NRR E-mail Capture - Acceptance Review: Turkey Point Units 3 and 4: Technical Specification Changes Regarding Section 5.0 Design Features LAR
ML11200A045
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 07/19/2011
From: Jason Paige
Plant Licensing Branch II
To: Czaya P, Hanek O, Tomonto B
Florida Power & Light Co
References
TAC ME6334, TAC ME6335
Download: ML11200A045 (2)


Text

1 NRR-PMDAPEm Resource From:

Paige, Jason Sent:

Tuesday, July 19, 2011 10:36 AM To:

Czaya, Paul; Hanek, Olga; Tomonto, Bob

Subject:

ACCEPTANCE REVIEW: TURKEY POINT UNITS 3 AND 4: TECHNICAL SPECIFICATION CHANGES REGARDING SECTION 5.0 DESIGN FEATURES LAR (TAC NOS. ME6334 AND ME6335)

SUBJECT:

TECHNICAL SPECIFICATION CHANGES REGARDING SECTION 5.0 DESIGN FEATURES

Bob, By letter dated May 25, 2011, Florida Power & Light Company submitted a license amendment for Turkey Point, Units 3 and 4. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

If you have any questions, please contact me.

Jason Paige, Turkey Point Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation US Nuclear Regulatory Commission Phone: (301) 415-5888

Hearing Identifier:

NRR_PMDA Email Number:

106 Mail Envelope Properties (Jason.Paige@nrc.gov20110719103600)

Subject:

ACCEPTANCE REVIEW: TURKEY POINT UNITS 3 AND 4: TECHNICAL SPECIFICATION CHANGES REGARDING SECTION 5.0 DESIGN FEATURES LAR (TAC NOS.

ME6334 AND ME6335)

Sent Date:

7/19/2011 10:36:23 AM Received Date:

7/19/2011 10:36:00 AM From:

Paige, Jason Created By:

Jason.Paige@nrc.gov Recipients:

"Czaya, Paul" <Paul.Czaya@fpl.com>

Tracking Status: None "Hanek, Olga" <Olga.Hanek@fpl.com>

Tracking Status: None "Tomonto, Bob" <Bob.Tomonto@fpl.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 1833 7/19/2011 10:36:00 AM Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received: