ML120190231
| ML120190231 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 01/19/2012 |
| From: | Wang A Plant Licensing Branch IV |
| To: | Baldwin T, Soenen P Pacific Gas & Electric Co |
| Wang, A B, NRR/DORL/LPLIV, 415-1445 | |
| References | |
| TAC ME7792, TAC ME7793 | |
| Download: ML120190231 (1) | |
Text
From:
Wang, Alan Sent:
Thursday, January 19, 2012 10:31 AM To:
Soenen, Philippe R; Baldwin, Thomas (DCPP)
Cc:
Burkhardt, Janet; Lent, Susan; Lynch, Steven; Sebrosky, Joseph
Subject:
Acceptance of Diablo Canyon Preemption Request (ME7792 and ME7793)
Tom and Philippe, By letter dated December 22, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML113610556), Pacific Gas and Electric Company, (PG&E, the licensee) submitted an application to the U.S. Nuclear Regulatory Commission (NRC) for stand-alone preemption authority pursuant under 42 U.S.C.. 2201a for the Diablo Canyon Power Plant.
The purpose of this letter is to provide the results of the NRC staff's acceptance review of this stand-alone preemption request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed stand-alone preemption in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
If you have any questions, please contact me at (301) 415-1445 or Steven Lynch at (301) 415-1524.
Alan Wang Project Manager (Diablo Canyon Power Plant)
Nuclear Regulatory Commission Division of Operating Reactor Licensing Alan.Wang@NRC.gov Tel: (301) 415-1445 Fax: (301) 415-1222