ML12023A020

From kanterella
Jump to navigation Jump to search

NRR E-mail Capture - Acceptance Review for HNP - Revise Minimum Water Level in the Plant Service Water Pump Well
ML12023A020
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 01/20/2012
From: Patrick Boyle
Plant Licensing Branch II
To: Ajluni M
Southern Nuclear Operating Co
References
TAC ME7706, TAC ME7707
Download: ML12023A020 (2)


Text

NRR-PMDAPEm Resource From: Boyle, Patrick Sent: Friday, January 20, 2012 12:32 PM To: 'Ajluni, Mark J.'; 'Stringfellow, N. Jack'; 'Hill, Lesa P.'; 'McKinney, B. Doug' Cc: Boyle, Patrick

Subject:

Acceptance Review for HNP - Revise Minimum Water Level in the Plant Service Water Pump Well Mr. Ajluni:

By letter dated December 15, 2011, SNC submitted a license amendment request (NL-10-2144), for the Edwin I. Hatch Nuclear Plant Units 1 and 2, License Amendment Request to Revise the Minimum Water Level in the Plant Service Water Pump Well." The purpose of this e-mail is to provide the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this license amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to continue its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal addresses the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.

Patrick Boyle, Project Manager LPL 2-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation TAC ME7706 and ME7707 Dockets: 50-321 and 50-366 1

Hearing Identifier: NRR_PMDA Email Number: 242 Mail Envelope Properties (C070F82E831E1C44879BFA258CF960C97E5A84E08E)

Subject:

Acceptance Review for HNP - Revise Minimum Water Level in the Plant Service Water Pump Well Sent Date: 1/20/2012 12:31:38 PM Received Date: 1/20/2012 12:31:38 PM From: Boyle, Patrick Created By: Patrick.Boyle@nrc.gov Recipients:

"Boyle, Patrick" <Patrick.Boyle@nrc.gov>

Tracking Status: None

"'Ajluni, Mark J.'" <MJAJLUNI@southernco.com>

Tracking Status: None

"'Stringfellow, N. Jack'" <NJSTRING@southernco.com>

Tracking Status: None

"'Hill, Lesa P.'" <LPHILL@southernco.com>

Tracking Status: None

"'McKinney, B. Doug'" <BDMCKINN@southernco.com>

Tracking Status: None Post Office: HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 2077 1/20/2012 12:31:38 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: