MONTHYEARML24022A2592024-01-22022 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Revise TS LCO 3.8.2 to Remove Note C-S Diesel Generator ML24016A0762024-01-16016 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2 - License Amendment Request to Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications ML23347A0642023-12-13013 December 2023 12-13-23 Email from Kimberly Green to Wells, Russell, Subject: Results of NRC SUNSI Review of Watts Bar Nuclear Plant Dual-Unit UFSAR, Amendment 5 ML23334A0932023-11-28028 November 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate During Mode 6 ML23319A1662023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant, Exemption Request Related to 10 CFR 37.11(c)(2) ML23254A2872023-09-11011 September 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Table 1.1-1 Re Number of Required Rvh Closure Bolts ML23236A2562023-08-24024 August 2023 NRR E-mail Capture - Acceptance Review Results for the Sequoyah and Watts Bar License Amendment Request to Adopt TSTF-567 (L-2023-LLA-0106) ML23191A8672023-07-10010 July 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23150A2472023-05-25025 May 2023 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23116A1492023-04-21021 April 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23075A0032023-03-13013 March 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1, 2, and 3, License Amendment Request to Revise TS 3.7.11, Required Actions A.1 and E.1 Footnotes Re Date for the Modification ML23072A0722023-03-10010 March 2023 NRR E-mail Capture - (External_Sender) State Consultation - Sequoyah Nuclear Plant, Units 1 and 2; and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23013A0382023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML23013A0362023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22356A2982022-12-22022 December 2022 Email Response to Letter, Dated November 22, 2022 Regarding Watts Bar Integrated Inspection Report ML22353A0812022-12-15015 December 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 2, Alternative Request WBN-2-ISI-01 Regarding Examination of Upper Head Injection Nozzle Dissimilar Metal Piping Butt Welds ML22348A0972022-12-14014 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML22348A0442022-12-13013 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0712022-08-15015 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 (EPID L-2022-LLA-0103) - Corrected ML22227A0262022-08-12012 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22215A2752022-08-0303 August 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-554 ML22194A8762022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-529 ML22166A4292022-06-0606 June 2022 NRR E-mail Capture - LAR to Adopt TSTF-577 ML22146A3342022-05-25025 May 2022 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Relief Requests (EPID L-2022-LLR-0045 - 0047) ML22136A0182022-05-16016 May 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, Alternative Request RP-11 and Watts Bar Nuclear Plant, Units 1 and 2, Alternative Request IST-RR-9 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML22123A1812022-05-0303 May 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-577 ML22115A1402022-04-25025 April 2022 NRR E-mail Capture - Requests for Confirmation of Information and Additional Information Regarding Watts Bar Nuclear Plant, Unit 2 Exemption Request Re 10 CFR Part 26 (L-2022-LLE-0017) ML22083A2372022-03-24024 March 2022 NRR E-mail Capture - Request for Additional Information and Confirmation of Information Related to Tva'S Request for Changes to Watts Bar Nuclear Plant, Units 1 and 2, Technical Specification 3.7.8 ML22081A2222022-03-22022 March 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 1, License Amendment Request to Revise Allowable Value for TS Table 3.3.2-1, Function 6.e(1) ML22056A3802022-02-25025 February 2022 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-02 ML22131A1902022-02-23023 February 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 2, Request to Revise the Reactor Vessel Surveillance Capsule Withdrawal Schedule ML22046A0392022-02-15015 February 2022 NRR E-mail Capture - Request for Confirmation of Information Regarding the Watts Bar Nuclear Plant, Unit 2, Cycle 4 Mid-Cycle Outage Generic Letter 95-05 Final Report ML22038A1882022-02-0404 February 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Revise the TVA Radiological Emergency Plan ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22011A0382022-01-10010 January 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-205-A, Rev. 3 and TSTF-563-A ML21306A2452021-11-0202 November 2021 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.7.8, Essential Raw Cooling Water (ERCW) System ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar ML21252A0912021-09-0909 September 2021 NRR E-mail Capture - Request for Comments on Proposed Issuance of Amendments to Watts Bar Nuclear Plant, Unit 2 - Revise Steam Generator Secondary Side Water Level ML21223A2592021-08-11011 August 2021 Affidavit - Prop Slides - Partially Closed Meeting with TVA Potential Watts Bar, Unit 2 Tube Locking LAR ML21221A2602021-08-0909 August 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Watts Bar, Unit 1 Tech Specs Related to Continuous Opening of the Auxiliary Building Secondary Containment Enclosure Boundary ML21215A1152021-07-26026 July 2021 NRR E-mail Capture - (External_Sender) Correction to WBN Chiller Replacement LAR ML21215A1142021-07-26026 July 2021 NRR E-mail Capture - (External_Sender) Correction to WBN Chiller Replacement LAR ML21197A0452021-07-15015 July 2021 WBN U1 Isi/Sgisi Request for Information (RFI) Letter ML21193A2422021-07-12012 July 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar Nuclear Plant, Unit 2 Technical Specifications Related to Steam Generator Inspection/Repair Program Provisions ML21189A0202021-06-29029 June 2021 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specifications 3.3.6 and 3.3.7 Re Radiation Monitor Redundant Unit of Measure 2024-01-22
[Table view] |
Text
WBN2Public Resource From: Poole, Justin Sent: Tuesday, May 31, 2011 8:53 AM To: Epperson, Dan Cc: WBN2HearingFile Resource
Subject:
FW: Bucket List 6/2/11 Attachments: NRC PM Open Items List 6-2-11.docx From: Crouch, William D [1]
Sent: Tuesday, May 31, 2011 7:06 AM To: Poole, Justin; Milano, Patrick; Campbell, Stephen Cc: Adair, James G; Arent, Gordon; Beach, Charles D; Bryan, Robert H Jr; Detchemendy, Thomas F; Elliott, Walter L Jr; Elton, Thomas L; Freeman, Edwin E; Glover, Christopher Edmund; Helms, Douglas F; Hemmer, Gerald L Jr; Henrich, Nolan T Jr; Hilmes, Steven A; Johnson, Robert M; Jones, Dennis Michael; Knuettel, Edward Terry; Koontz, Frank A Jr; Metzler, Ernest Thomas; Miller, Lee R; Olson, Peter Edwin; Riedl, Christopher John; Schlessel, Jerry V; Shea, Joe; Smith, James D; Snyder, Laura L; Spink, Thomas E; Stephenson, Catherine L; Stinson, Kelly David Jr; Stockton, Rickey A; Tinley, Mary Darlene; Woods, Steven E
Subject:
Bucket List 6/2/11 Updated List for this week.
William D. (Bill) Crouch (423) 3652004 WBN (256) 7777676 Cell 1
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 382 Mail Envelope Properties (19D990B45D535548840D1118C451C74D84F4B50B71)
Subject:
FW: Bucket List 6/2/11 Sent Date: 5/31/2011 8:52:50 AM Received Date: 5/31/2011 8:52:52 AM From: Poole, Justin Created By: Justin.Poole@nrc.gov Recipients:
"WBN2HearingFile Resource" <WBN2HearingFile.Resource@nrc.gov>
Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>
Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 921 5/31/2011 8:52:52 AM NRC PM Open Items List 6-2-11.docx 36032 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Page 1 of 7 NRC PM Open Items List 6/2/11 (423) 751-6338 ID 657601 No. Description Status Additional Comments Resp Org/Person
- 1. Cyber Security Plan/Controls and Assess Update Cyber Security Plan IAW NEI 08-09 Rev 6 per Heinrich/Snyder Implementation CDAs/Identify NRC letter dated 5/24/10. NRC Inspection in 2011 (Bryan)
Mods 2/28/11A Provide update to change commitment for April ready for Inspection RAI Response 4/7/11A Response to 3 Generic RAIs Plan for Common Systems 6/7/11 Identify Required Exemptions Scope Mods 5/31/11 TI issued 5/30/11 NRC Table Top/Pilot Oct 2011 Procedures complete 9/30/11
Page 2 of 7 No. Description Status Additional Comments Resp Org/Person Inspection Dec 2011
- 2. Instrumentation RAI List (Knuettel) Ongoing RAI Responses Eng/Hilmes (Smith) 5/20/11A Provide proprietary Westinghouse presentation 5/25/11A Provide requested WINCISE Proprietary Documents.
Documents available in Westinghouse offices. See email dated 5/25/11 6/17/11 Provide non-prop versions 6/3/11 NRC review draft RAIs for deletions
- 3. Resolve Licensing Basis Preservation 5/27/11 TVA to provide QA audit results Eng/Freeman Self Assessment PERs (Crouch) (Smith)
- 4. Status of GSI 199 Eastern Seismicity 6/12/11 TVA/NRR (Crouch)
- 5. Complete Implementation (Hemmer) RAI Response Respond to RAI Hemmer 3/29/11A (Smith)
Implement two unit commitments.
RAI Clarification Provide updated information for tables contained in for Fuel the 6/29/07 and 7/1/10 letters.
Question 2 5/9/10A Letter did not address Phase I commitments Diesel Diesel is onsite 6/1/11 Pump Relocation 6/17/11 Procedures Issued 6/30/11
Page 3 of 7 No. Description Status Additional Comments Resp Org/Person Inspection -
August 2011 Phase I commitments 8/1/11
- 6. Provide feedback on the status of NRC SSER 23 NRC to provide status of review in SSER 23 NRR review of Integrated Safeguards Test submittal
- 7. Document Control Issues for two letters 6/15/11 7/15, 10/5, 10/21 and 10/29 letters. NRC to reprint Licensing/Boyd 7/15 letter and provide to NRC Document control.
TVA/Bechtel to provide non-proprietary version of documents that can be released to the public. TVA to provide revised letter that says non-prop once prop documents removed. NRC action to contact Kenny Nguyen, NRC Document Control regarding A102.
- 8. Chapter 15.5 RAIs 12/10/10A Additional question regarding meteorology data from Wastrack RAI response 2008-2009 (Bryan) 6/5/11
- 9. Fire Protection Report Questions 3/31/11A Justification Criteria ENG/Hilmes regarding OMA (Crouch) 5/6/11A Set 3 RAIs 5/18/11A FPR 6/17/11 Justifications 5/26/11A Set 4A RAIs 6/7/11 Set 4B RAIs TBD Set 5 RAIs
- 10. IST Tech Spec Change 5/27/11 TVA Corporate Licensing (Shea)
Page 4 of 7 No. Description Status Additional Comments Resp Org/Person
- 11. Environmental Phone call to discuss 4/28/11A Responded to RAI and attached revised Impingement Environmental/
intake flow rate/velocity at IPS and Report Hopping SCCW in EIS versus NPDES. (Bryan)
- 12. Tech Spec Revisions from latest T/S 5/10/11A Meeting Licensing/Elton markup and NRC Review comments (Bryan) 6/10/11 Submittal
- 13. ASME III to XI transition Need NRC When does ISI program begin with partial plant N-3? Eng/Helms Letter Are repairs/mods after N-5 controlled under Section III (Crouch) or Section XI? The timing for the NIS-2 in the letter does not comply with the ASME Code . The NIS-2 must be before commercial operation.
- 14. Chapter 15 RAI on Dose calc basis 6/3/11 Bechtel (Fredrick) preparing answer. Eng/Koontz (Bryan)
- 15. Chapter 11/FSEIS RAIs 5/11/11A Public Meeting 5/11/11 Chem/Woods (Bryan) 5/20/11A Chapter 11/EIS Letter 6/3/11 X/Q info in FSAR 5/26/11A Chapter 11 RAI List 5/26/11A X/Q to 50 miles
- 16. Hydrology sand bag question 4/20/11A Five RAI questions Corp/Selman 5/11/11A NRC Visit to Knoxville/TVA dam 5/20/11A NRC Info Request 5/31/11 NRC Calc Request and PER Summary
- 17. Letter to notify NRC when Vital Area 5/31/11 Date for schedule Lic/Crouch Boundary returned to original location TBD Security Plan Update
- 18. Part 70 License 6/10/11 NRC to issue Part 70 license. Milano NRC question related to dry versus wet storage.
4/29/11 TVA issued letter regarding placement of new Unit 2
Page 5 of 7 No. Description Status Additional Comments Resp Org/Person fuel in new fuel vault and SFP.
- 19. ACRS Topics Improvements, Inspection status, Refurb status, Construction Status, Japan, IST Re-Presentation, Cyber Security
- 20. SAMDA RAIs 05/11/11A Meeting on 5/11/11 05/13/11A 1st Submittal 5/25/11A 2nd Submittal
- 21. SSER 22/23 Open Items Response 6/3/11 Addresses 15 Open Items - Need item 69 clarification
- 22. Chapter 12 RAI on Instrument Channel 6/24/11 ENG/Hilmes Operability Tests Fuel Vault Criticality Monitor 10 CFR TBD 70.24 vs 10 CFR 50.68
- 23. Transient Analysis issues ENG/Koontz Overpressurization 4/1/11A WEC/Morgan Boron Info 3/25/11A Inadvertent SI 4/29/11A CVCS Malfunction 4/29/11A 5/13/11A Steam line break Proprietary review of audit report 4/22/11A Audit Report Response 5/13/11A Audit Report Follow up Questions 5/24/11A Additional Follow up Questions TBD
- 24. Sump Strainer Loads RAI 4/28/11A Eng/Helms (Bryan)
- 25. Sump Strainer Flow RAI 4/28/11A Eng/Helms (Bryan)
Page 6 of 7 No. Description Status Additional Comments Resp Org/Person
- 26. NRR/Region assign SSER 22 items 1, 4, 5/17/11A Issue resolved at 5/17/11 NRC meeting Milano 7, 9, 11, 19, 21, 38
- 27. FSAR A104 6/3/11 Lic/Stockton
- 28. IEB 88-02 SG Tube Cracking TBD What are the SG inspection plans in light of the Corp SG/
experience with a French reactor exhibiting SG tube Webber cracking early? Is TVA planning to change the ISI/Tinley inspection plan due to this operating experience?
- 29. Develop list of planned License 9/1/11 Review Unit 1 SER for exemptions. NRR/TVA Conditions, Exemptions and Relief (Bryan)
Requests (Crouch)
- 30. Submit final REP prior to fuel load Complete NRR to determine if submittal has to occur before EP/
(Spink) License rather than before fuel load. Detchemendy (Bryan)
Complete 1. Fix Section 6.0, Event 6.2 in Rev 92xx.
10/1/11 2. Submit Final REP and EPIPs 180 days prior to OL.
- 31. Issue two Unit Offsite Dose Calculation 9/1/11 Chemistry/
Manual (Beach) Review TS Chapter 5 Woods programs also (Bryan)
- 32. Copy of Site Plan for NSR TBD Fire Ops/Sterchi
- 33. Issue Unit 2 Completion Letter (Crouch) 3/1/12 Licensing
- 34. Combined U1/U2 FSAR (Stockton) 3/1/12 Licensing
- 35. Submit final as-constructed FSAR 10/1/11 Licensing/
figures Stockton
- 36. Verify Tech Spec Setpoints match calcs 8/1/11 Eng/Hilmes (Bryan)
- 37. Letter to terminate Part 30/40 License 4/1/12 Licensing after receipt of Part 50 License (Crouch)
- 38. Discuss IPS velocity calc at 5/11 mtg 5/11/11A Discussed at meeting Lic (Bryan) 5/19/11A Provide submittal to describe intake configuration
- 39. Provide date of Unit 1 PASS T/S 5/3/11A Provide NRC SER to NRR via e-mail Licensing/
submittal and NRC SER date Stockton (Crouch)
Page 7 of 7 No. Description Status Additional Comments Resp Org/Person