Text

September 1, 2011

Mr. R. Vice President, Nuclear Licensing Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801

SUBJECT: MID-CYCLE LETTER FOR SEQUOYAH NUCLEAR PLANT UNITS 1 AND 2 (NRC INSPECTION REPORT 05000327 and 328/2011008)

Dear Mr. Krich:

On August 11, 2011, the NRC completed its mid-cycle performance review of the Sequoyah Nuclear Plant Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2010 through June 30, 2011. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRC's assessment of your performance in the Security Cornerstone and its security-related inspection plan. The NRC determined the performance at the Sequoyah Nuclear Plant Unit 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2012. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. We also plan on conducting an initial license exam at your facility in January, 2012.

TVA 2 In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRC's processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (TI) 183, "Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event," and TI-184, "Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs)" at your facility. Results of these inspections can be found here: http://www.nrc.gov/japan/japan-activities.html. Additionally, on May 11, 2011, the agency issued NRC Bulletin 2011-01, "Mitigating Strategies," to confirm compliance with Order EA-02-

026, subsequently imposed license conditions, and 10 CFR 50.54(hh)(2), and to determine the status of licensee mitigating strategies programs. On July 12, 2011, the NRC's Task Force made its recommendations to the Commission in its report, "Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident." The NRC is currently reviewing the Task Force's recommendations to determine what additional actions may be warranted.

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 404-997-4521 with any questions you have regarding this letter.

Sincerely,/RA/ Scott M. Shaeffer, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-327, 50-328 License Nos.: DPR-77, DPR-79

Enclosure:

Sequoyah Inspection/Activity Plan cc w/encl: (See page 3)

TVA 2 In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRC's processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (TI) 183, "Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event," and TI-184, "Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs)" at your facility. Results of these inspections can be found here: http://www.nrc.gov/japan/japan-activities.html. Additionally, on May 11, 2011, the agency issued NRC Bulletin 2011-01, "Mitigating Strategies," to confirm compliance with Order EA-02-

026, subsequently imposed license conditions, and 10 CFR 50.54(hh)(2), and to determine the status of licensee mitigating strategies programs. On July 12, 2011, the NRC's Task Force made its recommendations to the Commission in its report, "Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident." The NRC is currently reviewing the Task Force's recommendations to determine what additional actions may be warranted.

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 404-997-4521 with any questions you have regarding this letter.

Sincerely,/RA/ Scott M. Shaeffer, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-327, 50-328 License Nos.: DPR-77, DPR-79

Enclosure:

Sequoyah Inspection/Activity Plan cc w/encl: (See page 3) X PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE ADAMS: G Yes ACCESSION NUMBER:______ML112440179__________ X SUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP SIGNATURE JDH /RA/ SMS /RA/ NAME JHamman SShaeffer DATE 08/31/2011 09/01/2011 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL RECORD COPY DOCUMENT NAME: S:\DRP\PERIODIC ASSESSMENTS & REPORTS\EOC & MID-CYCLE\2011\MID-CYCLE\INPUT\RPB6\SEQUOYAH 2011 MID CYCLE LETTER.DOCX TVA 3 cc w/encl:

J. T. Carlin Site Vice President Sequoyah Nuclear Plant Tennessee Valley Authority Electronic Mail Distribution K. Langdon Plant Manager Sequoyah Nuclear Plant Tennessee Valley Authority Electronic Mail Distribution G. M. Cook Manager Licensing Sequoyah Nuclear Plant Electronic Mail Distribution Dan Green Manager, Corp. Nuclear Licensing - SQN Tennessee Valley Authority Electronic Mail Distribution E. J. Vigluicci Assistant General Counsel Tennessee Valley Authority Electronic Mail Distribution County Mayor Hamilton County Hamilton County Courthouse 208 Courthouse 625 Georgia Avenue Chattanooga, TN 37402-2801 Tennessee Department of Environment & Conservation Division of Radiological Health 401 Church Street Nashville, TN 37243 Ann Harris 341 Swing Loop Rockwood, TN 37854 TVA 4 Letter to R. from Scott M. Shaeffer dated September 1, 2011

SUBJECT: MID-CYCLE LETTER FOR SEQUOYAH NUCLEAR PLANT UNITS 1 AND 2 (NRC INSPECTION REPORT 05000327 and 328/2011008) Distribution w/encl: C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMSequoyah Resource ROP Assessment