MONTHYEARML24309A0552024-11-0101 November 2024 NRR E-mail Capture - Request for Additional Information - TVA LAR to Revised Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 Re TS Table 3.3.2-1, Function 5 ML24304A3752024-10-29029 October 2024 NRR E-mail Capture - Request for Additional Information - License Amendment Request (LAR) to Revise Watts Bar Updated Final Safety Analysis Report (UFSAR) for Hydrologic Analysis ML24274A2762024-09-24024 September 2024 Email from K.Green to S.Hughes, Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, Hydrologic LAR to Revise the UFSAR ML24260A0322024-09-10010 September 2024 NRR E-mail Capture - Request for Additional Information Regarding the Watts Bar Unit 2 Steam Generator Tube Inspection Report for U2R5 ML24215A3152024-07-24024 July 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-276-A, Revision 2 TS 3.8.1, AC Sources ML24177A1412024-06-11011 June 2024 NRR E-mail Capture - Audit Plan Related to Review of the Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, LAR to Revise Technical Specification Table 3.3.2-1 Function 5 ML24157A3152024-06-0303 June 2024 2024 Sequoyah Commercial Grade Dedication Inspection Information Request ML24155A1372024-05-29029 May 2024 Email from K. Green to S. Hughes Request for Additional Information Related to License Amendment Request to Revise Residual Heat Removal Flow Rate ML24156A0062024-05-22022 May 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Recapture Low-Power Testing Time ML24130A0132024-05-0707 May 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.7.11 for MCR Chiller Completion Time ML24123A0882024-05-0202 May 2024 NRR E-mail Capture - Correction Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24122B4872024-04-30030 April 2024 NRR E-mail Capture - Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24082A0662024-04-17017 April 2024 Email to Stuart Rymer on Exemption Decision for Watts Bar ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24082A0682024-04-10010 April 2024 Email to Stuart Rymer Re_ Availability of EA-FONSI for Watts Bar ML24100A8392024-04-0909 April 2024 Response from State of Tn Regarding Review of Environmental Assessment for Watts Bar Exemption Request ML24100A8402024-04-0808 April 2024 Email to State of Tn Requesting Review of Environmental Assessment for Watts Bar Exemption Request ML24071A0982024-03-0707 March 2024 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate ML24058A0962024-02-26026 February 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant License Amendment Request to Revise UFSAR for Hydrologic Analysis ML24047A2792024-02-15015 February 2024 RAI Related to the Exemption Request for 10 CFR 37.11 ML24045A0312024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML24033A0562024-02-0101 February 2024 NRR E-mail Capture - Correction Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-427-A, Revision 2 Regarding Degraded Barriers ML24036A0132024-01-23023 January 2024 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar Nuclear Plants, License Amendment Request to Revise TS Table 3.3.2-1, Function 5, Turbine Trip and Feedwater Isolation ML24022A2592024-01-22022 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Revise TS LCO 3.8.2 to Remove Note C-S Diesel Generator ML24016A0762024-01-16016 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2 - License Amendment Request to Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications ML23347A0642023-12-13013 December 2023 12-13-23 Email from Kimberly Green to Wells, Russell, Subject: Results of NRC SUNSI Review of Watts Bar Nuclear Plant Dual-Unit UFSAR, Amendment 5 ML23334A0932023-11-28028 November 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate During Mode 6 ML23319A1662023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant, Exemption Request Related to 10 CFR 37.11(c)(2) ML23254A2872023-09-11011 September 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Table 1.1-1 Re Number of Required Rvh Closure Bolts ML23236A2562023-08-24024 August 2023 NRR E-mail Capture - Acceptance Review Results for the Sequoyah and Watts Bar License Amendment Request to Adopt TSTF-567 (L-2023-LLA-0106) ML23191A8672023-07-10010 July 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23150A2472023-05-25025 May 2023 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23116A1492023-04-21021 April 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23075A0032023-03-13013 March 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1, 2, and 3, License Amendment Request to Revise TS 3.7.11, Required Actions A.1 and E.1 Footnotes Re Date for the Modification ML23072A0722023-03-10010 March 2023 NRR E-mail Capture - (External_Sender) State Consultation - Sequoyah Nuclear Plant, Units 1 and 2; and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23013A0362023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML23013A0382023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML22356A2982022-12-22022 December 2022 Email Response to Letter, Dated November 22, 2022 Regarding Watts Bar Integrated Inspection Report ML22353A0812022-12-15015 December 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 2, Alternative Request WBN-2-ISI-01 Regarding Examination of Upper Head Injection Nozzle Dissimilar Metal Piping Butt Welds ML22348A0972022-12-14014 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML22348A0442022-12-13013 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0712022-08-15015 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 (EPID L-2022-LLA-0103) - Corrected ML22227A0262022-08-12012 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22215A2752022-08-0303 August 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-554 ML22194A8762022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-529 ML22166A4292022-06-0606 June 2022 NRR E-mail Capture - LAR to Adopt TSTF-577 2024-09-24
[Table view] |
Text
WBN2Public Resource From: Clark, Mark Steven [msclark0@tva.gov]
Sent: Monday, November 14, 2011 11:20 AM To: Carte, Norbert; Poole, Justin Cc: Bryan, Robert H Jr; Kepler, Jeffrey T; McNeil, Douglas Ray
Subject:
RE: Discussion with the NRC Norbert:
TVA Licensing says they have not seen anything.
Justin:
Can you provide the draft of Norberts questions? We were supposed to include the response in the 11/14 letter, but it didnt get done and I want to be sure it is in the 11/30 letter and I want to be sure it is right this time.
- Regards, Steve Steve Clark Bechtel Power Corp.
Control Systems Watts Bar 2 Completion Project Phone: 423.365.3007 e-mail: msclark0@tva.gov From: Carte, Norbert [1]
Sent: Monday, November 14, 2011 10:16 AM To: Clark, Mark Steven Cc: Poole, Justin
Subject:
RE: Discussion with the NRC By Internal Memo dated October 11, 2011 (ML11270A306), I sent Justin some RAI Questions on 603. I do not know if Justin sent them out yet. After you get them in draft form, maybe we should talk about them to make sure they are clear.
Norbert Carte (301) 415-5890 COMPLEXITY in regulations and guidance may be necessary to afford flexibility in design and construction but often comes from layering of new information upon old without regard to overall continuity.
From: Clark, Mark Steven [2]
Sent: Monday, November 14, 2011 9:35 AM To: Carte, Norbert Cc: Hilmes, Steven A; Knuettel, Edward Terry; Poole, Justin; Kepler, Jeffrey T; Bryan, Robert H Jr
Subject:
RE: Discussion with the NRC Norbert:
I am behind with revising the IEEE 603 compliance white paper. In the most recent discussion you asked about why the focus of the paper was on Clause 4. At the time, I did not remember, but this morning I found 1
the following e-mail. I do not have a response. Did you or Justin send something to TVA Licensing that I did not receive? Im just looking for clarification as I start the revision.
- Thanks, Steve Steve Clark Bechtel Power Corp.
Control Systems Watts Bar 2 Completion Project Phone: 423.365.3007 e-mail: msclark0@tva.gov From: Clark, Mark Steven Sent: Tuesday, June 14, 2011 3:57 PM To: Crouch, William D; Bryan, Robert H Jr; Smith, James D; Hilmes, Steven A; Knuettel, Edward Terry Cc: 'Carte, Norbert'; Kepler, Jeffrey T; Raley, Thomas R
Subject:
Discussion with the NRC All:
Norbert Carte and I had an informal discussion this afternoon concerning the PAMS design bases question (Matrix Item 213). I requested clarification of the question after reviewing the various Reg Guides and Industry Standards. The proposed results the discussion are summarized below:
- 1. As previously agreed we will commit the Common Q PAMS to meet IEEE 603-1991.
- 2. We will not commit the Common Q PAMS to meet Reg Guide 1.153 (endorses 603-1991).
- 3. We will revise section 7.5 UFSAR discussion of variable types to reflect the fact that some type A variables are required to meet our Reg Guide 1.97 commitment and other type A variables are required to meet TVA operations requirements.
- 4. We will revise Table 7.5-2 to clearly identify which type A variables are required to meet our Reg Guide 1.97 commitment and which are not.
- 5. We will prepare a design basis response for the Common Q PAMS using the requirements of IEEE 603-1991 Clause 4.
Note: Items 3 and 4 or some other solution must be agreed on to resolve the disconnect between the FSAR Type A variable definition and the Type A variables identified in Table 7.5-2.
With the exception of item 5 we will review the above items at this Thursdays telecom meeting. Prior to the meeting, please review the items to determine if they are acceptable to TVA. Norbert agreed to do the same with his peers and management at the NRC.
- Regards, Steve Steve Clark Bechtel Power Corp.
Control Systems Watts Bar 2 Completion Project Phone: 423.365.3007 e-mail: msclark0@tva.gov 2
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 607 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF2540E51D)
Subject:
RE: Discussion with the NRC Sent Date: 11/14/2011 11:19:30 AM Received Date: 11/14/2011 11:19:40 AM From: Clark, Mark Steven Created By: msclark0@tva.gov Recipients:
"Bryan, Robert H Jr" <rhbryan@tva.gov>
Tracking Status: None "Kepler, Jeffrey T" <jtkepler@tva.gov>
Tracking Status: None "McNeil, Douglas Ray" <drmcneil@tva.gov>
Tracking Status: None "Carte, Norbert" <Norbert.Carte@nrc.gov>