|
---|
Category:Memoranda
MONTHYEARML23094A1252023-03-31031 March 2023 Talen Part 21 Final Notification P21-03032023-FN R0 Re Defect Identified in Automatic Transfer Switch ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML21054A3032021-04-22022 April 2021 Memo to File: Final Ea/Fonsi of Independent Spent Fuel Storage Facilities Decommissioning Funding Plans Related to Susquehanna ML17090A1332017-04-0505 April 2017 Notice of Meeting with Susquehanna Nuclear, LLC to Discuss the Nrc'S Assessment of Safety Performance at Susquehanna Steam Electric Station for 2016 ML17037B8502017-02-0606 February 2017 08/21/1975 Notice of Meeting with Architect Engineers of Mark II Owners to Discuss Load Combinations and Analytical Techniques for Determining Stresses in Mechanical Components and Structures of Mark II Containments ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML15345A0912015-12-17017 December 2015 Closure of Issue Found During 2014 Regulatory Commitment Audit ML15313A2392015-11-0606 November 2015 Request for Additional Information Proposed Relief Requests for the Third 10-Year Inservice Inspection Interval (TAC Nos. MF6302 Through MF6307) ML15093A3052015-04-0303 April 2015 Memorandum to the Participants NRC Staff Notification of Proposed Issuance of Order and Conforming License Amendments Approving Indirect Transfer ML14133A0592014-07-0101 July 2014 Summary of Closed Meeting Between Representatives of the Army Corps of Engineers, Nuclear Regulatory Commission, Federal Energy Regulatory Commission, Exelon Generation Co, LLC, and PPL Susquehanna, LLC, to Discuss Dam Failure Analysis.. ML14085A4112014-05-0606 May 2014 Final TIA Response Susquehanna SGTS and Secondary Ventilation ML14112A2392014-04-22022 April 2014 Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Peach Bottom Atomic Power Station Units 2 and 3, Susquehanna Steam Electric Station Units 1 and 2, and Three Mile Island Nuclear Station Unit 1 ML13309A0802013-12-11011 December 2013 Memorandum to File: Transcript for 10 CFR 2.206 Petition from Beyond Nuclear (Et Al) Regarding General Electric Mark I and Mark II Boiling-Water Reactors ML13043A4062013-02-12012 February 2013 Proposed Amendment No. 309 to License NPF-14 and Proposed Amendment No. 280 to License NPF-22: Change to Technical Specification Surveillance Requirement (SR) 3.8.1.9, 3.8.1.11,3.8.1.12, and 3.8.1.19 to Increase Diesel ML13035A2482013-02-0101 February 2013 ME9609 Susquehanna Steam Electric Station Proposed Amendment No. 309 to License NPF-14 and Proposed Amendment No. 280 to License Npf -22: Change to Technical Specification Surveillance Requirement 3.8.1.19 to Increase Diesel Generator E Min ML1114410162011-05-24024 May 2011 Summary of Susquehanna Annual Assessment Meeting, May 19, 2011 ML1014700962010-05-25025 May 2010 Summary of Annual Assessment Meeting with PPL Susquehanna, LLC, to Discuss Nrc'S Assessment of Safety Performance for Calendar Year 2009 ML0925103122009-09-0808 September 2009 Drop-in Visit from PPL Susquehanna, LLC - August 31, 2009 ML0919404402009-07-13013 July 2009 Meeting Summary, Public Meeting with PPL Susquehanna, LLC Re SCWE at Site ML0915505712009-06-0101 June 2009 Meeting Minutes of the Plant License Renewal Subcommittee on April 1, 2009 ML0900803792009-01-30030 January 2009 Summary of Telephone Conference Call Held on 12/18/08, Between the U.S. NRC and PPL Susquehanna, LLC, Concerning TLAA RAI ML0833101132008-12-0303 December 2008 Meeting Summary, Telephone Conference Call Between U.S. NRC and PPL Susquehanna, LLC, Concerning the Draft Request for Additional Information Pertaining to the Susquehanna Steam Electric Station Units 1 & 2, LRA ML0832307862008-11-19019 November 2008 11/13/2008-Summary of Telephone Conference Call Between NRC and PPL, Concerning the Responses to RAIs Pertaining to the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application ML0828901522008-10-21021 October 2008 Summary of Telephone Conference Call Held on October 8, 2008, Between the USNRC and PPL Susquehanna, Llc. Concerning Draft Requests for Additional Information Pertaining to the, License Renewal Application ML0822603532008-10-0101 October 2008 06/25/2008 Meeting Summary, Telephone Conference Call Between the NRC and PPL Susquehanna, LLC, Concerning Draft Request for Additional Information Pertaining to the Susquehanna, Units 1 and 2, License Renewal Application ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0806303822008-03-0505 March 2008 Notice of Meeting with PPL Susquehanna, LLC (PPL) to Discuss Ppl'S Plan Regarding Compliance with the License Conditions Related to the New Steam Dryer During Extended Power Uprate Power Ascension for the Upcoming Refueling Outage ML0728800512007-12-13013 December 2007 Summary of Telephone Conference Call Held on 10/03/07, Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, LLC, Concerning Fire ML0728511102007-11-16016 November 2007 Summary of Telephone Conference Call Held on October 3, 2007, Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, LLC Concerning Open Items Pertaining to the Susquehanna, Units 1 and 2, License Renewal Application ML0730200012007-10-25025 October 2007 FRN - Power Uprates (Susquehanna), November 14, 2007 ML0726401342007-10-24024 October 2007 Summary of Telephone Conference Call with PPL Susquehanna, LLC Concerning Requests for Additional Information ML0728906522007-10-24024 October 2007 Summary of July 19th Conference Call Between NRC DLR Environmental Staff; PPL Susquehanna, LLC; and PPL Generating Regarding PPL Generation'S Letter of Intent to File a Combined License Application for a Potential New Unit at the SSES Site ML0724900462007-09-18018 September 2007 and 09/05/2007 Summary of Telephone Conference Calls Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, LLC, Concerning D-RAI ML0723304142007-08-27027 August 2007 Summary of Telephone Conference Call Held on August 16, 2007, Between the Us NRC and PPL Susquehanna, Concerning Request for Additional Information Pertaining to the Susquehanna, Units 1 and 2, License Renewal Application ML0721101752007-07-30030 July 2007 Notice of Meeting with PPL Susquehanna, LLC (Ppl), Susquehanna Steam Electric Station, Units 1 and 2, to Conduct a Working Level-Discussion Related to NRC Staff'S Reactor Systems Safety Review of Proposed Extended Power Uprate Application ML0716400652007-06-14014 June 2007 Notice of with PPL Susquehanna, LLC (Ppl), Susquehanna, Units 1 and 2 to Conduct a Working Level-Discussion Related to the Steam Dryer Instrumentation Plan Finite Element Analysis Model Changes, Fabrication Improvements and Start-Up Limit. ML0705800922007-03-0202 March 2007 Summary of Telephone Conference Call Held on February 12, 2007, Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, Lcc, Concerning Requests for Additional Information Pertaining to the Susquehanna Steam Electric Station, Un ML0629104092006-11-0909 November 2006 Review of Susquehanna Steam Electric Station Units 1 and 2 Amendment Request to Revise Technical Specifications 3.8.1 ML0624202762006-08-30030 August 2006 09/13/2006 Notice of Forthcoming Meeting with PPL Susquehanna, LLC (PPL) Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2) on Pre-License Renewal Application ML0608107012006-03-22022 March 2006 04/05/06 - Forthcoming Meeting with PPL Susquehanna, LLC (Ppl), Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2) on License Renewal and Extended Power Uprate ML0530704902005-11-0303 November 2005 Forthcoming Meeting with PPL Susquehanna, LLC (Ppl), Susquehanna, Units 1 and 2 to Conduct a Working level-discussion Related to the Schedule, Approach, and Strategy for the Proposed Extended Power Uprate Application.. ML0527103892005-09-29029 September 2005 Meeting with PPL Susquehanna 1 & 2, Schedule, Approach and Strategy for the SSES Unit 1 Cycle 14 and Cycle 15 Minimum Critical Power Ratio Safety Limit Submittals in Light of the Control Cell Friction Issues Experienced on Unit 1 ML0510804732005-04-29029 April 2005 Correction to Letter Approving the Use of the Privatel Model 960V Validated to Federal Information Processing Standard (Fips) 140-1 ML0403001132004-01-30030 January 2004 Correction of License Authority Files ML0235404372002-12-18018 December 2002 Rquest for Additonal Information (RAI) for Emergency Plan (E-Plan) Revisions PLA-5567 - Attachment ML0235200602002-12-18018 December 2002 Draft Request for Additional Information (RAI) Response Regarding Amendment Request for Emergency Plan (E-Plan) Revisions ML0229705292002-10-24024 October 2002 Results of the Susquehanna Steam Electric Station Units 1 and 2 SDP Phase 2 Notebook Benchmarking Visit ML0226002922002-09-17017 September 2002 Memorandum Regarding Report on the Status of Open TIAs Assigned to NRR ML0219802582002-07-17017 July 2002 Safety Evaluation Input for Proposed Changes to the Susquehanna, Units 1 & 2 Technical Specifications Implementing Operability Requirements for the Ultimate Heat Sink Spray Valves (TAC Nos. MB2119 & MB2120) 2023-03-31
[Table view] |
Text
May 24, 2011 LICENSEE: PPL SUSQUEHANNA, LLC.
FACILITY: SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2
SUBJECT:
SUMMARY
OF MAY 19, 2011, ANNUAL ASSESSMENT MEETING WITH PPL SUSQUEHANNA, LLC.
On May 19, from 1:00 pm to 2:00 pm, an Annual Assessment Meeting was conducted at the Susquehanna Steam Electric Station in Berwick, Pennsylvania, between the U. S. Nuclear Regulatory Commission (NRC) and PPL Susquehanna, LLC. (PPL). The NRC requested the meeting with PPL management to discuss the NRC=s assessment of the safety performance of their Susquehanna Steam Electric Station (Susquehanna) Units 1 and 2 for the calendar year 2010. The NRC also conducted an Annual Assessment meeting with the public at the Eagle Building in Berwick, Pennsylvania from 3:30 pm to 5:30 pm the same day.
The NRC presented and discussed its assessment of the safety performance of Susquehanna Units 1 and 2 for the period between January 1 through December 31, 2010. The meetings also discussed the Assessment Follow up Letter for Susquehanna Unit 1 issued on May 3, 2011 (ML111230066). The NRC presentation included information on the Reactor Oversight Process (ROP), the results of NRC=s performance assessment for Susquehanna Units 1 and 2, and a presentation about United States nuclear plant safety in light of recent events in Japan.
Public attendees were offered the opportunity to communicate with the NRC regarding PPL=s performance at Susquehanna and the role of the agency in ensuring safe plant operations.
Questions from the public were addressed by the NRC.
The NRC=s assessment letter can be found in ADAMS under Accession Number ML110620317.
The annual assessment meeting notice with the attached meeting agenda can be found in ADAMS package ML111120313. The NRC slides can be located in ADAMS under Accession Number ML111440709. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
/RA/
Paul G. Krohn, Chief Projects Branch 4 Division of Reactor Projects
Enclosures:
Public Meeting Sign in Sheet
2 Name Organization Paul Krohn Nuclear Regulatory Commission (NRC)
Patrick Finney Nuclear Regulatory Commission (NRC)
Jonathan Greives Nuclear Regulatory Commission (NRC)
Andrew Rosebrook Nuclear Regulatory Commission (NRC)
Edgardo Torres Nuclear Regulatory Commission (NRC)
Neil Sheehan Nuclear Regulatory Commission (NRC)
Members of the Public on Sign-in Sheet
LICENSEE: PPL SUSQUEHANNA, LLC.
FACILITY: SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2
SUBJECT:
SUMMARY
OF MAY 19, 2011, ANNUAL ASSESSMENT MEETING WITH PPL SUSQUEHANNA, LLC.
On May 19, from 1:00 pm to 2:00 pm, an Annual Assessment Meeting was conducted at the Susquehanna Steam Electric Station in Berwick, Pennsylvania, between the U. S. Nuclear Regulatory Commission (NRC) and PPL Susquehanna, LLC. (PPL). The NRC requested the meeting with PPL management to discuss the NRC=s assessment of the safety performance of their Susquehanna Steam Electric Station (Susquehanna)
Units 1 and 2 for the calendar year 2010. The NRC also conducted an Annual Assessment meeting with the public at the Eagle Building in Berwick, Pennsylvania from 3:30 pm to 5:30 pm the same day.
The NRC presented and discussed its assessment of the safety performance of Susquehanna Units 1 and 2 for the period between January 1 through December 31, 2010. The meetings also discussed the Assessment Follow up Letter for Susquehanna Unit 1 issued on May 3, 2011 (ML111230066). The NRC presentation included information on the Reactor Oversight Process (ROP), the results of NRC=s performance assessment for Susquehanna Units 1 and 2 and a presentation about United States nuclear plant safety in light of recent events in Japan.
Public attendees were offered the opportunity to communicate with the NRC regarding PPL=s performance at Susquehanna and the role of the agency in ensuring safe plant operations. Questions from the public were addressed by the NRC.
The NRC=s assessment letter can be found in ADAMS under Accession Number ML110620317. The annual assessment meeting notice with the attached meeting agenda can be found in ADAMS package ML111120313. The NRC slides can be located in ADAMS under Accession Number ML111440709. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
/RA/
Paul G. Krohn, Chief Projects Branch 4 Division of Reactor Projects Distribution J. Clifford, DRP P. Finney, DRP, SRI W. Dean, RA P. Krohn, DRP J. Greives, DRP, RI D. Lew, DRA W. Schmidt, DRS S. Farrell, DRP, OA D. Roberts, DRP A. Rosebrook, DRP E. Torres, DRP SUNSI Review Complete: AAR (Reviewer=s Initials)
DOCUMENT NAME: G:\DRP\BRANCH4\ASSESSMENT (EOC, MC)\ROP 11\2010 EOC\AAM NOTICES\SQ 2010\
SSES 2010 AAM
SUMMARY
.DOCX After declaring this document AAn Official Agency Record@ it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE mmt R1/DRP R1/DRP NAME ARosebrook/ AAR PKrohn/ PGK DATE 05/24/11 05/ 24/11 OFFICIAL RECORD COPY