1 WBN2Public Resource From:
Poole, Justin Sent:
Monday, May 09, 2011 10:54 AM To:
Raghavan, Rags; Epperson, Dan Cc:
WBN2HearingFile Resource
Subject:
FW: NRC Bucket List 5/12/11 Attachments:
NRC PM Open Items List 5-12-11.docx JustinC.Poole ProjectManager NRR/DORL/LPWB U.S.NuclearRegulatoryCommission (301)4152048 email:Justin.Poole@nrc.gov From: Crouch, William D [1]
Sent: Monday, May 09, 2011 8:44 AM To: Poole, Justin; Milano, Patrick; Campbell, Stephen Cc: Adair, James G; Arent, Gordon; Beach, Charles D; Bryan, Robert H Jr; Detchemendy, Thomas F; Elliott, Walter L Jr; Elton, Thomas L; Freeman, Edwin E; Gillman, Marie; Glover, Christopher Edmund; Henrich, Nolan T Jr; Hilmes, Steven A; Johnson, Robert M; Jones, Dennis Michael; Knuettel, Edward Terry; Koontz, Frank A Jr; Metzler, Ernest Thomas; Miller, Lee R; Olson, Peter Edwin; Riedl, Christopher John; Schlessel, Jerry V; Shea, Joe; Smith, James D; Snyder, Laura L; Spink, Thomas E; Stephenson, Catherine L; Stinson, Kelly David Jr; Stockton, Rickey A; Tinley, Mary Darlene; Woods, Steven E
Subject:
NRC Bucket List 5/12/11 Iwentaheadandupdatedthelisttobeusedforthisweek.
William D. (Bill) Crouch (423)3652004WBN (256)7777676Cell
Hearing Identifier:
Watts_Bar_2_Operating_LA_Public Email Number:
370 Mail Envelope Properties (19D990B45D535548840D1118C451C74D7F87DDFDE0)
Subject:
FW: NRC Bucket List 5/12/11 Sent Date:
5/9/2011 10:54:06 AM Received Date:
5/9/2011 10:54:07 AM From:
Poole, Justin Created By:
Justin.Poole@nrc.gov Recipients:
"WBN2HearingFile Resource" <WBN2HearingFile.Resource@nrc.gov>
Tracking Status: None "Raghavan, Rags" <Rags.Raghavan@nrc.gov>
Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>
Tracking Status: None Post Office:
HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 1080 5/9/2011 10:54:07 AM NRC PM Open Items List 5-12-11.docx 33125 Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received:
Page 1 of 5 NRC PM Open Items List 5/12/11 (423) 751-6338 ID 657601 No.
Description Status Additional Comments Resp Org/Person
- 1.
Cyber Security Plan/Controls and Implementation Assess CDAs/Identify Mods 2/28/11A RAI Response 4/7/11A Scope Mods 5/31/11 TI issued 5/30/11 NRC Table Top/Pilot TBD Procedures complete 9/30/11 Inspection 10/23/11 Update Cyber Security Plan IAW NEI 08-09 Rev 6 per NRC letter dated 5/24/10. NRC Inspection in 2011 Provide update to change commitment for April ready for Inspection Response to 3 Generic RAIs Heinrich/Snyder (Bryan)
- 2. Instrumentation RAI List (Knuettel)
Ongoing 5/11/11 RAI Responses Public meeting. Provide WINCISE System Description Info Eng/Hilmes (Smith)
- 3. Resolve Licensing Basis Preservation Self Assessment PERs (Crouch) 5/15/11 TVA to provide QA audit results Eng/Freeman (Smith)
- 4. Status of GSI 199 Eastern Seismicity (Crouch) 5/12/11 TVA/NRR
Page 2 of 5 No.
Description Status Additional Comments Resp Org/Person
- 5. Complete Implementation (Hemmer)
RAI Response 3/29/11A RAI Clarification for Fuel Question 2 5/11/10 Diesel 6/1/11 Pump Relocation 6/17/11 Procedures Issued 6/30/11 Inspection -
August 2011 Phase I commitments 2/11/11 Respond to RAI Implement two unit commitments.
Provide updated information for tables contained in the 6/29/07 and 7/1/10 letters.
Letter did not address Phase I commitments Hemmer (Smith)
- 6. Provide feedback on the status of NRC review of Integrated Safeguards Test submittal SSER 23 NRC to provide status of review in SSER 23 NRR
- 7. Document Control Issues for two letters 5/15/11 7/15, 10/5, 10/21 and 10/29 letters. NRC to reprint 7/15 letter and provide to NRC Document control.
TVA/Bechtel to provide non-proprietary version of documents that can be released to the public. TVA to provide revised letter that says non-prop once prop documents removed. NRC action to contact Kenny Nguyen, NRC Document Control regarding A102.
Licensing/Boyd
Page 3 of 5 No.
Description Status Additional Comments Resp Org/Person
- 8. Chapter 15.5 RAIs 12/10/10A RAI response 6/5/11 Additional question regarding meteorology data from 2008-2009 Wastrack (Bryan)
- 9. Fire Protection Report Questions regarding OMA 3/31/11A Set 3 5/6/11A FPR Rev 5/13/11 Set 4 5/27/11 Justification Criteria Set 3 RAIs FPR and Justifications Set 4 RAIs ENG/Hilmes (Crouch)
- 11. Environmental Phone call to discuss intake flow rate/velocity at IPS and SCCW in EIS versus NPDES.
4/28/11A Responded to RAI and attached revised Impingement Report Environmental/
Hopping (Bryan)
- 12. Tech Spec Revisions from latest T/S markup and NRC Review comments 5/10/11 5/24/11 Meeting Submittal Licensing/Elton (Bryan)
Are repairs/mods after N-5 controlled under Section III or Section XI? The timing for the NIS-2 in the letter does not comply with the ASME Code. The NIS-2 must be before commercial operation.
Eng/Helms (Crouch)
- 14. Chapter 15 RAI on Dose calc basis 5/13/11 Bechtel (Fredrick) preparing answer.
Eng/Koontz (Bryan)
- 15. Chapter 11/12 E-mail RAIs 5/20/11 Public Meeting 5/11/11 Chem/Woods (Bryan)
- 16. Hydrology sand bag question 4/20/11A 5/11/11 Five RAI questions NRC Visit to Knoxville/TVA dam Corp/Selman
- 17. Letter to notify NRC when Vital Area Boundary returned to original location 5/31/11 Date for schedule Lic/Crouch
- 18. Part 70 License 5/13/11 NRC to issue Part 70 license.
NRC question related to dry versus wet storage.
Milano
Page 4 of 5 No.
Description Status Additional Comments Resp Org/Person 4/29/11 TVA issued letter regarding placement of new Unit 2 fuel in new fuel vault and SFP.
- 19. ACRS Topics Improvements, Inspection status, Refurb status, Construction Status, Japan, IST Re-Presentation, Cyber Security
- 20. SAMDA RAIs 05/11/11 05/18/11 Meeting on 5/11/11 Submittal
- 21. SSER 22/23 Open Items Response 5/20/11 Addresses 15 Open Items
- 22. Chapter 12 RAI on Instrument Channel Operability Tests 6/24/11 ENG/Hilmes
- 23. Transient Analysis issues Overpressurization Boron Info Inadvertent SI CVCS Malfunction Steam line break Proprietary review of audit report Audit Report Response 4/1/11 3/25/11 4/29/11 4/29/11 5/12/11 4/22/11A 5/12/11 ENG/Koontz WEC/Morgan
- 26. NRR/Region assign SSER 22 items 1, 4, 7, 9, 11, 19, 21, 38 5/17/11 1 pm telecon if required Milano
- 27. FSAR A104 5/20/11 Lic/Stockton
- 28. IEB 88-02 SG Tube Cracking TBD What are the SG inspection plans in light of the experience with a French reactor exhibiting SG tube cracking early? Telecon 5/13/11 Corp SG/
Webber ISI/Tinley
- 29. Develop list of planned License Conditions, Exemptions and Relief 9/1/11 Review Unit 1 SER for exemptions.
NRR/TVA (Bryan)
Page 5 of 5 No.
Description Status Additional Comments Resp Org/Person Requests (Crouch)
- 30. Submit final REP prior to fuel load (Spink)
Complete Item 1 10/1/11 Item 2 NRR to determine if submittal has to occur before License rather than before fuel load.
- 1. Fix Section 6.0, Event 6.2 in Rev 92xx.
EP/
Detchemendy (Bryan)
- 31. Issue two Unit Offsite Dose Calculation Manual (Beach) Review TS Chapter 5 programs also 9/1/11 Chemistry/
Woods (Bryan)
- 33. Issue Unit 2 Completion Letter (Crouch) 3/1/12 Licensing (Crouch)
- 34. Combined U1/U2 FSAR (Stockton) 3/1/12 Licensing (Crouch)
- 35. Submit final as-constructed FSAR figures 10/1/11 Licensing/
Stockton (Crouch)
- 36. Verify Tech Spec Setpoints match calcs 8/1/11 Eng/Hilmes (Bryan)
- 37. Letter to terminate Part 30/40 License after receipt of Part 50 License 4/1/12 Licensing (Crouch)
- 38. Discuss IPS velocity calc at 5/11 mtg 5/11/11 Lic (Bryan)
- 39. Provide date of Unit 1 PASS T/S submittal and NRC SER date 5/3/11A Provide NRC SER to NRR via e-mail Licensing/
Stockton (Crouch)
- 40. Provide feedback on need to revise submittal regarding testing of non-EQ hand switches.
5/4/11A See e-mail from Crouch dated 5/2/11.
NRR reviewed determined no need to revise submittal or NRC July 2 letter.
Milano