleet Safety Assurance Manager Radiation Protection Section Duke Energy Carolinas, LLC N.C. Department of Environmental Electronic Mail Distribution Commerce & Natural Resources Electronic Mail Distribution
INSERVICE INSPECTION DOCUMENT REQUEST Inspection Dates: March 19-21, 2012 Inspection Procedures: TI 2515-182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks Inspector: Alexandra Rogers (404) 997-4657, Reactor Inspector Alexandra.Rogers@nrc.gov A. Information Requested for the In-Office Preparation Week
- 1. The following documents listed below are requested (electronic copy CD ROM if possible) by March 12, 2012, to facilitate the preparation for the on-site inspection week.
- a. Organization list of site individuals responsible for the sites underground piping and tanks program; and
- b. Schedule for completion of the following NEI 09-14, Guideline For The Management of Underground Piping and Tank Integrity, Revision 1 attributes:
Buried Piping
- Asset Management Plan Underground Piping and Tanks
- Condition Assessment Plan
- Asset Management Plan Enclosure
2 B. Information to Be Provided On-Site to the Inspector at the Entrance Meeting
- a. Copy of EPRI document Recommendations for an Effective Program to Control the Degradation of Buried Pipe.
- b. Copy of Site Underground Piping and Tanks Program.
- c. Self or third party assessments of the Underground Piping and Tanks Program (if any have been performed).
- d. For any of the NEI 09-14 Revision 1 or subsequent revision attributes identified below which have been completed prior to the NRCs onsite inspection, provide written records that demonstrate that the program attribute is complete.
Buried Piping
- Asset Management Plan Underground Piping and Tanks