Commitment to Submit a License Amendment Request to Transition to 10 CFR 50.48(c), National Fire Protection Association Standard (NFPA) 805, and Request to Extend Enforcement Discretion
ML11201A007
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 08/08/2011
From: Giitter J
Division of Operating Reactor Licensing
To: Duncan R
Carolina Power & Light Co
Saba F
References
TAC ME6658
Download: ML11201A007 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 August 8, 2011 Mr. Robert J. Duncan II, Vice President H. B. Robinson Steam Electric Plant, Unit No.2 Carolina Power &Light Company 3581 West Entrance Road Hartsville, South Carolina 29550-0790

SUBJECT:

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT 2 - COMMITMENT TO SUBMIT A LICENSE AMENDMENT REQUEST TO TRANSITION TO 10 CFR 50.48(c), NATIONAL FIRE PROTECTION ASSOCIATION STANDARD (NFPA) 805, AND REQUEST TO EXTEND ENFORCEMENT DISCRETION (TAC NO. ME6658)

Dear Mr. Duncan:

By letter to the Nuclear Regulatory Commission (NRC, Commission) dated June 29,2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML11188A058), Carolina Power & Light Company: (1) committed to submit a license amendment request (LAR) by September 30, 2013, to transition to National Fire Protection Association Standard NFPA 805 in accordance with Title 10 of the Code of Federal Regulations 50.48(c), and (2) requested that enforcement discretion for fire protection issues be extended to correspond with the LAR submittal date.

The NRC Staff has reviewed your letter and finds it consistent with Commission direction as provided in SRM-SECY-11-0061, dated June 10, 2011 (ADAMS Accession No. ML111610616).

Therefore, your request to extend enforcement discretion is granted in accordance with the Interim Enforcement Policy concerning Enforcement Discretion for Certain Fire Protection Issues as published in the Federal Register on July 12, 2011 (76 FR 40777).

If you are unable to meet the above LAR submittal date, you are requested to contact the NRC staff at least 90 days in advance. Please contact Brenda Mozafari at 301-415-2020, if you have any questions.

Sincerely,

~

<1.~

o eph G. Giitter, Director vision of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-400 cc: Distribution via Listserv

ML111610616).

Therefore, your request to extend enforcement discretion is granted in accordance with the Interim Enforcement Policy concerning Enforcement Discretion for Certain Fire Protection Issues as published in the Federal Register on July 12, 2011 (76 FR 40777).

If you are unable to meet the above LAR submittal date, you are requested to contact the NRC staff at least 90 days in advance. Please contact Brenda Mozafari at 301-415-2020, if you have any questions.

Sincerely, IRA!

Joseph G. Giitter, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-400 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsOeMailCenter RidsNrrPMRobinson Lp12-2 Reading File RidsOgcRp RidsNrrLACSola RidsAcrsAcnw MailCTR RidsRgn2MailCenter RidsNrrDorlLpl2-2 RidsNrrDorl PLain, NRR/DRAlAFPB GGulla,OE RidsNrrDra HBarrett, NRR/DRAlAFPB JDozier, NRRlDRAlAPLA RidsNrrDraAfpb RidsNrrDraApla DPickett, NRR/DORL ADAMS Accession No ML11201A007

  • OFFICE LPL2-2/PM LPL2-2/LA DRAlAFPB/BC DRAlAPLAlBC NAME I BMozafari CSoia AKlein DHarrison DATE 07/20/11 07/20/11 07/25/11 07/26/11 LPL2-2/BC DORUD

~

DBroaddus JGiitter 08/04/11 08/08/11