Reactor Vessel Internals License Amendment Request Status Update License Amendment Request (LAR) No. 2010-06
ML11251A160
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 09/01/2011
From: Gillespie T
Duke Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LAR 2010-06
Download: ML11251A160 (2)


Text

T. PRESTON GILLESPIE, JR.

Vice President Energy, Oconee Nuclear Station Duke Energy ONO1 VP/ 7800 Rochester Hwy.

Seneca, SC 29672 864-873-4478 864-873-4208 fax September 1, 2011 T.Gillespie@duke-energy.com ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Subject:

Duke Energy Carolinas, LLC Oconee Nuclear Station, Units 1, 2, and 3 Docket Numbers 50-269, 50-270, and 50-287 Reactor Vessel Internals License Amendment Request Status Update License Amendment Request (LAR) No. 2010-06 On July 25, 2011, a conference call was held between Duke Energy Carolinas, LLC (Duke Energy) and the Nuclear Regulatory Commission (NRC) to discuss the status of License Amendment Request (LAR) 2010-06, "Proposed License Amendment Request for the Reactor Vessel Internals Inspection Plan." This LAR provides Oconee Nuclear Station's Reactor Vessel (RV) Internals Inspection Plan report and also provides a description of the inspection plan as it relates to the management of aging effects consistent with previous commitments.

As an action from this call, Duke Energy will submit a revision to LAR No. 2010-06 following a revision to Electric Power Research Institute's (EPRI's) materials reliability report titled, "Pressurized Water Reactor Internals Inspection and Evaluation Guidelines (MRP-227, Revision 0)." The need for the LAR revision is to comply with: (1) the changes associated with the aforementioned EPRI report and (2) the NRC's Regulatory Issue Summary (RIS) 2011-07.

Duke Energy will submit the revised LAR 90 days after the issuance of the revised EPRI report (MRP-227-A), but no later than October 1, 2012. Because Duke Energy anticipates the majority of the sections in the original LAR will require rework, Duke Energy does not recommend the NRC review the original submittal at this time.

If there are any questions regarding this letter, please contact Stephen C. Newman, Oconee Regulatory Compliance Group, at (864) 873-4388.

Sincerely, T. Preston Gillespie. Jr.,

Vice President, Oconee Nuclear Station A c)j www. duke-energy.corn

U. S. Nuclear Regulatory Commission September 1,2011 Page 2 cc:

V. M. McCree, Administrator, Region II U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 J. F. Stang, Senior Project Manager (ONS)

U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Mail Stop 8G9A Washington, DC 20555-0001 A. T. Sabisch, Senior Resident Inspector U.S. Nuclear Regulatory Commission Oconee Nuclear Station S. E. Jenkins, Manager Division of Radioactive Waste Management Bureau of Land and Waste Management Department of Health and Environmental Control 2600 Bull Street Columbia, SC 29201