UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 1, 2011 Mr. Mark B. Bezilla Site Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Mail Stop A-PY -A290 P.O. Box 97,10 Center Road Perry,OH 44081-0097
SUBJECT:
PERRY NUCLEAR POWER PLANT, UNIT 1 - WITHDRAWAL OF LICENSE AMENDMENT REQUEST (TAC NO. ME7232)
Dear Mr. Allen:
By letter dated October 3, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML112770098), you applied for an amendment for Perry Nuclear Power Plant, Unit 1 (PNPP) Operating License No. NPF-58. The proposed change would revise Technical Specification (TS) 3.8.1, <lAC Sources - Operating," to clarify that a delayed access circuit is temporarily qualified as one of the required otfsite circuits between the otfsite transmission network and the onsite Class 1 E alternating current (AC) electric power distribution system. The proposed change would also add a COMPLETION TIME allowed for circuit restoration if the only OPERABLE otfsite circuit is a delayed access circuit. Subsequently, by letter dated October 11, 2011, you withdrew the amendment request.
The purpose of this letter is to advise that the above-cited application is being treated as withdrawn. Notice of Consideration of Issuance of the proposed amendment had not been published in the Federal Register.
Sincerely.
l 'lJ~tf~V' ichael Mahoney, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440 cc: Distribution via Listserv
November 1, 2011 Mr. Mark B. Bezilla Site Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Mail Stop A-PY -A290 P.O. Box 97, 10 Center Road Perry,OH 44081-0097
SUBJECT:
PERRY NUCLEAR POWER PLANT, UNIT 1 - WITHDRAWAL OF LICENSE AMENDMENT REQUEST (TAC NO. ME7232)
Dear Mr. Allen:
By letter dated October 3, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML112770098), you applied for an amendment for Perry Nuclear Power Plant, Unit 1 (PNPP) Operating License No. NPF-58. The proposed change would revise Technical Specification (TS) 3.8.1, !lAC Sources - Operating, n to clarify that a delayed access circuit is temporarily qualified as one of the required offsite circuits between the offsite transmission network and the onsite Class 1 E alternating current (AC) electric power distribution system. The proposed change would also add a COMPLETION TIME allowed for circuit restoration if the only OPERABLE offsite circuit is a delayed access circuit. Subsequently, by letter dated October 11,2011, you withdrew the amendment request.
The purpose of this letter is to advise that the above-cited application is being treated as withdrawn.
Notice of Consideration of Issuance of the proposed amendment had not been published in the Federal Register.
Docket No. 50-440 cc: Distribution via Listserv Distribution:
PUBLIC LPL3-2 Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDirsltsb Resource RidsNrrDorlDprResource RidsOgcRp Resource ADAMS Accession No ML112920127 Sincerely, IRA by J. Wiebe fori Michael Mahoney, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation RidsNrrDorlLpl3-2 Resource RidsRgn3MailCenter Resource RidsNrrPMPerry Resource RidsNrrLASRohrer Resource NRR-106 IOFFICE i LPL3-2/PM LPL3*2/PM LPL3-2/LA LP3-2/BC INAME PHernandez MMahoney(JWiebe for)
SRohrer JZimmerman DATE 10/20/11 10/27/11 10/19/11 11/01/11