Request for Additional Information Regarding Application for Preemption Authority
ML112700219
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 09/28/2011
From: Boska J
Plant Licensing Branch 1
To:
Entergy Operations
Boska J, NRR/DORL/LPLI-1, 301-415-290
References
TAC ME6164, TAC ME6165
Download: ML112700219 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 28,2011 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511*0249

SUBJECT:

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1. 2, AND 3 - REQUEST FOR ADDITIONAL INFORMATION REGARDING APPLICATION FOR PREEMPTION AUTHORITY (TAC NOS. ME6164 AND ME6165)

Dear Sir or Madam:

By letter dated April 27, 2011, Entergy Nuclear Operations. Inc. (Entergy) submitted an application for preemption authority pursuant to Section 161A of the Atomic Energy Act. as amended, for Indian Point Nuclear Generating Unit Nos. 1. 2, and 3. The preemption authority would allow the use of certain weapons by the security personnel at the Indian Point site.

The Nuclear Regulatory Commission staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific question is found in the enclosed request for additional information (RAt). The Entergy staff stated that a response to the RAI would be provided within 30 days of the date of this letter.

Please contact me at (301) 415-2901 if you have any questions on this issue.

Sincerely.

O:~

hn P. Boska. Senior Project Manager

~

lant licenSing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.50-003, 50-247. and 50-286

Enclosure:

As stated cc w/encl: Distribution via Listserv

REQUEST FOR ADDITIONAL INFORMATION (RAI)

REGARDING PREEMPTION AUTHORITY ENTERGY NUCLEAR OPERATIONS. INC.

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1. 2, AND 3 DOCKET NOS.50-003, 50-247, AND 50-286 By letter dated April 27, 2011 (Agencywide Documents Access and Management System Accession No. ML11124A075), Entergy Nuclear Operations, Inc. (Entergy) submitted an application for preemption authority pursuant to Section 161A of the Atomic Energy Act, as amended, for Indian Point Nuclear Generating Unit Nos. 1, 2, and 3. The preemption authority would allow the use of certain weapons by the security personnel at the Indian Point site.

The Nuclear Regulatory Commission (NRC) staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific question is found below.

1.

Describe the impact on Indian Point's current physical protection program and capabilities, including response capabilities, if the NRC were to elect not to grant stand alone preemption authority to Indian Point.

Enclosure

September 28, 2011 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O, Box 249 Buchanan, NY 10511-0249

SUBJECT:

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1, 2, AND 3 - REQUEST FOR ADDITIONAL INFORMATION REGARDING APPLICATION FOR PREEMPTION AUTHORITY (TAC NOS, ME6164 AND ME6165)

Dear Sir or Madam:

By letter dated April 27, 2011, Entergy Nuclear Operations, Inc. (Entergy) submitted an application for preemption authority pursuant to Section 161A of the Atomic Energy Act, as amended, for Indian Point Nuclear Generating Unit Nos, 1, 2, and 3. The preemption authority would allow the use of certain weapons by the security personnel at the Indian Point site.

The Nuclear Regulatory Commission staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific questions are found in the enclosed request for additional information (RAI). The Entergy staff stated that a response to the RAI would be provided within 30 days of the date of this letter.

Please contact me at (301) 415-2901 if you have any questions on this issue.

Sincerely,

/ra/

John P. Boska, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos,50-003, 50-247, and 50-286

Enclosure:

As stated cc wlencl: Distribution via Listserv DISTRIBUTION:

RidsNrrDorlLpl1-1 RidsNrrPMJBoska PUBLIC LPL1-1 Reading File RidsNrrLASUttle RidsAcrsAcnw _MaiICTR RidsNrrDorlDpr RidsRgn1 MailCenter DGordon ARoundtree BSchnetzler RidsOGCRp NStAmour ADAMS ACCESSION NO'.. ML112700219

    • Via email OFFICE NRRIDORL NRR/DORL NSIR/DSP/RSLB**

NRR/DORL LPL 1-1/PM LPL 1-1/LA LPL1-1/BC NAME JBoska SUttle BSchnetzler NSalgado DATE 9/28/11 9/28/11 9/28/11 9/28/11 OFFICIAL RECORD COPY