SFP Rack Insert LAR Supplemental Information Request Teleconference Clarification
ML113480452
Person / Time
Site: Peach Bottom Constellation icon.png
Issue date: 12/13/2011
From: Tom Loomis
Exelon Corp
To: John Hughey
Plant Licensing Branch 1
Hughey J, NRR/DORL, 301-415-3204
References
Download: ML113480452 (2)


Text

From:

thomas.loomis@exeloncorp.com Sent:

Tuesday, December 13, 2011 2:20 PM To:

Hughey, John

Subject:

FW: Supplemental Information Request Letter for SFP Insert LAR John - Here is an accurate statement as you requested. We made some clarifications based on our understanding of the call. Please call for any clarifications. Please note that we discussed the analysis (singular). I made that correction below.

Thomas R. Loomis Licensing and Regulatory Affairs Kennett Square, PA From: Hughey, John [1]

Sent: Monday, December 12, 2011 8:43 AM To: Loomis, Thomas R:(GenCo-Nuc)

Subject:

Supplemental Information Request Letter for SFP Insert LAR Tom, We are about to issue the formal supplemental request letter for the Peach Bottom spent fuel pool rack insert amendment request. I wanted to capture the additional requests regarding the structural analysis and demonstration testing that we discussed during the teleconference on December 8, 2011. I have included a portion of the letter we intend to issue below and request that you reply confirming the accuracy of the information below:

The requested information and associated time frame was discussed with Mr. Thomas Loomis of your staff on December 8, 2011. During this teleconference, Exelon representatives stated that the structural analysis referred to in Attachment 1, Section 3.5, Structural, of the November 3, 2011, submittal had been completed. In addition, Exelon representatives stated that the rack insert clean pool testing associated with the demonstration program is complete referred to in Attachment 1, Section 3.4.3, Retention Forces, and Section 3.4.4, Insertion and Removal Forces, of the submittal had also been completed. Additional demonstration program testing is being performed at Peach Bottom to facilitate the installation. The NRC staff requested that the structural analysis issuance date and associated document number, as well as the completion date for the referenced demonstration program testing, be included in the licensees response. Mr. Loomis stated that the completion information for the structural analysis and clean pool demonstration program testing would be provided with the response as requested.

Please reply by COB today, December 12, 2011.

Thanks, John John Hughey Peach Bottom Project Manager

NRR / Division of Operating Reactor Licensing Phone: 301-415-3204 e-mail: John.Hughey@nrc.gov

                                                                                                    • This e-mail and any of its attachments may contain Exelon Corporation proprietary information, which is privileged, confidential, or subject to copyright belonging to the Exelon Corporation family of Companies.

This e-mail is intended solely for the use of the individual or entity to which it is addressed. If you are not the intended recipient of this e-mail, you are hereby notified that any dissemination, distribution, copying, or action taken in relation to the contents of and attachments to this e-mail is strictly prohibited and may be unlawful. If you have received this e-mail in error, please notify the sender immediately and permanently delete the original and any copy of this e-mail and any printout. Thank You. **************************************************