Ltr. LaSalle County Station Confirmation of Initial Operator License Examinations
ML11311A308
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 11/04/2011
From: Hironori Peterson
Operations Branch III
To: Pacilio M
Exelon Generation Co, Exelon Nuclear
loretta.sellers@nrc.gov
References
Download: ML11311A308 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 November 4, 2011 Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

CONFIRMATION OF INITIAL OPERATOR LICENSE EXAMINATIONS:

LASALLE COUNTY STATION

Dear Mr. Pacilio:

We have received your corporate letter RS-11-110, dated June 29, 2011. In that letter, you requested an initial operator licensing examination be scheduled at the LaSalle County Station for October 2016.

In response, we have scheduled an initial operator licensing examination for the weeks of October 24 and 31, 2016, at the LaSalle County Station with an on-site validation scheduled for the week of October 3, 2016.

We note that you were previously scheduled for an initial operator licensing exam the weeks of October 13 and 20, 2014. This date has changed. This exam date is now scheduled for the weeks of October 20 and 27, 2014, with an onsite validation date of September 29, 2014. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and make arrangements to administer the examination at a mutually acceptable date.

We understand that your staff will develop the examinations unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than nine applicants being considered for each of these examinations, the examinations were each scheduled for two weeks. Please inform us if the number of candidates change for any examination as this will impact the examination schedule. Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations.

A supplementary letter will be sent to the training department approximately 120 days prior to the examination informing the training manager of the chief examiners name. The letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the training program.

M. Pacilio In accordance with 10 CFR 2.930 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publically Available Records System (PARS) component of NRCs Agencywide Document Access and Management System (ADAMS), accessible from the NRC Web site at http://ww.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-373; 50-374 License Nos. NPF 11; NPF18 cc:

Distribution via ListServ'

M. Pacilio In accordance with 10 CFR 2.930 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publically Available Records System (PARS) component of NRCs Agencywide Document Access and Management System (ADAMS), accessible from the NRC Web site at http://ww.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-373; 50-374 License Nos. NPF 11; NPF18 cc:

Distribution via ListServ' DISTRIBUTION:

Amy Snyder RidsNrrDorlLpl3-2 Resource RidsNrrPMLaSalle RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource DOCUMENT NAME: G:\\DRSIII\\DRS\\WORK IN PROGRESS\\LTR 110411 LASALLE EXAM 2011.DOCX G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII N

NAME RKWalton:ls HPeterson DATE 10/31/11 11/04/11 OFFICIAL RECORD COPY