Email from Steven W Gebers to Bill Pook... Whitney Shipley, Daily Status
ML12012A242
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 06/10/2011
From: Gebers S
Omaha Public Power District
To: Clark J, Johnson P, John Kirkland, Laurel R, Oliver L, Plautz E, Pook B, Schwarz J, Shipley W, Stodola K, Theulen J
NRC/RGN-IV/DRP, State of NE, Emergency Mgmt Agency
References
FOIA/PA-2011-0339
Download: ML12012A242 (2)


Text

. Clay, Earnestine From: GEBERS, STEVEN W [sgebers@oppd.com]

Sent: Friday, June 10, 2011 7:32 AM To: Bill Pook; Dan; Eric Plautz; Clark, Jeff; Jeff Theulen; Jon Schwarz; Kathy Stodola; Kirkland, John-LarI liver;yLaurel Ryan; Paul Johnson; Whitney Shipley Cc: [(b)(6) PERCK, ALLEN; DEANGELIS, PETER A; HANKINS, RHONDA R;

-MOELLER, CHFIMTOPHER J; RELLER, MARK H; SILKE, DEENA L

Subject:

Daily Status Fort Calhoun Flooding Status

1. Reactor Status: Shutdown
2. Reactor is covered with > 23-ft of water 3, Offsite power and Emergency Diesel Generators are available. Both vital buses are energized at this time.
4. Spent Fuel Pooling cooling is in service and protected.
5. Shutdown cooling is in service and protected
6. Current river level is 1004' 4".
7. Current Blair gauge level is 30.13-ft with the current projection at 31.4-ft at about 19:00 on June 14, 2011.
8. The site has implemented procedures to protect power supplies and vital equipment. Water is onsite, and flood barriers are protecting vital equipment.
9. No release of radioactivity has occurred.
10. Fort Calhoun has declared a Notification of Unusual Even at 08:00 6/6/11.
11. Backup evacuation route onsite is inundated however the primary route onsite is passable and not expected to be affected.
12. Power was removed from siren 260 in Pottawattamie Co. IA,which is just outside the 10-mile EPZ south east of the plant. Siren 75 in Desoto National Wildlife Refuge has a 10 module failure. Currently the refuge is closed due to flooding.

13.At this time no known major evacuation routes are affected. Interstate 29 from milepost 55 (25th Street at the north edge of Council Bluffs) to the 1-291680 interchange (near Loveland): The road is expected to close within the next 24-48 hours; timing is contingent on rising flood water levels. .*t .Lý'ki'.tuuY14 Requested Information from states and counties:

1. When offsite evaluation routes are affected please contact emergency planning.
2. When the Blair Water plant is affected please contact emergency planning.
3. Authorized power outages that affect or could affect siren operability, please contact emergency planning.

The river flow rate has lowered at Blair NE, however the river level continues to rise. The Corp of Engineers will increase the flow from Gavins Point dam to 145,000 cfs today and hold for 4-days, and then increase to 150,000 cfs.

Emergency Planning Contacts at FCS:

Steve Gebers: H , ,Hsrecord was deleted informati0: i;i Pager(b)(6) .in acoprdarce with the F dor lat gof ation FOIA- . AT

Work Phone: 402-533-7308

<ell Phone: P 1)() 1 7 Mark Reller:

Pager: 1(b)(6) I Work Phone: 402-533-7314 Steve Gebers, CHP Manager Emergency Planning & Health Physics Fort Calhoun Nuclear Station e-mail (w) sqeberseop ._,I'*..

e*-mail (h)lf(b)('6) rnd,¢am .r Phone 402 533-7308 This e-mail con ins Omaha Pu wer District's confidential and proprieery information qd is for use only by the intended ecipient. Uess explic tly stated rwi , this e-m bnot contract r, amendment, nor acceptance. If y u are the intended r cipie*nou are no fied todisclosin cog, distributing or taking any action in reli on the contents of nformation is s y prohibited.

2