Proposed Model Application for TSTF-432, Revision 1, Change in Technical Specifications End States (WCAP-16294).ML113202614 |
Person / Time |
---|
Site: |
Technical Specifications Task Force |
---|
Issue date: |
11/14/2011 |
---|
From: |
Browning R, Croft W, Steelman W, Stringfellow N BWR Owners Group, PWR Owners Group, Technical Specifications Task Force |
---|
To: |
Document Control Desk, Office of Nuclear Reactor Regulation |
---|
References |
---|
TSTF-11-19, TSTF-432, Rev 1, WCAP-16294 |
Download: ML113202614 (7) |
|
|
---|
Category:Letter type:TSTF
MONTHYEARTSTF-22-07, Transmittal of TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2022-07-19019 July 2022 Transmittal of TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements TSTF-22-06, Technical Specifications Task Force - Request for a Workshop to Discuss the Interaction of Natural Phenomena Protection Design Features and Operability2022-07-0808 July 2022 Technical Specifications Task Force - Request for a Workshop to Discuss the Interaction of Natural Phenomena Protection Design Features and Operability TSTF-22-04, Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program2022-03-22022 March 2022 Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program TSTF-21-03, TSTF Response to NRC Questions on TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements and Submittal of Revision 12021-06-23023 June 2021 TSTF Response to NRC Questions on TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements and Submittal of Revision 1 TSTF-21-01, Transmittal of TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2021-01-26026 January 2021 Transmittal of TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling TSTF-20-04, Technical Specifications Task Force - Transmittal of TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections2020-06-0808 June 2020 Technical Specifications Task Force - Transmittal of TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections TSTF-20-01, Transmittal of TSTF-IG-20-02, Guidance on Evaluating One-Time Surveillance Frequency Changes Under the Surveillance Frequency Control Program (TSTF-425M SFCP)2020-04-0909 April 2020 Transmittal of TSTF-IG-20-02, Guidance on Evaluating One-Time Surveillance Frequency Changes Under the Surveillance Frequency Control Program (TSTF-425M SFCP) TSTF-19-14, Technical Specifications Task Force - TSTF Response to NRC Questions on TSTF-582, RPV WIC Enhancements2020-02-12012 February 2020 Technical Specifications Task Force - TSTF Response to NRC Questions on TSTF-582, RPV WIC Enhancements TSTF-19-11, TSTF Response to NRC Questions on TSTF-554, Revise Reactor Coolant Leakage Requirements2020-01-16016 January 2020 TSTF Response to NRC Questions on TSTF-554, Revise Reactor Coolant Leakage Requirements TSTF-19-09, Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements2019-12-13013 December 2019 Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements TSTF-19-13, Technical Specifications Task Force - Updated TSTF Membership and Distribution2019-12-0303 December 2019 Technical Specifications Task Force - Updated TSTF Membership and Distribution TSTF-19-12, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position.2019-11-0505 November 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position. TSTF-19-10, Transmittal of Errata Changes to TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2019-08-28028 August 2019 Transmittal of Errata Changes to TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position TSTF-19-03, Request for Fee Exemption for TSTF-554, Revision 0, Revise Reactor Coolant Leakage Requirements - Letter2019-07-0808 July 2019 Request for Fee Exemption for TSTF-554, Revision 0, Revise Reactor Coolant Leakage Requirements - Letter TSTF-19-08, Draft of Traveler TSTF-582, Revision 0, RPV WIC Enhancements.2019-07-0303 July 2019 Draft of Traveler TSTF-582, Revision 0, RPV WIC Enhancements. TSTF-19-06, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition2019-06-25025 June 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition TSTF-19-07, TSTF Handout for October 16, 2019, Meeting: Elimination of Commitment to Adopt TSTF-4932019-06-18018 June 2019 TSTF Handout for October 16, 2019, Meeting: Elimination of Commitment to Adopt TSTF-493 TSTF-19-05, Transmittal of TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2019-06-18018 June 2019 Transmittal of TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position TSTF-19-01, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems2019-01-17017 January 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems TSTF-18-13, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-557, Revision 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program.2018-12-20020 December 2018 TSTF Comments on Draft Safety Evaluation for Traveler TSTF-557, Revision 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program. TSTF-18-06, TSTF Response to NRC Questions on TSTF-569, Revise Response Time Testing Definition2018-10-31031 October 2018 TSTF Response to NRC Questions on TSTF-569, Revise Response Time Testing Definition TSTF-18-12, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-564, Revision 1, Safety Limit MCPR2018-10-24024 October 2018 TSTF Comments on Draft Safety Evaluation for Traveler TSTF-564, Revision 1, Safety Limit MCPR TSTF-18-11, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-563, Revision 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program.2018-10-12012 October 2018 TSTF Comments on Draft Safety Evaluation for Traveler TSTF-563, Revision 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program. TSTF-18-08, Updated TSTF Membership and Distribution2018-07-17017 July 2018 Updated TSTF Membership and Distribution TSTF-18-07, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-505, Provide Risk-Informed Extended Completion Times and Submittal of TSTF-505, Revision 22018-07-0202 July 2018 TSTF Comments on Draft Safety Evaluation for Traveler TSTF-505, Provide Risk-Informed Extended Completion Times and Submittal of TSTF-505, Revision 2 TSTF-18-05, TSTF Response to NRC Questions on TSTF-564, Safety Limit (Minimum Critical Power Ratio) MCPR2018-05-29029 May 2018 TSTF Response to NRC Questions on TSTF-564, Safety Limit (Minimum Critical Power Ratio) MCPR TSTF-17-19, TSTF Response to NRC Questions on TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2018-04-27027 April 2018 TSTF Response to NRC Questions on TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program TSTF-18-04, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues.2018-04-16016 April 2018 TSTF Comments on Draft Safety Evaluation for Traveler TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues. TSTF-18-03, Transmittal of TSTF-565, Revision 1, Revise the LCO 3.0.2 and LCO 3.0.3 Bases2018-03-30030 March 2018 Transmittal of TSTF-565, Revision 1, Revise the LCO 3.0.2 and LCO 3.0.3 Bases TSTF-18-02, Technical Specifications Task Force - Transmittal of TSTF-569, Revision 0, Revise Response Time Testing Definition.2018-02-0808 February 2018 Technical Specifications Task Force - Transmittal of TSTF-569, Revision 0, Revise Response Time Testing Definition. TSTF-17-18, Transmittal of TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems.2018-01-19019 January 2018 Transmittal of TSTF-566, Revision 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems. TSTF-18-01, Technical Specifications Task Force - Change in TSTF Traveler Invoicing2018-01-12012 January 2018 Technical Specifications Task Force - Change in TSTF Traveler Invoicing TSTF-17-17, Transmittal of TSTF-557, Revision 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program2017-12-19019 December 2017 Transmittal of TSTF-557, Revision 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program TSTF-17-16, Technical Specifications Task Force - Transmittal of TSTF-568, Clarify Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.22017-12-19019 December 2017 Technical Specifications Task Force - Transmittal of TSTF-568, Clarify Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 TSTF-17-13, Technical Specifications Task Force - Updated TSTF Membership and Distribution2017-10-30030 October 2017 Technical Specifications Task Force - Updated TSTF Membership and Distribution TSTF-17-12, Technical Specifications Task Force - Transmittal of TSTF-564, Safety Limit Mcpr.2017-08-28028 August 2017 Technical Specifications Task Force - Transmittal of TSTF-564, Safety Limit Mcpr. TSTF-17-10, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-551, Revision 3, Revise Secondary Containment Surveillance Requirements.2017-08-0202 August 2017 TSTF Comments on Draft Safety Evaluation for Traveler TSTF-551, Revision 3, Revise Secondary Containment Surveillance Requirements. TSTF-17-09, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-546, Revision 0, Revise APRM Channel Adjustment Surveillance Requirement.2017-07-24024 July 2017 TSTF Comments on Draft Safety Evaluation for Traveler TSTF-546, Revision 0, Revise APRM Channel Adjustment Surveillance Requirement. TSTF-17-08, Change in TSTF Traveler Invoicing2017-07-0505 July 2017 Change in TSTF Traveler Invoicing TSTF-17-07, Transmittal of TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2017-05-10010 May 2017 Transmittal of TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program TSTF-17-06, Request to Incorporate TSTF-565, Clarify the Term Operational Convenience in the LCO 3.0.2 Bases, Into the Standard Technical Specifications2017-05-0909 May 2017 Request to Incorporate TSTF-565, Clarify the Term Operational Convenience in the LCO 3.0.2 Bases, Into the Standard Technical Specifications TSTF-17-03, Technical Specifications Task Force - Request for Fee Exemption for TSTF-567, Add Containment Sump TS to Address GSI-191 Issues.2017-03-30030 March 2017 Technical Specifications Task Force - Request for Fee Exemption for TSTF-567, Add Containment Sump TS to Address GSI-191 Issues. TSTF-17-04, Technical Specifications Task Force - Transmittal of TSTF-567, Add Containment Sump TS to Address GSI-191 Issues.2017-03-30030 March 2017 Technical Specifications Task Force - Transmittal of TSTF-567, Add Containment Sump TS to Address GSI-191 Issues. TSTF-17-05, Technical Specifications Task Force (TSTF) - Updated TSTF Membership and Distribution2017-02-23023 February 2017 Technical Specifications Task Force (TSTF) - Updated TSTF Membership and Distribution TSTF-16-11, Response to NRC Request for Additional Information Regarding TSTF-546, Revision 0, Revise APRM Channel Adjustment Surveillance Requirement.2017-02-0202 February 2017 Response to NRC Request for Additional Information Regarding TSTF-546, Revision 0, Revise APRM Channel Adjustment Surveillance Requirement. TSTF-17-02, Technical Specifications Task Force - Request for NRC to Withdraw November 7, 2013 Letter to TSTF Concerning TSTF-51, TSTF-286, and TSTF-4712017-02-0202 February 2017 Technical Specifications Task Force - Request for NRC to Withdraw November 7, 2013 Letter to TSTF Concerning TSTF-51, TSTF-286, and TSTF-471 TSTF-17-01, TSTF Draft Response to NRC Questions on TSTF-505, Provide Risk-Informed Extended Completion Times for 02/16/2017 Public Meeting2017-01-31031 January 2017 TSTF Draft Response to NRC Questions on TSTF-505, Provide Risk-Informed Extended Completion Times for 02/16/2017 Public Meeting TSTF-16-12, Technical Specifications Task Force - Updated TSTF Membership and Distribution2016-11-18018 November 2016 Technical Specifications Task Force - Updated TSTF Membership and Distribution TSTF-16-10, TSTF Comments on Draft Safety Evaluation for Traveler TSTF-542, Revision 2, Reactor Pressure Vessel Water Inventory Control, and Transmittal of Editorial Corrections to TSTF-542, Revision 22016-11-0202 November 2016 TSTF Comments on Draft Safety Evaluation for Traveler TSTF-542, Revision 2, Reactor Pressure Vessel Water Inventory Control, and Transmittal of Editorial Corrections to TSTF-542, Revision 2 TSTF-16-08, Withdrawal of TSTF-553, Revision 0, Add Action for Two Inoperable Creatcs Trains.2016-10-13013 October 2016 Withdrawal of TSTF-553, Revision 0, Add Action for Two Inoperable Creatcs Trains. 2022-07-08
[Table view] |
Text
TECHNICAL SPECIFICATIONS TASK FORCE TSTF A JOINT OWNERS GROUP ACTIVITY November 14, 2011 TSTF-11-19 PROJ0753 Attn: Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
Proposed Model Application for TSTF-432, Revision 1, "Change in Technical Specifications End States (WCAP-16294)"
REFERENCE:
Letter from TSTF to U.S. NRC, "Response to NRC Request for Additional Information Regarding TSTF-432, Revision 0, 'Change in Technical Specifications End States (WCAP-16294)'," dated November 29, 2010.
Dear Sir or Madam:
In the referenced letter, the TSTF submitted Revision 1 of TSTF-432, "Change in Technical Specifications End States (WCAP-16294)." Subsequent to the submittal of TSTF-432, the TSTF agreed to provide proposed model applications for all TSTF Travelers. Attached for NRC use is the TSTF's proposed model application for TSTF-432.
Should you have any questions, please do not hesitate to contact us.
Norman J. Stringfellow (PWROG/W) Roy A. Browning (BWROG)
William J. Steelman (PWROG/CE) Wendy E. Croft (PWROG/B&W)
Enclosure cc: Robert Elliott, Technical Specifications Branch, NRC Michelle Honcharik, Licensing Processes Branch, NRC 11921 Rockville Pike, Suite 100, Rockville, MD 20852 Phone: 301-984-4400, Fax: 301-984-7600 Administration by EXCEL Services Corporation
PROPOSED MODEL APPLICATION FOR PLANT-SPECIFIC ADOPTION OF TSTF-432, REVISION 1, "CHANGE IN TECHNICAL SPECIFICATIONS END STATES (WCAP-16294)"
U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555
SUBJECT:
[PLANT]
DOCKET NO. 50-[XXX]
LICENSE AMENDMENT REQUEST FOR ADOPTION OF TECHNICAL SPECIFICATION TASK FORCE TRAVELER TSTF-432 REVISION 1, "CHANGE IN TECHNICAL SPECIFICATIONS END STATES (WCAP-16294)"
In accordance with the provisions of Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), [LICENSEE] is submitting a request for an amendment to the Technical Specifications (TS) for [PLANT NAME].
The proposed amendment would modify TS to risk-inform requirements regarding selected Required Action End States.
- Attachment 1 provides an evaluation of the proposed change.
- Attachment 2 provides markup pages of existing TS and TS Bases to show the proposed change.
- Attachment 3 provides revised (clean) TS pages.
[LICENSEE] requests approval of the proposed license amendment by [DATE], with the amendment being implemented [BY DATE OR WITHIN X DAYS].
In accordance with 10 CFR 50.91(a)(1), "Notice for Public Comment," a copy of this application, with attachments, including the analysis about the issue of no significant hazards consideration using the standards in 10 CFR 50.92 is being provided to the Commission in accordance with the distribution requirements in 10 CFR 50.4.
In accordance with 10 CFR 50.91(b)(1), "Notice for Public Comment; State Consultation," a copy of this application and its reasoned analysis about no significant hazards considerations is being provided to the designated [STATE] Official.
I declare [or certify, verify, state] under penalty of perjury that the foregoing is true and correct.
Executed on [date] [Signature]
If you should have any questions regarding this submittal, please contact [NAME, TELEPHONE NUMBER].
Sincerely,
[Name, Title]
Attachments: 1. Evaluation of the Proposed Change
- 2. Proposed Technical Specification and Bases Revisions (Mark-Up)
- 3. Revised Technical Specification Pages cc: [NRC Project Manager]
[NRC Regional Office]
[NRC Resident Inspector]
[State Contact]
ATTACHMENT 1 EVALUATION OF PROPOSED CHANGE License Amendment Request for Adoption of TSTF-432, Revision 1, "Change in Technical Specifications End States (WCAP-16294)"
1.0 DESCRIPTION
The proposed amendment would modify technical specifications to risk-inform requirements regarding selected Required Action End States. The changes are consistent with Technical Specification Task Force (TSTF) Standard Technical Specification (STS) Change Traveler TSTF-432 Revision 1, "Change in Technical Specifications End States (WCAP-16294)." The availability of this TS improvement was announced in the Federal Register on [DATE] ([ ] FR [
]) as part of the consolidated line item improvement process (CLIIP).
2.0 ASSESSMENT 2.1 Applicability of Topical Report, TSTF-432, and Published Safety Evaluation
[LICENSEE] has reviewed Westinghouse Topical Report (TR) WCAP-16294 (Reference 1), the Nuclear Regulatory Commission (NRC) safety evaluation for WCAP-16294 (Reference 2),
TSTF-432, Revision 1 (Reference 3), and the NRC model safety evaluation (Reference 4).
[LICENSEE] has concluded that the technical bases described in the Westinghouse topical report and TSTF-432, as well as the associated safety evaluations prepared by the NRC staff are applicable to [PLANT, UNIT NOS.] and support incorporation of this amendment request into the [PLANT] TS.
2.2 Optional Changes and Variations
[LICENSEE] [is / is not] proposing any variations or deviations from the Westinghouse topical report, the TS changes described in the TSTF-432 Revision 1, or the NRC staffs model safety evaluation published in the Federal Register on [DATE] ([ ] FR [ ]) as part of the CLIIP Notice of Availability. [Discuss any differences with TR WCAP-16294-A or TSTF-432, Revision 1, and the effect of any changes on the NRC staff model SE.]
3.0 REGULATORY ANALYSIS
3.1 No Significant Hazards Consideration Determination
[LICENSEE] has evaluated the proposed changes to the TS using the criteria in 10 CFR 50.92 and has determined that the proposed changes do not involve a significant hazards consideration.
Description of Amendment Request: The proposed amendment would modify TS to risk-inform requirements regarding selected Required Action End States.
As required by 10 CFR 50.91(a), the [LICENSEE] analysis of the issue of no significant hazards consideration is presented below:
- 1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated?
Response: No The proposed change modifies the end state (e.g., mode or other specified condition) which the Required Actions specify must be entered if compliance with the Limiting Conditions for Operation (LCO) is not restored. The requested Technical Specifications (TS) permit an end state of Mode 4 rather than an end state of Mode 5 contained in the current TS. In some cases, other Conditions and Required Actions are revised to implement the proposed change. Required Actions are not an initiator of any accident previously evaluated. Therefore, the proposed change does not affect the probability of any accident previously evaluated. The affected systems continued to be required to be operable by the TS and the Completion Times specified in the TS to restore equipment to operable status or take other remedial Actions remain unchanged. WCAP-16294-NP-A, Rev. 1, "Risk-Informed Evaluation of Changes to Tech Spec Required Action Endstates for Westinghouse NSSS PWRs," demonstrates that the proposed change does not significantly increase the consequences of any accident previously evaluated.
Therefore, the proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.
- 2. Does the proposed change create the possibility of a new or different kind of accident from any accident previously evaluated?
Response: No The proposed change modifies the end state (e.g., mode or other specified condition) which the Required Actions specify must be entered if compliance with the LCO is not restored. In some cases, other Conditions and Required Actions are revised to implement the proposed change. The change does not involve a physical alteration of the plant (i.e., no new or different type of equipment will be installed) or a change in the methods governing normal plant operation. In addition, the change does not impose any new requirements. The change does not alter assumptions made in the safety analysis.
Therefore, the proposed change does not create the possibility of a new or different kind of accident from any accident previously evaluated.
- 3. Does the proposed change involve a significant reduction in a margin of safety?
Response: No The proposed change modifies the end state (e.g., mode or other specified condition) which the Required Actions specify must be entered if compliance with the LCO is not restored. In some cases, other Conditions and Required Actions are revised to implement the proposed change. Remaining within the Applicability of the LCO is acceptable because WCAP-16294-NP-A demonstrates that the plant risk in MODE 4 is similar to or lower than MODE 5.
As a result, no margin of safety is significantly affected.
Therefore, the proposed changes do not involve a significant reduction in a margin of safety.
3.2 Applicable Regulatory Requirements/Criteria A description of the proposed TS change and its relationship to applicable regulatory requirements were published in the Federal Register Notice of Availability on [DATE] ([ ] FR [
]). [LICENSEE] has reviewed the NRC staffs model SE referenced in the CLIIP Notice of Availability and concluded that the regulatory evaluation section is applicable to [PLANT].
4.0 ENVIRONMENTAL EVALUATION The proposed change would change a requirement with respect to installation or use of a facility component located within the restricted area, as defined in 10 CFR Part 20, or would change an inspection or surveillance requirement. However, the proposed change does not involve (i) a significant hazards consideration, (ii) a significant change in the types or significant increase in the amounts of any effluents that may be released offsite, or (iii) a significant increase in individual or cumulative occupational radiation exposure.
Accordingly, the proposed change meets the eligibility criterion for categorical exclusion set forth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the proposed change.
5.0 REFERENCES
- 1. WCAP-16294-NP-A, Revision 1, "Risk-Informed Evaluation of Changes to Technical Specification Required Endstates for Westinghouse NSSS [Nuclear Steam Supply
System] PWRs [Pressurized Water Reactors], June 2010 (NRC ADAMS Accession Number ML052620374)
- 2. Final Safety Evaluation for NEI Topical Report WCAP-16294-NP, Revision 0, "Risk-Informed Evaluation of Changes to Technical Specification Required Endstates for Westinghouse NSSS [Nuclear Steam Supply System] PWRS [Pressurized Water Reactors]," August 2005 (NRC ADAMS Accession Number ML100770146)
- 3. TSTF-432, Revision 1, "Change in Technical Specifications End States WCAP-16294" dated November 29, 2010 (NRC ADAMS Accession number ML103360003)
- 4. Federal Register, ([ ] FR [ ]), "Notice of Availability of the Models for Plant-Specific Adoption of Technical Specifications Task Force Traveler TSTF-432, Revision 1, "Change in Technical Specifications End States (WCAP-16294)" [DATE].