MONTHYEARML1116001802011-06-0808 June 2011 License Amendment Request - Safety Limit Minimum Critical Power Ratio Change Project stage: Request ML1115908872011-06-0808 June 2011 Submittal of 10 CFR 26.719(c) Report, Unsatisfactory Laboratory Performance Tests Project stage: Request ML1118904382011-07-0808 July 2011 Acceptance Review for Peach Bottom U3 SLMCPR License Amendment Request Project stage: Acceptance Review ML1118600362011-07-27027 July 2011 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML1121504512011-07-29029 July 2011 SLMCPR RAIs Project stage: Other ML1121504002011-07-29029 July 2011 SLMCPR LAR Draft RAIs (ME6391) Project stage: Draft RAI ML1118600542011-08-18018 August 2011 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination and Opportunity for Hearing Project stage: Other ML1124505092011-09-0202 September 2011 Draft Request for Additional Information, Related to License Amendment Request for Technical Specification Changes to Safety Limit Minimum Critical Power Ratio Values Project stage: Draft RAI ML1124503962011-09-0202 September 2011 Draft RAIs SLMCPR Project stage: Draft RAI ML1118600152011-09-30030 September 2011 Issuance of Amendment Safety Limit Minimum Critical Power Ratio Value Change Project stage: Approval ML1129114102011-10-24024 October 2011 Correction Letter for Peach Bottom Atomic Power Station, Unit 3 - Safety Evaluation Regarding Safety Limit Minimum Critical Power Ratio Value Change Project stage: Approval ML1123718732011-10-25025 October 2011 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML1126301412011-10-25025 October 2011 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2011-07-29
[Table View] |
Text
From:
Hughey, John Sent:
Friday, September 02, 2011 1:47 PM To:
'thomas.loomis@exeloncorp.com'
Subject:
Draft RAIs for Peach Bottom SLMCPR LAR (ME6391)
Attachments:
3rd Draft RAI.docx Importance:
High
- Tom, Please find attached a Draft Request for Additional Information related to the Peach Bottom Unit 3 SLMCPR license amendment request. Please contact me by Tuesday, 9/6/2011, to advise if Exelon would like to have a teleconference scheduled to discuss the questions.
Thank you, John John Hughey Peach Bottom Project Manager NRR / Division of Operating Reactor Licensing Phone: 301-415-3204 e-mail: John.Hughey@nrc.gov