UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 29, 2011 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR MILLSTONE POWER STATION, UNIT NO.3 (TAC NO. 5389)

Dear Mr. Heacock:

By letter dated January 20,2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML110280208) Dominion Nuclear Connecticut, Inc. (DNC) submitted a license amendment request for temporary alternate repair criteria (H*) at Millstone Power Station, Unit NO.3 (MPS3). As part of the request, DNC submitted affidavit CAW-10-3003, dated November 8, 2010, executed by J. A. Gresham, Manager, Regulatory Compliance and Plant Licensing, Nuclear Services, Westinghouse Electric Company LLC (Westinghouse),

requesting that the information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:

WCAP-17330-P, Revision 0, "H*: Resolution of NRC Technical Issue Regarding Tubesheet Bore EccentriCity (Model F/Model D5)," dated November 2010 (Proprietary).

A nonproprietary copy of this document has been placed in the NRC's Public Document Room and added to the ADAMS Public Electronic Reading Room (ADAMS Accession No. ML110280213).

The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:

(a) The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouse's competitors without license from Westinghouse constitutes a competitive economic advantage over other companies.

(c) Its use by competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.

(e) It reveals aspects of past, present, or future Westinghouse or customer funded development plans and programs of potential commercial value to Westinghouse.

D. Heacock - 2 We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the Nuclear Regulatory Commission (NRC). You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at 301-415-1603.

Sincerely,

~nJ.~~, proj~r Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-423 cc:

J. A. Gresham Manager, Regulatory Compliance and Plant Licensing Westinghouse Electric Company LLC P.O. Box 355 Pittsburgh, PA 15230-0355 Additional Distribution via Listserv

ML ML111671993 OFFICE DORULPL1-2/PM DORULPL 1-2/LA DCIICSGB/BC DORULPL 1-2/BC NAME CSanders ABaxter RTaylor (EMurphy for) HChernoff DATE 6/27/11 6/27/11 6/29/11 6/29/11