oOFFICIAL USE or~LY = SECURITYuRELATED IPqFORM:ATle"1~
UNITED STATES NUCLEAR REGULATORY COMMISSION
, WASHINGTON, D.C. 20555-0001 February 7, 2012 Mr. Paul Freeman Site Vice President clo Michael O'Keefe Seabrook Station NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874
SUBJECT:
SEABROOK STATION, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION REGARDING THE PHYSICAL SECURITY PLAN
Dear Mr. Freeman:
By letter dated December S, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 11346AS94), NextEra Energy Seabrook, LLC (NextEra, the licensee) submitted the Seabrook Station's Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 17. The enclosure to the letter contained Safeguards Information and has been withheld from public disclosure. The U.S. Nuclear Regulatory Commission (NRC) staff is currently reviewing the submittal to ensure compliance with Title 10 of the Code of Federal Regulations, Section SO.S4(p)(2).
The NRC staff's request for additional information (RAI) is enclosed, A draft of these questions was previously sent, via email onJanuary30.2012(ADAMSAccessionNo.ML120300416).to Mr. Paul Willoughby of your staff with an opportunity to have a teleconference to ensure that the licensee understood the questions and their regulatory basis and to verify that the information was not previously docketed. On February 6, 2012, a teleconference was held between the NRC staff and NextEra personnel and at the end of the teleconference, Mr. Paul Willoughby of your staff agreed that NextEra would respond to the RAI within 30 days of the date of this letter.
Enclosure transmitted herewith contains Sensitive Unclassified Non.Safeguards Information. When separated from the enclosure, this transmittal I document is decontrolled.
oe)PI'PI'ICIAL USE OrqLY = SEGU~ITY-RElsATED INFORMATIO~
OfFiciAL USE ONLY SECURITY-RELATED Ir~FORPv'l;'\\TIO~
P. Freeman
- 2 If you have questions, you can contact me at 301-415-3100 andlor John.Lamb@nrc.gov.
. Lamb, Senior Project Manager Pia, Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosure:
Request for Additional Information cc wlo encls: Distribution via Listserv
-orFTCIAL usE ONLY
~EeURI'f T-RELA I ED II(JFORMATI~
OFFletAL USE ONLy SECORII V-RELATE{;) INFORMATIO~
-2 If you have questions, you can contact me at 301-415-3100 and/or John.Lamb@nrc.gov.
Sincerely,
/raJ John G. Lamb, Senior Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosure:
Request for Additional Information cc w/o encl: Distribution via Listserv DISTRIBUTION:
PUBLIC LPLI-2 R/F RidsAcrsAcnw_MailCTR Resource RidsNrrDorlDpr Resource RidsNrrDorlLpl1-2 Resource RidsRgn1 MailCenter Resource RidsNrrPMSeabrook Resource RidsNrrLMBaxter Resource RidsNsirDspERslb Resource RidsOgcRp Resource ADAMS ACCESSION NO.: LTR: ML120310469 RAI: ML120310489
- via email Packa e: ML120310457 OFFICE LPL1-2/PM LPL 1-2/LA NAME JLamb ABaxter DATE 02/03/2 02/01/2012 LPL1-2/PM MKhanna JLamb 217/12 2/7/12