MONTHYEARNL-11-0280, License Amendment Request for Steam Generator Water Level High-High Setpoint Change2011-03-0303 March 2011 License Amendment Request for Steam Generator Water Level High-High Setpoint Change Project stage: Request ML1108800402011-03-28028 March 2011 Email Acceptance Review for License Application NL-11-0280 Steam Generator Water Level Hi-Hi Setpoint Change Project stage: Acceptance Review ML11097A0062011-05-18018 May 2011 Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed NSHC Determination, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI Project stage: Request ML11103A0682011-05-18018 May 2011 (Vogtle 1 and 2) - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance NRC-2011-0111, Vogtle Units 1 and 2 (Vegp) - Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed NSHC Determination, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI2011-05-19019 May 2011 Vogtle Units 1 and 2 (Vegp) - Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed NSHC Determination, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI Project stage: Approval ML11097A0052011-05-19019 May 2011 (VEGP) - Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed NSHC Determination, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI Project stage: Other ML11158A2562011-06-15015 June 2011 Request for Additional Information, Steam Generator Water Level High-High Sp Change Technical Specification Table 3.3.2.1 TSTF-493-A Project stage: RAI ML11193A0032011-07-18018 July 2011 Request for Additional Information, Steam Generator Water Level High-High Setpoint Change Technical Specification Table 3.3.2.1 Technical Specifications Task Force-493-A Project stage: RAI NL-11-1559, NRC Request for Additional Information for License Amendment Request for Steam Generator Water Level High-High (P-14) Setpoint Change2011-08-12012 August 2011 NRC Request for Additional Information for License Amendment Request for Steam Generator Water Level High-High (P-14) Setpoint Change Project stage: Request ML11252A9012011-09-21021 September 2011 Request for Additional Information, Steam Generator Water Level High-High Setpoint Change Technical Specification Table 3.3.2.1 Technical Specifications Task Force-493-A Project stage: RAI NL-11-2279, Response to NRC Request for Additional Information for License Amendment Request for Steam Generator Water Level High (P-14) Setpoint Change2011-12-0909 December 2011 Response to NRC Request for Additional Information for License Amendment Request for Steam Generator Water Level High (P-14) Setpoint Change Project stage: Response to RAI ML11355A1182012-01-12012 January 2012 Request for Withholding Information from Public Disclosure for Vogtle Electric Generating Plant, Units 1 and 2 Project stage: Withholding Request Acceptance ML12033A1262012-02-27027 February 2012 Issuance of Amendments Regarding Steam Generator Water Level High-High Technical Specification, Table 3.3.1-1 and Table 3.3.2-1 Setpoint Changes Project stage: Approval 2011-06-15
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 18, 2011 Mr. M. J. Ajluni Nuclear licensing Director Southern Nuclear Operating Company, Inc.
40 Inverness Center Parkway Post Office Box 1295, Bin - 038 Birmingham, AL 35201-1295
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION (RAI), STEAM GENERATOR (SG) WATER LEVEL HIGH-HIGH SETPOINT CHANGE TECHNICAL SPECIFICATION (TS) TABLE 3.3.2.1 TS TASK FORCE-493-A (TAC NOS. ME5778 AND ME5779)
Dear Mr. Ajluni:
By letter dated March 3, 2011 (Agencywide Documents Access and Management System (ADAMS), Accession No. ML110660458), Southern Nuclear Operating Company, Inc. (SNC, the licensee). submitted a license amendment request to change the TSs for Vogtle Electric Generating Plant (Vogtle), Units 1 and 2. The amendment would revise a nonconservative error discovered in the Engineered Safety Feature Permissive P-14, SG Water Level High-High instrument setpoint and associated allowable value. The proposed change will also resolve operability determination issues associated with potentially non conservative TSs Allowable Values. This TS change incorporates the corrected nominal trip setpoint and allowable value in TS Table 3.3.2.1. "Engineered Safety Feature Actuation System Instrumentation," for Function 5c, SG Water Level High-High.
On June 15, 2011, the Nuclear Regulatory Commission (NRC) sent an RAI (ADAMS Accession No. ML11158A256) to SNC. Upon receipt of the letter SNC requested a conference call with the NRC, Westinghouse and licensing personnel from SNC to clarify the questions in the RAI.
The conference call was conducted on July 7, 2011. Subsequent to the call SNC requested an additional 30 days to respond to the RAI.
M. Ajluni
- 2 This letter authorizes an additional 30 calendar days for a total of 60 days, from June 15, 2011, to respond to the RAI.
Sincerely, Patrick G. Boyle, Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-424 and 50-425 cc: Distribution via Listserv
' ML11193A003 OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/LPL2-1/BC NRR/LPL2-1/PM NAME PBoyle MOBrien GKulesa (RMartin for)
PBoyle DATE 7/13/11 7/11/11 7/15/11 7/18/11