Oconee Tube Leak Chapter 14.0 B&W Cross Training Course 1
B&W Cross-Training Course R-326C
OBJECTIVES
- 1. List the symptoms of a steam generator tube leak.
- 2. Describe the actions that should be taken if the tube leakage exceeds technical specification limits.
p
- 3. List three actions that can be taken to minimize offsite releases during steam generator tube leakage events.
Appendix - Sequence of Events
Appendix - Sequence of Events
Appendix - Sequence of Events
Appendix - Sequence of Events
Pressure and OTSG Levels Fig. 14-1
System Temperature (Fig. 14-2)
Oconee 2 Main Steam System (Fig. 14-3)
Oconee 2 Condensate and Feed System Fig. 14-4