Commitment to Submit a License Amendment Request to Transition to 10 CFR 50.48(c), National Fire Protection Association Standard NFPA 805, and Request to Extend Enforcement Discretion (TAC ME6655 & ME6656)
ML11201A005
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 08/08/2011
From: Giitter J
Division of Operating Reactor Licensing
To: Annaccone M
Carolina Power & Light Co
Saba, Farideh
References
TAC ME6655, TAC ME6656
Download: ML11201A005 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 8, 2011 Mr. Michael J. Annacone, Vice President Brunswick Steam Electric Plant Carolina Power &Light Company Post Office Box 10429 Southport, North Carolina 28461 f

SUB~IECT: BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 - COMMITMENT TO SUBMIT A LICENSE AMENDMENT REQUEST TO TRANSITION TO 10 CFR 50.48(c), NATIONAL FIRE PROTECTION ASSOCIATION STANDARD NFPA 805, AND REQUEST TO EXTEND ENFORCEMENT DISCRETION (TAC NOS.

ME6655 AND ME6656)

Dear Mr. Annacone:

By letter to the Nuclear Regulatory Commission (NRC, Commission) dated June 29,2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML11188A058), Carolina Power & Light Company: (1) committed to submit a license amendment request (LAR) by September 30,2012, to transition to National Fire Protection Association Standard (NFPA) 805 in accordance with Title 10 of the Code of Federal Regulations 50.48(c), and (2) requested that enforcement discretion for fire protection issues be extended to correspond with the LAR submittal date.

The NRC Staff has reviewed your letter and finds it consistent with Commission direction as provided in SRM-SECY-11-0061, dated June 10,2011 (ADAMS Accession No. ML111610616).

Therefore, your request to extend enforcement discretion is granted in accordance with the Interim Enforcement Policy concerning Enforcement Discretion for Certain Fire Protection Issues as published in the Federal Register on July 12, 2011 (76 FR 40777).

If you are unable to meet the above LAR submittal date, you are requested to contact the NRC staff at least 90 days in advance. Please contact Farideh Saba at 301-415-1447, if you have any questions.

Sincerely,

~.~

Jo eph G. Giitter, Director

. ision of Operating Reactor Licensing Office of Nuclear Reactor Regulation

~

Docket Nos. 50-325 and 50-324 cc: Distribution via Listserv

ML111610616).

Therefore, your request to extend enforcement discretion is granted in accordance with the Interim Enforcement Policy concerning Enforcement Discretion for Certain Fire Protection Issues as published in the Federal Register on July 12, 2011 (76 FR 40777).

If you are unable to meet the above LAR submittal date, you are requested to contact the NRC staff at least 90 days in advance. Please contact Farideh Saba at 301-415-1447, if you have any questions.

Sincerely,

/RA/

Joseph G. Giitter, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-325 and 50-324 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsOeMailCenter RidsNrrPMBrunswick Lpl2-2 Reading File RidsOgcRp RidsNrrLACSola RidsAcrsAcnw_MailCTR RidsRgn2MailCenter RidsNrrDorlLpl2-2 RidsNrrDorl PLain, NRR/DRA/AFPB GGulla, OE RidsNrrDra HBarrett, NRR/DRA/AFPB JDozier, NRR/DRA/APLA RidsNrrDraAfpb RidsNrrDraApla DPickett, NRR/DORL ADAMS Accession No. ML11201A005 OFFICE LPL2-2/PM LPL2-2/LA DRA/AFPB/BC DRA/APLA/BC NAME FSaba (BMozafari for)

CSola AKlein DHarrison DATE 07/20/11 07/20/11 07/25/11 07/26/11 OFFICE LPL2-2/BC DORL/D NAME DBroaddus JGiitter DATE 08/04/11 08/08/11