UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 January 26, 2012 Progress Energy Carolinas, Inc.
ATTN: Mr. Henry Curry Training Manager Robinson Steam Electric Plant Unit 2 3581 West Entrance Road Hartsville, SC 29550
SUBJECT:
ROBINSON - NRC GENERIC FUNDAMENTALS EXAMINATION RESULTS
Dear Mr. Curry:
On December 7, 2011, the U.S. Nuclear Regulatory Commission (NRC) administered the generic fundamentals examination (GFE) of the written operator licensing examination to employees of your facility. Enclosed with this letter are copies of the final answer key, the grading results for your facility, and copies of individual answer sheets for each of your employees. Please forward the results to the individuals along with the copies of their respective answer sheets. A P in the RESULTS column indicates that the individual achieved a passing grade of 80 percent or better on the GFE, while an F indicates that the individual failed the examination.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter without its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
If you have any questions concerning this examination, please contact me at (404) 997-4608.
Sincerely,
/RA/
Bruno L. Caballero, Acting Chief Operations Branch 1 Division of Reactor Safety Docket No.: 50-261 License No.: DPR-23
Enclosures:
(See Page 2)
H. Curry 2
Enclosures:
- 1. Final Answer Key
- 2. Examination Results Summary
- 3. Individual Answer Sheets cc w/o encls.:
Progress Energy Carolinas, Inc.
ATTN: Mr. Robert J. Duncan II Vice President Robinson Steam Electric Plant Unit 2 3581 West Entrance Road Hartsville, SC 29550 Progress Energy Carolinas, Inc.
ATTN: Mr. Thomas Cosgrove Plant General Manager Robinson Steam Electric Plant Unit 2 3581 West Entrance Road Hartsville, SC 29550
H. Curry 2
Enclosures:
- 1. Final Answer Key
- 2. Examination Results Summary
- 3. Individual Answer Sheets cc w/o encls.:
Progress Energy Carolinas, Inc.
ATTN: Mr. Robert J. Duncan II Vice President Robinson Steam Electric Plant Unit 2 3581 West Entrance Road Hartsville, SC 29550 Progress Energy Carolinas, Inc.
ATTN: Mr. Thomas Cosgrove Plant General Manager Robinson Steam Electric Plant Unit 2 3581 West Entrance Road Hartsville, SC 29550 LETTER W/O ENCLS X PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE ADAMS: X Yes ACCESSION NUMBER: ML120310311 X SUNSI REVIEW COMPLETE OFFICE RII:DRS SIGNATURE BLC NAME BCABALLERO DATE 1/ 26/12 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO