Commitment to Submit a License Amendment Request to Transition to 10 CFR, Part 50, Section 50.48(c), National Fire Protection Assoc. Standard NFPA 805, and Request to Extend Enforcement Discretion(ME6606, ME6607)
ML11201A193
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 07/28/2011
From: Gitter J
Plant Licensing Branch II
To: Repko R
Duke Energy Carolinas
Thompson J
References
TAC ME6606, TAC ME6607
Download: ML11201A193 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 28, 2011 Mr. Regis T. Repko Vice President McGuire Nuclear Station Duke Energy Carolinas, LLC 12700 Hagers Ferry Road Huntersville, NC 28078

SUBJECT:

MCGUIRE NUCLEAR STATION, UNITS 1 AND 2 - COMMITMENT TO SUBMIT A LICENSE AMENDMENT REQUEST TO TRANSITION TO TITLE 10 OF THE CODE OF FEDERAL REGULA TlONS (10 CFR), PART 50, SECTION 50.48(c),

NATIONAL FIRE PROTECTION ASSOCIATION STANDARD NFPA 805, AND REQUEST TO EXTEND ENFORCEMENT DISCRETION - (TAC NOS. ME6606 AND ME6607)

Dear Mr. Repko:

By letter to the Nuclear Regulatory Commission (NRC) dated June 23, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML11188A175), Duke Energy Carolinas, LLC, (1) committed to submit a license amendment request (LAR) by September 30, 2013, to transition to National Fire Protection Association Standard NFPA 805 in accordance with 10 CFR 50.48( c), and (2) requested that enforcement discretion for fire protection issues be extended to correspond with the LAR submittal date.

The NRC staff has reviewed your letter and finds it consistent with Commission direction as provided in SRM-SECY-11-0061, dated June 10, 2011 (ADAMS Accession No. ML111610616).

Therefore, your request to extend enforcement discretion is granted in accordance with the Interim Enforcement Policy concerning Enforcement Discretion for Certain Fire Protection Issues as published in the Federal Register (FR) on July 12, 2011 (76 FR 40777).

R. Repko

- 2 If you are unable to meet the above LAR submittal date, you are requested to contact the NRC staff at least 90 days in advance. Please contact Jon H. Thompson, 301-415-1119, if you have any questions.

Sincerely,

~ Joseph G. Giitter, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-369 and 50-370 cc: Distribution via Listserv

ML11201A193 NRR-106 OFFICE LPL2-1/PM LPL2-1/LA DRNAFPB/BC DRNAPLAlBC LPL2-1/BC DORUD GKulesa JGiitter NAME JThompson MO'Brien AKlein DHarrison (LLund for)