Letter Sequence Other |
|---|
|
Results
Other: ML11256A036, ML120030022, ML120030027, ML15062A354, ML15062A362, ML15062A366, ML15062A373, ML15068A125, ML15128A134, ML15128A141, ML15128A143, NRC-2012-0014, G20110506/LTR-11-0402/EDATS: SECY-2011-0402, G20110492/LTR-11-0382/EDATS: OEDO-2011-0387 - FRN, 2.206 Final Director'S Decision, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station (TAC Nos. ME6681 and
|
MONTHYEARML11182B0292011-06-26026 June 2011 G20110492/LTR-11-0382/EDATS: SECY-2011-0387 - 2.206 - Omaha Public Power District and Ft. Calhoun Nuclear Power Plant Project stage: Request ML11192A2852011-07-0303 July 2011 G20110506/LTR-11-0402/EDATS: SECY-2011-0402 - Thomas Saporito 2.206 - Nebraska Public Power District and Cooper Nuclear Station, Et Al Project stage: Request ML11256A0362011-08-29029 August 2011 Transcript of 10 CFR 2.206 Petition Review Board Conference Call 2.206 Petition from Thomas Saporito Fort Calhoun Station and Cooper Nuclear Station Project stage: Other ML1200300222012-01-13013 January 2012 G20110506/LTR-11-0402/EDATS: SECY-2011-0402, G20110492/LTR-11-0382/EDATS: OEDO-2011-0387 - Letter, 2.206 Acknowledgement, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station Project stage: Other ML1200300272012-01-13013 January 2012 G20110506/LTR-11-0402/EDATS: SECY-2011-0402, G20110492/LTR-11-0382/EDATS: OEDO-2011-0387 - FRN, 2.206 Acknowledgement, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station Project stage: Other ML15041A4682015-02-0303 February 2015 Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Flooding Aspects of Recommendation 2.1 of Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident Project stage: Response to RAI LIC-15-0015, Response to Request for Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident-Fort Calhoun Station Flood Hazard Reevaluation2015-02-0404 February 2015 Response to Request for Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident-Fort Calhoun Station Flood Hazard Reevaluation Project stage: Request ML15068A1252015-03-0909 March 2015 NRR E-mail Capture - Update: Petitions Under 10 CFR 2.206 Pertaining to Flood Protection at Fort Calhoun Station and Cooper Nuclear Station Project stage: Other ML15062A3622015-04-15015 April 2015 G20110506/LTR-11-0402 - Letter to Cooper Licensee, 2.206 Proposed Directors Decision, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station Project stage: Other ML15062A3662015-04-15015 April 2015 G20110492/LTR-11-0382 - Letter to FCS Licensee, 2.206 Proposed Directors Decision, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station Project stage: Other ML15062A3542015-04-15015 April 2015 G20110506/LTR-11-0402 and G20110492/LTR-11-0382 - Letter to Petitioner, 2.206 Proposed Directors Decision, Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station Project stage: Other ML15062A3732015-04-15015 April 2015 G20110506/LTR-11-0402 and G20110492/LTR-11-0382 - 2.206 Proposed Directors Decision, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station Project stage: Other ML15128A1432015-06-0303 June 2015 G20110506/LTR-11-0402/EDATS: SECY-2011-0402, G20110492/LTR-11-0382/EDATS: OEDO-2011-0387 - FRN, 2.206 Final Director'S Decision, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station Project stage: Other NRC-2012-0014, G20110506/LTR-11-0402/EDATS: SECY-2011-0402, G20110492/LTR-11-0382/EDATS: OEDO-2011-0387 - FRN, 2.206 Final Director'S Decision, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station (TAC Nos. ME6681 and2015-06-0303 June 2015 G20110506/LTR-11-0402/EDATS: SECY-2011-0402, G20110492/LTR-11-0382/EDATS: OEDO-2011-0387 - FRN, 2.206 Final Director'S Decision, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station (TAC Nos. ME6681 and ME66 Project stage: Other ML15128A1412015-06-0303 June 2015 G20110506/LTR-11-0402/G20110492/LTR-11-0382 - 2.206 Final Director'S Decision, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station Project stage: Other ML15128A1342015-06-0303 June 2015 G20110506/LTR-11-0402/G20110492/LTR-11-0382 - Letter to Petitioner, 2.206 Final Director'S Decision, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station Project stage: Other 2015-02-03
[Table View] |
G20110506/LTR-11-0402/EDATS: SECY-2011-0402, G20110492/LTR-11-0382/EDATS: OEDO-2011-0387 - FRN, 2.206 Acknowledgement, Petitioner Thomas Saporito Related to Cooper Nuclear Station and Fort Calhoun Station| ML120030027 |
| Person / Time |
|---|
| Site: |
Cooper, Fort Calhoun  |
|---|
| Issue date: |
01/13/2012 |
|---|
| From: |
Leeds E Office of Nuclear Reactor Regulation |
|---|
| To: |
|
|---|
| Wilkins, L E, NRR/DORL/LPL4, 415-1377 |
| Shared Package |
|---|
| ML113530557 |
List: |
|---|
| References |
|---|
| G20110492, EDATS: OEDO-2011-0387, EDATS: SECY-2011-0402, G20110506, LTR-11-0382, LTR-11-0402, TAC ME6622, TAC ME6681, NRC-2012-0014 |
| Download: ML120030027 (3) |
|
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-285, License No. DPR-40; Docket No. 50-298, License No. DPR-46; NRC-2012-0014]
Request for Action against Omaha Public Power District and Nebraska Public Power District Notice is hereby given that by petitions dated June 26 and July 3, 2011, respectively, Thomas Saporito (the petitioner) has requested that the U.S. Nuclear Regulatory Commission (NRC or the Commission) take escalated enforcement actions against Omaha Public Power District, the licensee for Fort Calhoun Station, Unit 1 (FCS), and Nebraska Public Power District, the licensee for Cooper Nuclear Station (Cooper). The petitions dated June 26 and July 3, 2011, are publicly available in the NRCs Agencywide Documents Access and Management System (ADAMS) under Accession Nos. ML11182B029 and ML11192A285, respectively.
The petitioner has requested that the NRC take action to suspend or revoke the NRC licenses granted for the operation of nuclear power reactors and issue a notice of violation with a proposed civil penalty against the collectively named and each singularly named licensee in this matter - in the amount of $500,000 for Fort Calhoun Station and $1,000,000 for Cooper.
Additionally, the petitioner requested that the NRC issue confirmatory orders to prohibit restart at FCS and to bring Cooper to a cold shutdown mode of operation until such time as: (1) the floodwaters subside to an appreciable lower level or sea level; (2) the licensee upgrades its flood protection plan; (3) the licensee repairs and enhances its current flood protection berms; and (4) the licensee upgrades its station blackout procedures to meet a challenging extended loss of offsite power due to floodwaters and other natural disasters or terrorist attacks.
As the basis for these requests, the petitioner stated that: (1) the licensees installed flood protection measures and systems and barriers at FCS and Cooper are not sufficient to adequately protect the nuclear reactor from a full-meltdown scenario like that currently unfolding in Japan; and (2) the licensees station blackout procedures are not sufficient to meet a challenging extended loss of offsite power due to flood waters and other natural disasters or terrorist attacks.
The requests are being treated pursuant to Title 10 of the Code of Federal Regulations Section 2.206 of the Commission's regulations. The requests have been referred to the Director of the Office of Nuclear Reactor Regulation. As provided by Section 2.206, appropriate action will be taken on these petitions within a reasonable time. The petitioner requested an opportunity to address the Petition Review Board (PRB). The PRB held a recorded teleconference with the petitioner on August 29, 2011, during which the petitioner supplemented and clarified the petitions. The results of those discussions were considered in the PRBs determination regarding the petitioners requests. As a result, the PRB acknowledged the petitioners concerns regarding flood protection, including station blackout procedures, at FCS and Cooper. By letter dated January 13, 2012 (ADAMS Accession No. ML120030022), the Director of the NRCs Office of Nuclear Reactor Regulation denied the petitioners requests for immediate action. Additionally, the PRB noted that: (1) natural disasters such as earthquakes and flooding, and (2) station blackout regulations are undergoing NRC review as part of the lessons learned from the Fukushima event. The PRB intends to use the results of the Fukushima review to inform its final decision on whether to implement the requested actions.
Copies of the petitions dated June 26 and July 3, 2011, are available for inspection at the NRC's Public Document Room (PDR), located at One White Flint North, Public File Area O1F21, 11555 Rockville Pike (first floor), Rockville, Maryland 20852. Publicly available
documents created or received at the NRC are accessible electronically through ADAMS in the NRC Library at http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRCs PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by e-mail to PDR.Resource@nrc.gov.
Dated at Rockville, Maryland, this 13th day of January 2012.
FOR THE NUCLEAR REGULATORY COMMISSION.
/RA/
Eric J. Leeds, Director, Office of Nuclear Reactor Regulation.