E-mail from E. Love, NMSS to E. Benner, NMSS; Draft Communication Plan - North Anna Nuclear Power Plant
ML12005A060
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 09/14/2011
From: Earl Love
Office of Nuclear Material Safety and Safeguards
To: Eric Benner
Office of Nuclear Material Safety and Safeguards
References
FOIA/PA-2011-0357
Download: ML12005A060 (10)


Text

Rivera-Ortiz, Joel From: Love, Earl .

  • t'*

Sent: Wednesday, September 14, 2011 10:53 AM To: Benner, Eric Cc: Rivera-Ortiz, Joel; Carrion, Robert; Tripathi, Bhasker; Waters, Michael; Bjorkman, Gordon; Rankin, Jennivine; Pstrak, David

Subject:

RE: Draft Communication Plan - North Anna Nuclear Power Plant Restart Attachments: North Anna Seismic Issue Restart Action Plan word.docx Eric:

I think we should provide Meena with some comments (see attached). Feel free to add any comments you may have (Joel and Bob as well). In parallel, I will have a SFST action plan by EOB day tomorrow for your review. I anticipate that we'll start to implement the plan next week. The plan will include a site visit as well as a visit to TN. The plan will be derived with input from licensing, SMMB, Gordon and Region I1. Feel free to send to Meena or please advise.

Earl From: Benner, Eric Sent: Wednesday, September 14, 2011 10:28 AM To: Benner, Eric; Love, Earl

Subject:

RE: Draft Communication Plan - North Anna Nuclear Power Plant Restart Also, at the Op Plan meeting today we got the "blessing" to devote resources to this work, but with that comes the expectation for us to be tracking our progress.. so, the heat is on to put together our action plan.

From: Benner, Eric Sent: Tuesday, September 13, 2011 9:29 PM To: Love, Earl

Subject:

FW: Draft Communication Plan - North Anna Nuclear Power Plant Restart Are you going to the picnic tomorrow? Maybe we can grab Doug briefly regarding whether we need to be part of this comm. Plan, or push to have our own.

From: Khanna, Meena Sent: Tuesday, September 13, 2011 9:25 PM To: McCoy, Gerald; Franke, Mark; Benner, Eric; Love, Earl; Burnell, Scott

Subject:

FW: Draft Communication Plan - North Anna Nuclear Power Plant Restart Hi, pls let me know if you have any comments on the draft comm. plan for North Anna.

Thanks, meena From: Khanna, Meena Sent: Tuesday, September 13, 2011 8:25 PM To: Hiland, Patrick; Wilson, George Cc: Uribe, Juan; Manoly, Kamal

Subject:

Draft Communication Plan - North Anna Nuclear Power Plant Restart Pat and George,

Here is our draft Comm Plan. Pis schedules for the let us know if you communication timeline? have any comments.

Could we pls discuss Thanks, proposed time Meena 2

MEMORANDUM TO: Eric J. Leeds, Director Office of Nuclear Reactor Regulation FROM: Patrick L. Hiland, Director Division of Engineering

SUBJECT:

ACTION PLAN TO ADDRESS NORTH ANNA NUCLEAR POWER PLANT RESTART AS A RESULT OF AUGUST 23, 2011 EARTHQUAKE On August 23, 2011, the North Anna Power Station declared an Alert due to significant seismic activity onsite from an earthquake which had a measured magnitude of 5.8. On August 26,

.2011, initial reviews of the data determined that the seismic activity potentially exceeded the Design Basis Earthquake magnitude value. Subsequently on August 26, the licensee declared all safety-related structures, systems and components inoperable and issued a 10 CFR 50.72 Notification.

In response to the recent seismic event, the staff is undertaking various initiatives to address plant restart activities at the North Anna Nuclear Plant, which includes an Augmented Inspection Team that was dispatched on August 31, 2011. In addition, the staff is in the process of identifying issues and questions for the licensee to consider in order to obtain NRC authorization for plant restart in accordance with 10 CFR Part 100, Appendix A. The attached agency's action plan describes and tracks the ongoing initiatives related to the North Anna Nuclear Power Plant restart activities as a result of the recent seismic event.

Enclosure:

As stated CONTACT: Meena Khanna, NRRIDE/EMCB (301) 415-2150

MEMORANDUM TO: Eric J. Leeds, Director Office of Nuclear Reactor Regulation FROM: Patrick L. Hiland, Director Division of Engineering

SUBJECT:

ACTION PLAN TO ADDRESS NORTH ANNA NUCLEAR POWER PLANT RESTART AS A RESULT OF AUGUST 23, 2011 EARTHQUAKE On August 23, 2011, the North Anna Power Station declared an Alert due to significant seismic activity onsite from an earthquake which had a measured magnitude of 5.8. On August 26, 2011, initial reviews of the data determined that the seismic activity potentially exceeded the Design Basis Earthquake magnitude value. Subsequently on August 26, the licensee declared all safety-related structures, systems and components inoperable and issued a 10 CFR 50.72 Notification.

In response to the recent seismic event, the staff is undertaking various initiatives to address plant restart activities at the North Anna Nuclear Plant, which includes an Augmented Inspection Team that was dispatched on August 31, 2011. In addition, the staff is in the process of identifying issues and questions for the licensee to consider in order to obtain NRC authorization for plant restart in accordance with 10 CFR Part 100, Appendix A. The attached agency's action plan describes and tracks the ongoing initiatives related to the North Anna Nuclear Power Plant restart activities as a result of the recent seismic event.

Enclosure:

As stated CONTACT: Meena Khanna, NRRJDE/EMCB (301) 415-2150 INDICATE IN BOX: "C=COPY WIO ATrACHMENTIENCLOSURE, E'=COPY WIATT/ENCL, N'=NO COPY OFFICE EMCBDE . EMCB:DE DOR Z 1INJ DS:R C:R L:R NAME MKhanna KManoly RMartin WRuland MEvans BHolian 9/ /2011 9/ /2011 9/ /2011 9/ /2011 9/ /2011 9/ /2011 DATE OFFICE DRS:NRR Region 1I DE:NRR NRR uNRR YNRR NAME MCheok LWert PHiland BBoger JGrobe ELeeds 9/ /2011 9/ /2011 9/ /2011 9/ /2011 9/ /2011 9/ /2011 DATE OFFICIAL RECORD COPY

NORTH ANNA NUCLEAR POWER PLANT RESTART ACTION PLAN Last Update: 9/13/2011 Lead Division: DE Supporting Divisions: DSS, DCI, DLR, DRA Supporting Offices: Region II, NMSS, NRO, RES TAC Nos. ME7050 and ME7051 GOAL The goal of this action plan is to track the agency's ongoing initiatives related to the North Anna Nuclear Power Plant restart decision as a result of the recent seismic event on August 23, 2011.

BACKGROUND On August 23, 2011, NANP experienced a seismic activity event (5.8.magnitude earthquake reported by the U.S. Geological Survey) which resulted in a loss of offsite power and automatic reactor trip of both units. The licensee declared an Alert due to significant seismic activity at the site. Subsequent to the earthquake, the licensee stabilized both units, restored offsite power, and sent the retrieved recorded seismic results to the vendor for analysis. On August 26, 2011, initial reviews of the data determined that the seismic activity potentially exceeded the Design Basis Earthquake spectrum at frequencies above 5 Hz. Therefore, this event was reportable per 10 CFR 50.72(b)(3)(ii) (B) for the nuclear power plant being in an unanalyzed condition that may have significantly degraded plant safety.

The NANPP has two Safe Shutdown Earthquake (SSE) ground motions, one for structures, systems, and components (SSCs) located on top of rock, which is anchored at 0.12 g, and the other is for SSCs located on top of soil, which is anchored at 0.18 g. The NANPP has two corresponding Operating Basis Earthquake (OBE) ground motion spectra, anchored at 0.09 g for soil and 0.06 g for rock. The vendor has processed the initial seismic data. Preliminary results indicate certain measurements exceeded the SSE, at various frequencies above the limits reported in the final safety analysis report.

The current best estimate of the Peak Ground Acceleration (PGA) for the NANPP site is 0.26 g, which contains uncertainty. This estimate indicates that the ground motion likely exceeded the SSE response spectra for NANPP Units 1 and 2 (0.12 g) over a considerable frequency range.

The estimated ground motion from the earthquake was not a surprise based on the combined operating license application ground motion response spectrum for NANPP Unit 3. This preliminary estimate appears to validate the NRC's current seismic hazard assessment approaches and the basis for GI-199 reviews.

It was reported that North Anna potentially exceeded the Design Basis Earthquake (DBE) spectrum at frequencies above 5 Hz. The vibratory ground motions from the 5.8 magnitude earthquake were recorded in all three orientations at several locations in the plant using two types of instruments: the Engdahl scratch plates that record 12 discrete spectral accelerations between 2 and 25.4 Hz, and the Kinemetrics analog recorders that recorded time histories of the accelerations.

ENCLOSURE

Based on evaluation of recorded plant data, it was concluded that the Central Virginia earthquake of August 23, 2011, exceeded the spectral accelerations for the Operational Basis Earthquake (OBE) and DBE of North Anna Plant.

Both units are in Cold Shutdown with the Residual Heat Removal System providing core cooling. No significant equipment damage to Safety Related system (including Class 1 Structures) has been identified through site walk-downs nor has equipment degradation been detected through plant performance and surveillance testing following the earthquake. The licensee indicated that the Spent Fuel Pit cooling system also remains fully functional and the temperature of the Spent Fuel Pit remained unchanged during the event. The licensee also indicated that the vendor will complete the analysis of the seismic data and this information will be utilized to address the long term actions following the earthquake.

The licensee has retrieved its seismic instrumentation recordings located at different elevation levels from within the plant and has processed some of the information from these recordings.

Preliminary results from the seismic instrumentation indicate exceedance above the final safety analysis report (FSAR) design basis earthquake (DBE) spectra at various frequencies, depending on the building, measurement direction, and elevation.

It is also noted that the North Anna ISFSI suffered minor damage from the earthquake. Twenty five of the twenty seven TN-32 casks slid up to 4.5 inches on the concrete pad during the quake. Six cask sets (12 casks) were closer than the 16 foot separation distance specified in the FSAR. There was no damage to the pressure monitors in each cask and no pressure monitoring system alarms during or after the earthquake. There were no crack indications observed in the concrete pad or casks. For the TN-NUHOMS modules, some slight damage was identified around the outlet vents and some surface cracking indications were noted. Additionally, some modules showed gaps between them of approximately 1.5" versus the required 1.0" maximum gap.

The NRC initially dispatched a seismic and structural expert to assist the Agency's resident inspectors on site. The NRC then dispatched an Augmented Inspection Team on August 29, to gather important information for the NRC's continuing evaluation of earthquake risk at US Nuclear Plants.

REGULATORY OUTCOME In accordance with Appendix A to Part 100, Paragraph V(a)(2), a nuclear power plant is required to be shutdown when the vibratory ground motion exceeds that of the Operating Basis Earthquake. In addition, the regulations state that "prior to resuming operations, the licensee will be required to demonstrate to the Commission that no functional damage occurred to those features necessary for continued operation without undue risk to the health and safety of the public."

Licensee actions are underway to inspect, evaluate, test, and repair if necessary, the systems and components to ensure they are capable of performing their required functions. The licensee is performing plant walk downs in accordance with RG 1.167, "Restart of a Nuclear Power Plant Shutdown by a Seismic Event," which endorses EPRI's "Guidelines for Nuclear Plant Response to an Earthquake" with conditions.

The staffs assessment will utilize the guidance provided in NRC's Regulatory Guide (RG) 1.167, which endorses the EPRI's guidelines. In addition, the staff will utilizethe IAEA Safety Report Series No. 66, "Earthquake Preparedness and Response for Nuclear Power Plants," to

determine the adequacy of the licensee's restart determinations. It should be noted that the IAEA Safety Report acknowledges the prospect that hidden damage (especially after an SSE) is a real possibility and its effects should be evaluated with analytical work. Specific actions are identified in the table below, entitled, "North Anna Nuclear Power Plant Restart Action Plan Milestones."

The acceptance criteria that will be utilized by the staff for approval of plant restart include satisfactorily addressing the following:

(1) Confirmatory inspections by the region, (2) Visual walkdowns by the licensee in accordance with the EPRI guidelines, (3) Identification of short term evaluations by licensee (pre-restart), and (4) Identification of long term evaluations by licensee (post-restart).

Project Management Structure:

This project is being performed as a matrix organizational structure. Team members will support project activities directly but will report administratively through their normal management chain. Approvals will be achieved through the standard concurrence process.

Responsible Division Director: Patrick Hiland, DE Responsible Individuals: Meena Khanna and Kamal Manoly, DE Other stakeholders and roles:

DD DORL: Joe Glitter DD DSS: Bill Ruland DD DCI: Michele Evans DD DRA: Michael Cheok DD DLR: Brian Holian DD NMSS/SFST: Vonna Ordaz DDD NRO/DSER: Nilesh Chokshi DD, NRO/DE: T. Bergman OPA: S. Burnell, Manage External Communications OCA: E. Dacus, Congressional Liaison Regions: R. Conte, RI; M. Franke and Gerald McCoy, RII; D. Hills, RIII; G. Werner, RIV I DPR: A. Russell, Action Plan Structure, Action Plan website updates Project Attributes:

The project will consist of four broad phases. The first phase involves continued collection of issues that the staff expects the licensee to address in the short term and long term. Objectives during this phase include assembling a catalogue of questions to request of the licensee to address in either inspection or licensing space. The first phase involves inspection and assessment of the licensee's walkdowns and activities, via the Augmented Inspection Team.

The second phase involves identifying short term issues that the licensee must demonstrate prior to restart. The third phase involves identifying long term issues that the licensee must demonstrate post plant restart. These items may involve a series of public meetings, development of a temporary inspection instruction, and perhaps some audits. The fourth phase addresses the development of a regulatory vehicle to ensure that the licensee adequately addresses the new design basis earthquake in its Updated Final Safety Analysis Report, as appropriate. The fifth phase includes the development of regulatory products, which includes potentially issuing an Order, generic communications, and developing communications tools such as briefing sheets, etc., as appropriate.

Project Success Criteria Include:

Licensee adequately implements the RG 1.167 and EPRI guidelines and the initiative activities in accordance with the IAEA Safety Report No. 66, to effectively address short and long-term plant restart issues. Stakeholders are informed of and educated about the safety significance of this issue.

The milestones in the action plan, and documents or products that result from completed milestones should be publicly available. Planning information, personnel assignments and draft documents will not, in general, be made public.

Current Status: As noted in table Potential Problems: N/A Closeout Criteria: N/A Proposed Resources and Re-prioritization: Approximately 1.0 FTE is expected to be expended to address this issue. Re-prioritization may be required to support plant restart activities.

DE: G. Wilson, R. Matthew, M. Khanna DCI: T. McMurtray, T. Lupold, M. Mitchell, and M. Murphy DSS: G.Casto, R. Dennig, A. Ulses, A. Mendiola DLR: B. Pham, R. Auluck, D. Pelton DIRS: T. Tate, D. Harrison NRO: C. Munson, R. Karas NMSS: E. Love and E. Benner RES: A. Kammerer OPA: S. Burnell OCA: E. Dicus Region I: R. Conte Region Ih: M. Franke Region II: A. Shaihk Region IV: G. Werner

References:

10 CFR Part 100, Appendix A, Seismic and Geologic Siting for Nuclear Power Plants RG 1.167, "Restart of a Nuclear Power Plant Shut Down By a Seismic Event" EPRI NP-6695 Guideline, "Guidelines for Nuclear Power Plant Response to an Earthquake" IAEA Safety Report No. 66, "Earthquake Preparedness and Response for Nuclear Power Plants" Augmented Inspection Charter to Evaluate Total Loss of Offsite Power, Dual Unit Reactor Trips and Plant Equipment Issues Following a Seismic Event At North Anna Dominion Presentation Slides, September 8, 2011(ADAMS Accession No. xxxxxxxx)

NORTH ANNA NUCLEAR POWER PLANT RESTART ACTION PLAN MILESTONES

[tem# Milestone Completion Lead Date Applicable technical branches within DE, DSS, DCI, 9/16/2011 DE, NMSS NMSS and DLR to identify questions and issues that the licensee should address for restart. This includes short term (prior to restart) and long term initiatives (post restart).

2 As issues are identified and finalized, weekly Ongoing DORL conference calls/meetings will be held with licensee to address short and long term actions.

3 Short term and long term actions and issues shall be DE identified and documented for issuance to the licensee via DORL.

4 Questions and issues will be categorized in one of the DORL/DE/

following: (a) confirmatory inspections by the region, NMSS (b) items to be confirmed via licensee's visual inspection/walkdowns, (c) short term evaluations by licensee (pre-restart), and (d) long term evaluations by licensee (post-restart).

5 Address any safety related concerns associated with NMSS the movement of the ISFSIs as a result of the earthquake. via questiens and inspectiens. Perform a complete non-linear dynamic analysis or a soil-structure interaction (SSI) analysis. Evaluate the site's near-term actions including the extent that the internal structures of the cask systems need to be examined.

Evaluate the site's interactions with ISFSI Certificate of NMSS Compliance holder (TN) on responding to the event and their evaluation on the impact to the ISFSI.

6 Upon Augmented Team Inspection exit, any follow-up. REGION II issues/actions will be communicated and addressed by NMSS staff as appropriate. Region to seek assistance via appropriate vehicle to address outstanding issues.

SFST and RII to observe the extent of the damage on the ISFSI pad.

7 Develop a team to address path forward in reviewing DE licensee's submittal for plans to restart.

o Develop the language for an Order, which could later DORL/DE converted to a Confirmatory Action Letter, if needed.

9 Upon receipt of licensee's formal request for restart DE submittal, team to assess results of their inspections and readiness reviews, with support from technical branches, as appropriate. This will include developing

"t4 I

  • I I questions and final input to NRC restart documi 10 Assess root cause for diesel generator failure and include input in staffs document for restart. Any other issues shall be addressed similarly.

Item# Milestone Completion Lead Date 11 Conduct inspections at site to verify any outstanding REGION II issues. Agree to site's corrective actions for the NMSS damaged/shifted ISFSI system (long-term safety and compliance). Evaluate the acceptability of any repairs made to damaged ISFSI HSM's.

12 Develop template for NRC Restart Document and DORL incorporate input from OGC, etc., as appropriate.

13 Conduct Public Meeting prior to issuance of NRC DORL Restart Document.

14 Issue NRC Restart Document. DORL 15 As necessary, determine the need for appropriate DORL/OGC/OE/

regulatory vehicle for long term issues, i.e., revisions to NMSS FSAR to address new DBE.

16 Address any potential generic issues, e.g., seismic Region II instrumentation power supplies, seismic monitor NMSS/DE/DPR locations on structures as well as in the "free field,"

and seismic monitors on ISFSI pads.

17 Continue to respond to routine communications Ongoing DE between the resident inspectors and local officials based on public interest. See DE Communication Plan (ADAMS ML #).

18 Address Issues for Resolution, as applicable DE/DIRS