ML11136A042

From kanterella
Jump to navigation Jump to search
Submittal of Annual Radioactive Effluent Release Report 2010
ML11136A042
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 04/29/2011
From: Weber T
Arizona Public Service Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
102-06355-TNW/KAR
Download: ML11136A042 (205)


Text

Technical Specification 5.6.3 11 ý A subsidiaryof Pinnacle West Capital Corporation Thomas N. Weber Mail Station 7636 Palo Verde Nuclear Department Leader Tel. 623-393-5764 PO Box 52034 Generating Station Regulatory Affairs Fax 623-393-5442 Phoenix, Arizona 85072-2034 102-06355-TNW/KAR April 29, 2011 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Dear Sir:

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Units 1, 2, and 3 Docket Nos. STN 50-528/529/530 Annual Radioactive Effluent Release Report 2010 In accordance with PVNGS Technical Specification (TS) 5.6.3, enclosed please find the Annual Radioactive Effluent Release Report for 2010. In accordance with PVNGS TS 5.5.1, the enclosed report also includes Revision 25 of the Offsite Dose Calculation Manual (ODCM), which was implemented in 2010.

No commitments are being made to the NRC in this letter. Should you need further information regarding this submittal, please contact Russell A. Stroud, Licensing Section Leader, at (623)393-5111.

Sincerely,

,"A, a)YN kj,I TNW/RAS/KARPgat

Enclosure:

2010 ANNUAL RADIOACTIVE EFFLUENT RELEASE REPORT cc: E. E. Collins Jr. NRC Region IV Regional Administrator L. K. Gibson NRC NRR Project Manager for PVNGS J. R. Hall NRC NRR Senior Project Manager M. A. Brown NRC Senior Resident Inspector A. V. Godwin Arizona Radiation Regulatory Agency (ARRA)

T. Morales Arizona Radiation Regulatory Agency (ARRA) A-00

)0 A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway

  • Comanche Peak - Diablo Canyon
  • Palo Verde ° San Onofre - South Texas ° Wolf Creek

ENCLOSURE 2010 ANNUAL RADIOACTIVE EFFLUENT RELEASE REPORT

PALO VERDE NUCLEAR GENERATING STATION UNITS 1,2 AND 3 2010 ANNUAL RADIOACTIVE EFFLUENT RELEASE REPORT USNRC Docket No. STN 50-528/529/530 RCTSAI 1566 Prepared by: Kutner, Kevin.zolo"'......

DN: =Kr KKevn W(Z58001I W (Z58001) ......................

Reviewed by: Gray, Thomas SD z'M",o,0° DNT*=Gsy,Thomas b............

S(Z996 S(Z99610)

S(991Data,R................

20110- 0716:14:0M 7'0 Approved by: OigtaUySignood ON.-Instratio, Ad byJohnGaffney Jo-n Gaffney =RP

-u=800, John Gaffney .............

R.

Reasn 4.1am 2 approing thisdWum Doate201 04.1422:0M:59 -OT00

TABLE OF CONTENTS SECTION PAGE INT R O D UC T IO N ........................................................................................................................................ 5 BIBLIO G R A P HY ......................................................................................................................................... 6 APPENDIX A SOURCE TERMS AND EFFLUENT AND WASTE DISPOSAL REPORTS ....................... 7 APPENDIX B METEOROLOGY ............................................................................................................... 60 APPENDIX C DOSE CALCULATIONS .................................................................................................. 83 APPENDIX D NEI 07-07 GROUNDWATER PROTECTION INITIATIVE SAMPLING .............................. 92 APPENDIX E OFFSITE DOSE CALCULATION MANUAL Revision 25 ................................................. 101 LIST OF TABLES TABLE PAGE 1 E va p o ratio n P o n d Da ta ................................................................................................................................... 17 2 B a tch R e le a se Da ta ........................................................................................................................................ 17 3 Units 1, 2 & 3 Gaseous Effluents Average Lower Limit Of Detection ........................................................ 18 4 Unit 1 Gaseous Effluents - Summation Of All Releases .............................................................................. 19 5 Unit 1 Gaseous Effluents - Ground Level Releases - Continuous - Fission Gases and lodines .................. 20 6 Unit 1 Gaseous Effluents - Ground Level Releases - Continuous - Particulates ........................................ 21 7 Unit 1 Gaseous Effluents - Ground Level Releases - Batch - Fission Gases and lodines ........................... 22 8 Unit 1 Gaseous Effluents - Ground Level Releases - Batch - Particulates ................................................ 23 9 Unit 1 Gaseous Effluents - Continuous and Batch - Fission Gases and lodines ........................................ 24 10 Unit 1 Gaseous Effluents - Continuous and Batch - Particulates ................................................................ 25 11 Unit 1 Radiation Doses At And Beyond The Site Boundary ........................................................................ 26 2 PVNGS ARERR 2010

LIST OF TABLES TABLE PAGE 12 Unit 2 Gaseous Effluents - Summation Of All Releases ............................................................................ 27 13 Unit 2 Gaseous Effluents - Ground Level Releases - Continuous - Fission Gases and lodines ................. 28 14 Unit 2 Gaseous Effluents - Ground Level Releases - Continuous - Particulates ....................................... 29 15 Unit 2 Gaseous Effluents - Ground Level Releases - Batch - Fission Gases and lodines ......................... 30 16 Unit 2 Gaseous Effluents - Ground Level Releases - Batch - Particulates ................................................ 31 17 Unit 2 Gaseous Effluents - Continuous and Batch - Fission Gases and lodines ......................................... 32 18 Unit 2 Gaseous Effluents - Continuous and Batch - Particulates ............................................................... 33 19 Unit 2 Radiation Doses At And Beyond The Site Boundary ..................................... 34 20 Unit 3 Gaseous Effluents - Summation Of All Releases ............................................................................ 35 21 Unit 3 Gaseous Effluents - Ground Level Releases - Continuous - Fission Gases and lodines ................. 36 22 Unit 3 Gaseous Effluents - Ground Level Releases - Continuous - Particulates ......................................... 37 23 Unit 3 Gaseous Effluents - Ground Level Releases - Batch - Fission Gases and lodines ......................... 38 24 Unit 3 Gaseous Effluents - Ground Level Releases - Batch - Particulates ................................................ 39 25 Unit 3 Gaseous Effluents - Continuous and Batch - Fission Gases and lodines ....................................... 40 26 Unit 3 Gaseous Effluents - Continuous and Batch - Particulates ............................................................... 41 27 Unit 3 Radiation Doses At And Beyond The Site Boundary ....................................................................... 42 3 PVNGS ARERR 2010

LIST OF TABLES TABLE PAGE 28 Units 1, 2, and 3 Gaseous Effluents - Continuous - Fission Gases and lodines - Total By Quarter ........... 43 29 Units 1, 2, and 3 Gaseous Effluents - Continuous - Particulates - Total By Quarter .................................. 44 30 Units 1, 2, and 3 Gaseous Effluents - Batch - Fission Gases and lodines - Total By Quarter .................... 45 31 Units 1,2, and 3 Gaseous Effluents - Batch - Particulates - Total By Quarter ............................................ 46 32 Units 1, 2, and 3 Gaseous Effluents - Continuous and Batch - Fission Gases and lodines - Total By Quarter 47 33 Units 1, 2, and 3 Gaseous Effluents - Continuous and Batch - Particulates - Total By Quarter .................. 48 34 Units 1, 2 and 3 Gaseous Effluents- Continuous - Fission Gases and Iodine - Total By Unit .................... 49 35 Units 1, 2 and 3 Gaseous Effluents- Continuous - Particulates - Total By Unit ......................................... 50 36 Units 1, 2 and 3 Gaseous Effluents- Batch - Fission Gases and Iodine - Total By Unit .............................. 51 37 Units 1, 2 and 3 Gaseous Effluents- Batch - Particulates - Total By Unit ................................................... 52 38 Units 1, 2 and 3 Gaseous Effluents- Continuous and Batch - Fission Gases and Iodine - Total By Unit ........ 53 39 Units 1, 2 and 3 Gaseous Effluents - Continuous and Batch - Particulates - Total By Unit ......................... 54 40 Estim ation of Total P erce nt Error .................................................................................................................... 55 41 Effluent Monitoring Instrumentation Out Of Service Greater Than 30 Days .............................................. 56 42 S o lid W a ste S umma ry ..................................................................................................................................... 57 43 Doses To Special Locations For 2010 ......................................................................................................... 86 44 Integrated Population Dose for 2010 ........................................................................................................ 87 45 Sum mary of Individual Doses for 2010 ...................................................................................................... 91 4 PVNGS ARERR 2010

INTRODUCTION This report summarizes effluent and waste disposal source term data, meteorological data and doses from radioactive effluents for the Palo Verde Nuclear Generating Station (PVNGS) for the period of January through December 2010. The data presented meets the reporting requirements of Regulatory Guide 1.21 (Revision 1, June 1974) of the U.S. Nuclear Regulatory Commission and the PVNGS Technical Specifications.

5 PVNGS ARERR 2010

BIBLIOGRAPHY U.S. Nuclear Regulatory Commission, Regulatory Guide 1.21, "Measuring, Evaluating, and Reporting Radioactivity in Solid Wastes and Releases of Radioactive Materials in Liquid and Gaseous Effluents from Light-Water-Cooled Nuclear Power Plants," Revision 1, 1974.

U.S. Nuclear Regulatory Commission, Regulatory Guide 1.23 (Safety Guide 23), "Onsite Meteorological Programs," 1972.

U.S. Nuclear Regulatory Commission, NUREG/CR-2919, "XOQDOQ: Computer Program for the Meteorological Evaluation of Routine Effluent Releases at Nuclear Power Stations," 1982.

U.S. Nuclear Regulatory Commission, NUREG-0579, "Users Guide to GASPAR Code," June 1980.

U.S. Nuclear Regulatory Commission, Regulatory Guide 1.109, "Calculations of Annual Doses to Man from Routine Releases of Reactor Effluents for the Purpose of Evaluating Compliance with 10 CFR 50, Appendix I," Revision 1, 1977.

U.S. Nuclear Regulatory Commission, NUREG-0172, "Age-specific Radiation Dose Commitment Factors for a One-Year Chronic Intake," 1977.

U.S. Nuclear Regulatory Commission, NUREG-0133, "Preparation of Radiological Effluent Technical Specifications for Nuclear Power Plants," 1978.

Technical Specifications, Palo Verde Nuclear Generating Station, Units 1, 2 and 3, Docket No. 50-528/529/530.

Bechtel Power Corp., "Cooling Tower Blowdown System Solar Evaporation Pond," Sept. 1980.

Generation Engineering, "Geotechnical Exploration for Evaporation Pond #2," Oct. 1986 Letter No. 212-00789-WFQ/RHM, "1989 PVNGS Evaporation Pan Data," Jan. 1989.

Offsite Dose Calculation Manual Palo Verde Nuclear Generating Station Units 1, 2 and 3, Rev. 25.

NEI 07-07, Nuclear Energy Institute, Industry Ground Water Protection Initiative - Final Guidance Document, August 2007.

Calculation 13-NC-CH-0200, Rev 7,FSAR - Primary Coolant Activities (PCA) 6 PVNGS ARERR 2010

APPENDIX A SOURCE TERMS AND EFFLUENT AND WASTE DISPOSAL REPORTS 7 PVNGS ARERR 2010

Supplemental Information 1.0 REGULATORY LIMITS 1.1 Liquid Releases 1.1.1 PVNGS ODCM Requirement 3.2 The concentration of radioactive material discharged from secondary system liquid waste to the circulating water system shall be limited to:

5.0E-07 pCi/ml for the principal gamma emitters (except Ce-144) 3.0E-06 4Ci/ml for Ce-144 1.0E-06 jiCi/ml for 1-131.

1.OE-03 pICi/ml for H-3 The concentration of radioactive material discharged from secondary system liquid waste to the onsite evaporation ponds shall be limited to:

2.0E-06 [tCi/ml for Cs-1 34 2.OE-06 pICi/ml for Cs-1 37 The concentrations specified in 10 CFR Part 20.1001-20.2402, Appendix B, Table 2, Column 2, for all other isotopes 1.1.2 PVNGS ODCM Requirement 4.4 The dose or dose commitment to a MEMBER OF THE PUBLIC from radioactive materials in liquid effluents released, from each reactor unit, to areas at and beyond the SITE BOUNDARY shall be limited:

a. During any calendar quarter to less than or equal to 1.5 mrems to the total body and to less than or equal to 5 mrems to any organ, and
b. During any calendar year to less than or equal to 3 mrems to the total body and to less than or equal to 10 mrems to any organ.

8 PVNGS ARERR 2010

1.2 Gaseous Releases 1.2.1 PVNGS ODCM Requirement 3.1 The dose rate due to radioactive materials released in gaseous effluents from the site shall be limited to the following:

a. For noble gases: Less than or equal to 500 mrems/yr to the total body and less than or equal to 3000 mrems/yr to the skin, and
b. For 1-131 and 1-133, for tritium, and for all radionuclides in particulate form with half-lives greater than 8 days: Less than or equal to 1500 mrems/yr to any organ.

1.2.2 PVNGS ODCM Requirement 4.1 The air dose due to noble gases released in gaseous effluents, from each reactor unit, to areas at and beyond the SITE BOUNDARY shall be limited to the following:

a. During any calendar quarter: Less than or equal to 5 mrads for gamma radiation and less than or equal to 10 mrads for beta radiation and,
b. During any calendar year: Less than or equal to 10 mrads for gamma radiation and less than or equal to 20 mrads for beta radiation.

1.2.3 PVNGS ODCM Requirement 4.2 The dose to a MEMBER OF THE PUBLIC from iodine-1 31, iodine-1 33, tritium, and all radionuclides in particulate form with half-lives greater than 8 days in gaseous effluents released, from each reactor unit, to areas at and beyond the SITE BOUNDARY shall be limited to the following:

a. During any calendar quarter: Less than or equal to 7.5 mrems to any organ and,
b. During any calendar year: Less than or equal to 15 mrems to any organ.

1.2.4 PVNGS ODCM Requirement 4.3 The GASEOUS RADWASTE SYSTEM and the VENTILATION EXHAUST TREATMENT SYSTEM shall be used to reduce radioactive materials in gaseous waste prior to their discharge when the projected gaseous effluent air doses due to gaseous effluent releases, from each reactor unit, from the site, when averaged over 31 days, would exceed 0.2 mrad for gamma radiation and 0.4 mrad for beta radiation. The VENTILATION EXHAUST TREATMENT SYSTEM shall be used to reduce radioactive materials in gaseous waste prior to their discharge when the projected doses due to gaseous effluent releases, from each reactor unit, to areas at and beyond the SITE BOUNDARY when averaged over 31 days, would exceed 0.3 mrem to any organ of a MEMBER OF THE PUBLIC.

9 PVNGS ARERR 2010

1.3 Total Dose 1.3.1 PVNGS ODCM Requirement 5.1 The annual (calendar year) dose or dose commitment to any MEMBER OF THE PUBLIC due to releases of radioactivity and to direct radiation from uranium fuel cycle sources shall be limited to less than or equal to 25 mrems to the total body or any organ, except the thyroid, which shall be limited to less than or equal to 75 mrems.

2.0 MAXIMUM PERMISSIBLE CONCENTRATIONS Air: Release Concentrations are limited to dose rate limits described in section 1.2.1 of this report.

3.0 AVERAGE ENERGY The average energy (E) of the radionuclide mixture in releases of fission and activation gases is not applicable to PVNGS.

4.0 MEASUREMENTS AND APPROXIMATIONS OF TOTAL RADIOACTIVITY IN GASEOUS EFFLUENTS For continuous releases, sampling is in accordance with PVNGS ODCM Table 3-1.

Particulate and iodine radionuclides are sampled continuously at the Plant Vent and Fuel Building exhaust points. The particulate filters and charcoal cartridges are exchanged for analysis at least four times per month. Noble gas and tritium are sampled at least once per 31 days. The hourly average Radiation Monitoring System (RMS) effluent monitor readings are used, when available, to account for increases and decreases in noble gas concentrations between noble gas grab samples. The tritium concentration is assumed constant between sampling periods.

For batch releases, sampling is also in accordance with PVNGS ODCM Table 3-1. For containment purges, the noble gas concentration may be adjusted to account for decreases or increases in concentration during the purge using RMS readings. The volume of air released during the purge is determined using the exhaust fan rated flow rate. For Waste Gas Decay Tank releases, the volume released is corrected to standard pressure.

Effective January 1, 2004, Containment Purge release permits are updated by removing the permit pre-release particulate and iodine activity. This eliminates double accounting for the Containment Purge particulate and iodine activity at the Plant Vent but allows the particulate and iodine activity to be included in the Containment Purge pre-release dose projection.

The Lower Limit of Detection (LLD) of a measurement system is defined in Table 3 - 1 of the PVNGS ODCM. An average LLD for each radionuclide is provided in Table 3.

10 PVNGS ARERR 2010

5.0 BATCH RELEASES 5.1 Gaseous.

Batch release durations are presented in Table 2.

5.2 Liquid None.

6.0 ABNORMAL RELEASES None.

7.0 OFFSITE DOSE CALCULATION MANUAL AND PROCESS CONTROL PROGRAM (PCP) REVISIONS 7.1 ODCM, Revision 25, effective October 27, 2010, contains changes associated with the implementation of the Radioactive Environmental Monitoring Program (REMP).

The ODCM revision is included as Appendix E.

7.2 There were no revisions to the Process Control Program (PCP) in 2010.

8.0 EFFLUENTS AND SOLID WASTES 8.1 Gaseous Effluents Gaseous effluent information is presented in Table 1 through Table 41. Included in these tables are summaries of the effluents and estimated total error.

8.2 Liquid Effluents There were no liquid effluent releases beyond the Site Boundary from PVNGS.

8.3 Solid Waste Solid waste shipments are summarized in Table 42.

11 PVNGS ARERR 2010

9.0 MISCELLANEOUS INFORMATION 9.1 EVAPORATION PONDS Releases made to the Evaporation Ponds are limited to the concentrations specified in PVNGS ODCM Requirement 3.2. The Evaporation Ponds were monitored in accordance with PVNGS ODCM Requirement 6.1.

The average historical evaporation is approximately 12 inches, per pond, for each of the first and fourth quarters, and 33 inches, per pond, for each of the second and third quarters. Evaporation Pond One is approximately 250 acres. This equates to 3.08E+11 cc evaporated from Pond One for each of the first and fourth quarters and 8.48E+11 cc evaporated from Pond One for each of the second and third quarters. Evaporation Pond Two is approximately 235 acres. The amount evaporated from Pond Two is 2.90E+1 1 cc for each of the first and fourth quarters and 7.97E+11 cc for each of the second and third quarters.

Evaporation Pond Three is constructed of two smaller ponds of 90 acres each (3A and 3B). The amount evaporated from each section of Pond Three is 1.11 E+11 cc for each of the first and fourth quarters and 3.05E+11 cc for each of the second and third quarters.

Evaporation Pond 2 was empty for maintenance for the entire year.

Evaporation Pond 3B was empty during quarters one and two.

Using a site boundary X/Q of 5.OE-05 sec/m3 for the evaporation ponds and equation 4-3 from the ODCM, the dose from the evaporation ponds to a hypothetical individual at the site boundary, for all pathways, is summarized in Table 1.

9.2 RADIATION MONITORING SYSTEM SETPOINT VERIFICATION Current effluent monitor noble gas channel alert alarm setpoints are based on an assumed one per cent failed fuel source term. The current setpoints are more conservative than setpoints calculated using the actual noble gas source term presented in Table 38.

9.3 RCS RADIOIODINE (TRM T5.0.600)

There were no cases where primary coolant specific activity exceeded the Technical Specification 3.4.17 limits during the reporting period.

9.4 INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI)

There are no radioactive effluents from the NAC-UMS System. Direct dose at the Site Boundary is reported in the Annual Radiological Environmental Operating Report.

12 PVNGS ARERR 2010

9.5 MAJOR CHANGES TO THE RADIOACTIVE WASTE SYSTEMS (liquid, gaseous, and solid).

Licensee-initiated major changes to the radioactive waste systems (liquid, gaseous, and solid) are submitted as part of the FSAR update (TRM T5.0.500.4.a).

9.6 SAMPLES RESULTS FROM GROUNDWATER WELLS THAT ARE NOT DESCRIBED IN THE ODCM AS PART OF THE REMP (NEI 07-07, Industry Groundwater Protection Initiative, August 2007), are included in Appendix D. This initiative provides added assurance that ground water will not be adversely affected by PVNGS operations.

There were no NEI 07-07, reportable leaks or spills.

There were no positive sample results.

9.7 REPORT ADDENDUM None.

13 PVNGS ARERR 2010

10.0 DISCUSSION 10.1 Unit One Unit One operated with a refueling outage (U1 R15) from April 3, 2010 to May 23, 2010.

Maintenance outages:

U1M15B, March 7, 2010 to March 20, 2010.

Estimated number of fuel defects (source: INPO, CDE)

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 0 0 0 0 0 0 0 0 0 0 0 10.2 Unit Two Unit Two operated without a refueling outage.

Maintenance outages:

NONE.

Estimated number of fuel defects (source: INPO, CDE)

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 0 0 0 0 0 0 0 0 0 0 0 10.3 Unit Three Unit Three operated with a refueling outage (U3R15) from October 2, 2010 to November 10, 2010.

Maintenance outages:

NONE.

Estimated number of fuel defects (source: INPO, CDE)

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 0 0 0 0 0 0 0 0 0 0 0 0 14 PVNGS ARERR 2010

10.4 Carbon-14 Carbon-14 is formed naturally in the upper atmosphere and also is formed in operating nuclear reactors.

Carbon-14 is not a new power plant emission. Because the overall quantity of radioactive releases has steadily decreased due to improvements in power plant operations, carbon-14 may now qualify as a "principal radionuclide" under revised federal regulatory guidance. The levels of other releases have declined, so carbon-14 releases, expressed as a percentage of total releases, have the potential to achieve "principal radionuclide" status (anything greater than one percent of overall radioactivity in effluents) per updated federal regulatory guidance.

The radiation dose to the public from carbon-14 is much lower than regulatory limits and has been a very small contributor to the total radiation dose that Americans receive each year from natural and manmade sources.

Studies by the United Nations Scientific Committee on the Effects of Atomic Radiation, the National Research Council's BEIR VII study group and the National Council on Radiation Protection and Measurements all show that the risk associated with low-dose radiation from natural and man-made sources, including nuclear power plants, is negligible.

Radiation is measured in units called millirem. The average American is exposed to 620 millirem of radiation every year. Approximately 311 millirem of this comes from natural sources. The majority of the remaining dose (approximately 300 millirem) comes from medical procedures such as CAT scans.Less than one-tenth of a percent of all radiation exposure is from nuclear facilities.

Reference:

NCRP Report No. 160, Table 1.1.

Starting with the 2010 Annual Radioactive Effluent Release Report, PVNGS will include the estimated exposure from carbon-14 in the Appendix C, dose calculations. The PVNGS calculated production of carbon-14 is 18.5 Curies per cycle (500 days) or 13.5 curies per year. Based on published literature, twenty percent (20%) of the carbon-14 released is assumed to be in an inorganic form (C0 2 ). PVNGS will use an estimated value of 2.7 curies of carbon-14 released, per reactor, per year. The 2.7 curies will be divided equally between each quarter (0.68 curies per reactor, per quarter). Appendix C, dose calculations include this estimated carbon-14 dose. Appendix C also includes the dose excluding carbon-14 for comparision with historical reports.

10.5 Tritium PVNGS does not have a liquid release pathway. Removal of tritium is performed by operation of the Boric Acid Concentrator (BAC) in the release mode.

Comparison of PVNGS annual tritium curies released to other utilities should be made only after summing both liquid and gaseous tritium curies released.

15 PVNGS ARERR 2010

10.6 Dose Summary Dose for 2010 was primarily due to the release of tritium. Tritium production is approximately 1000 curies per Reactor Unit per year. In order to control plant tritium concentrations, tritium releases should match tritium production. For 2010, PVNGS released a total of 2540 curies of tritium (see Table 39).

Total dose due to releases from all three Units for 2010 were slightly higher than 2009, primarily due to releases of tritium and the addition of carbon-14 in the dose calcuations.

16 PVNGS ARERR 2010

Table 1: Evaporation Pond Data Evaporation Pond 1 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year Historical volume of water evaporated 3.08E+11 8.48E+11 8.48E+11 3.08E+11 (ml)

Tritium Concentration (uCi/cc) 1.15E-06 1.32E-06 1.19E-06 8.77E-07 Tritium Curies 3.55E-01 1.12E+00 1.01E+00 2.70E-01 2.75E+00 Evaporation Pond 2 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year Historical volume of water evaporated 2.90E+11 7.97E+11 7.97E+11 2.90E+11 (ml)

Tritium Concentration (uCi/cc) N/A N/A N/A N/A Tritium curies 0.OOE+00 0.OOE+00 0.00E+00 0.00E+00 0.00E+00 Evaporation Pond 3A Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year Historical volume of water evaporated 1.11E+11 3.05E+11 3.05E+11 1.11E+11 (ml) 3A Tritium Concentration (uCi/cc) 5.46E-07 6.42E-07 1.01E-06 5.1OE-07 3A Tritium curies 6.06E-02 1.96E-01 3.07E-01 5.66E-02 6.20E-01 Evaporation Pond 3B Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year Historical volume of water evaporated 1.11 E+11 3.05E+11 3.05E+11 1.11E+11 (ml) 3B Tritium Concentration (uCi/cc) 6.36E-07 6.48E-07 7.27E-07 6.56E-07 3B Tritium curies 7.06E-02 1.98E-01 2.22E-01 7.28E-02 5.63E-01 Dose (mRem) Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year Pond 1 4.93E-03 1.55E-02 1.40E-02 3.75E-03 3.82E-02 Pond 2 0.00E+00 0.00E+00 0.00E+00 0.00E+00 0.00E+00 Pond 3 1.82E-03 5.46E-03 7.34E-03 1.79E-03 1.64E-02 Total 6.75E-03 2.10E-02 2.13E-02 5.54E-03 5.46E-02 Table 2: Batch Release Data All times are in hours Unit 1 Unit 2 Unit 3 January - June Number of batch releases 54 30 26 Total time period for batch releases 2634.71 518.84 708.67 Maximum time period for a batch release 168.00 138.00 168.00 Average time period for a batch release 48.79 17.29 27.26 Minimum time period for a batch release 0.04 0.10 0.50 July - December Number of batch releases 27 28 33 Total time period for batch releases 38.02 409.36 1912.86 Maximum time period for a batch release 6.45 139.30 168.00 Average time period for a batch release 1.41 14.62 57.97 Minimum time period for a batch release 0.22 0.20 0.20 January - December Number of batch releases 81 58 59 Total time period for batch releases 2672.73 928.20 2621.53 Maximum time period for a batch release 168.00 139.30 168.00 Average time period for a batch release 33.00 16.00 44.43 Minimum time period for a batch release 0.04 0.10 0.20 17 PVNGS ARERR 2010

Table 3:

Units 1, 2 & 3 Gaseous Effluents Average Lower Limit Of Detection

ýiCi/cc Nuclide Continuous Batch Nuclide Continuous Batch Antimony-122 2.20E-13 1.90E-11 Argon-41 4.50E-08 4.50E-08 Antimony-124 8.40E-14 1.70E-11 Krypton-85 7.40E-06 7.40E-06 Barium-140 3.40E-13 5.70E-11 Krypton-85m 2.20E-08 2.20E-08 Bromine-82 3.30E-13 1.40E-11 Krypton-87 5.70E-08 5.70E-08 Cerium-141 8.70E-14 3.10E-11 Krypton-88 7.40E-08 7.40E-08 Cerium-144 3.60E-13 6.50E-11 Xenon-125 2.20E-08 2.20E-08 Cesium-134 1.OOE-13 2.60E-11 Xenon-127 2.1 OE-08 2.10E-08 Cesium-137 8.10E-14 1.70E-11 Xenon-131m 9.1OE-07 9.1OE-07 Cesium-138 5.20E- 10 7.30E-10 Xenon-133 6.30E-08 6.30E-08 Chromium-51 6.90E-13 1.40E-10 Xenon-133m 1.90E-07 1.90E-07 Cobalt-58 8.50E-14 1.70E-11 Xenon-135 2.OOE-08 2.OOE-08 Cobalt-60 1.OOE-13 1.90E-11 Xenon-135m 8.90E-08 8.90E-08 Iron-59 1.70E-13 3.20E-11 Xenon-138 2.OOE-07 2.OOE-07 Lanthanum-140 2.80E-13 2.10E-11 Iodine-131 8.OOE-14 7.OOE-12 Manganese-54 8.30E-14 1.70E-11 Iodine-132 6.60E-12 1.90E-11 Molybdenum-99 2.40E-13 2.80E-11 Iodine-133 4.70E-13 1.10E-11 Niobium-95 8.70E-14 1.80E-11 Iodine-134 5.90E-11 8.20E-11 Rubidium-88 1.90E-08 1.90E-08 Iodine-135 7.OOE-12 5.50E-11 Ruthenium-103 7.40E-14 1.50E-11 Strontium-89 2.15E-15 (1)

Strontium-90 5.60E-16 (1)

Tellurium-123m 6.60E-14 1.50E-11 Tritium 3.80E-07 3.80E-07 Zinc-65 1.90E-13 3.80E-11 Zirconium-95 1.80E-13 4.10E-11 Gross Alpha 3.60E-15 (1)

(1) Not required for batch releases.

18 PVNGS ARERR 2010

Table 4:

Unit I Gaseous Effluents - Summation Of All Releases Total For Est. Total Error Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year  % (1)

A. Fission & activation gases

1. Total release Ci 8.05E-02 4.80E-01 1.33E-01 1.35E-01 8.29E-01 3.54E+01
2. Average release rate for period ptCi/sec 1.04E-02 6.11E-02 1.67E-02 1.70E-02 2.63E-02
3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)

B. Iodine 131

1. Total Iodine 131 Ci 2.54E-06 1.44E-05 < LLD < LLD 1.69E-05 3.32E+01
2. Average release rate for period liCi/sec 3.27E-07 1.83E-06 < LLD < LLD 5.36E-07
3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)

C. Particulates

1. Particulates with half- lives > 8 days Ci < LLD 2.44E-04 1.02E-06 < LLD 2.45E-04 3.43E+01
2. Average release rate for period iiCi/sec < LLD 3.10E-05 1.28E-07 < LLD 7.77E-06
3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)
4. Gross Alpha radioactivity Ci < LLD < LLD < LLD < LLD < LLD D. Tritium z
1. Total release Ci 5.71 E+02 2.56E+02 3.28E+01 1.88E+01 8.78E+02 3.85E+01
2. Average release rate for period iCi/sec 7.34E+01 3.26E+01 4.13E+00 2.37E+00 2.78E+01 C', 3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)

(1) Estimated total error methodology is presented in Table 40.

C)

(2) See Table 11 for percent of ODCM Requirement limits.

Table 5:

Unit I Gaseous Effluents - Ground Level Releases - Continuous - Fission Gases and lodines Nuclides Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Released Year total

1. Fission gases Ar-41 Ci < LLD < LLD < LLD < LLD < LLD Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci < LLD < LLD < LLD < LLD < LLD Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD < LLD < LLD < LLD < LLD Xe-133 Ci < LLD < LLD < LLD < LLD < LLD Xe-133m Ci < LLD < LLD < LLD < LLD < LLD Xe-135 Ci < LLD < LLD < LLD < LLD < LLD Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD < LLD < LLD < LLD < LLD
2. lodines 1-131 Ci 2.54E-06 4.44E-06 < LLD < LLD 6.97E-06 1-132 Ci < LLD < LLD < LLD < LLD < LLD 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 2.54E-06 4.44E-06 < LLD < LLD 6.97E-06 20 PVNGS ARERR 2010

Table 6:

Unit I Gaseous Effluents - Ground Level Releases - Continuous - Particulates Nuclides Released Unit L Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total 3.Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD < LLD < LLD Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD 8.85E-05 1.02E-06 < LLD 8.95E-05 Co-60 Ci < LLD < LLD < LLD < LLD < LLD Cr-51 Ci < LLD 9.67E-06 < LLD < LLD 9.67E-06 Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD < LLD < LLD < LLD < LLD Cs-138 Ci < LLD < LLD < LLD < LLD < LLD Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD < LLD < LLD < LLD < LLD Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD 1.13E-06 < LLD < LLD 1.13E-06 Os-191 Ci < LLD 1.03E-06 < LLD < LLD 1.03E-06 Rb-88 Ci < LLD < LLD < LLD < LLD < LLD Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci < LLD < LLD < LLD < LLD < LLD Sr-90 Ci < LLD < LLD < LLD < LLD < LLD Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD 1.OOE-04 1.02E-06 < LLD 1.01 E-04 4.Tritium H-3 Ci 4.89E+01 5.28E+01 3.28E+01 1.87E+01 1.53E+02 21 PVNGS ARERR 2010

Table 7:

Unit 1 Gaseous Effluents - Ground Level Releases - Batch - Fission Gases and lodines Nuclides Released I Unit I Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

1. Fission gases Ar-41 Ci 7.83E-02 5.57E-02 1.01E-01 1.OOE-01 3.36E-01 Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci 3.39E-07 < LLD < LLD < LLD 3.39E-07 Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD 1.50E-03 < LLD < LLD 1.50E-03 Xe-133 Ci 2.38E-03 4.20E-01 3.18E-02 3.49E-02 4.89E-01 Xe-133m Ci 2.26E-06 2.29E-03 < LLD < LLD 2.29E-03 Xe-135 Ci 1.25E-05 4.65E-04 2.81E-04 3.15E-04 1.07E-03 Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 8.07E-02 4.80E-01 1.33E-01 1.35E-01 8.29E-01
2. lodines 1-131 Ci < LLD 9.92E-06 < LLD < LLD 9.92E-06 1-132 Ci < LLD 1.30E-04 < LLD < LLD 1.30E-04 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD 1.39E-04 < LLD < LLD 1.39E-04 22 PVNGS ARERR 2010

Table 8:

Unit 1 Gaseous Effluents - Ground Level Releases - Batch - Particulates Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD < LLD < LLD Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD 8.72E-05 < LLD < LLD 8.72E-05 Co-60 Ci < LLD 4.67E-06 < LLD < LLD 4.67E-06 Cr-51 Ci < LLD 4.41E-05 < LLD < LLD 4.41 E-05 Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD 8.1OE-07 < LLD < LLD 8.10E-07 Cs-1 38 Ci 5.92E-07 < LLD < LLD < LLD 5.92E-07 Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD 2.07E-06 < LLD < LLD 2.07E-06 Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD 3.72E-06 < LLD < LLD 3.72E-06 Os-191 Ci < LLD 8.79E-07 < LLD < LLD 8.79E-07 Rb-88 Ci 3.11E-06 < LLD < LLD < LLD 3.11E-06 Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci Note 1 Note 1 Note 1 Note 1 Note 1 Sr-90 Ci Note 1 Note 1 Note 1 Note 1 Note 1 Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 3.70E-06 1.43E-04 < LLD < LLD 1.47E-04 4.Tritium H-3 Ci 5.22E+02 2.03E+02 1.27E-02 9.86E-03 7.25E+02 Note 1 - Not required for batch releases 23 PVNGS ARERR 2010

Table 9:

Unit 1 Gaseous Effluents - Continuous and Batch - Fission Gases and lodines Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

1. Fission gases Ar-41 Ci 7.83E-02 5.57E-02 1.01E-01 1.OOE-01 3.36E-01 Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci 3.39E-07 < LLD < LLD < LLD 3.39E-07 Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD 1.50E-03 < LLD < LLD 1.50E-03 Xe-133 Ci 2.38E-03 4.20E-01 3.18E-02 3.49E-02 4.89E-01 Xe-133m Ci 2.26E-06 2.29E-03 < LLD < LLD 2.29E-03 Xe-135 Ci 1.25E-05 4.65E-04 2.81E-04 3.15E-04 1.07E-03 Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD. < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 8.07E-02 4.80E-01 1.33E-01 1.35E-01 8.29E-01
2. lodines 1-131 Ci 2.54E-06 1.44E-05 < LLD < LLD 1.69E-05 1-132 Ci < LLD 1.30E-04 < LLD < LLD 1.30E-04 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 2.54E-06 1.44E-04 < LLD < LLD 1.46E-04 24 PVNGS ARERR 2010

Table 10:

Unit 1 Gaseous Effluents - Continuous and Batch - Particulates Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD < LLD < LLD Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD 1.76E-04 1.02E-06 < LLD 1.77E-04 Co-60 Ci < LLD 4.67E-06 < LLD < LLD 4.67E-06 Cr-51 Ci < LLD 5.37E-05 < LLD < LLD 5.37E-05 Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD 8.1OE-07 < LLD < LLD 8.10E-07 Cs-138 Ci 5.92E-07 < LLD < LLD < LLD 5.92E-07 Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD 2.07E-06 < LLD < LLD 2.07E-06 Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD 4.85E-06 < LLD < LLD 4.85E-06 Os-191 Ci < LLD 1.91E-06 < LLD < LLD 1.91 E-06 Rb-88 Ci 3.11E-06 < LLD < LLD < LLD 3.11E-06 Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci < LLD < LLD < LLD < LLD < LLD Sr-90 Ci < LLD < LLD < LLD < LLD < LLD Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 3.70E-06 2.44E-04 1.02E-06 < LLD 2.48E-04 Total > 8 days Ci < LLD 2.44E-04 1.02E-06 < LLD 2.45E-04 4.Tritium H-3 Ci 5.71E+02 2.56E+02 3.28E+01 1.88E+01 8.78E+02 25 PVNGS ARERR 2010

Table 11:

Unit I Radiation Doses At And Beyond The Site Boundary Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total Gamma Air Dose mrad 2.06E-04 1.89E-04 2.70E-04 2.67E-04 9.31E-04 ODCM Req 4.1 Limit mrad 5.OOE+00 5.OOE+00 5.OOE+00 5.OOE+00 1.OOE+01

% ODCM Limit  % 4.12E-03 3.78E-03 5.40E-03 5.34E-03 9.31 E-03 Beta Air Dose mrad 7.32E-05 1.78E-04 1.04E-04 1.03E-04 4.58E-04 ODCM Req 4.1 Limit mrad 1.00E+01 1.OOE+01 1.00E+01 1.OOE+01 2.OOE+01

% ODCM Limit  % 7.32E-04 1.78E-03 1.04E-03 1.03E-03 2.29E-03 Maximum Organ Dose (excludingasn) Do mrem 2.05E-01 9.19E-02 1.18E-02 6.73E-03 3.15E-01 (excluding skin)

Age Teen Teen Teen Teen Teen Organ Thyroid Thyroid Lung (1) Thyroid ODCM Req. 4.2 Limit mrem 7.50E+00 7.50E+00 7.50E+00 7.50E+00 1.50E+01

% ODCM Limit  % 2.73E+00 1.23E+00 1.57E-01 8.97E-02 2.10E+00 Calculations are based on parameters and methodologies of the ODCM using historical meteorology. Dose is calculated to a hypothetical individual. In contrast, Appendix C dose calculations are based on concurrent meteorology, a real individual, and only the actual pathways present.

Note 1 - All organs except Bone.

26 PVNGS ARERR 2010

Table 12:

Unit 2 Gaseous Effluents - Summation Of All Releases Quarter 2 Quarter 4 Total For Total Error Unit A. Fission & activation gases

1. Total release Ci 9.07E-02 1.09E-01 1.43E-01 7.71E-01 1.11E+00 3.54E+01
2. Average release rate for period pCi/sec 1.1 7E-02 1.39E-02 1.80E-02 9.70E-02 3.52E-02
3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)

B. Iodine 131

1. Total Iodine 131 Ci < LLD < LLD < LLD < LLD <LLD 3.32E+01
2. Average release rate for period ItCi/sec < LLD < LLD < LLD < LLD < LLD
3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)

C. Particulates

1. Particulates with half- lives > 8 days Ci < LLD 1.23E-06 < LLD < LLD 1.23E-06 3.43E+01
2. Average release rate for period pCi/sec < LLD 1.56E-07 < LLD < LLD 3.90E-08
3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)
4. Gross Alpha radioactivity Ci < LLD < LLD < LLD < LLD < LLD

-u D. Tritium z

0 1. Total release Ci 8.45E+01 1.86E+02 1.78E+01 1.86E+02 4.74E+02 3.85E+01 02

2. Average release rate for period f Ci/sec 1.09E+01 2.37E+01 2.24E+00 2.34E+01 1.50E+01 m
3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)

C3 C3 (1) Estimated total error methodology is presented in Table 40.

(2) See Table 19 for percent of ODCM Requirement limits.

Table 13:

Unit 2 Gaseous Effluents - Ground Level Releases - Continuous - Fission Gases and lodines Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

1. Fission gases Ar-41 Ci < LLD < LLD < LLD < LLD < LLD Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci < LLD < LLD < LLD < LLD < LLD Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD < LLD < LLD < LLD < LLD Xe-133 Ci < LLD < LLD < LLD < LLD < LLD Xe-133m Ci < LLD < LLD < LLD < LLD < LLD Xe-135 Ci < LLD < LLD < LLD < LLD < LLD Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD < LLD < LLD < LLD < LLD
2. lodines 1-131 Ci < LLD < LLD < LLD < LLD < LLD 1-132 Ci < LLD < LLD < LLD < LLD < LLD 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD < LLD < LLD < LLD < LLD 28 PVNGS ARERR 2010

Table 14:

Unit 2 Gaseous Effluents - Ground Level Releases - Continuous - Particulates Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD < LLD < LLD Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD < LLD < LLD < LLD < LLD Co-60 Ci < LLD < LLD < LLD < LLD < LLD Cr-51 Ci < LLD < LLD < LLD < LLD < LLD Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD < LLD < LLD < LLD < LLD Cs-138 Ci < LLD < LLD < LLD < LLD < LLD Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD < LLD < LLD < LLD < LLD Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD < LLD < LLD < LLD < LLD Os-191 Ci < LLD < LLD <. LLD < LLD < LLD Rb-88 Ci < LLD < LLD < LLD < LLD < LLD Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci < LLD < LLD < LLD < LLD < LLD Sr-90 Ci < LLD < LLD < LLD < LLD < LLD Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD < LLD < LLD < LLD < LLD
4. Tritium H-3 Ci 1.76E+01 1.89E+01 1.78E+01 1.31E+01 6.74E+01 29 PVNGS ARERR 2010

Table 15:

Unit 2 Gaseous Effluents - Ground Level Releases - Batch - Fission Gases and lodines Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

1. Fission gases Ar-41 Ci 9.03E-02 1.05E-01 9.22E-02 5.98E-01 8.85E-01 Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci < LLD < LLD < LLD < LLD < LLD Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD < LLD < LLD < LLD < LLD Xe-133 Ci 3.28E-04 4.07E-03 4.94E-02 1.68E-01 2.22E-01 Xe-1 33m Ci < LLD < LLD < LLD < LLD < LLD Xe-135 Ci < LLD 5.25E-05 1.84E-03 5.05E-03 6.94E-03 Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 9.07E-02 1.09E-01 1.43E-01 7.71E-01 1.11E+00
2. lodines 1-131 Ci < LLD < LLD < LLD < LLD < LLD 1-132 Ci < LLD < LLD < LLD < LLD < LLD 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD < LLD < LLD < LLD < LLD 30 PVNGS ARERR 2010

Table 16:

Unit 2 Gaseous Effluents - Ground Level Releases - Batch - Particulates Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD < LLD < LLD Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD < LLD < LLD < LLD < LLD Co-60 Ci < LLD < LLD < LLD < LLD < LLD Cr-51 Ci < LLD < LLD < LLD < LLD < LLD Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD 1.23E-06 < LLD < LLD 1.23E-06 Cs-138 Ci < LLD < LLD < LLD < LLD < LLD Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD < LLD < LLD < LLD < LLD Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD < LLD < LLD < LLD < LLD Os-191 Ci < LLD < LLD < LLD < LLD < LLD Rb-88 Ci < LLD < LLD < LLD < LLD < LLD Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci Note 1 Note 1 Note 1 Note 1 Note 1 Sr-90 Ci Note 1 Note 1 Note 1 Note 1 Note 1 Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD 1.23E-06 < LLD < LLD 1.23E-06
4. Tritium H-3 Ci 6.69E+01 1.67E+02 1.28E-02 1.73E+02 4.07E+02 Note 1 - Not required for batch releases 31 PVNGS ARERR 2010

Table 17:

Unit 2 Gaseous Effluents - Continuous and Batch - Fission Gases and lodines Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

1. Fission gases Ar-41 Ci 9.03E-02 1.05E-01 9.22E-02 5.98E-01 8.85E-01 Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci < LLD < LLD < LLD < LLD < LLD Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD < LLD < LLD < LLD < LLD Xe-133 Ci 3.28E-04 4.07E-03 4.94E-02 1.68E-01 2.22E-01 Xe-133m Ci < LLD < LLD < LLD < LLD < LLD Xe-135 Ci < LLD 5.25E-05 1.84E-03 5.05E-03 6.94E-03 Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 9.07E-02 1.09E-01 1.43E-01 7.71E-01 1.11E+00
2. lodines 1-131 Ci < LLD < LLD < LLD < LLD < LLD 1-132 Ci < LLD < LLD < LLD < LLD < LLD 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD < LLD < LLD < LLD < LLD 32 PVNGS ARERR 2010

Table 18:

Unit 2 Gaseous Effluents - Continuous and Batch - Particulates Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD < LLD < LLD Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD < LLD < LLD < LLD < LLD Co-60 Ci < LLD < LLD < LLD < LLD < LLD Cr-51 Ci < LLD < LLD < LLD < LLD < LLD Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD 1.23E-06 < LLD < LLD 1.23E-06 Cs-138 Ci < LLD < LLD < LLD < LLD < LLD Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD < LLD < LLD < LLD < LLD Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD < LLD < LLD < LLD < LLD Os-191 Ci < LLD < LLD < LLD < LLD < LLD Rb-88 Ci < LLD < LLD < LLD < LLD < LLD Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci < LLD < LLD < LLD < LLD < LLD Sr-90 Ci < LLD < LLD < LLD < LLD < LLD Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD 1.23E-06 < LLD < LLD 1.23E-06 Total > 8 days Ci < LLD 1.23E-06 < LLD < LLD 1.23E-06
4. Tritium H-3 Ci 8.45E+01 1.86E+02 1.78E+01 1.86E+02 4.74E+02 33 PVNGS ARERR 2010

Table 19:

Unit 2 Radiation Doses At And Beyond The Site Boundary Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total Gamma Air Dose mrad 2.37E-04 2.75E-04 2.48E-04 1.59E-03 2.35E-03 ODCM Req 4.1 Limit mrad 5.OOE+00 5.OOE+00 5.OOE+00 5.OOE+00 1.OOE+01

% ODCM Limit  % 4.74E-03 5.50E-03 4.96E-03 3.18E-02 2.35E-02 Beta Air Dose mrad 8.38E-05 9.81E-05 1.01E-04 6.07E-04 8.91E-04 ODCM Req 4.1 Limit mrad 1.OOE+01 1.OOE+01 1.OOE+01 1.OOE+01 2.OOE+01

% ODCM Limit  % 8.38E-04 9.81 E-04 1.01E-03 6.07E-03 4.46E-03 Maximum Organ Dose (excludingsn) Dos mrem 3.03E-02 6.66E-02 6.38E-03 6.69E-02 1.70E-01 (excluding skin)

Age Teen Teen Teen Teen Teen Organ (1) Liver (1) (1) Liver ODCM Req. 4.2 Limit mrem 7.50E+00 7.50E+00 7.50E+00 7.50E+00 1.50E+01

% ODCM Limit  % 4.04E-01 8.88E-01 8.51E-02 8.92E-01 1.13E+00 Calculations are based on parameters and methodologies of the ODCM using historical meteorology. Dose is calculated to a hypothetical individual. In contrast, Appendix C dose calculations are based on concurrent meteorology, a real individual, and only the actual pathways present.

Note 1 - All organs except Bone.

34 PVNGS ARERR 2010

Table 20:

Unit 3 Gaseous Effluents - Summation Of All Releases Quarter 2 Quarter 3 Quarter 4 Total For Est. Total Error Unit Quarter 1 Year  % (1)

A. Fission & activation gases

1. Total release Ci 6.73E-02 7.90E-02 7.80E-02 4.98E-01 7.22E-01 3.54E+01
2. Average release rate for period pCi/sec 8.65E-03 1.OOE-02 9.81 E-03 6.27E-02 2.29E-02
3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)

B. Iodine 131

1. Total Iodine 131 Ci 2.76E-06 < LLD 9.71 E-07 9.89E-06 1.36E-05 3.32E+01
2. Average release rate for period pCi/sec 3.55E-07 < LLD 1.22E-07 1.24E-06 4.31E-07 3.. Percent i of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)

C. Particulates

1. Particulates with half- lives > 8 days Ci < LLD 3.45E-07 1.15E-06 3.57E-04 3.59E-04 3.43E+01
2. Average release rate for period pCi/sec < LLD 4.39E-08 1.45E-07 4.49E-05 1.14E-05
3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)
4. Gross Alpha radioactivity Ci < LLD < LLD < LLD < LLD < LLD

-o D. Tritium z0

1. Total release Ci 3.98E+02 2.33E+02 3.90E+02 1.65E+02 1.19E+03 3.85E+01 C)
2. Average release rate for period gCi/sec 5.12E+01 2.96E+01 4.91E+O1 2.08E+01 3.77E+01
0 3. Percent of ODCM Requirement limit  % NA (2) NA (2) NA (2) NA (2) NA (2)

P0 (1) Estimated total error methodology is presented in Table 40.

(2) See Table 27 for percent of ODCM Requirement limits.

Table 21:

Unit 3 Gaseous Effluents - Ground Level Releases - Continuous - Fission Gases and lodines Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

1. Fission gases Ar-41 Ci < LLD < LLD < LLD < LLD < LLD Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci < LLD < LLD < LLD < LLD < LLD Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD < LLD < LLD < LLD < LLD Xe-133 Ci < LLD < LLD < LLD < LLD < LLD Xe-133m Ci < LLD < LLD < LLD < LLD < LLD Xe-135 Ci < LLD < LLD < LLD < LLD < LLD Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD < LLD < LLD < LLD < LLD
2. lodines 1-131 Ci 2.76E-06 < LLD 9.71 E-07 3.53E-06 7.26E-06 1-132 Ci < LLD < LLD < LLD 2.32E-04 2.32E-04 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 2.76E-06 < LLD 9.71 E-07 2.36E-04 2.40E-04 36 PVNGS ARERR 2010

Table 22:

Unit 3 Gaseous Effluents - Ground Level Releases - Continuous - Particulates

,Nuclides Released I Unit I Quarter 1 Quarter 2 1Quarter 3 1Quarter 4 1Year total

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD < LLD < LLD Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD 3.45E-07 < LLD 1.61E-04 1.62E-04 Co-60 Ci < LLD < LLD 1.15E-06 9.34E-06 1.05E-05 Cr-51 Ci < LLD < LLD < LLD 2.57E-05 2.57E-05 Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD < LLD < LLD < LLD < LLD Cs-138 Ci < LLD < LLD < LLD < LLD < LLD Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD < LLD < LLD 1.48E-06 1.48E-06 Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD < LLD < LLD < LLD < LLD Os-191 Ci < LLD < LLD < LLD < LLD < LLD Rb-88 Ci < LLD < LLD < LLD < LLD < LLD Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci < LLD < LLD < LLD < LLD < LLD Sr-90 Ci < LLD < LLD < LLD < LLD < LLD Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD 8.99E-07 8.99E-07 Total Ci < LLD 3.45E-07 1.15E-06 1.99E-04 2.OOE-04
4. Tritium H-3 Ci 2.12E+01 1.67E+01 1.51E+01 2.79E+01 8.10E+01 37 PVNGS ARERR 2010

Table 23:

Unit 3 Gaseous Effluents - Ground Level Releases - Batch - Fission Gases and lodines Nuclides Released I Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

1. Fission gases Ar-41 Ci 6.73E-02 7.90E-02 7.80E-02 4.94E-01 7.18E-01 Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci < LLD < LLD < LLD < LLD < LLD Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD < LLD < LLD < LLD < LLD Xe-133 Ci < LLD < LLD < LLD 3.79E-03 3.79E-03 Xe-133m Ci < LLD < LLD < LLD < LLD < LLD Xe-135 Ci < LLD < LLD < LLD < LLD < LLD Xe-1 35m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 6.73E-02 7.90E-02 7.80E-02 4.98E-01 7.22E-01
2. lodines 1-131 Ci < LLD < LLD < LLD 6.36E-06 6.36E-06 1-132 Ci < LLD < LLD < LLD 1.57E-04 1.57E-04 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD < LLD < LLD 1.63E-04 1.63E-04 38 PVNGS ARERR 2010

Table 24:

Unit 3 Gaseous Effluents - Ground Level Releases - Batch - Particulates Nuclides Released )Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD 2.31E-06 2.31 E-06 Ce-141 Ci < LLD <LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD < LLD < LLD 1.29E-04 1.29E-04 Co-60 Ci < LLD < LLD < LLD 5.87E-06 5.87E-06 Cr-51 Ci < LLD < LLD < LLD 1.19E-05 1.19E-05 Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD < LLD < LLD 1.20E-07 1.20E-07 Cs-138 Ci < LLD < LLD < LLD < LLD < LLD Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD < LLD < LLD 2.02E-07 2.02E-07 Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD < LLD < LLD 5.54E-06 5.54E-06 Os-191 Ci < LLD < LLD < LLD < LLD < LLD Rb-88 Ci < LLD < LLD < LLD < LLD < LLD Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci Note 1 Note 1 Note I Note 1 Note 1 Sr-90 Ci Note 1 Note 1 Note 1 Note 1 Note 1 Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD 5.84E-06 5.84E-06 Total Ci < LLD < LLD < LLD 1.61E-04 1.61E-04
4. Tritium H-3 Ci 3.77E+02 2.16E+02 3.75E+02 1.37E+02 1.10E+03 Note 1 - Not required for batch releases 39 PVNGS ARERR 2010

Table 25:

Unit 3 Gaseous Effluents - Continuous and Batch - Fission Gases and lodines Nuclides Released Unit Quarter I Quarter 2 Quarter 3 Quarter4 Year total

1. Fission gases Ar-41 Ci 6.73E-02 7.90E-02 7.80E-02 4.94E-01 7.18E-01 Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci < LLD < LLD < LLD < LLD < LLD Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD < LLD < LLD < LLD < LLD Xe-133 Ci < LLD < LLD < LLD 3,79E-03 3.79E-03 Xe-133m Ci < LLD < LLD < LLD < LLD < LLD Xe-135 Ci < LLD < LLD < LLD < LLD < LLD Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 6.73E-02 7.90E-02 7.80E-02 4.98E-01 7.22E-01
2. lodines 1-131 Ci 2.76E-06 < LLD 9.71E-07 9.89E-06 1.36E-05 1-132 Ci < LLD < LLD < LLD 3.89E-04 3.89E-04 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 2.76E-06 < LLD 9.71 E-07 3.99E-04 4.03E-04 40 PVNGS ARERR 2010

Table 26:

Unit 3 Gaseous Effluents - Continuous and Batch - Particulates Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD 2.31E-06 2.31 E-06 Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD 3.45E-07 < LLD 2.90E-04 2.91E-04 Co-60 Ci < LLD < LLD 1.15E-06 1.52E-05 1.64E-05 Cr-51 Ci < LLD < LLD < LLD 3.76E-05 3.76E-05 Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD < LLD < LLD 1.20E-07 1.20E-07 Cs-138 Ci < LLD < LLD < LLD < LLD < LLD Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD < LLD < LLD 1.68E-06 1.68E-06 Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD < LLD < LLD 5.54E-06 5.54E-06 Os-191 Ci < LLD < LLD < LLD < LLD < LLD Rb-88 Ci < LLD < LLD < LLD < LLD < LLD Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci < LLD < LLD < LLD < LLD < LLD Sr-90 Ci < LLD < LLD < LLD < LLD < LLD Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD 6.74E-06 6.74E-06 Total Ci < LLD 3.45E-07 1.15E-06 3.60E-04 3.61 E-04 Total > 8 days Ci < LLD 3.45E-07 1.15E-06 3.57E-04 3.59E-04
4. Tritium H-3 Ci 3.98E+02 2.33E+02 3.90E+02 1.65E+02 1.19E+03 41 PVNGS ARERR 2010

Table 27:

Unit 3 Radiation Doses At And Beyond The Site Boundary Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total Gamma Air Dose mrad 1.77E-04 2.08E-04 2.05E-04 1.30E-03 1.89E-03 ODCM Req 4.1 Limit mrad 5.OOE+00 5.OOE+00 5.OOE+00 5.OOE+00 1.OOE+01

% ODCM Limit  % 3.54E-03 4.16E-03 4.1OE-03 2.60E-02 1.89E-02 Beta Air Dose mrad 6.23E-05 7.32E-05 7.22E-05 4.59E-04 6.67E-04 ODCM Req 4.1 Limit mrad 1.OOE+01 1.OOE+01 1.OOE+01 1.OOE+01 2.OOE+01

% ODCM Limit  % 6.23E-04 7.32E-04 7.22E-04 4.59E-03 3.34E-03 Maximum Organ Dose (excludingsn) Dos mrem 1.43E-01 8.35E-02 1.40E-01 5.93E-02 4.26E-01 (excluding skin)

Age Teen Teen Teen Teen Teen Organ Thyroid Lung Thyroid Lung Thyroid ODCM Req. 4.2 Limit mrem 7.50E+00 7.50E+00 7.50E+00 7.50E+00 1.50E+01

% ODCM Limit  % 1.91 E+00 1.11E+00 1.87E+00 7.91 E-01 2.84E+00 Calculations are based on parameters and methodologies of the ODCM using historical meteorology. Dose is calculated to a hypothetical individual. In contrast, Appendix C dose calculations are based on concurrent meteorology, a real individual, and only the actual pathways present.

Note 1 - All organs except Bone 42 PVNGS ARERR 2010

Table 28:

Units 1, 2, and 3 Gaseous Effluents - Continuous - Fission Gases and lodines -

Total By Quarter Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

1. Fission gases Ar-41 Ci < LLD < LLD < LLD < LLD < LLD Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci < LLD < LLD < LLD < LLD < LLD Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD < LLD < LLD < LLD < LLD Xe-133 Ci < LLD < LLD < LLD < LLD < LLD Xe-133m Ci < LLD < LLD < LLD < LLD < LLD Xe-135 Ci < LLD < LLD < LLD < LLD < LLD Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD < LLD < LLD < LLD < LLD
2. lodines 1-131 Ci 5.30E-06 4.44E-06 9.71E-07 3.53E-06 1.42E-05 1-132 Ci < LLD < LLD < LLD 2.32E-04 2.32E-04 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 5.30E-06 4.44E-06 9.71 E-07 2.36E-04 2.47E-04 43 PVNGS ARERR 2010

Table 29:

Units 1, 2, and 3 Gaseous Effluents - Continuous - Particulates -

Total By Quarter Nuclides Released Unit I Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

3. Particulates Ag-11Orn Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD < LLD < LLD Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD 8.89E-05 1.02E-06 1.61E-04 2.51 E-04 Co-60 Ci < LLD < LLD 1.15E-06 9.34E-06 1.05E-05 Cr-51 Ci < LLD 9.67E-06 < LLD 2.57E-05 3.54E-05 Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD < LLD < LLD < LLD < LLD Cs-138 Ci < LLD < LLD < LLD < LLD < LLD Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD < LLD < LLD 1.48E-06 1.48E-06 Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD 1.13E-06 < LLD < LLD 1.13E-06 Os-191 Ci < LLD 1.03E-06 < LLD < LLD 1.03E-06 Rb-88 Ci < LLD < LLD < LLD < LLD < LLD Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci < LLD < LLD < LLD < LLD < LLD Sr-90 Ci < LLD < LLD < LLD < LLD < LLD Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD 8.99E-07 8.99E-07 Total Ci < LLD 1.01 E-04 2.18E-06 1.99E-04 3.01E-04
4. Tritium H-3 Ci 8.77E+01 8.85E+01 6.56E+01 5.98E+01 3.02E+02 44 PVNGS ARERR 2010

Table 30:

Units 1, 2, and 3 Gaseous Effluents - Batch - Fission Gases and lodines -

Total By Quarter Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

1. Fission gases Ar-41 Ci 2.36E-01 2.39E-01 2.72E-01 1.19E+00 1.94E+00 Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci 3.39E-07 < LLD < LLD < LLD 3.39E-07 Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD 1,50E-03 < LLD < LLD 1.50E-03 Xe-133 Ci 2.71E-03 4.24E-01 8.12E-02 2.07E-01 7.14E-01 Xe-133m Ci 2.26E-06 2.29E-03 < LLD < LLD 2.29E-03 Xe-135 Ci 1.25E-05 5.18E-04 2.12E-03 5.37E-03 8.02E-03 Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 2.39E-01 6.67E-01 3.55E-01 1.40E+00 2.67E+00
2. lodines 1-131 Ci < LLD 9.92E-06 < LLD 6.36E-06 1.63E-05 1-132 Ci < LLD 1.30E-04 < LLD 1.57E-04 2.86E-04 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci < LLD 1.39E-04 < LLD 1.63E-04 3.02E-04 45 PVNGS ARERR 2010

Table 31:

Units 1, 2, and 3 Gaseous Effluents - Batch - Particulates -

Total By Quarter Nuclides Released Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD 2.31E-06 2.31E-06 Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD 8.72E-05 < LLD 1.29E-04 2.16E-04 Co-60 Ci < LLD 4.67E-06 < LLD 5.87E-06 1.05E-05 Cr-51 Ci < LLD 4.41 E-05 < LLD 1.19E-05 5.60E-05 Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD 2.04E-06 < LLD 1.20E-07 2.16E-06 Cs-138 Ci 5.92E-07 < LLD < LLD < LLD 5.92E-07 Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD 2.07E-06 < LLD 2.02E-07 2.28E-06 Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD 3.72E-06 < LLD 5.54E-06 9.26E-06 Os-191 Ci < LLD 8.79E-07 < LLD < LLD 8.79E-07 Rb-88 Ci 3.11E-06 < LLD < LLD < LLD 3.11E-06 Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci Note 1 Note 1 Note 1 Note 1 Note 1 Sr-90 Ci Note 1 Note 1 Note 1 Note 1 Note 1 Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD 5.84E-06 5.84E-06 Total Ci 3.70E-06 1.45E-04 < LLD 1.61E-04 3.09E-04
4. Tritium H-3 Ci 9.66E+02 5.85E+02 3.75E+02 3.10E+02 2.24E+03 Note 1 - Not required for batch releases 46 PVNGS ARERR 2010

Table 32:

Units 1, 2, and 3 Gaseous Effluents - Continuous and Batch - Fission Gases and lodines -

Total .By Quarter Nuclides Released I Unit I Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

1. Fission gases Ar-41 Ci 2.36E-01 2.39E-01 2.72E-01 1.19E+00 1.94E+00 Kr-83m Ci < LLD < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD < LLD Kr-85m Ci 3.39E-07 < LLD < LLD < LLD 3.39E-07 Kr-87 Ci < LLD < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD < LLD Xe-131m Ci < LLD 1.50E-03 < LLD < LLD 1.50E-03 Xe-133 Ci 2.71E-03 4.24E-01 8.12E-02 2.07E-01 7.14E-01 Xe-133m Ci 2.26E-06 2.29E-03 < LLD < LLD 2.29E-03 Xe-135 Ci 1.25E-05 5.18E-04 2.12E-03 5.37E-03 8.02E-03 Xe-135m Ci < LLD < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 2.39E-01 6.67E-01 3.55E-01 1.40E+00 2.67E+00
2. lodines 1-131 Ci 5.30E-06 1.44E-05 9.71 E-07 9.89E-06 3.05E-05 1-132 Ci < LLD 1.30E-04 < LLD 3.89E-04 5.19E-04 1-133 Ci < LLD < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD < LLD Total Ci 5.30E-06 1.44E-04 9.71E-07 3.99E-04 5.49E-04 47 PVNGS ARERR 2010

Table 33:

Units 1, 2, and 3 Gaseous Effluents - Continuous and Batch - Particulates -

Total By Quarter Nuclides Released Unit I Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD 2.31E-06 2.31E-06 Ce-141 Ci < LLD < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD < LLD Co-58 Ci < LLD 1.76E-04 1.02E-06 2.90E-04 4.67E-04 Co-60 Ci < LLD 4.67E-06 1.15E-06 1.52E-05 2.1OE-05 Cr-51 Ci < LLD 5.37E-05 < LLD 3.76E-05 9.14E-05 Cs-134 Ci < LLD < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD < LLD Cs-137 Ci < LLD 2.04E-06 < LLD 1.20E-07 2.16E-06 Cs-138 Ci 5.92E-07 < LLD < LLD < LLD 5.92E-07 Fe-59 Ci < LLD < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD < LLD Mn-54 Ci < LLD 2.07E-06 < LLD 1.68E-06 3.76E-06 Mo-99 Ci < LLD < LLD < LLD < LLD < LLD Nb-95 Ci < LLD 4.85E-06 < LLD 5.54E-06 1.04E-05 Os-191 Ci < LLD 1.91 E-06 < LLD < LLD 1.91 E-06 Rb-88 Ci 3.11E-06 < LLD < LLD < LLD 3.11E-06 Ru-103 Ci < LLD < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD < LLD Sr-89 Ci < LLD < LLD < LLD < LLD < LLD Sr-90 Ci < LLD < LLD < LLD < LLD < LLD Tc-99m Ci < LLD < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD < LLD 6.74E-06 6.74E-06 Total Ci 3.70E-06 2.45E-04 2.18E-06 3.60E-04 6.11E-04 Total > 8 days Ci < LLD 2.45E-04 2.18E-06 3.57E-04 6.05E-04
4. Tritium H-3 Ci 1.05E+03 6.74E+02 4.41E+02 3.70E+02 2.54E+03 48 PVNGS ARERR 2010

Table 34:

Units 1, 2 and 3 Gaseous Effluents- Continuous - Fission Gases and Iodine -

Total By Unit Nuclides Released Unit Unit 1 Unit 2 Unit 3 Total Units 1,2and3

1. Fission gases Ar-41 Ci < LLD < LLD < LLD < LLD Kr-83m Ci < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD Kr-85m Ci < LLD < LLD < LLD < LLD Kr-87 Ci < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD Xe-131m Ci < LLD < LLD < LLD < LLD Xe-133 Ci < LLD < LLD < LLD < LLD Xe-133m Ci < LLD < LLD < LLD < LLD Xe-135 Ci < LLD < LLD < LLD < LLD Xe-135m Ci < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD Total Ci < LLD < LLD < LLD < LLD
2. lodines 1-131 Ci 6.97E-06 < LLD 7.26E-06 1.42E-05 1-132 Ci < LLD < LLD 2.32E-04 2.32E-04 1-133 Ci < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD Total Ci 6.97E-06 < LLD 2.40E-04 2.47E-04 49 PVNGS ARERR 2010

Table 35:

Units 1, 2 and 3 Gaseous Effluents- Continuous - Particulates -

Total By Unit Nuclides Released Unit Unit 1 Unit 2 Unit 3 1Total Toal Units U

_________________________________ _______ j1,2 and 3

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD < LLD < LLD Ce-141 Ci < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD Co-58 Ci 8.95E-05 < LLD 1.62E-04 2.51E-04 Co-60 Ci < LLD < LLD 1.05E-05 1.05E-05 Cr-51 Ci 9.67E-06 < LLD 2.57E-05 3.54E-05 Cs-134 Ci < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD Cs-137 Ci < LLD < LLD < LLD < LLD Cs-138 Ci < LLD < LLD < LLD < LLD Fe-59 Ci < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD Mn-54 Ci < LLD < LLD 1.48E-06 1.48E-06 Mo-99 Ci < LLD < LLD < LLD < LLD Nb-95 Ci 1.13E-06 < LLD < LLD 1.13E-06 Os-191 Ci 1.03E-06 < LLD < LLD 1.03E-06 Rb-88 Ci < LLD < LLD < LLD < LLD Ru-103 Ci < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD Sr-89 Ci < LLD < LLD < LLD < LLD Sr-90 Ci < LLD < LLD < LLD < LLD Tc-99m Ci < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD 8.99E-07 8.99E-07 Total Ci 1.01E-04 < LLD 2.OOE-04 3.01E-04
4. Tritium H-3 Ci 1.53E+02 6.74E+01 8.10E+01 3.02E+02 50 PVNGS ARERR 2010

Table 36:

Units 1, 2 and 3 Gaseous Effluents- Batch - Fission Gases and Iodine -

Total By Unit Nuclides Released 1 J

Unit Unit 1 Unit 2

___ _ I Unit 3

___ _ J Total Units 1,2and3

1. Fission gases Ar-41 Ci 3.36E-01 8.85E-01 7.18E-01 1.94E+00 Kr-83m Ci < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD Kr-85m Ci 3.39E-07 < LLD < LLD 3.39E-07 Kr-87 Ci < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD Xe-131m Ci 1.50E-03 < LLD < LLD 1.50E-03 Xe-133 Ci 4.89E-01 2.22E-01 3.79E-03 7.14E-01 Xe-1 33m Ci 2.29E-03 < LLD < LLD 2.29E-03 Xe-135 Ci 1.07E-03 6.94E-03 < LLD 8.02E-03 Xe-135m Ci < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD Total Ci 8.29E-01 1.11E+00 7.22E-01 2.67E+00
2. lodines 1-131 Ci 9.92E-06 < LLD 6.36E-06 1.63E-05 1-132 Ci 1.30E-04 < LLD 1.57E-04 2.86E-04 1-133 Ci < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD Total Ci 1.39E-04 < LLD 1.63E-04 3.02E-04 51 PVNGS ARERR 2010

Table 37:

Units 1, 2 and 3 Gaseous Effluents- Batch - Particulates -

Total By Unit Nuclides Released Unit Unit 1 Unit 2 Unit 3 1Total Units

__~~~, _ __ _ and 3

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD .2.31E-06 2.31E-06 Ce-141 Ci < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD Co-58 Ci 8.72E-05 < LLD 1.29E-04 2.16E-04 Co-60 Ci 4.67E-06 < LLD 5.87E-06 1.05E-05 Cr-51 Ci 4.41E-05 < LLD 1.19E-05 5.60E-05 Cs-134 Ci < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD Cs-137 Ci 8.10E-07 1.23E-06 1.20E-07 2.16E-06 Cs-1 38 Ci 5.92E-07 < LLD < LLD 5.92E-07 Fe-59 Ci < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD Mn-54 Ci 2.07E-06 < LLD 2.02E-07 2.28E-06 Mo-99 Ci < LLD < LLD < LLD < LLD Nb-95 Ci 3.72E-06 < LLD 5.54E-06 9.26E-06 Os-191 Ci 8.79E-07 < LLD < LLD 8.79E-07 Rb-88 Ci 3.11E-06 < LLD < LLD 3.11E-06 Ru-103 Ci < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD Sr-89 Ci Note 1 Note 1 Note 1 Note 1 Sr-90 Ci Note 1 Note 1 Note 1 Note 1 Tc-99m Ci < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD 5.84E-06 5.84E-06 Total Ci 1.47E-04 1.23E-06 1.61E-04 3.09E-04
4. Tritium H-3 Ci 7.25E+02 4.07E+02 1.1OE+03 2.24E+03 Note 1 - Not required for batch releases 52 PVNGS ARERR 2010

Table 38:

Units 1, 2 and 3 Gaseous Effluents- Continuous and Batch - Fission Gases and Iodine -

Total By Unit Nuclides Released Unit Unit 1 Unit 2 Unit 3 Total Units 1,2and3

1. Fission gases Ar-41 Ci 3.36E-01 8.85E-01 7.18E-01 1.94E+00 Kr-83m Ci < LLD < LLD < LLD < LLD Kr-85 Ci < LLD < LLD < LLD < LLD Kr-85m Ci 3.39E-07 < LLD < LLD 3.39E-07 Kr-87 Ci. < LLD < LLD < LLD < LLD Kr-88 Ci < LLD < LLD < LLD < LLD Kr-89 Ci < LLD < LLD < LLD < LLD Kr-90 Ci < LLD < LLD < LLD < LLD Xe-131m Ci 1.50E-03 < LLD < LLD 1.50E-03 Xe-133 Ci 4.89E-01 2.22E-01 3.79E-03 7.14E-01 Xe-133m Ci 2.29E-03 < LLD < LLD 2.29E-03 Xe-135 Ci 1.07E-03 6.94E-03 < LLD 8.02E-03 Xe-135m Ci < LLD < LLD < LLD < LLD Xe-137 Ci < LLD < LLD < LLD < LLD Xe-138 Ci < LLD < LLD < LLD < LLD Total Ci 8.29E-01 1.11E+00 7.22E-01 2.67E+00
2. lodines 1-131 Ci 1.69E-05 < LLD 1.36E-05 3.05E-05 1-132 Ci 1.30E-04 < LLD 3.89E-04 5.19E-04 1-133 Ci < LLD < LLD < LLD < LLD 1-134 Ci < LLD < LLD < LLD < LLD 1-135 Ci < LLD < LLD < LLD < LLD Total Ci 1.46E-04 < LLD 4.03E-04 5.49E-04 53 PVNGS ARERR 2010

Table 39:

Units 1, 2 and 3 Gaseous Effluents - Continuous and Batch - Particulates -

Total By Unit Nuclides Released Unit Unit 1 Unit 2 Unit 3 Total Units 1, 2 and 3

3. Particulates Ag-110m Ci < LLD < LLD < LLD < LLD Ba-140 Ci < LLD < LLD < LLD < LLD Br-82 Ci < LLD < LLD 2.31E-06 2.31 E-06 Ce-141 Ci < LLD < LLD < LLD < LLD Ce-144 Ci < LLD < LLD < LLD < LLD Co-57 Ci < LLD < LLD < LLD < LLD Co-58 Ci 1.77E-04 < LLD 2.91E-04 4.67E-04 Co-60 Ci 4.67E-06 < LLD 1.64E-05 2.1OE-05 Cr-51 Ci 5.37E-05 < LLD 3.76E-05 9.14E-05 Cs-134 Ci < LLD < LLD < LLD < LLD Cs-136 Ci < LLD < LLD < LLD < LLD Cs-137 Ci 8.10E-07 1.23E-06 1.20E-07 2.16E-06 Cs-1 38 Ci 5.92E-07 < LLD < LLD 5.92E-07 Fe-59 Ci < LLD < LLD < LLD < LLD La-140 Ci < LLD < LLD < LLD < LLD Mn-54 Ci 2.07E-06 < LLD 1.68E-06 3.76E-06 Mo-99 Ci < LLD < LLD < LLD < LLD Nb-95 Ci 4.85E-06 < LLD 5.54E-06 1.04E-05 Os-191 Ci 1.91 E-06 < LLD < LLD 1.91E-06 Rb-88 Ci 3.11E-06 < LLD < LLD 3.11E-06 Ru-103 Ci < LLD < LLD < LLD < LLD Ru-106 Ci < LLD < LLD < LLD < LLD Sb-122 Ci < LLD < LLD < LLD < LLD Sb-124 Ci < LLD < LLD < LLD < LLD Sb-125 Ci < LLD < LLD < LLD < LLD Se-75 Ci < LLD < LLD < LLD < LLD Sn-113m Ci < LLD < LLD < LLD < LLD Sr-89 Ci < LLD < LLD < LLD < LLD Sr-90 Ci < LLD < LLD < LLD < LLD Tc-99m Ci < LLD < LLD < LLD < LLD Te-123m Ci < LLD < LLD < LLD < LLD Zn-65 Ci < LLD < LLD < LLD < LLD Zr-95 Ci < LLD < LLD 6.74E-06 6.74E-06 Total Ci 2.48E-04 1.23E-06 3.61E-04 6.11E-04 Total > 8 days Ci 2.45E-04 1.23E-06 3.59E-04 6.05E-04
4. Tritium H-3 Ci 8.78E+02 4.74E+02 1.19E+03 2.54E+03 54 PVNGS ARERR 2010

Table 40:

Estimation of Total Percent Error The estimated total error is calculated as follows:

2 2 2 2 Total Percent Error = (E 1 + E 2 + E 3 + ... + En )1/2 Where En = Percent error associated with each contributing parameter.

Parameters contributing to errors in the measurement of gaseous effluents; process flow rates, sample collection, analytical counting and tank volumes.

The following values (%) were used for error calculations.

Fission & Act gases 1-131 Particulates Tritium 25 25 25 25 Sample counting error 10 10 10 10 Counting system calibration error 5 5 5 5 Counting system source error 20 N/A N/A N/A Temperature/volume correction error 10 10 10 10 Process flow measuring device (1)

N/A 15 15 15 Sample flow measuring device N/A 5 N/A N/A Iodine collection efficiency error N/A N/A 10 N/A Plateout error N/A N/A N/A 20 Bubbler collection efficiency error N/A N/A N/A 2 Sample volume transfer error (pipette)

N/A N/A N/A 2 Sample volume error (graduate)

Note 1 - % of full scale 55 PVNGS ARERR 2010

Table 41:

Effluent Monitoring Instrumentation Out Of Service Greater Than 30 Days Unit Instrument Date span of Cause of inoperability inoperability Explanation NONE 56 PVNGS ARERR 2010

Table 42:

Solid Waste Summary A. Solid Waste Shipped Offsite For Burial Or Disposal (not irradiated fuel) 1.0 Type of Waste Unit Jan-Dec estimated total error %

l.a. Spent resin, filters, sludges, evaporator m3 0.OOE+00 N/A bottoms, etc. Ci 0.OOE+00 2.50E+01 1.b. Dry compressible waste, contaminated m3 8.54E+02 N/A equipment, etc. Ci 3.27E-01 2.50E+01 m3 O.OOE+00 N/A 1.c. Irradiated components, control rods, etc.

Ci 0.00E+00 2.50E+01 m3 9.43E+00 N/A 1.d. Other Ci 7.09E-04 2.50E+01 57 PVNGS ARERR 2010

2.0 Principal Radionuclides 2.a Estimate of major nuclide concentrations for spent resins, filters, sludges, evaporator bottoms, etc.

NONE.

2.b Estimate of major nuclide concentrations for dry compressible waste, contaminated equipment, etc.

Percent Waste Class Nuclide Name Audce Abundance Curies A Fe-55 4.19E+01 1.37E-01 A Co-58 3.30E+01 1.08E-01 A Co-60 5.89E+00 1.93E-02 A Cr-51 4.67E+00 1.53E-02 A Ni-63 4.42E+00 1.45E-02 A Zr-95 2.54E+00 8.30E-03 A Nb-95 2.17E+00 7.09E-03 A H-3 1.18E+00 3.84E-03 A Mn-54 9.63E-01 3.15E-03 A Cs-137 9.14E-01 2.99E-03 A Fe-59 8.86E-01 2.90E-03 A C-14 5.86E-01 1.92E-03 A Sb-125 2.17E-01 7.08E-04 A Ni-59 1.80E-01 5.87E-04 A Co-57 1.63E-01 5.33E-04 A Ce-144 1.35E-01 4.42E-04 A Sn-113 1.24E-01 4.06E-04 A Cs-134 4.20E-02 1.37E-04 A Sb-124 3.07E-02 1.01E-04 A Te-123m 2.66E-02 8.68E-05 A Pu-241 2.28E-02 7.46E-05 A Am-241 7.05E-03 2.31E-05 A Sr-90 4.42E-03 1.44E-05 A Ag-110m 3.02E-03 9.89E-06 A Sr-89 2.75E-03 9.OOE-06 A Pu-239 1.69E-03 5.51E-06 A Ce-141 1.48E-03 4.83E-06 A Cm-242 7.62E-04 2.49E-06 A Pu-238 6.11E-04 2.OOE-06 A Cm-243 4.66E-04 1.52E-06 A Ru-103 3.79E-04 1.24E-06 A Hf-181 1.70E-04 5.57E-07 A Zn-65 1.23E-04 4.02E-07 Total 3.27E-01 58 PVNGS ARERR 2010

2.c Estimate of major nuclide concentrations for irradiated components, control rods, etc.

None 2.d Other 2.d.1 Oil Percent Waste Class Nuclide Name Audce Abundance Curies A H-3 9.98E+01 7.08E-04 A Ce-144 8.02E-02 5.69E-07 A Cs-137 5.36E-02 3.80E-07 A Co-60 2.65E-02 1.88E-07 A Cs-134 1.96E-03 1.39E-08 Total 7.09E-04 3.0 Solid Waste Disposition 3.a Shipments Mode Of Destination Transportation 33 Truck EnergySolutions, UT (Bulk Waste Facility) 1 Truck EnergySolutions, TN 3.b Irradiated Fuel Shipments: None 3.c Supplemental Information:

Number of Container Solidification Containers Volume ft3 Type of Waste Container Type Agent 2 Bulk Dry Active Waste 45 Mil Wrap None 14 1031.3 Dry Active Waste 20' Intermodal None 43 1360 Dry Active Waste 20' Sealand None 1 1360 Oil 20' Sealand None 59 PVNGS ARERR 2010

APPENDIX B METEOROLOGY 60 PVNGS ARERR 2010

JOINT FREQUENCY DISTRIBUTION TABLES The tables presented in this section are results obtained from processing the hourly meteorological data collected at the Palo Verde Nuclear Generating Station for the period of January - December 2010. The joint frequency distribution (JFD) tables represent the frequency, in terms of the number of observations, that a particular wind speed, wind direction, and stability category occurred simultaneously. On a quarterly, semiannual and annual basis, the JFDs were produced for 35-foot wind speed and wind direction by atmospheric stability class corresponding to the seven Pasquill stability categories, and for wind speed and wind direction for all stability classes combined. Atmospheric stability was classified per Regulatory Guide 1.23, using the 200-foot to 35-foot temperature difference (delta T).

In accordance with NUREG-01 33, the batch releases for the year were considered as "long term,"

since the batch releases are sufficiently random in both time of day and duration. Consequently, the JFDs for the batch releases for all quarters are the same as for the continuous releases.

Discussion A summary of 2010 Joint Frequency Distribution (JFD) shows a somewhat typical, but variable year. Of the 8760 hours0.101 days <br />2.433 hours <br />0.0145 weeks <br />0.00333 months <br /> available, zero hours of data were lost for an effective 100% data recovery.

The average 35 foot wind speed was 6.7 mph. Distribution of directions was spread over the compass with a predominant direction (3 sectors of 22.5 degrees each) centered on southwest.

(32.5%) A secondary maximum of threesectors centered on the north contained 26.9% of the total. Southwesterly flow winds averaged higher speeds with the most frequent speed at 10 mph.

With the northerly directions, the highest frequency occurred at 4.0 mph.

Stability class summary:

Stability class E, F, G, (stable categories) 58.3%.

Stability class G, (extremely stable) 25.0%.

Stability class A, B, C, (unstable categories) 22.6%.

Stability class D, (neutral category) 19.1%.

Overall stable conditions (E,F,G) existed for the year.

61 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 1/01/2010 TO 3/31/2010

... IST QRTR STABILITY CLASS A STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 5 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 0 0 B S 0 0 0 0 0 0 0 0 0 0 0 0 0 4.51- 5.50 0 0 0 0 0 0 0 0 0 0 0 0 0 5.51- 6.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6.51- 8.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8.51-11.50 0 1 S 0 0 B 0 0 0 0 1 0 0 1 0S 0 3 11.51-14.50 0 1 1 0 B B 0 0 0 0 4 0 0 0 0 0 6 14.51-20.50 1 0 0 1 0 0 0 0 0 1 3 0 1 5 0 0 12

>20.50 0 0 0 0 0 0 0 0 5 0 0 0 0 1 0 0 6 TOTAL 1 2 1 1 0 0 0 0 5 1 8 0 1 7 0 27 STABILITY CLASS B SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 a 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4.51- 5.50 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 5.51- 6.50 0 2 3 1 2 0 0 0 0 0 0 0 0 0 0 0 a 6.51- 8.50 0 1 3 4 1 0 0 0 1 0 0 1 0 0 1 1 13 8.51-11.50 2 1 6 4 0 1 0 0 0 0 1 0 1 2 0 1 19 11.51-14.50 0 0 1 0 0 0 0 0 0 0 4 1 1 1 1 i 10 14.51-20.50 1 0 0 0 0 0 0 0 0 0 1 0 1 2 1 0 6

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o o 0 TOTAL 3 5 13 9 3 1 0 0 1 0 6 2 3 5 3 3 57 STABILITY CLASS C SPEED (MPH) N NNE NE ENE E E0E SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 1 3.51- 4.50 0 1 1 0 0 0 0 1 1 1 0 0 1 0 0 0 6 4.51- 5.50 1 4 4 2 0 0 0 1 0 0 3 0 1 0 1 18 5.51- 6.50 1 2 3 3 1 1 0 0 3 1 3 1 0 2 0 1 22 6.51- 8.50 3 1 7 4 3 0 3 1 3 1 4 2 0 1 0 1 34 8.51-11.50 2 0 3 6 5 1 1 0 1 3 3 4 1 1 0 34 11.51-14.50 0 0 1 2 0 0 0 0 0 2 4 0 2 1 1 15 14.51-20.50 0 0 0 4 0 0 0 0 0 0 4 0 1 2 0 0 11

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 7 8 . 19 22 9 2 4 3 8 a 21 9 6 9 2 141 62 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 1/01/2010 TO 3/31/2010

- 1ST QRTR STABILITY CLASS D STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED

.(MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 1 0 0 0 1 0 4 1 4 2 1 5 3 6 1 29 2.51- 3.50 7 5 4 2 2 1 2 1 5 7 10 11 6 10 7 9 89 3.51- 4.50 6 7 7 4 4 1 0 1 5 13 15 7 6 6 3 7 92 4.51- 5.50 4 5 8 6 4 0 2 2 3 7 13 9 1 1 2 3 70 5.51- 6.50 2 8 9 4 3 2 1 1 2 5 6 5 1 1 3 1 54 6.51- 8.50 3 5 4 9 10 4 4 0 11 4 7 4 2 0 1 0 68 8.51-11.50 1 2 1 B 7 8 3 4 2 3 6 10 7 0 2 0 64 11.51-14.50 0 0 1 2 11 1 0 0 2 5 8 5 4 6 0 1 46 14.51-20.50 0 0 0 0 2 0 0 0 0 2 6 5 3 3 2 0 23

>20.50 0 0 0 0 0 0 0 0 2 1 0 1 0 0 0 0 4 TOTAL 23 33 34 35 43 18 12 13 33 51 73 58 35 30 26 22 539 STABILITY CLASS E SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 1 1.51- 2.50 2 0 1 0 1 0 2 0 1 1 0 1 3 5 3 2 22 2.51- 3.50 5 3 0 0 1 2 0 4 0 1 2 5 2 8 12 9 54 3.51- 4.50 5 4 2 1 1 0 0 1 3 3 4 7 5 8 8 0 52 4.51- 5.50 1 6 2 2 0 0 0 3 2 4 7 3 3 3 4 2 42 5.51- 6.50 5 1 0 3 1 0 0 0 1 8 6 3 4 3 3 4 42 6.51- 8.50 2 4 5 3 3 1 1 4 3 9 11 5 2 2 0 0 55 8.51-11.50 0 2 1 2 2 3 1 1 3 10 6 5 3 0 6 1 46 11.51-14.50 1 0 0 0 4 0 0 3 1 5 5 1 2 4 3 1 30 14.51-20.50 0 0 0 0 5 1 0 0 1 0 4 2 0 2 2 1 18

-20.50 0 0 0 0 3 0 0 0 2 0 1 0 0 0 0 0 6 TOTAL 21 20 11 11 21 7 4 16 17 41 47 32 24 35 41 20 368 STABILITY CLASS F SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM S

.76- 1.50 0 0 0 0 0 0 0 0 S S S 0 5 0 5 0 0 1.51- 2.50 0 1 0 4 1 0 0 0 0 0 1 4 4 7 4 5 31 2.51- 3.50 10 7 5 1 1 0 0 0 1 2 6 6 10 4 24 17 94 3.51- 4.50 13 1 4 1 0 0 0 1 0 1 1 6 3 10 12 10 63 4.51- 5.50 5 6 3 0 0 0 0 0 0 3 1 4 0 4 11 11 48 5.51- 6.50 9 4 5 0 0 0 0 0 1 0 4 4 1 3 4 6 41 6.51- 8.50 10 1 5 2 0 0 0 1 1 6 9 4 6 6 3 8 62 8.51-11.50 6 3 0 0 0 0 B 0 0 1 6 0 2 0 1 2 21 11.51-14.50 0 0 0 0 0 0 0 0 0 0 1 0 0 1 1 1 4 14.51-20.50 0 0 0 0 0 0 0 0 0 0 0 Q 0 0 0 1 1

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 *0 TOTAL 53 23 22 8 2 0 2 3 13 29 28 26 35 60 61 365 63 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 1/01/2010 TO 3/31/2010

... IST QRTR ...

STABILITY CLASS G STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 1 1 0 0 0 0 H S 0 0 0 0 1 0 1 4 1.51- 2.50 9 5 1 1 0 0 0 0 0 0 1 3 4 8 14 12 58 2.51- 3.50 28 10 2 3 0 0 0 0 1 0 1 3 1 16 28 42 135 3.51- 4.50 56 15 3 1 0 0 0 0 0 0 2 0 2 6 21 38 144 4.51- 5.50 54 17 1 0 0 0 0 0 0 0 0 0 2 0 10 28 112 5.51- 6.50 35 19 3 1 0 0 0 0 0 0 2 2 1 2 5 14 84 6.51- 8.50 38 26 3 2 0 0 0 0 0 0 2 3 2 1 2 19 98 8.51-11.50 9 7 1 0 0 0 0 0 0 2 3 1 0 0 1 3 27 11.51-14.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 14.51-20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 229 300 15 8 0 0 0 0 1 2 ii 12 12 34 81 158 663 STABILITY CLASS ALL SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 1 1 0 0 0 0 0 0 0 1 0 0 1 0 1 5 1.51- 2.50 11 7 2 5 2 1 2 4 2 5 4 9 16 23 27 20 140 2.51- 3.50 50 25 11 7 4 3 2 5 7 10 19 25 19 38 71 77 373 3.51- 4.50 80 28 17 7 5 1 0 4 9 18 22 20 17 30 44 55 357 4.51- 5.50 65 39 18 10 4 0 2 6 5 14 24 17 6 9 27 45 291 5.51- 6.50 52 36 23 12 7 3 1 1 7 14 21 15 7 11 15 26 251 6.51- 8.50 56 38 2? 24 17 5 8 6- 19 20 33 19 12 10 7 29 330 8.51-11.50 20 16 12 20 14 13 5 5 6 19 26 19 17 4 11 7 214 11.51-14.50 1 1 4 4 15 1 0 3 3 12 26 9 7 14 6 6 112 14.51-20.50 2 0 0 5 7 1 0 0 1 3 18 7 6 14 5 2 71

>20.50 0 0 0 0 3 0 0 0 9 1 1 1 0 1 0 0 15 TOTAL 337 191 115 94 78 28 20 34 68 116 195 141 107 155 213 268 2160 TOTAL NUMBER OF OBSERVATIONS: 2160 TOTAL NUMBER OF VALID OBSERVATIONS: 2160 TOTAL NUMBER OF MISSING OBSERVATIONS: 0 PERCENT DATA RECOVERY FOR THIS PERIOD: 100.0 %

MEAN WIND SPEED FOR THIS PERIOD: 6.2 MPH TOTAL NUMBER OF OBSERVATIONS WITH BACKUP DATA:

PERCENTAGE OCCURRENCE OF STABILITY CLASSES A B C D E F G 1.25 2.64 6.53 24.95 17.04 16.90 30.69 DISTRIBUTION OF WIND DIRECTION VS STABILITY N NNE NE ENE E ESE SE SSE S SSW SW WSW N WNW NW NNW CALM A 1 2 1 1 0 0 0 0 5 1 8 0 1 7 0 0 0 B 3 5 13 9 3 1 0 0 1 0 6 2 3 5 3 3 0 C 7 8 19 22 9 2 4 3 B 8 21 9 6 9 2 4 0 D 23 33 34 35 43 18 12 13 33 51 73 58 35 30 26 22 0 E 21 20 11 11 21 7 4 16 17 41 47 32 24 35 41 20 0 F 53 23 22 8 2 0 0 2 3 13 29 28 26 35 60 61 0 G 229 100 15 8 0 0 0 0 1 2 11 12 12 34 81 158 0 TOTAL 337 191 115 94 78 28 20 34 68 116 195 141 107 155 213 268 0 64 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 4/01/2010 TO 6/30/2010

- 2ND QRTR STABILITY CLASS A STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

3.51- 4.50 1 1 0 0 0 0 0 0 1 0 0 0 0 0 0 o 3 0

4.51- 5.50 0 0 0 0 0 1 3 3 1 0 1 0 0 0 9 5.51- 6.50 0 0 0 0 0 2 4 11 5 5 0 1 0 0 o 29 6.51- 8.50 0 0 1 1 2 3 2 6 7 16 19 10 9 1 0 o 77 8.51-11.50 0 0 0 3 1 1 2 14 25 35 18 7 3 2 3 116 11.51-14.50 0 0 2 0 1 1 0 0 3 13 30 7 5 7 3 72 0

14.51-20.50 0 1 0 3 0 0 0 0 7 33 12 4 El 7 80 0

>20.50 0 0 0 0 0 0 0 0 0 0 6 2 0 2 3 0 13 TOTAL 2 8 1 9 5 5 13 39 69 129 49 27 24 12 6 399 STABILITY CLASS B SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 0 0 1 1 0 0 0 0 1 1 2 0 0 0 1 0 7 4.51- 5.50 0 0 0 2 0 0 0 3 18 2 2 2 2 0 0 2 33 5.51- 6.50 1 0 1 1 1 0 3 8 23 12 4 4 0 2 0 0 60 6.51- 8.50 0 0 1 1 1 1 0 1 16 8 13 7 5 1 0 0 55 8.51-11.50 0 0 1 4 0 1 0 1 3 2 12 7 1 0 0 33 11.51-14.50 0 0 0 0 0 0, 0 0 0 1 4 5 4 0 0 15 14.51-20.50 0 0 0 0 0 0 0 0 0 0 6 1 0 1 1 1 10

>20.50 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 1 TOTAL 1 0 4 9 2 2 3 13 61 26 44 26 9 9 2 3 214 STABILITY CLASS C SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 1 0 1 0 1 1 0 0 0 0 0 4 3.51- 4.50 0 1 1 2 1 1 0 3 5 6 2 2 2 0 0 0 26 4.51- 5.50 0 1 1 0 0 0 0 1 16 7 1 2 2 0 0 0 31 5.51- 6.50 0 0 1 2 0 0 2 3 13 7 4 4 0 0 0 0 36 6.51- 8.50 0 0 0 2 0 0 1 2 1 3 11 9 3 0 0 0 32 8.51-11.50 0 0 0 0 0 0 1 0 0 3 8 4 3 1 1 0 21 11.51-14.50 0 0 0 0 1 0 0 0 1 0 4 0 1 1 0 1 9 14.51-20.50 0 1 0 0 1 1 0 0 . 0 2 2 0 0 0 0 0 7

>20.50 0 0 0 0 0 0 0 0 0 0 0 2 0 0 0 0 2 TOTAL 0 3 3 6 3 3 4 10 36 29 33 23 11 2 1 1 168 65 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 4/01/2010 TO 6/30/2010

- 2ND QRTR STABILITY CLASS D STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 . 0 0 0 0 0 0 B 0 0 0 0 0 0 0 0 0 1.51- 2.50 1 4 0 3 1 0 1 1 2 2 0 1 0 0 1 0 17 2.51- 3.50 1 6 2 7 1 1 0 2 5 3 4 4 0 5 1 4 46 3.51- 4.50 2 4 0 5 6 0 2 1 11 10 4 2 1 0 1 1 50 4.51- 5.50 0 0 2 1 0 0 0 1 5 3 2 6 1 0 0 0 21 5.51- 6.50 0 2 0 1 0 0 0 0 4 5 4 1 3 0 0 0 20 6.51- 8.50 0 0 1 1 0 0 0 1 1 5 9 4 5 2 3 0 32 8.51-11.50 0 1 0 0 0 1 0 1 0 1 10 10 4 2 0 1 31 11.51-14.50 0 0 0 0 0 0 0 0 0 4 7 3 3 5 0 0 22 14.51-20.50 0 0 0 0 0 0 0 0 0 2 12 3 3 2 1 1 24

>20.50 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 1 TOTAL 4 17 5 18 8 3 3 7 28 35 52 34 20 16 7 7 264 STABILITY CLASS E SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 1 1 0 0 0 0 2 1.51- 2.50 1 0 0 1 1 2 0 0 0 0 0 1 2 0 3 1 12 2.51- 3.50 2 4 1 0 1 0 0 0 1 0 5 2 8 4 1 30 3.51- 4.50 1 4 0 2 1 0 0 0 2 4 3 3 0 0 1 0 21 4.51- 5.50 1 2 1 0 1 0 0 0 0 4 7 4 4 0 21 0 26 5.51- 6.50 1 2 0 0 0 0 0 0 0 4 5 4 3 1 0 21 6.51- 8.50 0 0 1 0 0 0 0 0 0 4 17 24 13 3 4 1 67 8.51-11.50 1 0 1 3 2 0 0 0 3 12 38 27 9 5 1 1 103 11.51-14.50 1 0 0 0 0 0 0 0 0 13 30 7 6 2 4 0 63 14.51-20.50 2 0 0 0 0 0 0 0 0 0 4 3 3 0 0 2 14

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 10 12 4 6 6 2 0 0 6 41 110 76 48 15 17 6 359 STABILITY CLASS F SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1050 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 2 1.51- 2.50 1 3 1 0 0 0 0 0 0 0 0 0 1 1 2 0 9 2.51- 3.50 4 4 1 1 0 2 0 1 1 2 2 4 9 5 2 6 44 3.51- 4.50 2 4 1 0 0 1 1 0 2 5 3 2 5 3 11 2 42 4.51- 5.50 0 2 3 1 0 0 0 0 0 7 7 6 6 2 4 3 41 5.51- 6.50 0 2 0 0 0 0 1 0 0 6 10 4 10 4 5 2 44 6.51- 8.50 0 0 1 0 0 0 0 1 2 11 41 17 16 6 4 3 102 8.51-11.50 0 0 0 0 0 0 0 1 0 8 42 7 1 2 0 0 61 11.51-14.50 0 0 0 0 0 0 0 0 0 1 2 0 0 0 0 1 4 14.51-20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1

>20.50 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 TOTAL 7 16 7 2 0 3 2 3 5 40 107 40 49 24 28 18 351 66 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 4/01/2010 TO 6/30/2010

- 2ND QRTR STABILITY CLASS G STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 2 1.51- 2.50 3 1 2 0 1 2 0 0 1 0 2 2 2 2 3 5 26 2.51- 3.50 24 9 5 2 1 0 0 2 1 2 4 3 4 8 10 9 84 3.51- 4.50 42 20 0 2 1 1 0 0 0 0 3 4 6 5 9 25 118 4.51- 5.50 35 28 3 3 2 0 2 0 0 0 3 1 5 4 4 17 107 5.51- 6.50 9 17 3 3 0 0 0 0 0 0 3 0 2 2 3 5 47 6.51- 8.50 8 10 5 0 1 0 0 0 0 2 3 1 0 1 1 2 34 8.51-11.50 1 1 0 1 0 0 0 0 0 1 5 0 0 0 0 2 11 11.51-14.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 14.51-20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 122 86 18 11 6 3 2 2 2 5 23 11 19 23 31 65 429 STABILITY CLASS ALL SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 1 1 1 2 1 0 6 1.51- 2.50 6 8 3 4 3 4 1 1 3 2 2 4 5 3 9 6 64 2.51- 3.50 31 23 9 10 3 4 0 6 8 8 16 13 21 22 14 20 208 3.51- 4.50 48 34 3 12 9 3 3 4 22 26 17 13 14 8 23 28 267 4.51- 5.50 36 33 10 7 3 0 2 6 42 26 23 21 21 6 10 22 268 5.51- 6.50 11 23 6 7 1 0 8 15 51 39 35 17 19 9 9 7 257 6.51- 8.50 8 10 10 5 4 4 3 11 27 49 113 72 51 14 12 6 399 8.51-11.50 2 2 4 8 5 3 2 5 20 52 150 73 25 14 4 7 376 11.51-14.50 1 0 2 0 2 1 0 0 4 32 77 22 16 19 4 5 185 14.51-20.50 2 2 2 0 4 1 0 0 0 11 57 19 10 14 9 5 136

>20.50 0 1 0 0 0 1 0 0 0 0 7 4 0 2 3 0 18 TOTAL 145 136 49 53 34 21 19 48 177 245 498 259 183 113 98 106 2184 TOTAL NUMBER OF OBSERVATIONS: 2184 TOTAL NUMBER OF VALID OBSERVATIONS: 2184 TOTAL NUMBER OF MISSING OBSERVATIONS: 0 PERCENT DATA RECOVERY FOR THIS PERIOD: 100.0 MEAN WIND SPEED FOR THIS PERIOD: 7.6 MPH TOTAL NUMBER OF OBSERVATIONS WITH BACKUP DATA: 0 PERCENTAGE OCCURRENCE OF STABILITY CLASSES A B C D E F G 18.27 9.80 7.69 12.09 16.44 16.07 19.64 DISTRIBUTION OF WIND DIRECTION VS STABILITY N NNE NE ENE E ESE SE SEE S SSW SW WSW N WNW NW NNW CALM A 2 2 8 1 9 5 5 13 39 69 129 49 27 24 12 6 0 B 1 0 4 9 2 2 3 13 61 26 44 26 9 9 2 3 0 C 0 3 3 6 3 3 4 10 36 29 33 23 11 2 1 1 0 D 4 17 5 18 8 3 3 7 28 35 52 34 20 16 7 7 0 E 10 12 4 6 6 2 0 0 6 41 110 76 48 15 17 6 0 F 7 16 7 2 0 3 2 3 5 40 107 40 49 24 28 18 0 G 122 86 18 11 6 3 2 2 2 5 23 11 19 23 31 65 0 TOTAL 145 136 49 53 34 21 19 48 177 245 498 259 183 113 98 106 0 67 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 1/01/2010 TO 6/30/2010 LST SEMI ...

STABILITY CLASS A STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 1 1 0 0 0 0 0 0 1 0 0 0 0 0 0 0 3 4.51- 5.50 0 0 0 0 0 0 0 1 3 3 1 0 1 0 0 0 9 5.51- 6.50 0 0 1 0 0 0 2 4 11 5 5 0 1 0 0 0 29 6.51- 8.50 0 0 1 1 2 3 2 6 7 16 19 10 9 1 0 0 77 8.51-11.50 0 1 2 0 3 1 1 2 14 25 36 LB 7 4 2 3 119 11.51-14.50 0 1 3 0 1 1 0 0 3 13 34 7 5 7 0 3 78 14.51-20.50 1 1 2 1 3 0 0 0 0 8 36 12 5 16 7 0 92

>20.50 0 0 0 0 0 0 0 0 5 0 6 2 0 3 3 0 19 TOTAL 2 4 9 2 9 5 5 13 44 70 137 49 28 31 12 6 426 STABILITY CLASS B SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 0 0 1 1 0 0 0 0 1 1 2 0 0 0 1 0 7 4.51- 5.50 0 1 0 2 0 0 0 3 18 2 2 2 2 0 0 2 34 5.51- 6.50 1 2 4 2 3 0 3 8 23 12 4 4 0 2 0 0 68 6.51- 8.50 0 1 4 5 2 1 0 1 17 8 13 8 5 1 1 1 68 8.51-11.50 2 1 7 8 0 2 0 1 3 2 13 7 2 3 0 1 52 11.51-14.50 0 0 1 0 0 0 0 0 0 1 8 6 2 5 1 1 25 14.51-20.50 1 0 0 0 0 0 0 0 0 0 7 1 1 3 2 1 16

>20.50 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 1 TOTAL 4 5 17 18 5 3 3 13 62 26 50 28 12 14 5 6 271 STABILITY CLASS C SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 1 0 1 0 1 0 1 1 0 0 0 0 0 5 3.51- 4.50 0 2 2 2 1 1 0 4 6 7 2 2 3 0 0 0 32 4.51- 5.50 1 5 5 2 0 0 0 2 16 7 4 3 2 1 0 1 49 5.51- 6.50 1 2 4 5 1 1 2 3 16 8 7 5 0 2 0 1 58 6.51- 8.50 3 1 7 6 3 0 4 3 4 4 15 11 3 1 0 1 66 8.51-i1.50 2 0 3 6 5 1 2 0 1 6 11 7 7 2 2 0 55 11.51-14.50 0 0 1 2 1 0 0 0 1 2 8 2 1 3 1 2 24 14.51-20.50 0 1 0 4 1 1 0 0 0 2 6 0 1 2 0 0 18

>20.50 0 0 0 0 0 0 0 0 0 0 0 2 0 0 0 0 2 TOTAL 7 11 22 28 12 5 8 13 44 37 54 32 17 11 3 5 309 68 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 1/01/2010 TO 6/30/2010

- 1ST SEMI STABILITY CLASS D STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 1 5 0 3 1 1 1 5 3 6 2 2 5 3 7 1 46 2.51- 3.50 8 11 6 9 3 2 2 3 10 10 14 15 6 15 8 13 135 3.51- 4.50 8 11 7 9 10 1 2 2 16 23 19 9 7 6 4 8 142 4.51- 5.50 4 5 10 7 4 0 2 3 8 10 15 15 2 1 2 3 91 5.51- 6.50 2 10 9 5 3 2 1 1 6 10 10 6 4 1 3 1 74 6.51- 850 3 5 5 10 10 4 4 1 12 9 16 8 7 2 4 0 100 8.51-11.50 1 3 1 8 7 9 3 5 2 4 16 20 11 2 2 1 95 11.51-14.50 0 0 1 2 11 1 0 0 2 9 15 8 7 11 0 1 68 14.51-20.50 0 0 0 0 2 0 0 0 0 4 18 8 6 5 3 1 47

,20.50 0 0 0 0 0 1 0 0 2 1 0 1 0 0 0 0 5 TOTAL 27 50 39 53 51 21 15 20 61 86 125 92 55 46 33 29 803 STABILITY CLASS E SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 o 0 0 2 1 0 0 0 0 3 1.51- 2.50 3 0 1 2 2 2 0 1 1 0 2 5 5 6 3 34 2.51- 3.50 7 7 o 2 2 0 4 1 1 7 7 10 12 13 10 84 3.51- 4.50 6 8 2 3 2 0 0 1 5 7 7 10 5 8 9 0 73 4.51- 5.50 2 8 3 2 1 0 0 3 2 8 14 7 7 3 6 2 68 5.51- 6.50 6 3 0 3 1 0 0 0 1 12 11 7 7 4 4 4 63 6.51- 8.50 2 4 6 3 3 1 1 4 3 13 28 29 15 5 4 1 122 8.51-11.50 1 2 2 15 5 4 3 1 1 6 22 44 32 12 5 7 2 149 11.51-14.50 2 0 0 o 4 0 5 3 1 18 35 8 8 6 7 1 93 14.51-20.50 2 0 0 o 5 1 0 o 1 0 8 5 3 2 2 3 32

>20.50 0 0 0 o 3 0 0 0 2 0 1 0 0 0 0 0 6 TOTAL 31 32 Is 17 27 9 4 16 23 82 157 108 72 50 58 26 727 STABILITY CLASS F SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 2 1.51- 2.50 1 4 6 4 1 0 0 o o 0 1 4 5 8 6 5 40 2.51- 3.50 14 11 2 1 2 0 1 2 4 8 10 19 9 26 23 138 3.51- 4.50 15 5 6 0 1 1 1 2 6 4 8 8 13 23 12 105 4.51- 5.50 5 8 5 1 0 0 0 0 o 10 8 10 6 6 15 14 89 5.51- 6.50 9 6 6 0 0 1 o 1 6 14 8 11 7 9 8 85 6.51- 8.50 10 1 0 2 0 0 0 2 3 17 50 21 22 12 7 11 164 8.51-11.50 6 3 6 o 0 0 0 1 0 9 48 7 3 2 1 2 82 11.51-14.50 0 0 0 o 0 0 0 o 0 1 3 0 o 1 1 2 8 14.51-20.50 0 0 0 0 0 0 0 0 0 0 0 0 Q 0 0 2 2 20 .50 0 1 Q 0 0 0 0 0 0 0 0 0 0 0 0 1 TOTAL 60 39 29 10 2 3 2 5 8 53 136 68 75 59 88 79 716 69 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 1/01/2010 TO 6/30/2010

... IST SEMI STABILITY CLASS G STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 1 1 0 0 0 0 0 0 0 0 0 0 2 1 1 6 1.51- 2.50 12 6 3 1 1 2 0 0 1 0 3 5 6 10 17 17 84 2.51- 3.50 52 19 7 5 1 0 0 2 2 2 5 6 5 24 38 51 219 3.51- 4.50 98 35 3 3 1 1 0 0 0 0 5 4 8 11 30 63 262 4.51- 5.50 89 45 4 3 2 0 2 0 0 0 3 1 7 4 14 45 219 5.51- 6.50 44 36 6 4 0 0 0 0 0 0 5 2 3 4 8 19 131 6.51- 8.50 46 36 8 2 1 0 0 0 0 2 5 4 2 2 3 21 132 8.51-11.50 10 8 1 1 0 0 0 0 0 3 8 1 0 0 1 5 38 11.51-14.50 0 0 0 0 0 0 0' 0 0 0 0 0 0 0 0 1 1 14.51-20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 351 186 33 19 6 3 2 2 3 7 34 23 31 57 112 223 1092 STABILITY CLASS ALL SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 1 1 0 0 0 0 0 0 0 2 1 1 3 1 1 11 1.51- 2.50 17 15 5 9 5 5 3 5 5 7 6 13 21 26 36 26 204 2.51- 3.50 81 48 20 17 7 7 2 11 15 18 35 38 40 60 85 97 581 3.51- 4.50 128 62 20 19 14 4 3 8 31 44 39 33 31 38 67 83 624 4.51- 5.50 101 72 28 17 7 0 4 12 47 40 47 38 27 15 37 67 559 5.51- 6.50 63 59 29 19 8 3 9 16 58 53 56 32 26 20 24 33 508 6.51- 8.50 64 48 37 29 21 9 11 17 46 69 146 91 63 24 19 35 729 8.51-11.50 22 18 16 28 19 16 7 10 26 71 176 92 42 18 15 14 590 11.51-14.50 2 1 6 4 17 2 0 3 7 44 103 31 23 33 10 11 297 14.51-20.50 4 2 2 5 11 2 0 0 1 14 75 26 16 28 14 7 207

>20.50 0 1 0 0 3 1 0 0 9 1 8 5 0 3 3 0 34 TOTAL 482 327 164 147 112 49 39 82 245 361 693 400 290 268 311 374 4344 TOTAL NUMBEROF OBSERVATIONS: 4344 TOTAL NUMBEROF VALID OBSERVATIONS: 4344 TOTAL NUMBEROF MISSING OBSERVATIONS: 0 PERCENT DATA RECOVERYFOR THIS PERIOD: 100.0 %

MEANWIND SPEED FOR THIS PERIOD: 6.9 MPH TOTAL NUMBEROF OBSERVATIONS WITH BACKUPDATA: 0 PERCENTAGE OCCURRENCEOF STABILITY CLASSES A B C D E F G 9.81 6.24 7.11 18.49 16.74 16.48 25.14 DISTRIBUTION OF WIND DIRECTION VS STABILITY N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW CALM A 2 4 9 2 9 5 5 13 44 70 137 49 28 31 12 6 0

  • 4 5 17 18 5 3 3 13 62 26 50 28 12 14 5 6 0 C 7 11 22 28 12 5 8 13 44 37 54 32 17 11 3 5 0 D 27 50 39 53 51 21 15 20 61 86 125 92 55 46 33 29 0 E 31 32 15 17 27 9 4 16 23 82 157 108 72 50 58 26 0 F 60 39 29 10 2 3 2 5 8 53 136 68 75 59 88 79 0 G 351 186 33 19 6 3 2 2 3 7 34 23 31 57 112 223 0 TOTAL 482 327 164 147 112 49 39 82 245 361 693 400 290 268 311 374 0 70 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 7/01/2010 TO 9/30/2010

- 3RD QRTR STABILITY CLASS A STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 S 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 3.51- 4.50 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 1 4.51- 5.50 0 0 0 0 0 2 1 1 1 3 0 1 0 0 0 0 9 5.51- 6.50 0 0 1 1 1 3 1 1 8 4 4 2 2 0 0 28 0

6.51- 8.50 0 0 1 1 4 6 4 7 11 13 23 10 3 1 0 05 8.51-11.50 0 0 0 0 5 4 1 2 13 11 19 26 5 0 0 87 11.51-14.50 0 0 0 1 1 2 0 1 2 6 6 7 1 0 0 0 27 14.51-20.50 0 0 0 0 7 0 0 0 1 11 11 4 0 0 0 O 34

>20.50 0 0 0 0 2 0 0 0 0 2 0 0 0 0 0 0 4 TOTAL 0 0 2 3 20 17 7 12 36 51 63 50 2 0 275 STABILITY CLASS B SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 0 1 0 0 0 0 0 0 1 2 0 0 0 0 0 0 4 4.51- 5.50 1 0 2 1 2 0 1 2 7 5 7 3 1 0 0 1 33 5.51- 6.50 1 2 2 4 3 1 3 6 14 13 9 3 5 1 1 0 68 6.51- 8.50 0 0 0 1 4 4 6 3 8 14 12 14 3 0 0 0 69 8.51-11.50 0 0 0 0 3 1 0 1 6 7 9 10 5 0 0 0 42 11.51-14.50 0 0 0 0 3 2 0 1 1 0 3 2 0 0 0 0 12 14.51-20.50 0 0 0 0 5 0 0 0 0 0 2 0 0 0 0 0 7

>20.50 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 1 TOTAL 2 3 4 6 20 8 10 13 37 41 43 32 14 1 1 1 236 STABILITY CLASS C SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 0 2 3.51- 4.50 1 0 0 4 0 0 3 1 1 4 3 2 0 1 0 20 4.51- 5.50 1 2 3 1 1 3 1 1 9 9 10 4 4 1 0 51 5.51- 6.50 0 2 1 1 4 0 1 2 7 10 5 1 0 0 0 1 36 6,51- 8.50 0 1 1 1 1 3 2 4 4 2 10 6 0 0 39 8951-11.50 0 0 0 1 0 4 2 0 1 2 B 4 0 0 22 11,51-14.50 0 1 0 0 1 0 0 2 0 0 4 3 0 0 1 0 12 14,51-20.50 0 0 0 0 2 0 0 0 0 0 1 1 00 0 0 0 4

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 2 6 5 8 9 10 9 10 22 27 41 2:2 8 3 3 1 186 71 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 7/01/2010 TO 9/30/2010

- 3RD QRTR STABILITY CLASS D STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1.51- 2.50 3 1 1 0 0 0 0 0 1 0 0 3 0 1 12 2.51- 3.50 4 2 2 2 3 1 3 2 4 B 5 1 9 0 3 50 3.51- 4.50 3 3 5 1 0 2 0 1 4 1 7 3 5 5 4 0 44 4.51- 5.50 2 2 4 2 0 0 3 0 3 6 12 4 4 2 2 1 47 5.51- 6.50 0 3 5 4 0 0 0 2 3 4 7 6 1 3 1 0 39 6.51- 8.50 1 4 3 2 0 2 3 3 5 7 10 12 3 0 0 0 55 8.51-11.50 3 4 1 2 3 6 2 2 0 12 18 14 3 0 1 0 71 11.51-14.50 2 4 0 1 5 2 0 1 3 3 27 7 0 0 0 0 55 14.51-20.50 0 0 0 0 10 0 0 1 1 1 12 2 0 0 0 0 27

>20.50 0 1 0 1 0 3 0 0 0 0 1 0 0 0 0 0 6 TOTAL iB 24 21 15 21 16 21 12 24 42 99 52 25 12 10 5 407 STABILITY CLASS E SPEED (MPH) N NNE NE ENS E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1.51- 2.50 1 1 3 0 0 0 0 0 1 0 1 1 0 1 3 0 12 2.51- 3.50 2 5 3 1 3 0 0 0 2 0 4 4 7 4 9 4 48 3.51- 4.50 7 4 2 2 1 0 0 0 4 2 8 4 6 2 4 4 50 4.51- 5.50 3 1 2 1 1 0 0 0 2 1 8 6 1 3 3 2 34 5.51- 6.50 1 5 1 1 1 1 0 0 0 5 16 7 4 1 0 2 45 6.51- 8.50 3 4 4 1 4 3 5 2 2 18 24 26 7 1 1 0 105 8.51-11.50 0 2 7 9 10 10 7 1 1 12 42 19 5 1 0 1 127 11.51-14.50 0 0 1 5 11 5 4 0 0 5 32 3 2 1 0 0 69 14.51-20.50 1 1 0 0 13 2 0 0 0 0 1 0 0 1 0 0 19

>20.50 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 1 TOTAL 18 23 23 20 44 22 16 3 12 43 136 70 32 15 20 14 511 STABILITY CLASS F SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 1 1 0 0 1 0 0 0 4 4 3 14 2.51- 3.50 8 1 3 1 0 0 1 0 1 0 4 4 14 4 12 7 60 3.51- 4.50 10 4 2 0 0 0 0 0 1 1 4 7 8 8 3 8 56 4.51- 5.50 3 8 1 0 0 0 1 0 1 5 5 6 5 4 1 4 44 5,51- 6.50 2 1 1 1 0 0 0 0 1 2 6 7 5 0 0 1 27 6.51- 8.50 1 3 6 1 0 0 0 1 2 8 15 11 7 3 0 0 58 8.51-11.50 0 1 2 3 1 0 0 0 0 2 3 6 0 0 0 0 18 11.51-14.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 14.51-20.50 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 1

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 24 18 15 7 1 1 3 1 6 19 37 41 39 23 20 23 278 72 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 7/01/2010 TO 9/30/2010

- 3RD QRTR STABILITY CLASS G STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 1 0 0 0 0 0 0 0 0 0 1 0 1 0 0 3 1.51- 2.50 1 2 1 0 0 0 0 o 1 0 0 1 1 5 4 6 22 2.51- 3.50 16 6 3 2 0 0 2 0 1 1 2 1 3 2 8 10 57 3.51- 4.50 22 8 3 1 2 0 0 0 1 1 2 2 2 1 7 21 73 4.51- 5.50 39 15 3 0 0 1 0 0 0 0 1 3 2 0 5 18 87 5.51- 6.50 20 13 0 1 0 0 0 0 0 0 2 0 0 0 1 4 41 6.51- 8.50 8 14 1 0 0 0 0 0 0 0 2 0 0 0 0 3 28 8.51-11.50 1 1 0 0 0 0 0 0 0 0 1 0 1 0 0 0 4 11.51-14.50 0 0 0 0 0. 0 0 0 0 0 0 0 0 0 0 0 U 14.51-20.50 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0

>20.50 0 0 0 0 0 5 0 0 0 0 0 0 0 0 0 0 0 TOTAL 107 60 11 4 2 1 2 0 3 2 10 8 9 9 25 62 315 STABILITY CLASS ALL SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 1 0 0 0 0 0 0 0 0 0 5 0 2 0 1 5 1.51- 2.50 5 4 5 0 0 1 1 0 3 1 1 5 1 11 12 10 60 2.51- 3.50 30 14 11 6 6 1 6 2 8 9 15 11 34 10 30 24 217 3.51- 4.50 43 20 12 8 3 2 3 2 12 12 24 18 21 16 19 33 248 4.51- 5.50 49 28 15 5 4 6 7 4 23 29 43 27 17 10 12 26 305 5.51- 6.50 24 26 11 13 9 5 5 i1 33 38 49 26 17 6 3 8 284 6.51- 8.50 13 26 16 7 13 18 20 20 32 62 96 79 26 6 2 3 439 8.51-11.50 4 8 10 15 22 25 12 6 21 46 100 79 19 2 1 1 371 11.51-14.50 2 5 1 7 21 11 4 5 6 14 72 22 3 1 1 0 175 14.51-20.50 1 1 0 1 37 2 0 1 2 12 27 7 0 1 0 . 0 92

>20.50 0 1 0 1 2 4 0 0 0 2 2 0 0 0 0 0 12 TOTAL 171 134 81 63 117 75 58 51 140 225 429 275 138 65 80 106 2208 TOTAL NUMBER OF OBSERVATIONS: 2208 TOTAL NUMBER OF VALID OBSERVATIONS: 2208 TOTAL NUMBER OF MISSING OBSERVATIONS: 0 PERCENT DATA RECOVERY FOR THIS PERIOD: 100.0 MEAN WIND SPEED FOR THIS PERIOD: 7.3 MPH TOTAL NUMBER OF OBSERVATIONS WITH BACKUP DATA: 0 PERCENTAGE OCCURRENCE OF STABILITY CLASSES A B C D E F G 12.45 10.69 8.42 18.43 23.14 12.59 14.27 DISTRIBUTION OF WIND DIRECTION VS STABILITY N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW CALM A 0 0 2 3 20 17 7 12 36 51 63 50 11 2 1 0 0 B 2 3 4 6 20 8 10 13 37 41 43 32 14 1 1i 1 0 C 2 6 5 8 9 10 9 10 22 27 41 22 8 3 3 1 0 D 18 24 21 15 21 16 11 12 24 42 99 52 25 12 10 5 0 E 18 23 23 20 44 22 16 3 12 43 136 70 32 15 20 14 0 F 24 18 15 7 1 1 3 1 6 19 37 41 39 23 20 23 0 G 107 60 10 4 2 1 2 0 3 2 10 8 9 9 25 62 0 TOTAL 171 134 81 63 117 75 58 51 140 225 429 275 138 65 80 106 0 73 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 10/01/2010 TO 12/31/2010

- 4TH QRTR ...

STABILITY CLASS A STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ROE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 0 0 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 0 4.51- 5.50 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 2 5.51- 6.50 0 0 0 0 0 1 0 0 0 1 0 0 0 0 0 4 6.51- 8.50 0 0 0 0 1 1 2 1 0 0 0 0 0 0 0 5 8.51-11.50 0 0 0 0 0 0 0 0 1 0 0 2 2 1 0 0 7 11.51-14.50 0 0 0 0 0 0 0 0 1 1 0 3 0 1 1 0 7 14.51-20.50 0 0 0 0 0 0 0 0 0 4 1 0 0 0 1 0 6

>20.50 0 0 0 0 0 0 0 0 0 0 0 1 1 0 2 TOTAL 0 0 0 3 1 2 2 4 5 2 5 2 3 3 0 33 STABILITY CLASS B SPEED (MPH) N NNE NE ENE ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 0 1 0 0 0 1 0 0 0 1 0 0 0 0 1 0 4 4.51- 5.50 0 2 0 1 0 0 0 0 2 3 1 1 0 0 0 1 11 5.51- 6.50 0 0 1 0 0 1 1 0 1 1 3 0 0 0 0 B B 6.51- 8.50 1 0 3 2 1 3 1 1 3 0 3 1 0 0 1 0 20 8.51-11.50 0 0 0 1 1 0 0 1 0 0 2 2 1 2 4 1 15 11.51-14.50 0 0 0 1 0 0 0 0 1 2 4 0 1 0 0 10 14.51-20.50 0 0 0 1 2 0 0 0 0 1 2 0 0 0 1 0 7

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 1 3 4 6 5 5 2 2 6 7 13 8 1 3 2 75 STABILITY CLASS C SPEED (MPH) N NNE NE ENE ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 1 3,51- 4.50 0 3 0 0 2 0 0 2 4 5 3 5 1 1 3 29 4.51- 5.50 0 2 0 2 0 0 1 5 4 3 5 2 0 0 1 2 27 5.51- 6.50 0 2 0 0 1 0 1 3 6 3 5 4 0 0 0 0 25 6.51- 8.50 0 0 5 4 2 2 2 4 2 3 2 2 1 2 1 1 33 8.51-11.50 0 0 2 3 5 1 0 1 2 2 2 0 4 2 2 27 11.51-14.50 0 0 0 1 7 0 0 1 0 1 1 0 0 1 1 0 13 14.51-20.50 0 0 0 0 5 0 0 0 0 0 1 0 2 0 0 0 8

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 1 S

TOTAL 0 7 7 10 23 3 5 15 17 17 19 15 4 9 8 164 74 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 10/01/2010 TO 12/31/2010

- 4TH QRTR ...

STABILITY CLASS D STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SBE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 1 1.51- 2.50 0 3 3 2 0 1 2 5 1 2 2 1 1 2 7 1 32 2.51- 3.50 2 1 3 4 1 4 4 6 17 16 14 3 8 0 5 8 96 3.51- 4.50 6 2 2 3 3 3 2 4 10 10 15 3 6 3 2 5 79 4.51- 5.50 5 3 7 5 0 1 4 4 11 7 10 7 5 3 2 5 79 5.51- 6.50 0 0 3 1 2 1 0 4 9 4 6 4 2 1 0 1 38 6.51- 8.50 0 0 4 4 2 2 2 1 2 2 10 11 5 2 2 0 49 8.51-11.50 0 1 2 3 7 3 1 2 0 2 5 7 0 3 3 1 40 11.51-14.50 0 0 0 2 7 0 0 0 0 2 5 1 2 2 0 0 21 14.51-20.50 0 0 1 1 10 0 0 0 0 0 6 4 1 3 1 0 27

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 3 0 0 3 TOTAL 13 1 24 25 32 15 15 26 50 46 73 41 30 22 22 21 465 STABILITY CLASS E SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 1 1 0 0 1 0 0 0 0 0 0 0 0 0 3 1.51- 2.50 4 1 0 0 1 0 0 2 2 5 2 2 1 4 1 4 29 2.51- 3.50 7 5 2 0 0 2 0 1 2 3 5 7 4 9 12 5 64 3.51- 4.50 6 3 4 2 1 1 0 2 2 2 4 7 4 3 7 6 54 4.50- 5.50 5 4 1 1 0 2 0 0 4 8 7 10 2 0 3 4 51 5.51- 6.50 2 3 2 1 0 2 0' 0 5 7 8 4 2 5 1 1 43 6.51- 8.50 1 2 5 3 3 1 1 5 3 6 12 8 7 5 2 3 67 8.51-11.50 0 0 2 5 2 2 3 2 1 3 4 1 9 11 5 1 51 11.51-14.50 0 0 0 0 2 1 0 0 0 1 2 1 4 2 0 1 14 14.51-20.50 0 0 0 1 1 0 0 0 0 1 3 2 4 1 0 0 13

,20.50 0 0 0 0 0 0 0 0 0 0 0 1 0 1 0 0 2 TOTAL 25 18 17 14 10 11 5 12 19 36 47 43 37 41 31 25 391 STABILITY CLASS F SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1.51- 2.50 5 2 0 0 0 1 0 0 0 2 2 2 11 3 10 3 41 2.51- 3.50 8 4 1 1 1 0 0 2 0 1 3 4 9 9 11 10 64 3.51- 4.50 7 5 0 1 1 2 0 0 0 2 4 11 7 7 5 53 4.51- 5.50 6 2 1 0 0 0 1 1 3 7 5 0 2 3 6 38 5.51- 6.50 2 2 1 1 0 0 0 0 0 5 5 2 2 2 3 6 32 6.51- 8.50 3 4 2 2 1 0 0 0 4 4 1 4 6 3 12 47 8.51-11.50 0 0 2 1 0 1 1 0 0 1 1 1 4 2 0 6 20 11.51-14.50 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 2 3 14.51-20.50 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 1 0

0

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 31 19 7 6 5 4 2 3 16 24 19 41 31 37 51 300 75 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 10/01/2010 TO 12/31/2010

- 4TH QRTR STABILITY CLASS G STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 1 0 0 0 O 0 0 1 0 2 1 1 0 1 7 1.51- 2.50 3.3 7 2 1 0 S 2 0 1 4 3 1 6 7 18 17 82 2.51- 3.50 39 24 9 4 0 2 2 1 1 2 2 1 7 24 45 53 216 3.51- 4.50 60 22 6 5 2 1 B 0 2 0 2 4 6 5 34 70 219 4.51- 5.50 57 25 5 0 0 0 o 1 0 1 0 2 1 2 8 27 129 5.51- 6.50 22 14 4 1 0 0 o 0 0 0 0 0 1 0 2 9 53 6.51- 8.50 21 19 4 0 0 0 o 0 0 0 0 0 0 1 2 14 61 8..51-11.50 6 5 0 0 0 0 O 0 0 0 0 0 0 0 0 1 12 11.51-14.50 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 1 14.51-20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

>20.50 0 0 0 0 0 0 0 0 0 0 B 0 0 0 0 B 0 TOTAL 218 116 31 12 2 3 4 2 4 8 7 10 22 40 109 192 780 STABILITY CLASS ALL SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0- 2 1 0 0 1 0 0 2 0 2 1 1 0 2 12 1.51- 2.50 22 13 4 3 1 2 4 7 4 13 9 6 19 16 36 25 184 2.51- 3.50 56 34 15 9 3 8 6 10 20 22 24 15 28 42 73 76 441 3.51- 4.50 79 36 12 11 9 8 2 8 19 18 26 23 28 19 51 89 438 4.51- 5.50 73 38 14 10 0 3 6 11 23 25 30 27 8 7 17 45 337 5.51- 6.50 26 21 11 6 3 4 3 7 22 20. 28 14 7 8 6 17 203 6.51- 8.50 26 25 23 15 9 9 7 13 12 15 31 23 17 16 11 30 282 8.51-11.50 6 6 8 13 16 7 6 5 3 8 14 15 16 23 14 12 172 11.51-14.50 0 0 0 5 18 1 0 1 1 6 10 9 6 7 2 3 69 14.51-20.50 0 0 1 3 19 0 0 0 0 6 13 6 7 4 3 0 62

>20.50 0 0 0 0 0 0 0 0 0 0 0 1 0 6 1 0 8 TOTAL 288 173 90 76 78 42 35 62 104 135 185 141 137 149 214 299 2208 TOTAL NUMBER OF OBSERVATIONS: 2208 TOTAL NUMBER OF VALID OBSERVATIONS: 2208 TOTAL NUMBER OF MISSING OBSERVATIONS: 0 PERCENT DATA RECOVERY FOR THIS PERIOD: 100.0 %

MEAN WIND SPEED FOR THIS PERIOD: 5.6 MPH TOTAL NUMBER OF OBSERVATIONS WITH BACKUP DATA: 0 PERCENTAGE OCCURRENCE OF STABILITY CLASSES A B C D E F G 1.49 3.40 7.43 21.06 17.71 13.59 35.33 DISTRIBUTION OF WIND DIRECTION VS STABILITY N NNE NE ENE E ESE SE SSE S SSW SW WSW N WNW NW NNW CALM A 0 0 0 3 1 1 2 2 4 5 2 5 2 3 3 0 0 B 1 3 4 6 5 5 2 2 6 7 13 8 1 3 7 2 0 C 0 7 7 10 23 3 5 15 17 17 19 15 4 9 5 8 0 D 13 10 24 25 32 15 15 26 50 46 73 41 30 22 22 21 0 E 25 18 17 14 10 11 5 12 19 36 47 43 37 41 31 25 0 F 31 19 7 6 5 4 2 3 4 16 24 19 41 31 37 51 0 G 218 116 31 12 2 3 4 2 4 8 7 10 22 40 109 192 0 TOTAL 288 173 90 76 78 42 35 62 104 135 185 141 137 149 214 299 0 76 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 7/01/2010 TO 12/31/2010 2ND SEMI STABILITY CLASS A STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 1 4.51- 5.50 0 0 1 0 2 1 1 2 3 0 1 0 0 0 0 11 5.51- 6.50 0 0 0 3 1 3 2 1 8 4 5 2 2 0 0 0 32 6.51- 8.50 0 0 1 4 7 5 9 12 13 23 10 3 1 1 0 90 8.51-11.50 0 0 0 0 6 4 1 2 14 19 28 0 94 0 11 7 2 0 0 34 11.51-14.50 0 0 0 1 1 2 0 1 3 7 6 10 1 1 1 14.51-20.50 0 0 0 7 0 1 15 12 4 0 40 0 0 0 0 0 1 0 6

>20.50 0 0 0 2 0 0 0 0 2 0 0 0 1 1 0 308 TOTAL 0 0 2 6 21 18 9 14 40 56 65 55 13 5 4 STABILITY CLASS B SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 0 2 0 0 0 2 0 0 1 3 0 0 0 0 1 0 8 4.51- 5.50 1 2 2 2 2 0 1 2 9 8 8 4 1 0 0 2 44 5.51- 6.50 1 2 3 4 3 2 4 6 15 14 12 3 5 1 1 0 76 6.51- 8.50 1 0 3 3 5 7 7 4 11 14 15 15 3 0 1 0 89 8.51-11.50 0 0 0 1 4 1 0 2 6 7 11 12 6 2 4 1 57 11.51-14.50 0 0 0 1 4 2 0 1 1 1 5 6 0 1 0 0 22 14.51-20.50 0 0 0 1 7 0 0 0 0 1 4 0 0 0 1 0 14

>20.50 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 1 TOTAL 3 6 8 12 25 13 12 15 43 48 56 40 15 4 8 3 311 STABILITY CLASS C SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 1 0 0 0 0 0 0 1 1 0 0 0 3 3.51- 4.50 1 3 0 4 2 0 3 3 5 9 6 7 1 1 1 3 49 4.51- 5.50 1 4 3 3 1 3 2 6 13 12 15 6 4 1 2 2 78 5.51- 6.50 0 4 1 1 5 0 2 5 13 13 10 5 0 1 0 1 61 6.51- 8.50 0 1 6 5 3 5 4 0 6 5 12 8 4 3 1 1 72 8.51-11.50 0 0 2 4 5 5 3 0 2 4 10 6 0 4 2 2 49 11.51-14.50 0 1 0 1 8 0 0 3 0 1 5 3 0 1 2 0 25 14.51-20.50 0 0 0 0 7 0 0 0 0 0 2 1 2 0 0 0 12

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 1 TOTAL 2 13 12 18 32 13 14 25 39 44 60 37 12 12 8 9 350 77 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 7/01/2010 TO 12/31/2010 2ND SEMI ...

STABILITY CLASS D STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 1 0 0 0 1 0 0 2 1.51- 2.50 3 4 3 2 0 1 2 5 2 2 2 4 1 3 8 2 44 2.51- 3.50 6 3 5 6 4 5 7 8 21 24 19 4 17 0 6 11 146 3.51- 4.50 9 5 7 4 3 5 2 5 14 11 22 6 11 8 6 5 123 4.51- 5.50 7 5 11 7 0 1 7 4 14 13 22 Li 9 5 4 6 126 5.51- 6.50 0 3 8 5 2 1 0 6 12 8 13 10 3 4 1 1 77 6.51- 8.50 1 4 7 6 2 4 5 4 7 9 20 23 8 2 2 0 104 8.51-11.50 3 5 3 5 10 9 3 4 0 14 23 21 3 3 4 1 111 11.51-14.50 2 4 0 3 12 2 0 1 3 5 32 8 2 2 0 0 76 14.51-20.50 0 0 1 1 20 0 0 1 1 1 18 6 1 3 1 0 54

>20.50 0 1 0 1 0 3 0 0 0 0 1 0 0 3 0 0 9 TOTAL 31 34 45 40 53 31 26 38 74 88 172 03 55 34 32 26 872 STABILITY CLASS E SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 1 1 0 0 1 0 0 0 0 0 0 0 0 1 4 1.51- 2.50 5 2 3 0 1 0 0 2 3 5 3 3 1 5 4 4 41 2.51- 3.50 9 10 5 1 3 2 0 1 4 3 9 11 11 13 21 9 112 3.51- 4.50 13 7 6 4 2 1 0 2 6 4 12 11 10 5 Ii 10 104 4.51- 5.50 8 5 3 2 1 2 0 0 6 9 15 16 3 3 6 6 85 5.51- 6.50 3 8 3 2 1 3 0 0 5 12 24 11 6 6 1 3 88 6.51- 8B50 4 6 9 4 7 4 6 7 5 24 36 34 14 6 3 3 172 8.51-11.50 0 2 9 14 12 12 10 3 2 15 46 20 14 12 5 2 178 11.51-14.50 0 0 1 5 13 6 4 0 0 6 34 4 6 3 0 1 83 14.51-20.50 1 1 0 1 14 2 0 0 0 1 4 2 4 2 0 0 32

>20.50 0 0 0 0 0 1 0 0 0 0 0 1 0 1 0 0 3 TOTAL 43 41 40 34 54 33 21 15 31 79 183 113 69 56 51 39 902 STABILITY CLASS F SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1.51- 2.50 5 2 0 0 0 2 1 0 0 3 2 2 11 7 14 6 55 2.51- 3.50 16 5 4 2 1 0 1 2 1 1 7 8 23 13 23 17 124 3.51- 4.50 17 9 2 1 1 2 0 0 2 1 6 11 19 15 10 13 109 4.51- 5.50 9 10 2 0 0 0 2 1 2 8 12 11 5 6 4 10 82 5.51- 6.50 4 3 2 2 0 0 0 0 2 7 11 9 7 2 3 7 59 6.51- 8.50 4 7 8 3 1 0 0 1 3 12 19 12 11 9 3 12 105 8.51-11.50 0 1 4 4 1 1 1 0 0 3 4 7 4 2 0 6 38 11.51-14.50 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 2 3 14.51-20.50 0 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0 2

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 55 37 22 13 6 5 5 4 10 35 61 60 80 54 57 74 578 78 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 7/01/2010 TO 12/31/2010

- 2ND SEMI STABILITY CLASS G STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 1 1 0 0 0 0 0 0 1 0 3 1 2 0 1 10 1.51- 2.50 14 9 3 1 0 0 2 0 2 4 3 2 7 12 22 23 104 2.51- 3.50 55 30 12 6 0 2 4 1 2 3 4 2 10 26 53 63 273 3.51- 4.50 82 30 9 6 4 1 0 0 3 1 4 6 8 6 41 91 292 4.51- 5.50 96 40 8 0 0 1 0 1 0 1 1 5 3 2 13 45 216 5.51- 6.50 42 27 4 2 0 0 0 0 0 0 2 0 1 0 3 13 94 6.51- 8.50 29 33 5 0 0 0 0 0 0 0 2 0 0 1 2 17 89 8.51-11.50 7 6 0 0 0 0 0 0 0 0 1 0 1 0 0 1 16 11.51-14.50 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 1 14.51-20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 325 176 42 16 4 4 6 2 7 10 17 18 31 49 134 254 1095 STABILITY CLASS ALL SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 1 2 1 0 0 1 0 0 2 0 3 3 3 0 3 17 1.51- 2.50 27 17 9 3 1 3 5 7 7 14 10 11 20 27 48 35 244 2.51- 3.50 86 48 26 15 9 9 12 12 28 31 39 26 62 52 103 100 658 3.51- 4.50 122 56 24 19 12 10 5 10 31 30 50 41 49 35 70 122 686 4.51- 5.50 122 66 29 15 4 9 13 15 46 54 73 54 25 17 29 71 642 5.51- 6.50 50 47 22 19 12 9 8 18 55 58 77 40 24 14 9 25 487 6.51- 6.50 39 51 39 22 22 27 27 33 44 77 127 102 43 22 13 33 721 8.51-11.50 10 14 18 28 38 32 18 11 24 54 114 94 35 25 15 13 543 11.51-14.50 2 5 1 12 39 12 4 6 7 20 82 31 9 8 3 3 244 14.51-20.50 1 1 1 4 56 2 0 1 2 18 40 13 7 5 3 0 154

>20.50 0 1 0 1 2 4 0 0 0 2 2 1 0 6 1 0 20 TOTAL 459 307 171 139 195 117 93 113 244 360 614 416 275 214 294 405 4416 TOTAL NUMBER OF OBSERVATIONS: 4416 TOTAL NUMBER OF VALID OBSERVATIONS: 4416 TOTAL NUMBER OF MISSING OBSERVATIONS: 0 PERCENT DATA RECOVERY FOR THIS PERIOD: 100.0 %

MEAN WIND SPEED FOR THIS PERIOD: 6.4 MPH TOTAL NUMBER OF OBSERVATIONS WITH BACKUP DATA: 0 PERCENTAGE OCCURRENCE OF STABILITY CLASSES A B C D E F G 6.97 7.04 7.93 19.75 20.43 13.09 24.80 DISTRIBUTION OF WIND DIRECTION VS STABILITY N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW CALM A 0 0 2 6 21 18 9 14 40 56 65 55 13 5 4 0 0 B 3 6 8 12 25 13 12 15 43 48 56 40 15 4 8 3 0 C 2 13 12 28 32 13 14 25 39 44 60 37 12 12 8 9 0 D 31 34 45 40 53 31 26 38 74 88 172 93 55 34 32 26 0 E 43 41 40 34 54 33 21 15 31 79 183 113 69 56 51 39 0 F 55 37 22 13 6 5 5 4 10 35 61 60 80 54 57 74 0 G 325 176 42 16 4 4 6 2 7 10 17 18 31 49 134 254 0 TOTAL 459 307 171 139 195 117 93 113 244 360 614 416 275 214 294 405 0 79 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 1/01/2010 TO 12/31/2010

- ANNUAL STABILITY CLASS A STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 B S S0 0 0 0 5 0 0 0 1.51- 2.50 0 0 o 0 0 6 0 0 o B 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 B S S S 0 0 0 B S S B 0 0 3.51- 4.50 1 1 0 0 0 0 0 0 1 1 0 0 0 0 0 0 4 4.51- 5.50 0 0 0 1 0 2 1 2 5 6 1 1 1 0 0 0 20 5.51- 6.50 0 0 2 3 1 3 4 5 19 9 10 2 3 0 0 0 61 6.51- 8.50 0 0 2 2 6 10 7 15 19 29 42 20 12 2 1 0 167 8.51-11.50 0 1 2 0 9 5 2 4 28 36 55 46 14 6 2 3 213 11.51-14.50 0 1 3 1 2 3 0 1 6 20 40 17 6 8 1 3 112 14.51-20.50 1 1 2 1 10 0 0 0 1 23 48 16 5 16 8 0 132

>20.50 O 0 0 0 2 0 0 0 5 2 6 2 0 4 4 0 25 TOTAL 2 4 Li 8 30 23 14 27 84 126 202 104 41 36 16 6 734 STABILITY CLASS B SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3.51- 4.50 0 2 1 1 0 1 0 0 2 4 2 0 0 0 2 0 15 4.51- 5.50 1 3 2 4 2 0 1 5 27 10 10 6 3 0 0 4 78 5.51- 6.50 2 4 7 6 6 2 7 14 38 26 16 7 5 3 1 0 144 6.51- 8.50 1 1 7 8 7 8 7 5 28 22 28 23 8 1 2 1 157 8.51-11.50 2 1 7 9 4 3 0 3 9 9 24 19 8 5 4 2 109 11.51-14.50 0 0 1 1 4 2 0 1 1 2 13 12 2 6 1 1 47 14.51-20.50 1 0 0 1 7 0 0 0 0 1 11 1 1 3 3 1 30

,20.50 0 0 0 0 0 0 0 0 0 0 2 0 0 0 0 0 2 TOTAL 7 11 25 30 30 16 15 28 . 105 74 106 68 27 18 13 9 582 STABILITY CLASS C SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1.51- 2.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2.51- 3.50 0 0 0 1 1 1 0 1 0 1 1 1 1 0 0 0 8 3.51- 4.50 1 5 2 6 3 1 3 7 11 16 8 9 4 1 1 3 81 4.51- 5.50 2 9 8 5 1 3 2 8 29 19 19 9 6 2 2 3 127 5.51- 6.50 1 6 5 6 6 1 4 8 29 21 17 10 0 3 0 2 119 6.51- 8.50 3 2 13 33 6 5 8 31 20 9 27 19 7 4 1 2 138 8.51-11.50 2 0 5 10 10 6 5 0 3 10 21 13 7 6 4 2 104 11.51-14.50 0 1 1 3 9 0 0 3 1 3 13 5 1 4 3 2 49 14.51-20.50 0 1 0 4 8 1 0 0 0 2 8 1 3 2 0 0 30 s20.50 0 0 0 0 0 0 0 0 0 0 0 2 0 1 0 0 3 TOTAL B 24 34 46 44 18 22 38 83 81 114 69 29 23 11 14 659 80 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 1/01/2010 TO 12/31/2010

.*. ANNUAL *.*

STABILITY CLASS D STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 1 0 0 0 1 0 0 2 1.51- 2.50 4 9 3 5 1 2 3 10 5 8 4 6 6 6 15 3 90 2.51- 3.50 14 14 11 15 7 7 9 Li 31 34 33 19 23 15 14 24 281 3.51- 4.50 17 16 14 13 13 6 4 7 30 34 41 15 18 14 i0 13 265 4.51- 5.50 11 10 21 14 4 1 9 7 22 23 37 26 11 6 6 9 217 5.51- 6.50 2 13 17 10 5 3 1 7 18 18 23 16 7 5 4 2 151 6.51- 8.50 4 9 12 16 12 8 9 5 19 18 36 31 15 4 6 0 204 8.51-11.50 4 8 4 13 17 18 6 9 2 18 39 41 14 5 6 2 206 11.51-14.50 2 4 1 5 23 3 0 1 5 14 47 16 9 13 0 1 144 14.51-20.50 0 0 1 1 22 0 0 1 1 5 36 14 7 8 4 1 101

>20.50 0 1 0 1 0 4 0 0 2 1 1 1 0 3 0 0 14 TOTAL 58 84 84 93 104 52 41 58 135 174 297 185 110 80 65 55 1675 STABILITY CLASS E SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 1 1 0 0 1 0 0 0 2 1 0 0 0 2 7 1.51- 2.50 8 2 4 1 3 2 2 2 4 6 3 5 6 10 10 7 75 2.51- 3.50 16 17 6 1 5 4 0 5 5 4 16 18 21 25 34 19 196 3.51- 4.50 19 15 8 7 4 1 0 3 11 11 19 21 15 13 20 10 177 4.51- 5.50 10 13 6 4 2 2 0 3 8 17 29 23 10 6 12 8 153 5.51- 6.50 9 11 3 5 2 3 0 0 6 24 35 18 13 10 5 7 151 6.51- 8.50 6 10 15 7 10 5 7 11 8 37 64 63 29 11 7 4 294 8.51-11.50 1 4 11 19 16 15 11 4 8 37 90 52 26 17 12 4 327 11.51-14.50 2 0 1 5 17 6 4 3 1 24 69 12 14 9 7 2 176 14.51-20.50 3 1 0 1 19 3 0 0 1 1 12 7 7 4 2 3 64

>20.50 0 0 0 0 3 1 0 0 2 0 1 1 0 1 0 0 9 TOTAL 74 73 55 51 81 42 25 31 54 161 340 221 141 106 109 65 1629 STABILITY CLASS F SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 1 3 1.51- 2.50 6 6 1 4 1 2 1 0 0 3 3 6 16 15 20 11 95 2.51- 3.50 30 16 10 4 2 2 1 3 3 5 15 18 42 22 49 40 262 3.51- 4.50 32 14 7 2 1 3 1 1 4 7 10 19 27 28 33 25 214 4.51- 5.50 14 18 8 1 0 0 2 1 2 18 20 21 11 12 19 24 171 5.51- 6.50 13 9 7 2 0 0 1 0 3 13 25 17 18 9 12 15 144 6.51- 8.50 14 8 14 5 1 0 0 3 6 29 69 33 33 21 10 23 269 8.51-11.50 6 4 4 4 1 1 1 1 0 12 52 14 7 4 1 8 120 11.51-14.50 0 0 0 0 1 0 0 0 0 1 3 0 0 1 1 4 11 14.51-20.50 0 0 0 1 1 0 0 0 0 0 0 0 0 0 0 2 4

>20.50 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 TOTAL 115 76 51 23 8 8 7 9 18 88 197 128 155 113 145 153 1294 81 PVNGS ARERR 2010

ARIZONA PUBLIC SERVICE CO. - PALO VERDE NUCLEAR GENERATING STATION JOINT FREQUENCY DISTRIBUTION FOR THE PERIOD 1/01/2010 TO 12/31/2010

- ANNUAL ...

STABILITY CLASS G STABILITY BASED ON: DELTA T BETWEEN 200.0 AND 35.0 FEET WIND MEASURED AT: 35.0 FEET WIND THRESHOLD AT: .75 MPH JOINT FREQUENCY DISTRIBUTION OF WIND SPEED AND DIRECTION IN HOURS AT 35.00 FEET SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 2 2 0 0 0 0 0 0 1 0 3 1 4 1 2 16 1.51- 2.50 26 15 6 2 1 2 2 0 3 4 6 7 13 22 39 40 lBS 2.51- 3.50 107 49 19 11 1 2 4 3 4 5 9 8 15 50 91 114 492 3.51- 4.50 180 65 12 9 5 2 0 0 3 1 9 10 16 17 71 154 554 4.51- 5.50 185 85 12 3 2 1 2 1 0 1 4 6 10 6 27 90 435 5.51- 6.50 86 63 10 6 0 0 0 0 0 0 7 2 4 4 11 32 225 6.51- 8.50 75 69 13 2 1 0 0 0 0 2 7 4 2 3 5 38 221 8.51-11.50 17 14 1 1 0 0 0 0 0 3 9 1 1 0 1 6 54 11.51-14.50 0 0 0 1 0 0 0 0 0 0 0 0 0 0 1 2 14.51-20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

>20.50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL 676 362 75 35 10 7 8 4 10 17 51 41 62 106 246 477 2187 STABILITY CLASS ALL SPEED (MPH) N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW TOTAL CALM 0

.76- 1.50 0 2 3 1 0 0 1 0 0 2 2 4 2 6 1 4 28 1.51- 2.50 44 32 14 12 6 8 8 12 12 21 16 24 41 53 84 61 448 2.51- 3.50 167 96 46 32 16 16 14 23 43 49 74 64 102 112 188 197 1239 3.51- 4.50 250 118 44 38 26 14 8 18 62 74 89 74 80 73 137 205 1310 4.51- 5.50 223 138 57 32 11 9 17 27 93 94 120 92 52 32 66 138 1201 5.51- 6.50 113 106 51 38 20 12 17 34 113 il 133 72 50 34 33 58 995 6.51- 8.50 103 99 76 51 43 36 38 50 90 146 273 193 106 46 32 68 1450 8.51-11.50 32 32 34 56 57 48 25 21 50 125 290 186 77 43 30 27 1133 11.51-14.50 4 6 7 16 56 14 4 9 14 64 185 62 32 41 13 14 541 14.51-20.50 5 3 3 9 67 4 0 1 3 32 115 39 23 33 17 7 361

>20.50 0 2 0 1 5 5 0 0 9 3 10 6 0 9 4 0 54 TOTAL 941 634 335 286 307 166 132 195 489 721 1307 816 565 482 605 779 8760 TOTAL NUMBER OF OBSERVATIONS: 8760 TOTAL NUMBER OF VALID OBSERVATIONS: 8760 TOTAL NUMBER OF MISSING OBSERVATIONS: 0 PERCENT DATA RECOVERY FOR THIS PERIOD: 100.0 %

MEAN WIND SPEED FOR THIS PERIOD: 6.7 MPH TOTAL NUMBER OF OBSERVATIONS WITH BACKUP DATA: B PERCENTAGE OCCURRENCE OF STABILITY CLASSES A B C D E F G 8.38 6.64 7.52 19.12 18.60 14.77 24.97 DISTRIBUTION OF WIND DIRECTION VS STABILITY N NNE NE ENE E ESE SE SSE S SSW SW WSW W WNW NW NNW CALM A 2 4 11 8 30 23 14 27 84 126 202 104 41 36 16 6 0 B 7 11 25 30 30 16 15 28 105 74 106 68 27 18 13 9 0 C 9 24 34 46 44 18 22 38 83 81 114 69 29 23 11 14 0 D 58 84 84 93 104 52 41 58 135 174 297 185 110 80 65 55 0 E 74 73 55 51 61 42 25 31 54 161 340 221 141 106 109 65 0 F 115 76 51 23 8 8 7 9 18 88 197 128 155 113 145 153 0 G 676 362 75 35 10 7 8 4 10 17 51 41 62 106 246 477 0 TOTAL 941 634 335 286 307 166 132 195 489 721 1307 816 565 482 605 779 0 82 PVNGS ARERR 2010

APPENDIX C DOSE CALCULATIONS 83 PVNGS ARERR 2010

GASEOUS EFFLUENT DOSE CALCULATIONS Doses to the maximum individual and the surrounding population resulting from the release of radioactive material in gaseous effluents from the Palo Verde Nuclear Generating Station were cal-culated using the GASPAR computer program. The radionuclides considered in the dose calcula-tions were Tritium, lodine-131, lodine-132, lodine-133, lodine-135, all noble gases, and particulates having a half-life greater than eight days and for which dose factors are contained in NUREG-0172. Locations selected for individual dose calculations included for each sector, the site boundary, and within five miles, if present, the nearest residence, the nearest garden, and the nearest milk animal. GASPAR implements the radiological dose models of Regulatory Guide 1.109 to determine the radiation exposure to man from four principal atmospheric exposure pathways:

plume, ground deposition, inhalation, and ingestion. Doses to the maximum individual and the population were calculated as a function of age group and pathway for significant body organs.

Table 43 presents the doses on a quarterly, semiannual and annual basis for the Energy Informa-tion Center. An occupancy factor of 1.0 (implying continuous occupancy over the entire year) was considered for the Energy Information Center and the exposure pathways considered to calculate its doses were plume, ground deposition, and inhalation.

Table 44 presents the population dose..

Table 45 summarizes the individual doses and compares the result to PVNGS ODCM Require-ment limits. The site boundary and residence locations for which data are presented represent the highest annual doses.

Based on results obtained by placing TLDs on the site boundary in each sector, the net dose for this reporting period, from direct-radiation, (plume and ground deposition) from all three units was indistinguishable from preoperational values of 8 - 14 hR/hr (17 - 30 mR/Std Qtr).

There were no liquid effluents associated with the operation of this facility.

84 PVNGS ARERR 2010

Dose Calculation Models The GASPAR computer code was used to evaluate the radiological consequences of the routine release of gaseous effluents. GASPAR implements the dose calculational methodologies of Regu-latory Guide 1.109, Revision 1.

Source terms for each quarter are combined with station-specific demographic data and each quarter's atmospheric diffusion estimates for gaseous dose calculations.

Atmospheric diffusion estimates are generated by the XOQDOQ computer code using onsite meteorological data as input. Additional input to GASPAR includes the following site-specific data:

0 to 5 mile nearest residence, milk animal and garden in each of the 16 compass sectors, based on the 2010 Land Use Census.

0 to 10 mile population distribution based on the Maricopa County Department of Emergency Management 2010 Population and Special Needs Survey Information.

The 10 to 50 mile population distribution from the PVNGS UFSAR, Figure 2.1-11.

The population distribution of metropolitan Phoenix greater than 50 miles from PVNGS, based on the 1980 federal census results, is conservatively included in the 40 to 50 mile sectors (NE=123; ENE=140,097; E=621,130; ESE=8,392).

Absolute humidity of 6.0 g/m 3 from the PVNGS UFSAR, Table 2.3-16.

The fraction of the year that vegetables are grown (0.667) from the PVNGS ER-OL, Section 2.1.3.4, Table 2.1-8.

The fraction of daily feed derived from pasture while on pasture (0.35) and length of grazing season for milk animals beyond 5 miles (0.75) from the PVNGS ER-OL, Section 2.1.3.4.3.

The fraction of daily feed derived from pasture while on pasture (0.05) and length of grazing season for meat animals (0.25) from the PVNGS ER-OL, Section 2.1.3.4.4.

There were five (5) sectors containing milk animal (goat or cow) locations within five (5) miles. For calculational purposes these milk animals are assumed to be fed 100% on pasture grass during the year.

Other values used for input to GASPAR are default values from Regulatory Guide 1.109, Revision 1.

85 PVNGS ARERR 2010

Table 43:

Doses To Special Locations For 2010 ENERGY INFORMATION CENTER LOCATED ONSITE 0.45 MILE S FROM UNIT 1, 0.29 MILE SSE FROM UNIT 2 AND 0.20 MILE ESE FROM UNIT 3 (MREM) T.BODY GI-TRACT BONE LIVER KIDNEY THYROID LUNG SKIN 1ST QUARTER ADULT 9.63E-01 9.63E-01 1. IE-03 9. 63E-01 9.63E-01 9.63E-01 9.63E-01 9.64E-01 TEEN 9.70E-01 9. 70E-01 1.lIE-03 9.70E-01 9. 70E-01 9.70E-01 9.70E-01 9.71E-01 CHILD 8.57E-01 8. 57E-01 1. IE-03 8.57E-01 8. 57E-01 8. 57E-01 8.57E-01 8.58E-01 INFANT 4.93E-01 4. 93E-01 1. 11E-03 4.93E-01 4. 93E-01 4. 93E-01 4.93E-01 4.94E-01 2ND QUARTER ADULT 2.98E-01 2. 98E-01 6. 30E-04 2.98E-01 2 .98E-01 2.98E-01 2.98E-01 2.98E-01 TEEN 2.99E-01 2 .99E-01 6. 30E-04 2.99E-01 2. 99E-01 2. 99E-01 2.99E-01 3. CCE-01 CHILD 2.65E-01 2.65E-01 6.31E-04 2. 65E-01 2.65E-01 2. 65E-01 2.65E-01 2.66E-01 INFANT 1.53E-01 1.53E-01 6.30E-04 1. 53E-01 1. 53E-01 1.53E-01 1.53E-01 1.53E-01 1ST SEMI-ANNUAL ADULT 1.26E+00 1. 26E+00 1. 74E-03 1. 26E+00 1. 26E+00 1. 26E+00 1. 26E+00 1 .26E+00 TEEN 1.27E+00 1. 27E+00 1. 74E-03 1.27E+00 1. 27E+00 1 .27E+00 1. 27E+00 1. 27E+00 CHILD 1.12E+00 1. 12E+00 1.74E-03 1. 12E+00 1. 12E+00 1. 12E+00 1. 12E+00 1. 12E+00 INFANT 6.46E-01 6. 46E-01 1. 74E-03 6.46E-01 6.46E-01 6.46E-01 6.46E-01 6.47E-01 3RD QUARTER ADULT 1.60E-01 1.60E-01 5. 96E-04 1. 60E-01 1. 60E-01 1. 60E-01 1 . 60E-01 1.60E-01 TEEN 1.61E-01 1.61E-01 5.96E-04 1.61E-01 1.61E-01 1. 61E-01 1.61E-01 1.61E-01 CHILD 1.42E-01 1. 42E-01 5. 96E-04 1.42E-01 1.42E-01 1.42E-01 1.42E-01 1.43E-01 INFANT 8.21E-02 8. 21E-02 5. 96E-04 8 .21E-02 8.21E-02 8. 21E-02 8. 21E-02 8. 24E-02 4TH QUARTER ADULT 3.93E-01 3. 93E-01 6.84E-03 3.93E-01 3.93E-01 3.93E-01 3.93E-01 3.96E-01 TEEN 3.95E-01 3. 96E-01 6. 84E-03 3.95E-01 3. 95E-01 3. 96E-01 3.96E-01 3.98E-01 CHILD 3.51E-01 3.51E-01 6.84E-03 3. 51E-01 3.51E-01 3.51E-01 3.51E-01 3.54E-01 INFANT 2.05E-01 2.05E-01 6. 84E-03 2.05E-01 2. 05E-01 2 .05E-01 2. 5OE-01 1.48E-01 2ND SEMI-ANNUAL ADULT 5.53E-01 5. 53E-01 7. 44E-03 5.53E-01 5 .53E-01 5.53E-01 5.53E-01 5.56E-01 TEEN 5.56E-01 5. 57E-01 7 . 44E-03 5.56E-01 5.56E-01 5.57E-01 5.57E-01 5.60E-01 CHILD 4.93E-01 4.93E-01 7. 44E-03 4.93E-01 4 .93E-01 4.93E-01 4.93E-01 4.97E-01 INFANT 2.87E-01 2. 87E-01 7. 44E-03 2.87E-01 2.87E-01 2. 87E-01 2.87E-01 2.30E-01 ANNUAL ADULT 1.81E+00 1. 81E+00 9.18E-03 1. 81E+00 1. 81E+00 1. 81E+00 1. 81E+00 1. 82E+00 TEEN 1.83E+00 1. 83E+00 9 . 18E-03 1.83E+00 1 83E+00 1. 83E+00 1. 83E+00 1. 83E+00 CHILD 1.62E+00 1. 62E+00 9.18E-03 1. 62E+00 1 62E+00 1. 62E+00 1. 62E+00 1. 62E+00 INFANT 9.33E-01 9. 33E-01 9.18E-03 9.33E-01 9.33E-01 9.33E-01 9.33E-01 8.78E-01 86 PVNGS ARERR 2010

Table 44:

Integrated Population Dose for 2010 JAN - MAR PATHWAY T.BODY GI-TRACT BONE LIVER KIDNEY THYROID LUNG SKIN


+/--

PLUME 7.04E-05 7.04E-05 7.04E-05 7.04E-05 7.04E-05 7.04E-05 j 7.04E-05 1.26E-04

.00% .00% 99.17%I .00% .00% .00% .00% .00%


+-------------------+---+ --------- -+--------------

GROUND 1.47E-08 1.47E-0S 1.47E-08 1.47E-08 i1.47E-08 1.47E-08 1.47E-08 1.79E-08

.00% .00% .02% .00% .00% .00% .00% j .00%

INHAL 2.20E+00 2.20E+00 1.93E-07 2.20EK00 2.20E+00 2.20E+00 2.20E+00 I 2,20E+00 21.00% 21.00% .27% 21.00% 21.00% 21.00% 21.00% 21.00%


+-------------------+---+ --- +----- -+---------------

VEGET 7.25E+00 7.25E+00C 3.38E-07 j 7.25E+00 7.25E+00 7.25E+00 7.25EKr0 I 7,25E+00 69.22% 69.22% .48% 69.22% 69.22% 69.22% I 69.22% 69.22%


+ --- + --- +

COW MILK 6.63E-01C 6.63K-01 4.32E-08 6.63E-01 j 6.63E-01 6.63E-01 6.63E-01 6,63E-01 6.32% 6.32% .06% [ 6.32% j 6.32% 6.32% ( 6.32% j 6.32%

MEAT j 3.62E-01 3.62E-01 6.63E-l1 3.62E-01 3.62E-01 3.62E-01 3.62E-01 3.62E-01 3.46% J 3.46% J .00% J 3.46% j 3.46% 3.46% J 3.46% J 3.46%

-- + +----------------- --------------- + -------- *-

  • TOTAL* I 1.05E+01 I 1.05E+01 I 7.10E-05 I1105+01I 1.05E+01 I 1.05E+01 I 1.05E01 I 1.05E+01 I

-+--------------+-

(1) I I I I I I I 1

PER CAPITAI 5.36E-06 5.36E-06 3.62E-I1 5.36E-06 5.36E-06 5.36E-06 5.36E-06 5.36E-06 DOSE (REM)I I I-- --- I I APR - JUN PATHWAY T.BODY GI-TRACT BONE LIVER KIDNEY THYROID LUNG SKIN


+-------------------------+---+---------------+ ------- +--

PLUME 2.17E-04 2.17E-04 2.17E-04 2.17E-04 2.17E-04.1 2.17E-04 2.17E-04 I 5.90E-04

.00% .00% j 63.06% 1 .00% 1 .00% 1 .00% 1 .00% 1 .01% 1


+---+-----------* -------- --- +------

GROUND 1.11E-04 1.IIE-04 i.11E-04 1.I1E-04 1.11E-04 1.I1E-04 1.IIE-04 1.30E-04

.00% .00% 32.29% .00% .00% .00% .00% .00%


+ +-------+---+---*


--- +----+-

INHAL 1,74E+00 1.74E+00 1.94E-06 i1.74E+00 1.74E+00 1.74E+00 i1.74E+00 1.74E+00 30.47% 30.47% .56% 30.47% 30.47% 30.47% 30.47% 30.46%


+ -- ------------------------------

+---+---+---+-------+ ------- +--

VEGET J 3.28E+00 j 3.28E+00 1.04E-05 j 3.28E+00 J 3.28E+00 J 3.28E+00 j 3.28E+00 J 3.28E+00 57.50% 57.50% 3.03% 57.50% 57.50% 57.50% 557.50% 57.50%

S+-------------------------------------+---+---+---+---+---.4 --- +---+--

COW MILK 5.55E-01 5.55E-01 3.53E-06 5.55E-01 5.55E-01 5.55E-01 5.55E-01 5.55E-01 I 9.73% I 9.73% 1.03% 9.73% 9.73% I 9.73% I 9.7396 9.73%I


+--------------------------------------+---+ ----------- +--

MEAT 1.31E-01 1.31E-01 1.05E-07 1.31E-01 1.31E-01 1.31E-01 1.31E-01 1.31E-01 2.29% 2.29% .03% 2.29% 2.29% 2.29% 2.29% I 2.29%


+/---------------------------+---+---+-------+---+ ------- +--

  • TOTAL* I 5.70E+00 I 5.70E+00 I 3.44E-04 I 5.70E+00 I 5.70E+00 I 5.70E+00 I 5.70E+00 I 5.70E+00 I

+-----------------------------+ ----------- +--

(1) I I I I I I I I PER CAPITAl 2.91E-06 I 2.91E-06 I 1.76E-10 I 2.91E-06 I 2.91E-06 I 2.91E-06 I 2.91E-06 I 2.91E-06 I DOSE (KKM)I I I I I I I I I

-++ -+--- +------------------- +

87 PVNGS ARERR 2010

Table 44: (continued)

Integrated Population Dose for 2010 PATHWAY T.BODY GI-TRACT BONE LIVER KIDNEY THYROID LUNG SKIN


+ ------------ +----- I-PLUME 2.87E-04 2.87E-04 2.87E-04 2.87E-04 2.87E-04 2.87E-04 2.87E-04 7.16E-04

.00% .00%1 69.24% .00% I .00% .00% .00% j .00%

+

GROUND 1.11E-04 1.11E-04 1.11E-04 I.11E-04 1 j 1.11E-04 1.1IE-04 1.1E-04 1.30E-04

.00% j .00% 26.77% .00% .00% .00% .00% .00%

INHAL 3.94E+00 3.94E+00 2.13E-06 j 3.94E+00 3.94E+00 3.94E+00 3.94E+00 F 3.94E+00 24.33% 24.33% .51% 24.33% 24.33% 24.33% 24.33% 24.33%

VEGET i.05E+01 1.05E+01 1.07E-05 1.05E+01 1.05E+01 1.05E+01 1.05E+01 1.05E+01 65.09% 65.09% 2.59% 65.09% 65.09% 65.09% 65.09% 65.09%

COW MILK 1.22E+00 F 1.22E+00 3.57E-06 1.22E+00 1.22E+00 1.22E+00 1.22E+00K 1.22E+00 7.52% 7.52% .86% 7.52% 7.52% 7.52% 7.52% 7.52%

HEAT 4.93K-Si 4.93K-0i 1.05E-07 4.93K-0i1 4.93K-01 4.93K-01 4.93K-01 4.93K-0i 3.05% 3.05% .03% 3.05% 3.05% 3.05% j 3.05% 3.05%

--- -+-----------------------------+---+---+---+---+ --- +------

  • TOTAL* I 1.62E+01 1.62E+01 1 4.15E-041 1.62E+011 1.62E+01 I 1.62E+01 j 1.62E+01 I 1.62E÷01

--- -+------------------------------+---+---+---+---+ --- +-----

(1) 1 I I I I I I I PER CAPITAl 8.27E-06 8.27E-06 2.12E-10i 8.27E-06 8.27E-06 [ 8.27E-06 8.27E-06 8.27E-06 DOSE CREW) F F F F F F F 4 -- - - - --

4-- - - - ------------------------- -- - - - --

JUL - SEP PATHWAY T.BODY GI-TRACT BONE L IVER KIDNEY THYROID LUNG SKIN PLUME F 9.21E-05 F 9.21E-05 F 9.21E-05 F 9. 21E-05 F 9.21E-05 F 9.21E-05 F 9.21E-05 1.92E-04 F F .00% F .00% F 87.62% F .00%F .oo%F .00% F .00% F .01%

GROUND 1.29E-05 F 1.29E-05 F 1.29E-05 F 1.29E-05 F 1.29E-05 F 1.29E-05 F 1.29E-05 F1.52E-05 F F .00% F .00% F 12.28% F .00% F .00% F .00% F .00% F .00% F


+------------------------+ ---+ --- +-----

INHAL F 8.04K-01 8.04E-01 F 3.10E-08 F 8.04E-01 F 8.04E-01 F 8.04E-01 F 8.04E-0S 1 8.04E-0i F F 28.82% F 28.82% F .03% F 28.82% F 28.82% F 28.82% F 28.82% F 28.82% F VEGET F 1.67E+00 F 1.67E+00 5.89E-08 F 1.67E+00 F 1.67E+00 F 1.67E+00 F 1.67E+00 11.67E+00 F F 59.75% F 59.75% .06% F 59.75% F 59.75% F 59.75% F 59.75% F 59.75% F COW MILK F 2.46E-01 F 2.46E-01 1.11KE-08 2.46E-01 F 2.46E-01 F 2.46E-01 F 2.46E-01 F 2.46E-01 F F 8.81% F 8.81% F .01% F 8.81% F 8.81% F 8.81% F 8.81% F 8.81% F MEAT F 7.30E-02 F 7.30E-02 F 8.64E-12 F 7.30E-02 F 7.30E-02 F 7.30E-02 F7.30E-02 F 7.30E-02 F F 2.61% F 2.61% F .00% F 2.61% F 2.61% F 2.61% F 2.61% 2.61% F

  • TOTAL* I 2.79E+00 I 2.79E+00 I 1.05E-04 I 2.79E+00 F 2.79E+00 I 2.79E+00 F 2.79E+00 I 2.79E+00 I S+----------------------------+-----------+--- +-----

(2) 1 F F F F 1 PER CAPITAF 1.42E-06 I 1.42E-06 I 5.36E-11 I 1.42K-06 I 1.42E-06 I 1.42E-06 IS1.42K-6 F.42E-06 I I DOSE (REH)I I I I I I

- + --- .-------

+ +- -+ - - --- F- - - -- -F-- - - -

88 PVNGS ARERR 2010

Table 44: (continued)

Integrated Population Dose for 2010 OCT - DEC PATHWAY T.BODY GI-TRACT BONE LIVER KIDNEY THYROID LUNG SKIN 4 -- - - - - - - - - - - - - - - -

PLUME 5.03E-04 5.03E-04 55.03E-04 5.03E-04 5.03E-04 5.03E.04 5.03E-04 1.02E-03

.01% .01% 74.30% .01% .01% .01% .01% .02%

GROUND 1.70E-04 1i.70E-04 I1.70E-04 i1.70E-04 i1.70E-04 i1.70E-04 1.70E-04 2.SSE-04

.00% .00% 25.19% .00% .00% .00% .00% .00%

INHAL 1.24K+00 1.24E+00 1.. 94E-06 I1.24E+00 1.24E+00 I1.24E+00 1.24EK00 1.24EO00O I 24.67% 24.67% .29% 24.67% 24.67% 24.67% 24.68% 24.67%

VEGET 3.22E+00 3.22E+00 K .29E-06 3.22EK00 3.22E+00 3.22E+00 3.22E+00K 3.22E+00 64,22% 64.22% .19% 64.22% 64.22% 64.22% 64.21% J 64.21%

- - - - - - - -+--

COW MILK 3.98E-01 3.98E-01i .33E-07 3.98E-01 3.98E-01 3.98E-01 3.98E-01 I 3.98E-01 7.93% I 7.93% I .03% 7.93% 7.93% I 7.93% I 7.93% I 7.93% I MEAT I 1.59E-01 I 1.59E-01 9 .08E-09 1.59K-01 1.59E-01 1.59E-01i 1.59E-01 I 1.59E-01 3.17% 3.17% .00% 3.17% 3.17% 3.17% 3.17% 3.17%

  • TOTAL* I 5.02EO001 5.02E+00 1 6.76E-04 I 5.02E+00 I 5.02E+00 I 5.02E+00 I 5.02E+00 I 5.02E+00 I (1) 1 I I PER CAPITAl 2.56E-06 2.56E-06 3.45E-i0 2.56E-06 2.56E-06 l2.56E-06 2.56E-06 2.56E-06 DOSE (REM)I I----- ---

JUL - DEC PATHWAY T.BODY GI-TRACT BONE LIVER KIDNEY THYROID LUNG SKIN

-+----------------------------------+

--- +--- +--

PLUME 5.95E-04 5.95E-04 5.95E-04 5.95E-04 5.95E-04 5.95E-04 5.95E-04 1.21E-03

.01% .01% 76.09% .01% .01% .01% .01% j .02%

GROUND 1.83E-04 1.83E-04 i1.83E-04 1.83E-04 1.83E-04 1.83E-04 1.83E-04 2.15E-04

.00% .00% 23.45% .00% .00% .00% .00% .00%

INHAL [. 2.04E+00 2.04E+00 1.98E-06 2.04E+00 2.04E+00 2.04E+00 2.04EK-00 2.04E+00 26.15% 26.15% .25% 26.15% 26.15% 26.15% I 26.16% 26.15%

-+----------------------------+---+-------+-----

VEGET 4.89E+00 4.89E+00 1.34E-06 I 4.89E-00 4.89EK00 4.89E+00K 4.89E+00 4.89E+00 62.62% 62.62% .17% 62.62% 62.62% 62.62% 62.62% 62.62%

COW MILK 6.44E-S01 6.44E-01 2.44E-07 6.44E-01 6.44E-01 6.44E-01 6.44E-01 6.44E-01 i 8.25% 8.25% .03% 8.25% 8.25% 8.25% 8.25% 8.25%

MEAT 2.32E-01 2.32E-01 9,09E-09 2.32E-01 2.32E-01 2.32E-01 2.32E-01 2.32E-01 2.97% 2.97% .00% 2.97% 2.97% 2.97% 2.97% 2.97%

  • TOTAL* I 7.81E+00 I 7.81E+00 I 7.82E-04 I 7.81E+00 I 7.81E+00 K 7.81E+00 I 7.81E+00 K 7.81E+00 K

(1 ) 1I I I I I I I I PER CAPITAl 3.99E-06S 3.99E-06 3.99E-I0 3.99E-06 3.99E-06 3.99E-06 3.99E-06 3.99E-06 DOSE (REM)l I

--- - + - - - - - - - - - -

I I I 1 I 1 I 89 PVNGS ARERR 2010

Table 44: (continued)

Integrated Population Dose for 2010 JAN - DEC PATHWAY T.BODY GI-TRACT BONE LIVER KIDNEY THYROID LUNG SKIN PLUME 8.82E-04 8.82E-04 8.82E-04 8.82E-04 I 8.82E-04 8.82E-04 8.82E-04 1.93E-03

.00% .00% 73.71% I .00% .00% .00% .00% .01%

-A----------------------------+---+-------+-------+--- +--

GROUND 2.94E-04 2.94E-04 2.94E-04 2.94E-04 2.94E-04 2.94E-04 2.94E-04 3.46E-04

.00% .00% 24.60% j .00% j .00% .00% .00% .00%

INHAL 5.98E+00 5.98E+00 J 4.11E-06 J 5.98E+00 5.98E+00 J 5.98E+00 J 5.98E+00 5.98E+00 24.93% 24.93% .34% 24.93% 24.93% 24.93% 24.93% j 24.92%

÷ ÷ +- - + --- - + - -- - - - - - ++-+-

VEGET I1.54E+01 1.54E+01 1.21E-05 1.54E+01 1.54E+01J 1.54E+01 1.54E+01 1.54E+01 64.29% 64.29% 1.01% 64.29% 64.29% 64.29% 64.29% 64.29% I

+----

L---+---+---+ +------

COW MILK 1.86E+00 1.86E+00 3.81E-06 1.86E+00 1.86E+00 1.86E+00 1.86E+00 1.86E+00 7.76% 7.76% .32% 7.76% 7.76% L 7.76% 7.76% 7.76%

+*---+--

  • +* +- -+ -- ------ +

MEAT I 7.25E-01 7.25E-01 1.14E-07 7.25E-01 I 7.25E-01 1,7.25E-01 I 7.25E-01 I 7.25E-01 I 3.02% 3.02% .01% 3.02% t 3.02% 1 3.02% 1 3.02% 1 3.02% 1

  • TOTAL* i 2.40E+01 I 2.40E+01 I 1.20E-03 I 2.40E+01 I 2.40E+01 I 2.40E+01 I 2.40E+01 I 2.40E+01 I

--- - -- +---- -- - +-

-- -- -- +- --- -- -+- --- -- ----- + -- - - -+ - - - - +-

(1) 1 I I I I I I I I PER CAPITAl 1.23E--05 1.23E-05 6.13E-10 1.23E-05 1.23E-05 1.23E-05 1.23E-05 1.23E-05 DOSE (REM)I I I [ I I I I I Note 1:'Personrem total divided by 50-mile population of 1,959,000 90 PVNGS ARERR 2010

Table 45:

Summary of Individual Doses for 2010 Unit Quarter 1 Quarter 2 Quarter 3 Quarter 4 Year total Gamma Air Dose mrad 4.44E-04 3.09E-04 2.34E-04 2.64E-03 3.44E-03 ODCM Req. 4.1 Limit mrad 5.OOE+00 5.OOE+00 5.OOE+00 5.00E+00 1.00E+01

% ODCM Limit  % 8.88E-03 6.18E-03 4.68E-03 5.28E-02 3.44E-02 Beta Air Dose mrad 1.57E-04 1.56E-04 9.05E-05 9.86E-04 1.31E-03 ODCM Req. 4.1 Limit mrad 1.OOE+01 1.00E+01 1.OOE+01 1.00E+01 2.OOE+01

% ODCM Limit  % 1.57E-03 1.56E-03 9.05E-04 9.86E-03 6.55E-03 Maximum Individual Total Body mrem 2.94E-04 2.04E-04 1.56E-04 1.75E-03 2.28E-03 Skin mrem 4.73E-04 3.39E-04 2.52E-04 2.82E-03 3.69E-03 Site Boundary Location Unit 1 miles 1.27 SE 1.40 SSW 1.40 SSW 1.27 SE 1.27 SE Unit2 miles 1.31 SE 1.14SSW 1.14SSW 1.31 SE 1.31 SE Unit3 miles 1.40 SE 1.00SSW 1.00SSW 1.40 SE 1.40 SE Age Infant Infant Infant Infant Infant Maximum Organ Dose Organ Thyroid (2) Bone Bone Bone Bone (excluding skin) - Tyo(2Bn Bn Bone Bone mrem 7.83E-01 3.18E-01 2.39E-01 6.01E-01 1.73E+00 ODCM Req. 4.2 Limit mrem 7.50E+00 7.50E+00 7.50E+00 7.50E+00 1.50E+01

% ODCM Limit(1)  % 1.04E+01 4.24E+00 3.19E+00 8.01E+00 1.15E+01 Location Unit 1 miles 1.88 ESE 1.88 ESE 1.88 ESE 1.88 ESE 1.88 ESE Unit 2 miles 1.95 ESE 1.95 ESE 1.95 ESE 1.95 ESE 1.95 ESE Unit 3 miles 1.96 ESE 1.96 ESE 1.96 ESE 1.96 ESE 1.96 ESE Maximum Organ Dose Age Infant Infant Infant Infant Infant excluding C-14 (3) Organ Thyroid (2) Thyroid (2) Thyroid (2) Thyroid (2) Thyroid (2)

(excluding skin) mrem 6.60E-01 2.32E-01 1.12E-01 2.38E-01 1.24E+00 ODCM Req. 4.2 Limit 7.50E+00 7.50E+00 7.50E+00 7.50E+00 1.50E+01

% ODCM Limit(1) 8.80E+00 3.09E+00 1.49E+00 3.17E+00 8.27E+00 Organ dose from tritium only for Unit 2 location mrem 6.60E-01 2.32E-01 1.12E-01 2.38E-01 1.24E+00 above Fraction of organ dose from tritium only for Unit 2 location  % 84% 73% 46% 39% 71%

above(2,3)

X/Q for Unit 2 location above sec/m3 2.70E-06 1.49E-06 1.12E-06 2.82E-06 2.03E-06 2 1.51 E-09 D/Q for Unit 2 location above m- 1.96E-09 11.42E-09 8.06E-10 11.85E-09 Note 1: ODCM Requirement 5.1 has higher limits than ODCM Requirement 4.2, therefore the percent of limits are more conservative based on ODCM Requirement 4.2 than on ODCM Requirement 5.1.

Note 2: All organs except bone Note 3 Refer to discussion in section 10.4 91 PVNGS ARERR 2010

APPENDIX D NEI 07-07 GROUNDWATER PROTECTION INITIATIVE SAMPLING 92 PVNGS ARERR 2010

Legend Shallow Aquifer Monitoring Well A Palo Verde Clay Aquifer Monitoring Well N Regional Aquifer Monitoring Well

'17 45 Acre Water Storage Reservoir

'.T

Tk'Tý'

PP-12

ý"ý#IAPP-10 .7 PV.R AR

ýIge LanjfTll APP-9 q

0

- 06 ell NObl,`!, Lndt,[I -

Pp-B Iv, APP 18 717 7 "ticIwBasin/

lineci Sedimaut' Xý 11 VS IT5 PV1 A T

PVj iý 'IAPPA 01 PP-1 P _Q8 A

A P r5 PV-34H 0 AZ 't on it. A -1 APP-3

ýq APP Groundwater Monitoring Locations - Water Quality Sampling PVNGS ARERR 2010

Onsite Radiological Groundwater Monitoring Data (from the Aquifer Protection Permit Monitoring Program)

Client ID Collection Date Analyte Result Unit Sampling type APP-10 1/14/10 10:30 Tritium <476 pCi/L Routine APP-10 4/15/10 10:20 Iodine-131 <3.9 pCi/L Routine APP-10 4/15/10 10:20 Cesium-134 <2.4 pCi/L Routine APP-10 .4/15/10 10:20 Cesium-137 <2.0 pCi/L Routine APP-10 4/15/10 10:20 Cobalt-60 <2.1 pCi/L Routine APP-10 4/15/10 10:20 Tritium <459 pCi/L Routine APP-10 7/21/109:49 Tritium <245 pCi/L Routine APP-10 10/14/10 9:12 Tritium <253 pCi/L Routine APP-12 1/14/10 9:15 Tritium <476 pCi/L Routine APP-12 4/16/10 6:48 Cesium-1 37 <3.0 pCi/L Routine APP-12 4/16/10 6:48 Iodine-131 <2.4 pCi/L Routine APP-12 4/16/10 6:48 Cobalt-60 <2.8 pCi/L Routine APP-12 4/16/10 6:48 Cesium-134 <2.2 pci/L Routine APP-12 4/16/10 6:48 Tritium <459 pCi/L Routine APP-12 7/21/10 9:17 Tritium <245 pCi/L Routine APP-12 10/14/10 8:45 Tritium <253 pCi/L Routine APP-13 3/17/10 8:39 Tritium <450 pCi/L Routine APP-13 5/25/10 8:55 Tritium <463 pCi/L Routine APP-13 5/25/10 8:55 Iodine-131 <3.6 pCi/L Routine APP-13 5/25/10 8:55 Cesium-134 <2.3 pCi/L Routine APP-13 .5/25/10 8:55 Cesium-137 <2.2 pCi/L Routine APP-13 5/25/10 8:55 Cobalt-60 <2.3 pCi/L Routine APP-13 ,9/10/10 8:25 Tritium <254 pCi/L Routine APP-13 11/18/10 9:57 Tritium <234 pCi/L Routine APP-13 Dup 11/18/10 13:48 Tritium <234 pCi/L *RoutineQA/QC sampling APP-14 3/17/10 8:53 Tritium <450 pCi/L Routine APP-14 5/25/10 9:10 Iodine-131 <4.2 pCi/L Routine APPR14 5/25/10 9:10 Cesium-134 <2.4 pCi/L Routine APP-14 5/25/10 9:10. Cesium-137 <2.1 pCi/L Routine APP-14 5/25/10 9:10 Cobalt-60 <2.0 pCi/L Routine APP-14 5/25/10 9:10 Tritium <463 pCi/L Routine APP-14 9/10/10 8:40 Tritium <254 pCi/L Routine APP-14 ,11/18/10 10:18 Tritium <234 pCi/L Routine.

APP-14 Dup 11/18/10 10:18 Tritium <234 pCi/L Routine QA/QC sampling APP-15 3/18/10 10:45 Tritium <450 pCi/L Routine APP-15 5/27/10 15:31 Cesium-134 <2.3 pCi/L Routine APP-15 5/27/10 15:31 Tritium <463 pCi/L Routine APP-15 5/27/10 15:31 Cesium-137 <2.2 pCi/L Routine APP-15 5/27/10 15:31 lodine-131 <3.3 pCi/L Routine APP-1i5 5/27/10 15:31 Cobalt-60 <2.2 pCi/L Routine APP-15 9/22/10 8:32 Tritium <251 pCi/L Routine APP-15 11/23/10 9:42 Tritium <237 pCi/L Routine APP-18 1/29/10 8:23 Iodine-131 <3.7 pCi/L Ambient monitoring APP-18 1/29/10 8:23 Tritium <484 pCi/L Ambient monitoring APP-18 *1/29/10 8:23 Cobalt-60 <2.4 pCi/L Ambient monitoring APP-18 1/29/10 8:23 Cesium-134 <2.5 pCi/L Ambient monitoring PVNGS ARERR 2010

Onsite Radiological Groundwater Monitoring Data (from the Aquifer Protection Permit Monitoring Program)

Client ID Collection Date Analyte Result Unit Sampling type APP-18 1/29/10 8:23 Cesium-1 37 <2.4 pCi/L Ambient monitoring APP-18 2/5/10 8:10 Cesium-137 <2.0 pCi/L Ambient monitoring APP-18 2/5/10 8:10 Cesium-134 <2.3 pCi/L Ambient monitoring APP-18 2/5/10 8:10 Cobalt-60 <2.2 pCi/L Ambient monitoring APP-18 2/5/10 8:10 Tritium <474 pCi/L Ambient monitoring APP-18 2/5/10 8:10 Iodine-131 <4.4 pCi/L Ambient monitoring APP-18 3/12/10 8:14' Iodine-131 <3.9 pCi/L Ambient monitoring APP-18 3/12/10 8:14 Cesium-134 <2.4 pCi/L Ambient monitoring APP-18 3/12/10 8:14 Cesium-137 <2.1 pCi/L Ambient monitoring APP-18 3/12/10 8:14 Cobalt-60 <2.1 pCi/L Ambient monitoring APP-18 3/12/10 8:14 Tritium <472 pCi/L Ambient monitoring APP-18 4/14/10 11:05 Cobalt-60 <2.3 pCi/L Ambient monitoring APP-18 4/14/10 11:05 Iodine-131 <4.1 pCi/L Ambient monitoring APP-18 4/14/10 11:05 Cesium-137 <2.0 pCi/L Ambient monitoring APP-18 4/14/10 11:05 Tritium <459 pCi/L Ambient monitoring APP-18 4/14/10 11:05 Cesium-134 <2.2 pCi/L Ambient monitoring APP-18 5/18/10 10:05 Cobalt-60 <2.3 pCi/L Ambient monitoring APP-18 5/18/10 10:05 Tritium <470 pCi/L Ambient monitoring APP-18 5/18/10 10:05 Iodine-131 <4.1 pCi/L Ambient monitoring APP-18 5/18/10 10:05 Cesium-134 <2.2 pCi/L Ambient monitoring APP-18 5/18/10 10:05 Cesium-137 <2.1 pCi/L Ambient monitoring APP-18 6/23/10 9:12 , Cesium-137 <2.1 pCi/L Ambient monitoring APP-18 6/23/10 9:12 Cobalt-60 <2.2 pCi/L Ambient monitoring APP-18 6/23/10 9:12 Cesium-134 <2.1 pCi/L Ambient monitoring APP-18 6/23/10 9:12 Iodine-131 <3.8 pCi/L Ambient monitoring APP-18 6/23/10 9:12 Tritium <248 pCi/L Ambient monitoring APP-18 7/15/10 6:44 Cobalt-60 <2.2 pCi/L Ambient monitoring APP-18 7/15/10 6:44 Iodine-131 <4.3 pCi/L Ambient monitoring APP-18 7/15/10 6:44 Tritium <245 pCi/L Ambient monitoring APP-18 7/15/10 6:44 Cesium-134 <2.4 pCi/L Ambient monitoring APP-18 7/15/10 6:44 Cesium-137 <2.2 pCi/L Ambient monitoring APP-18 8/20/10 6:30 Cesium-134 <2.2 pCi/L Ambient monitoring APP-18 8/20/10 6:30 Cesium-137 <2.1 pCi/L Ambient monitoring APP-18 8/20/10 6:30 Cobalt-60 <2.2 pCi/L Ambient monitoring APR-1 8 8/20/10 6:30 Iodine-131 <3.7 pC'IL Ambient monitoring APP-18 8/20/10 6:30 Tritium <245 pCi/L Ambient monitoring APP-18 9/16/10 9:35 Cobalt-60 <4.3 pCi/L Ambient monitoring APP-18 9/16/10 9:35 Tritium <257 pCi/L Ambient monitoring APP-18 9/16/10 9:35 Iodine-131 <3.7 pCi/L Ambient monitoring APP-18 9/16/10 9:35 Cesium-137 <4.2 pCi/L Ambient monitoring APP-18 9/16/10 9:35 Cesium-1 34 <4.3 pCi/L Ambient monitoring APP-18 10/27/10 9:51 Cesium-134 <3.4 pCi/L Ambient monitoring APP-18 10/27/10 9:51 Tritium <230 pCi/L Ambient monitoring APP-18 10/27/10 9:51 Cobalt-60 <3.2 pCi/L Ambient monitoring APP-18 10/27/10 9:51 Iodine-131 <3.6 pCi/L Ambient monitoring APP-18 10/27/10 9:51 Cesium-137 <3.3 pCi/L Ambient monitoring PVNGS ARERR 2010

Onsite Radiological Groundwater Monitoring Data (from the Aquifer Protection Permit Monitoring Program)

Client ID Collection Date Analyte Result Unit Sampling type APP-18 11/16/10 9:50 Cesium-134 <2.1 pCi/L Ambient monitoring APP-18 11/16/10 9:50 Cesium-137 <3.1 pCi/L Ambient monitoring APP-18 11/16/10 9:50 Cobalt-60 <3.2 pCi/L Ambient monitoring APP-18 11/16/10 9:50 Iodine-131 <4.3 pCi/L Ambient monitoring APP-18 11/16/10 9:50 Tritium <234 pCi/L Ambient monitoring APP-18 12/2/10 10:47 Cobalt-60 <2.6 pCi/L Ambient monitoring APP-18 12/2/10 10:47 Cesium-137 <2.7 pCi/L Ambient monitoring APP-18 12/2/10 10:47 lodine-131 <6.4 pCi/L Ambient monitoring APP-18 12/2/10 10:47 Tritium <227 pCi/L Ambient monitoring APP-18 12/2/10 10:47 Cesium-134 <3.1 pCi/L Ambient monitoring APP-3 1/27/10 10:21 Tritium <484 pCi/L Routine APP-3 4/23/10 8:10 Iodine-131 <4.1 pCi/L Routine APP-3 4/23/10 8:10 Cesium-134 <2.1 pCi/L Routine APP-3 4/23/10 8:10 Tritium <466 pCi/L Routine APP-3 4/23/10 8:10 Cobalt-60 <2.1. pCi/L Routine APP-3 4/23/10 8:10 Cesium-137 <1.9 pCi/L Routine APP-3 8/11/10 9:28 Tritium <245 pCi/L Routine APP-3 11/10/10 8:55 Tritium <229 pCi/L Routine APP-3 Dup 4/23/10 8:10 Cesium-137 <2.0 pCi/L Routine QA/QC sampling APP-3 Dup 4/23/10 8:10 Iodine-131 <4.5 pCi/L Routine QA/QC sampling APP-3 Dup 4/23/10 8:10 Cesium-134 <2.1 pCi/L Routine QA/QC sampling APP-3 Dup 4/23/10 8:10 Cobalt-60 <2.1 pCi/L Routine QA/QC sampling APP-3 Dup 4/23/10 8:10 Tritium . <466 .pCi/L Routine QA/QC sampling APP-4R 1/27/10 11:10 Tritium <484 pCi/L Routine APP-4R 4/23/10 8:25 Tritium <466 pCi/L Routine APP-4R 4/23/10 8:25 Cobalt-60 <2.3 pCi/L Routine APP-4R 4/23/10 8:25 Cesium-137 <2.1 pCi/L Routine APP-4R 4/23/10 8:25 Cesium-1 34 <2.3 pCi/L Routine APP-4R 4/23/10 8:25 Iodine-131 <3.4 pCi/L Routine APP-4R 8/12/10 8:41 Tritium <245 pCi/L Routine APP-4R 11/16/10 10:22 Tritium <234 pCi/L Routine APP-4R Dup 4/23/10 8:25 Iodine-131 <3.5 pCi/L Routine QAIQC sampling APP-4R Dup 4/23/10 8:25 Tritium <466 pCi/L Routine QA/QC sampling APP-4R Dup 4/23/10 8:25 Cesium-137 <2.1 pCi/L Routine QA/QC sampling APP-4R Dup 4/23/10 8:25 Cesium-134 <2.4. pCi/L Routine QA/QC sampling APP-4R Dup 4/23/10 8:25 Cobalt-60 <2.2 pCi/L Routine QA/QC sampling APP-5 2/16/10 9:37 Tritium <475 pCi/L Routine APP-5 4/30/10 10:31 Iodine-131 <4.7 pCi/L Routine APP-5 4/30/10 10:31 Tritium <470 pCi/L Routine APP-5 4/30/10 10:31 Cobalt-60 <2.4 pCi/L Routine APP-5 4/30/10 10:31 Cesium-137 <2.2 pCi/L Routine APP-5 4/30/10 10:31 Cesium-134 <2.3 pCi/L, Routine APP-5 8/25/10 9:05 Tritium <266 pCi/L Routine APP-5 11/17/10 9:51 Tritium <234 pCi/L Routine.

APP-5-DUP 8/25/10 9:05 Tritium <266 pCi/L Routine QA/QC sampling APP-6 2/24/10 8:51 Tritium <468 pCi/L Routine PVNGS ARERR 2010

Onsite Radiological Groundwater Monitoring Data (from the Aquifer Protection Permit Monitoring Program)

Client IDi Collection DaIte Analyte" Result Unit Sapnling* type APP-6 5/21/10 7:51 Iodine-131 <3.3 pCi/L Routine APP-6 5/21/10 7:51 Cesium-134 <2.2 pCi/L Routine APP-6 5/21/10 7:51 Cesium-137 <2.2 pCi/L Routine APP-6 5/21/10 7:51 Cobalt-60 <2.1 pCi/L Routine APP-6 5/21/10 7:51 Tritium <470 pCi/L Routine APP-6 8/26/10 8:52 Tritium <266 pCi/L Routine APP-6 11/23/10 8:35 Tritium <237 pCi/L Routine APP-6-DUP 8/26/10 8:52 Tritium <266 pCi/L Routine QA/QC sampling APP-7 3/25/10 9:22 Tritium <468 pCi/L Routine APP-7 6/17/10 7:42 Iodine-131 <3.0 pCi/L Routine APP-7 6/17/10 7:42 Cesium-134 <2.4 pCi/L Routine APP-7 6/17/10 7:42 Tritium <460 pCi/L Routine APP-7 6/17/10 7:42 Cesium-137 <2.2 pCi/L Routine APP-7 6/17/10 7:42 Cobalt-60 <2.2 pCi/L Routine APP-7 9/29/10 8:50 Tritium <257 pCi/L Routine APP-7 12/1/10 9:16 Tritium <227 pCi/L Routine APP-8 1/20/10 12:35 Tritium <477 pCi/L Routine APP-8 4/20/10 10:18 Cesium-134 <2.2 pCi/L Routine APP-8 4/20/10 10:18 Iodine-131 <3.7 pCi/L Routine APP-8 4/20/10 10:18 Cesium-137 <2.1 pCi/L Routine APP-8 4/20/10 10:18 Cobalt-60 <2.3 pCi/L Routine APP-8 4/20/10 10:18 Tritium <466 pCi/L Routine APP-8 7/26/10 8:19 Tritium <244 pCi/L Routine APP-8 10/14/10 10:48 Tritium- <253 pCi/L Routine APP-8 Dupe 1/20/10 12:35 Tritium <477 pCi/L Routine QA/QC sampling APP-9 1/14/10 10:00 Tritium <476 pCi/L Routine APP-9 4/15/10 10:38 Cesium-137 <2.1 pCi/L Routine APP-9 4/15/10 10:38 Iodine-131 <3.6 pCi/L Routine APP-9 4/15/10 10:38 Tritium <459 pCi/L Routine APP-9 4/15/10 10:38 Cesium-134 <2.1 pCi/L Routine APP-9 4/15/10 10:38 Cobalt-60 <2.3 pCi/L Routine APP-9 7/21/10 10:17 Tritium <245 pCi/L Routine APP-9 10/14/10 9:38 Tritium <253 pCi/L Routine PV-14H 2/23/10 10:25 Tritium <468 pCi/L Routine PV-14H 5/21/10 8:37 Tritium, <470 pCi/L Routine PV-14H 5/21/10 8:37 Cobalt-60 <2.2. pCi/L Routine PV-14H 5/21/10 8:37 Iodine-131 <3.0 pCi/L Routine PV-14H 5/21/10 8:37 Cesium-134 <2.3 pCi/L Routine PV-14H 5/21/10 8:37 Cesium-137 <2.1 pCi/L Routine PV-14H 8/26/10 9:29 Tritium <266 pCi/L Routine PV-14H 11/23/10 9:30 Tritium <237 pCi/L Routine PV-14H Dup 11/23/10 9:30 Tritium <237 pCi/L Routine QA/QC sampling PV-173R 1/26/10 13:24 Tritium <484 pCi/L Ambient monitoring PV-173R 1/26/10 13:24 Cesium-137 <2.0 pCi/L Ambient monitoring PV-173R 1/26/10 13:24 Cobalt-60 <2.2 IpCi/L Ambient monitoring PV-173R 1/26/10 13:24 Iodine-131 <3.5 pCi/L Ambient monitoring PVNGS ARERR 2010

Onsite Radiological Groundwater Monitoring Data (from the Aquifer Protection Permit Monitoring Program)

ClientID Collection Date Analyte Result Unit Sampling type PV-173R 1/26/10 13:24 Cesium-134 <2.3 pCi/L Ambient monitoring PV-173R 2/4/10 14:20 Tritium <474 pCi/L Ambient monitoring PV-173R 2/4/10 14:20 Cobalt-60 <2.3 pCi/L Ambient monitoring PV-173R 2/4/10 14:20 Cesium-137 <2.1 pCi/L Ambient monitoring PV-173R 2/4/10 14:20 Iodine-131 <3.8 pCi/L Ambient monitoring PV-173R 2/4/10 14:20 Cesium-134 <2.2 pCi/L Ambient monitoring PV-173R 3/9/10 13:52 Cobalt-60 <2.1 pCi/L Ambient monitoring PV-173R 3/9/10 13:52 lodine-131 <3.4 pCi/L Ambient monitoring PV-173R 3/9/10 13:52 Cesium-134 <2.2 pCi/L Ambient monitoring PV-173R 3/9/10 13:52 Cesium-137 <2.4 pCi/L Ambient monitoring PV-173R 3/9/10 13:52 Tritium <472 pCi/L Ambient monitoring PV-173R 4/14/10 12:25 Iodine-131 <4.0 pCi/L Ambient monitoring PV-173R 4/14/10 12:25 Cesium-134 <2.1 pCi/L Ambient monitoring PV-173R 4/14/10 12:25 Cesium-137 <2.1 pCi/L Ambient monitoring PV-173R 4/14/10 12:25 Cobalt-60 <2.1 pCi/L Ambient monitoring PV-173R 4/14/10 12:25 Tritium <459 pCi/L Ambient monitoring PV-173R 5/18/10 13:48 lodine-131 <3.2 pCi/L Ambient monitoring PV-173R 5/18/10 13:48 Tritium - <470 pCi/L Ambient monitoring PV-173R 5/18/10 13:48 Cobalt-60 <2.4 pCi/L Ambient monitoring PV-173R 5/18/10 13:48 Cesium-134 <2.3 pCi/L Ambient monitoring PV-173R 5/18/10 13:48 Cesium-1 37 <2.2 pCi/L Ambient monitoring PV-173R 6/24/10 10:44 Tritium <248 pCi/L Ambient~monitoring PV-173R 6/24/10 10:44 Cobalt-60 <2.4 pCi/L Ambient monitoring PV-173R 6/24/10 10:44 Cesium-137 <2.2 pCi/L Ambient monitoring PV-173R 6/24/10 10:44 Cesium-134 <2.3 pCi/L Ambient monitoring PV-173R 6/24/10 10:44 Iodine-131 <3.1 pCi/L Ambient monitoring PV-173R 7/14/10 8:06 Iodine-131 <3.9 pCi/L Ambient monitoring PV-173R 7/14/10 8:06 Tritium <245 pCi/L Ambient monitoring PV-173R 7/14/10 8:06 Cobalt-60 <2.2 pCi/L Ambient monitoring PV-173R 7/14/10 8:06 Cesium-137 <2.2 pCi/L Ambient monitoring PV-173R 7/14/10 8:06 Cesium-134 <2.2 pCi/L Ambient monitoring PV-173R 8/19/10 12:12 Cesium-137 <1.9 pCi/L Ambient monitoring PV-173R 8/19/10 12:12 Cesium-134 <2.1 pCi/L Ambient monitoring PV-173R 8/19/10 12:12 Tritium <245 pCi/L Ambient monitoring PV-173R 8/19/10 12:12 Iodine-131 <3.7 pCi/L Ambient monitoring PV-173R 8/19/10 12:12 Cobalt-60 <2.1 pCi/L Ambient monitoring PV-173R 9/15/10 6:54 Cobalt-60 <4.1 pCi/L Ambient monitoring PV-173R 9/15/10 6:54 Cesium-1 37 <4.1 pCi/L Ambient monitoring PV-173R 9/15/10 6:54 Iodine-131 <3.1 pCi/L Ambient monitoring PV-173R 9/15/10 6:54 Tritium <251 pCi/L Ambient monitoring PV-173R 9/15/10 6:54 Cesium-134 <4.1 pCi/L Ambient monitoring PV-173R 10/26/10 14:00 Cobalt-60 <2.7 pCi/L Ambient monitoring PV-173R 10/26/10 14:00 lodine-131 <3.4 pCi/L Ambient monitoring PV-173R 10/26/10 14:00 Cesium-137 <2.8 pCi/L Ambient monitoring PV-173R 10/26/10 14:00 Cesium-134 <3.1 pCi/L Ambient monitoring PV-173R 10/26/10 14:00 Tritium <230 pCi/L Ambient monitoring PVNGS ARERR 2010

Onsite Radiological Groundwater Monitoring Data (from the Aquifer Protection Permit Monitoring Program)

Client ID Collection Date Analyte Result, Unit ,Sampling, type, PV-173R 11/10/10 14:30 Cesium-134 <3.1 pCi/L Ambient monitoring PV-173R 11/10/10 14:30 Tritium <230 pCi/L Ambient monitoring PV-173R 11/10/10 14:30 Cesium-137 <2.7 pCi/L Ambient monitoring PV-173R 11/10/10 14:30 lodine-131 <3.9 pCi/L Ambient monitoring PV-173R 11/10/10 14:30 Cobalt-60 <2.8 pCi/L Ambient monitoring PV-173R 12/2/10 10:01 Cesium-134 <2.8 pCi/L Ambient monitoring PV-173R 12/2/10 10:01 Cesium-137 <2.5 pCi/L Ambient monitoring PV-173R 12/2/10 10:01 Cobalt-60 <2.5 pCi/L Ambient monitoring PV-173R 12/2/10 10:01 lodine-131 <6.1 pCi/L Ambient monitoring PV-173R 12/2/10 10:01 Tritium <227 pCi/L Ambient monitoring PV-193A 2/12/10 8:27 Tritium <471 pCi/L Routine PV-193A 4/23/10 8:55 Tritium <466 pCi/L Routine PV-193A 4/23/10 8:55 Iodine-131 <3.5 pCi/L Routine PV-193A 4/23/10 8:55 Cesium-134 <2.3 pCi/L Routine PV-193A 4/23/10 8:55 Cesium-137 <2.1 pCi/L Routine PV-193A 4/23/10 8:55 Cobalt-60 <2.3 pCi/L Routine PV-193A 8/18/10 10:02 Tritium <224 pCi/L Routine PV-193A 11/16/10 10:55 Tritium <234 pCi/L Routine PV-193A Dup 4/23/10 8:55 Tritium <466 pCi/L Routine QA/QC sampling PV-193A Dup ,4/23/10 8:55 Cesium-1 34 <2.2 pCi/L Routine QA/QC sampling PV-193A Dup 4/23/10 8:55 Cesium-137 <2.1 pCi/L Routine QA/QC sampling PV-193A Dup 4/23/10 8:55 Cobalt-60 <2.1 pCi/L Routine QAIQC sampling PV-193A Dup 4/23/10 8:55 Iodine-131 <3.7 pCi/L Routine QA/QC sampling PV-195A 3/18/10 13:15 Tritium <450 pCi/L Routine PV-195A 5/28/10 8:47 Iodine-131 <3.1 pCi/L Routine PV-195A 5/28/10 8:47 Cesium-134 <2.4 pCi/L Routine PV-195A 5/28/10 8:47 Cesium-137 <2.0 pCi/L Routine PV-195A 5/28/10 8:47 Cobalt-60 <2.1 pCi/L Routine PV-195A 5/28/10 8:47 Tritium <463 pCi/L Routine PV-195A 9/22/10 9:10 Tritium <251 pCi/L Routine PV-195A 11/23/10 10:28 Tritium <237 pCi/L Routine PV-198AR 1/6/10 10:26 Tritium <478 pCi/L Routine PV-198AR 2/4/10 13:18 Tritium <474 pCi/L Routine PV-198AR 3/11/10 10:36 Tritium <472 pCi/L Routine PV-198AR 4/13/10 9:56 Tritium <459 pCi/L Routine PV-198AR 4/13/10 9:56 Iodine-131 <4.1 pCi/L Routine PV-198AR 4/13/10 9:56 Cesium-134 <2.2 pCi/L Routine PV-198AR 4/13/10 9:56 Cesium-1 37 <2.2 pCi/L Routine PV-198AR 4/13/10 9:56 Cobalt-60 <2.0 pCi/L Routine PV-198AR 5/3/10 8:18 Tritium <470 pCi/L Routine PV-198AR 6/10/10 7:23 Tritium <460 pCi/L Routine PV-198AR 7/13/10 9:00 Tritium, <245 pCi/L Routine PV-198AR 8/17/10 9:08 Tritium <245 pCi/L Routine PV-198AR 9/14/10 9:30 Tritium <251 pCi/L Routine PV-198AR 10/21/10 9:43 Tritium <251 pCi/L Routine PV-198AR 11/10/10 9:41 Tritium <229 pCi/L Routine PVNGS ARERR 2010

Onsite Radiological Groundwater Monitoring Data (from the Aquifer Protection Permit Monitoring Program)

Client ID Collection Date Analyte Result Unit Sampling type PV-198AR 12/1/10 10:42 Tritium <232 pCi/L Routine PV-198AR-DUP 1/6/10 10:26 Tritium <478 pCi/L Routine QA/QC sampling PV-206A 1/27/10 9:22 Tritium <484 pCi/L Routine PV-206A 4/21/10 8:50 Tritium <466 pCi/L Routine PV-206A 4/21/10 8:50 Cobalt-60 <2.2 pCi/L Routine PV-206A 4/21/10 8:50 Cesium-137 <2.2 pCi/L Routine PV-206A 4/21/10 8:50 Cesium-134 <2.1 pCi/L Routine PV-206A 4/21/10 8:50 Iodine-131 <3.1 pCi/L Routine PV-206A 7/29/10 6:45 Tritium <244 pCi/L Routine PV-206A 10/15/10 8:21 Tritium <253 pCi/L Routine PV-206A-Dupe 1/27/10 9:22. Tritium <484 pCi/L Routine QA/QC sampling PV-34H 2/16/10 9:50 Tritium <475 pCi/L Routine PV-34H 4/30/10 11:02 Cobalt-60 <2.3 pCi/L Routine PV-34H 4/30/10 11:02 Iodine-131 <4.4 pCi/L Routine PV-34H 4/30/10 11:02 Cesium-134 <2.3 pCi/L Routine PV-34H 4/30/10 11:02 Cesium-137 <2.2 pCi/L Routine PV-34H 4/30/10 11:02 Tritium <470 pCi/L Routine PV-34H 8/25/10 9:15 Tritium <266 pCi/L Routine PV-34H 11/18/10 9:23 Tritium <234 pCi/L Routine PV-34H DUP 8/25/10 9:15 Tritium <266 pCi/L Routine QA/QC sampling PV-Q8 1/7/10 10:02 Tritium <478 pCi/L Routine PV-Q8 2/5/10 7:45 Tritium <474 pCi/L Routine PV-Q8 4/13110 9:10 Cobalt-60 <2.4 pCi/L Routine PV-Q8 4/13/10 9:10 Tritium <459 pCi/L Routine PV-Q8 4/13/10 9:10 Cesium-137 <2.0 pCi/L Routine PV-Q8 4/13/10 9:10 Cesium-134 <2.2 pCi/L Routine PV-Q8 4/13/10 9:10 lodine-131 <3.9 pCi/L Routine PV-Q8 7/29/10 8:48 Tritium <244 pCi/L Routine PV-Q8 10/27/10 9:15 Tritium <230 pCi/L Routine PV-R2AR 3/25/10 8:53 Tritium <468 pCi/L Routine PV-R2AR 6/17/10 7:11 Cobalt-60 <2.3 pCi/L Routine PV-R2AR 6/17/10 7:11 Cesium-137 <2.1 pCi/L Routine PV-R2AR 6/17/10 7:11 Cesium-134 <2.2 pCi/L Routine PV-R2AR 6/17/10 7:11 Iodine-131 <3.0 pCi/L Routine PV-R2AR 6/17/10 7:11 Tritium <460 pCi/L Routine PV-R2AR 9/29/10 8:10 Tritium <257 pCi/L Routine PV-R2AR 12/1/10 8:55 Tritium <227 pCi/L IRoutine PVNGS ARERR 2010

APPENDIX E OFFSITE DOSE CALCULATION MANUAL Revision 25 101 PVNGS ARERR 2010

OFFSITE DOSE CALCULATION MANUAL PALO VERDE NUCLEAR GENERATING STATION UNITS 1, 2 AND 3 REVISION 25 DS signed 3Digitally by Drino. sky, Louis uflnovsky, Loui (Z33699)

DN: cn=Ddnovsky, Louis J(Z33699)

J(Z33699) Reason: I am the author of this document Date: 2010.06.15 08:07:48 -0700' Originator Digitally signed by Kutner, Kevin W(Z5800t)

Kutner, Kevin W DN: cn=Kutner, Kevin W(Z58001)

Reason: I have performed an independent (Z58001) review of this document Date: 2010.06.15 08:16:18 -0700' Technical Reviewer Gaffney, John P Digitally signed by Gaffney, John P(Z36459)

ON: cn=Gaffney, John P(Z36459)

Director, Radiation Reason: f am approving this document (Z36459) Date: 2010,06.22 15:01:43 -07'00' Protection Digitally signed by W. Grover Hettel ON: cn=W. Grover Hettel, c=US, o=Operations, W . G rover Hettel ou=8220, e.ail=gro.er.hettel@ap...om Reason: Iam approving this documen2 PRB Date: 201 0.07.20 14:51:25 -07'00' Effective Date: August 27, 2010

TABLE OF CONTENTS TITLE PAGE

1.0 INTRODUCTION

1 1.1 Liquid Effluent Pathways 1 1.2 Gaseous Effluent Pathways 2 1.3 Nuisance Pathways 2 1.4 Meteorology 4 2.0 GASEOUS EFFLUENT MONITOR SETPOINTS 5

2.1 Requirements

Gaseous Monitors 5 2.1.1 Surveillance Requirements 5 2.1.2 Implementation of the Requirements 12 2.1.2.1 Equivalent Dose Factor Determination 13 2.1.2.2 Site Release Rate Limit (QSITE) 14 2.1.2.3 Unit Release Rate Limits (QUNIT) 15 2.1.2.4 Setpoint Determination 15 2.1.2.5 Monitor Calibration 16 3.0 GASEOUS AND LIQUID EFFLUENT DOSE RATES 17

3.1 Requirements

Gaseous Effluents 17 3.1.1 Surveillance Requirements 17 3.1.2 Implementation of the Requirements 18

3.2 Requirements

Secondary System Liquid Waste Discharges To Onsite Evaporation Ponds or Circulating Water System - Concentration 26 3.2.1 Surveillance Requirements 26 3.2.2 Implementation of the Requirements 26 4.0 GASEOUS & LIQUID EFFLUENTS - DOSE 31

4.1 Requirements

Noble Gases 31 4.1.1 Surveillance Requirements 31 4.1.2 Implementation of the Requirement: Noble Gas 32

4.2 Requirement

Iodine-131, Iodine-133, Tritium, and All Radionuclides in Particulate Form With Half-Lives Greater Than 8 Days 33 4.2.1 Surveillance Requirements 33 4.2.2 Implementation of the Requirement 34

4.3 Requirements

Gaseous Radwaste Treatment 36 4.3.1 Surveillance Requirements 36 4.3.2 Implementation of the Requirement 37

4.4 Requirements

Liquid Effluents 57 4.4.1 Surveillance Requirements 57 4.4.2 Implementation of the Requirements 57 i ODCM Rev, 25

TABLE OF CONTENTS TITLE PAGE 5.0 TOTAL DOSE AND DOSE TO PUBLIC ONSITE 58

5.1 Requirement

Total Dose 58 5.1.1 Surveillance Requirements 58 5.1.2 Implementation of the Requirement 58 6.0 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM (REMP) 62

6.1 Requirement

REMP 62 6.1.1 Surveillance Requirements 63 6.1.2 Implementation of the Requirements 63

6.2 Requirement

Land Use Census 71 6.2.1 Surveillance Requirements 71 6.2.2 Implementation of the Requirements 71

6.3 Requirement

Interlaboratory Comparison Program 72 6.3.1 Surveillance Requirements 72 6.3.2 Implementation of the Requirements 72 7.0 RADIOLOGICAL REPORTS 83

7.1 Requirement

Annual Radioactive Effluent Release Report 83

7.2 Requirement

Annual Radiological Environmental Operating Report 85 APPENDIX A DETERMINATION OF CONTROLLING LOCATION 86 APPENDIX B BASES FOR REQUIREMENTS 87 2.1 RADIOACTIVE GASEOUS EFFLUENT MONITORING INSTRUMENTATION 87 3.1 GASEOUS EFFLUENT - DOSE RATE 87 3.2 SECONDARY SYSTEM LIQUID WASTE DISCHARGE TO ONSITE EVAPORATION PONDS - CONCENTRATION 88 4.1 GASEOUS EFFLUENT - DOSE, Noble Gases 88 4.2 GASEOUS EFFLUENT - DOSE - Iodine-131, Iodine-133, Tritium, and All Radionuclides in Particulate Form With Half-Lives Greater Than 8 Days89 4.3 GASEOUS RADWASTE TREATMENT 89 4.4 SECONDARY SYSTEM LIQUID WASTE DISCHARGE TO ONSITE EVAPORATION PONDS - DOSE 90 5.1 TOTAL DOSE AND DOSE TO PUBLIC ONSITE 90 6.1 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM (REMP) 91 6.2 LAND USE CENSUS 91 6.3 INTERLABORATORY COMPARISON PROGRAM 91 APPENDIX C DEFINITIONS 92 APPENDIX D REFERENCES 96 ii ODCM Rev. 25

LIST OF TABLES TABLE TITLE PAGE 1-1 NUISANCE PATHWAYS 3 2-1 RADIOACTIVE GASEOUS EFFLUENT MONITORING INSTRUMENTATION 6 2-2 RADIOACTIVE GASEOUS EFFLUENT MONITORING INSTRUMENTATION SURVEILLANCE REQUIREMENTS 10 3-I RADIOACTIVE GASEOUS WASTE SAMPLING AND ANALYSIS PROGRAM 20 3-2 DISPERSION AND DEPOSITION PARAMETERS FOR LONG TERM RELEASES AT THE SITE BOUNDARY 23 3-3 DOSE FACTORS FOR NOBLE GASES AND DAUGHTERS 24 3-4 Pi VALUES FOR THE INHALATION PATHWAY 25 3-5 RADIOACTIVE LIQUID WASTE SAMPLING AND ANALYSIS PROGRAM 27 3-6 RADIOACTIVE LIQUID EFFLUENT MONITORING INSTRUMENTATION 30 3-7 RADIOACTIVE LIQUID EFFLUENT MONITORING INSTRUMENTATION SURVEILLANCE REQUIREMENTS. 30 4-1 Ri DOSE CONVERSION FACTORS FOR THE GROUND PLANE PATHWAY 39 4-2 Ri DOSE CONVERSION FACTORS FOR THE VEGETATION PATHWAY - ADULT RECEPTOR 40 4-3 Ri DOSE CONVERSION FACTORS FOR THE VEGETATION PATHWAY - TEEN RECEPTOR 41 4-4 Ri DOSE CONVERSION FACTORS FOR THE VEGETATION PATHWAY - CHILD RECEPTOR 42 4-5 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MEAT PATHWAY - ADULT RECEPTOR 43 4-6 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MEAT PATHWAY - TEEN RECEPTOR 44 4-7 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MEAT PATHWAY - CHILD RECEPTOR 45 4-8 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MILK PATHWAY - ADULT RECEPTOR 46 4-9 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MILK PATHWAY - TEEN RECEPTOR 47 4-10 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MILK PATHWAY - CHILD RECEPTOR 48 iii ODCM Rev. 25

LIST OF TABLES TABLE TITLE PAGE 4-11 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MILK PATHWAY - INFANT RECEPTOR 49 4-12 Ri DOSE CONVERSION FACTORS FOR THE INHALATION PATHWAY - ADULT RECEPTOR 50 4-13 Ri DOSECONVERSION FACTORS FOR THE INHALATION PATHWAY - TEEN RECEPTOR 51 4-14 Ri DOSE CONVERSION FACTORS FOR THE INHALATION PATHWAY - CHILD RECEPTOR 52 4-15 Ri DOSE CONVERSION FACTORS FOR THE INHALATION PATHWAY - INFANT RECEPTOR 53 4-16 PALO VERDE NUCLEAR GENERATING STATION DISPERSION AND DEPOSITION PARAMETERS FOR LONG TERM RELEASES AT THE NEAREST PATHWAY LOCATIONS CENTERED ON UNIT 1 54 4-17 PALO VERDE NUCLEAR GENERATING STATION DISPERSION AND DEPOSITION PARAMETERS FOR LONG TERM RELEASES AT THE NEAREST PATHWAY LOCATIONS CENTERED ON UNIT 2 55 4-18 PALO VERDE NUCLEAR GENERATING STATION DISPERSION AND DEPOSITION PARAMETERS FOR LONG TERM RELEASES AT THE NEAREST PATHWAY LOCATIONS CENTERED ON UNIT 3 56 6-1 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM 64 6-2 REPORTING LEVELS FOR RADIOACTIVITY CONCENTRATIONS IN ENVIRONMENTAL SAMPLES 68 6-3 DETECTION CAPABILITIES FOR ENVIRONMENTAL ANALYSIS 69 6-4 RADIOLOGICAL ENVIRONMENTAL MONITORING SAMPLE COLLECTION LOCATIONS 73 C-1 FREQUENCY NOTATION 95 iv ODCM Rev. 25

LIST OF FIGURES FIGURE TITLE PAGE 6-1 Radiological Environmental Monitoring Program Sample Sites 0 - 10 Miles 77 6-2 Radiological Environmental Monitoring Program Sample Sites 10 - 35 Miles 78 6-3 Radiological Environmental Monitoring Program Sample Sites 35 - 75 Miles DELETED 79 6-4 Site Exclusion Area Boundary DELETED 80 6-5 Gaseous Effluent Release Points 81 6-6 Low Population Zone DELETED 82 V ODCM Rev. 25

1.0 INTRODUCTION

The Offsite Dose Calculation Manual (ODCM) implements the program elements which are required by the Administrative Controls section of the Technical Specifications. The ODCM contains the operational requirements, the surveillance requirements, and actions required if the operational requirements are not met for the Radioactive Effluent Controls Program and the Radiological Environmental Monitoring Program to assure compliance with 10 CFR 20.1302, 40 CFR Part 190, 10 CFR 50.36a, and Appendix I to 10 CFR Part 50. The Technical Specifications, Section 3.0, also apply to the ODCM. Substitute the word "Requirements" for "Limiting Condition for Operation." It should be noted that the hot and cold shutdown and operability requirements in Technical Specification 3.0.3 and 3.0.4 do not apply to any of the requirements contained in this ODCM. The ODCM also contains descriptions of the information that should be included in the Annual Radiological Environmental Operating Report and the Annual Radioactive Effluent Release Report required by the Technical Specifications.

The ODCM provides the parameters and methodology to be used in calculating offsite doses resulting from radioactive effluents, in the calculation of gaseous effluent monitor Alarm/Trip Setpoints, and in the conduct of the Radiological Environmental Monitoring Program. Included are methods for determining air, whole body, and organ dose at the controlling location due to plant effluents to assure compliance with the regulatory requirements detailed in the ODCM. Methods are included for performing dose projections to assure compliance with the gaseous treatment system operability sections of the ODCM. The ODCM utilizes information from NRC Regulatory Guide 1.109, "Calculation of Annual Doses to Man from Routine Releases of Reactor Effluents for the Purpose of Evaluating Compliance with 10 CFR Part 50, Appendix I," October 1977, and NRC NUREG 0133, "Preparation of Radiological Effluent Technical Specifications for Nuclear Power Plants,"

October 1978. NUREG 0133 utilizes some of the key information in Regulatory Guide 1.109 to provide methods which were used in the preparation of *the radiological effluent Technical Specifications and which have now been transferred to the ODCM in accordance with NRC Generic Letter 89-01, "Implementation of Programmatic Controls for Radiological Effluent Technical Specifications in the Administrative Controls Section of the Technical Specifications and the Relocation of Procedural Details of RETS to the Offsite Dose Calculation Manual or to the Process Control Program," January 31, 1989, and NUREG 1301, "Offsite Dose Calculation Manual Guidance:

Standard Radiological Effluent Controls for Pressurized Water Reactors," Generic Letter 89-01, Supplement No. 1, April 1991. Further guidance for the implementation of the new 10 CFR Part 20, effective January 1, 1994, was obtained from the Federal Register, Vol. 58, December 23, 1993. It is recognized that this is only draft guidance, however, it is the only guidance for referencing the new 10 CFR 20 in the ODCM.

1.1 Liquid Effluent Pathways Dose calculation methodology for radioactive liquid effluents is not included in this manual due to the desert location of the plant, the hydrology of the area, and the fact that there are no liquid releases to areas at or beyond the SITE BOUNDARY during normal operation. All liquid discharges to the onsite evaporation ponds are controlled by Section 3.2. The impact of postulated accidental seepages on the groundwater system, and in particular on the existing wells located in the 5-mile zone around the site area has been calculated and analyzed in Section 2.4.13.3 of the PVNGS FSAR.

If plant operating conditions become such that the likelihood of a liquid effluent pathway is created, then dose calculation methodology for this pathway will be added to this manual.

I ODCM Rev. 25

1.2 Gaseous Effluent Pathways All gaseous effluents are treated as ground level releases and are considered to be "long-term" as discussed in NUREG-0133, "Preparation of Radiological Effluent Technical Specifications for Nuclear Power Plants." This includes the containment purge and Waste Gas Decay Tank releases as well as the normal ventilation system and condenser vacuum exhaust releases. All releases are either greater than 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> in duration or are made at random, not depending upon atmospheric conditions or time of day. The releases are lumped together and calculated as an entity. Historical annual average X/Q values are used throughout this manual for all gaseous effluent setpoint and dose calculations. Airborne releases are further subdivided into two subclasses:

1.2.1 Iodine-131, Iodine-133, Tritium and Radionuclides in Particulate Form with Half-lives Greater than Eight Days In this model, a controlling location is identified for assessing the maximum exposure to a MEMBER OF THE PUBLIC for the various pathways and to critical organs. Infant exposure occurs through inhalation and any actual milk pathway. Child, teenager and adult exposure derives from inhalation, consumed vegetation pathways, and any actual milk and meat pathways. Dose to each of the seven organs listed in Regulatory Guide 1.109 (bone, liver, total body, thyroid, kidney, lung and GI-LLI) are computed from individual nuclide contributions in each sector. The largest of the organ doses in any sector is compared to 10 CFR 50, Appendix I design objectives. The release rates of these nuclides will be converted to instantaneous dose rates for comparison to the limits of 10 CFR 20.

1.2.2 Noble Gases The air dose from both the beta and gamma radiation component of the noble gases will be assessed and compared to the 10 CFR 50, Appendix I design objectives. The noble gas release rate will be converted to instantaneous dose rates for comparison to the limits of 10 CFR 20.

Section 2.0 of this manual 'discusses the methodology to be used in determining effluent monitor alarm/trip setpoints to assure compliance with the 10 CFR Part 20 limits as implemented in Section 3.0. Section 4.0 discusses the methods to assure releases are As Low As Reasonably Achievable (ALARA) in accordance with Appendix I to 10 CFR Part 50.

Methods are described in Section 5.0 for determining the annual cumulative dose to a MEMBER OF THE PUBLIC from gaseous effluents and direct radiation to assure compliance with 40 CFR Part 190.

The requirements for the Annual Radiological Effluent Release Report and the Radiological Environmental Monitoring Program, including the Annual Land Use Census and the Interlaboratory Comparison Program, and the Annual Environmental Report are described in Sections 6.0 and 7.0 of this manual.

1.3 Nuisance Pathways This section addresses the potential release pathways which should not contribute more than 10% of the doses evaluated in this manual. Table 1-1 lists examples of potential release pathways. The ODCM methodology for calculation of doses will be applied to an applicable release pathway if a likely potential arises for contributing more than 10% of the doses evaluated in this manual.

2 ODCM Rev. 25

TABLE 1-1 NUISANCE PATHWAYS (EXAMPLES)

Evaporation Pond Cooling Towers Laundry/Decon Building Exhaust Unmonitored Secondary System Steam Vents/Reliefs Turbine Building Ventilation Exhaust Unmonitored Tank Atmospheric Vents Dry Active Waste Processing and Storage (DAWPS) Building Respirator Cleaning Facility Secondary Side Decontamination Equipment Low Level Radioactive Material Storage Facility 3 ODCM Rev. 25

1.4 Meteorology Historical annual average atmospheric dispersion (X/Q) and deposition (D/Q) data, based on nine years of meteorological data, and given in Table 3-2 for each of the three nuclear generating units are used to demonstrate compliance with the ODCM Requirements. These Requirements include:

Section 2.0 Gaseous Effluent Monitor Setpoints; Section 3.0 Gaseous and Liquid Effluent - Dose Rate Section 4.0 Gaseous and Liquid Effluent - Dose Section 5.0 Total Dose and Dose to Public Onsite Sections 2.0 and 3.0 specify utilizing the highest X/Q or D/Q meteorological dispersion parameter at the Site Boundary for any of the three units as applicable. Using the highest dispersion parameter for any of the units provides a conservative assumption to assure compliance with the higher 10 CFR Part 20 limits.

Section 4.0 specifies utilizing the highest X/Q at the Site Boundary for the particular unit, from Table 3-2 for noble gases. The highest X/Q and D/Q are utilized for the particular unit's releases as applicable for gases other than noble gases (iodines, particulates, and tritium) for the controlling pathway's location (site boundary using Table 3-2 or other controlling locations using Table 4-16, 4-17, or 4-18).

Section 5.0 specifies utilizing the highest X/Q for the particular unit's releases at the controlling location from Table 4-16, 4-17, or 4-18, for noble gases. The highest X/Q and D/Q are utilized for the particular unit's releases as applicable for gases other than noble gases at the controlling pathway's location using Table 4-16, 4-17, or 4-18.

Section 7.0 requires that the meteorological conditions concurrent with the time of release of radioactive materials in gaseous effluents, as determined by sampling frequency and measurement, shall be used for determining the gaseous pathway doses.

4 ODCM Rev. 25

2.0 GASEOUS EFFLUENT MONITOR SETPOINTS

2.1 Requirements

Gaseous Monitors The radioactive gaseous effluent monitoring instrumentation channels shown in Table 2-1 shall be OPERABLE with their alarm/trip setpoints set to ensure that the dose requirements in Section 3.0 are not exceeded. The alarm/trip setpoints of these channels shall be determined and adjusted in accordance with the methodology and parameters in Section 2.1.2.

Applicability: As shown in Table 2-1.

Action:

a. With the low range radioactive gaseous effluent monitoring instrumentation channel alarm/trip setpoint less conservative than required by the above Requirement, immediately suspend the release of radioactive gaseous effluents monitored by the affected channel, or declare the channel inoperable, or change the setpoint so it is acceptably conservative.
b. With less than the minimum number of radioactive gaseous effluent monitoring instrumentation channels OPERABLE, take the ACTION shown in Table 2-1. Restore the inoperable instrumentation to OPERABLE status within 30 days or, if unsuccessful, explain in the next Annual Radioactive Effluent Release Report why this inoperability was not corrected within the time specified.

2.1.1 Surveillance Requirements

a. Each radioactive gaseous effluent monitoring instrumentation channel shall be demonstrated OPERABLE by performance of the CHANNEL CHECK, SOURCE CHECK, CHANNEL CALIBRATION, and CHANNEL FUNCTIONAL TEST operations at the frequencies shown in Table 2-2.

5 ODCM Rev. 25

TABLE 2-1 RADIOACTIVE GASEOUS EFFLUENT MONITORING INSTRUMENTATION MINIMUM CHANNELS INSTRUMENT OPERABLE APPLICABILITY ACTION

1. GASEOUS RADWASTE SYSTEM
a. Noble Gas Activity Monitor - Providing Alarm and Automatic Termination of Release #RU-12 1 35
b. Flow Rate Monitor 1 36
2. NOT USED
3. DELETED
4. PLANT VENT SYSTEM A. Low Range Monitors
a. Noble Gas Activity Monitor #RU-143 1 37
b. Iodine Sampler 1 40
c. Particulate Sampler 1* 40 1*
d. Flow Rate Monitor 36
e. Sampler Flow Rate Measuring Device 1* 36 B. High Range Monitors
a. Noble Gas Activity Monitor #RU-144 1* 42
b. Iodine Sampler I* 42 Oc. Particulate Sampler 1* 42
d. Sampler Flow Rate Measuring Device 42

TABLE 2-1 (Continued)

RADIOACTIVE GASEOUS EFFLUENT MONITORING INSTRUMENTATION MINIMUM CHANNELS INSTRUMENT OPERABLE APPLICABILITY ACTION

5. FUEL BUILDING VENTILATION SYSTEM A. Low Range Monitors
a. Noble Gas Activity Monitor #RU-145 37,41
b. Iodine Sampler 40
c. Particulate Sample 40
d. Flow Rate Monitor 36
e. Sampler Flow Rate Measuring Device 36 B. High Range Monitors
a. Noble Gas Activity Monitor #RU-146 42
b. Iodine Sampler 42
c. Particulate Sample 42
d. Sampler Flow Rate Measuring Device 42 0

0*

Table 2-1 (Continued)

TABLE NOTATION

  • At all times.
    • During GASEOUS RADWASTE SYSTEM operation
      • Whenever the condenser air removal system is in operation, or whenever turbine glands are being supplied with steam from sources other than the auxiliary boiler(s).
  1. During waste gas release.
    1. In MODES 1, 2, 3, and 4 or when irradiated fuel is in the fuel storage pool.

ACTION 35 - With the number of channels OPERABLE less than required by the Minimum Channels OPERABLE requirement, the contents of the tank(s) may be released to the environment provided that prior to initiating the release:

a. At least two independent samples of the tanks contents are analyzed, and
b. At least two technically qualified members of the facility staff independently verify the release rate calculations and discharge valve lineup; Otherwise, suspend release of radioactive effluents via this pathway.

ACTION 36 - With the number of channels OPERABLE less than required by the Minimum Channels OPERABLE requirement, effluent releases via this pathway may continue provided the flow rate is estimated at least once per 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

ACTION 37 - With the number of channels OPERABLE less than required by the Minimum Channels OPERABLE requirement, effluent releases via this pathway may continue provided the actions of (a) or (b) or (c) are performed:

a. Initiate the Preplanned Alternate Sampling Program to monitor the appropriate parameter(s).
b. Place moveable air monitors in-line.
c. Either take grab samples at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, OR obtain gas channel monitor readings locally at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> if the channel is functional locally but inoperable due to loss of communication with the minicomputer. The surveillance requirements of Section 2.1.1 must be performed at the required frequencies for the channel to be functional locally.

ACTION 38 - NOT USED ACTION 39 - NOT USED ACTION 40 - With the number of channels OPERABLE less than required by the Minimum Channels OPERABLE requirement, effluent releases via the effected pathway may continue provided samples are continuously collected with auxiliary sampling equipment as required in Table 3-1 within one hour after the channel has been declared inoperable.

ACTION 41 - With the number of channels OPERABLE less than required by the Minimum Channels OPERABLE requirements, comply with Technical Requirements Manual TLCO 3.3.108.

8 ODCM Rev. 25

Table 2-1 (Continued)

TABLE NOTATION ACTION 42 - With the number of channels OPERABLE less than required by the Minimum Channels OPERABLE requirement restore the channel to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or:

a. Initiate the Preplanned Alternate Sampling Program to monitor the appropriate parameter(s) when it is needed.
b. Prepare and submit a Special Report to the Commission within 30 days following the event outlining the action(s) taken, the cause of the inoperability, and the plans and schedule for restoring the system to OPERABLE status.

9 ODCM Rev. 25

TABLE 2-2 RADIOACTIVE GASEOUS EFFLUENT MONITORING INSTRUMENTATION SURVEILLANCE REQUIREMENTS CHANNEL MODE IN WHICH CHANNEL SOURCE CHANNEL FUNCTIONAL SURVEILLANCE INSTRUMENT CHECK CHECK CALIBRATION TEST IS REQUIRED

1. GASEOUS RADWASTE SYSTEM
a. Noble Gas Activity Monitor - Providing Alarm and Automatic Termination of Release RU-12 P P(7) R(3) Q(1),(2),P### #
b. Flow Rate Monitor P N.A. R Q,P### #
2. DELETED
3. DELETED
4. PLANT VENT SYSTEM (RU-143 and RU-144) 0 *g
a. Noble Gas Activity Monitor D(5) M(7) R(3) Q(2)
b. Iodine Sampler N.A. N.A. N.A. N.A.
c. Particulate Sampler N.A. N.A. N.A. N.A.
d. Flow Rate Monitor D(6) N.A. R Q
e. Sampler Flow Rate Measuring Device D(6) N.A. R Q
5. FUEL BUILDING VENTILATION SYSTEM (RU-145 and RU-146)
a. Noble Gas Activity Monitor D(5) M(7) R(3) Q(2)
b. Iodine Sampler N.A. N.A. N.A. N.A. #4t 0 c. Particulate Sample N.A. N.A. N.A. N.A.

(~J

d. Flow Rate Monitor D(6) N.A. R Q
e. Sampler Flow Rate Measuring Device D(6) N.A. R Q (A

Table 2-2 (Continued)

TABLE NOTATION

  • At all times.
    • During GASEOUS RADWASTE SYSTEM operation
      • Whenever the condenser air removal system is in operation, or whenever turbine glands are being supplied with steam from sources other than the auxiliary boiler(s).
  1. During waste gas release.
    1. In MODES 1, 2, 3, and 4 or when irradiated fuel is in the fuel storage pool.
      1. Functional test should consist of, but not be limited to, a verification of system isolation capability by the insertion of a simulated alarm condition.

(1) The CHANNEL FUNCTIONAL TEST shall also demonstrate that automatic isolation of this pathway occurs if the instrument indicates measured levels above the alarm/trip setpoint.

(2) The CHANNEL FUNCTIONAL TEST shall also demonstrate that control room alarm annunciation occurs if any of the following conditions exists:

1. Instrument indicates measured levels above the alarm setpoint.
2. Circuit failure.
3. Instrument indicates a downscale failure.
4. Instrument controls not set in operate mode.

(3) The initial CHANNEL CALIBRATION shall be performed using one or more of the reference standards certified by the National Institute of Standards and Technology (NIST) or using standards that have been obtained from suppliers that participate in measurement assurance activities with NIST. These standards shall permit calibrating the system over its intended range of energy and measurement range. For subsequent CHANNEL CALIBRATION, sources that have been related to the initial calibration may be used in lieu of the reference standards associated with the initial calibration.

(4) NOT USED (5) The channel check for channels in standby status shall consist of verification that the channel is on-line and reachable.

(6) Daily channel check not required for flow monitors in standby status.

(7) LED may be utilized as the check source in lieu of a source of increased activity.

I1I ODCM Rev. 25

2.1.2 Implementation of the Requirements The general methodology for establishing low range gaseous effluent monitor setpoints is based upon a site release rate limit in *tCi/sec derived from site specific meteorological dispersion conditions, radioisotopic distribution, and whole body and skin dose factors. The high alarm of the low range monitors will alarm/trip when the release rate from an individual vent will result in exceeding the limits in Section 3.1. 80% of Section 3.1 limits is considered to be the site release rate limit. The site release rate limit will be allocated among the licensed units' release points. The unit release rate limit will then be utilized for the determination of gaseous effluent monitor setpoints. A fraction of the unit release rate limit is then allotted to each release point and its monitor alert setpoint (gCi/cc) is derived using actual or fan design flow rates.

Administrative values are used to reduce each setpoint to account for the potential activity in other releases. These administrative values shall be reviewed based on actual release data.

For the purpose of implementation of Section 2.1, the alarm setpoint levels for low range effluent noble gas monitors are established to ensure that personnel are alerted when the noble gas releases are at a rate such that if the releases would continue for the year they would approach the total body dose rate of 500 mrem/yr and 3000 mrem/yr skin dose in Section 3.1.

The equations in Section 3.1 of this manual provide the methodology for calculating the gaseous effluent dose rate.

The evaluation of doses due to releases of radioactive material can be simplified by the use of equivalent dose factors as defined in Section 2.1.2.1.

The equivalent dose factors will be evaluated periodically to assure that the best information on'isotopic distribution is being used for the dose equivalent value.

12 ODCM Rev. 25

2.1.2.1 Equivalent Dose Factor Determination The equivalent whole body dose factor is calculated as follows:

Keq = -j(Ki)(fi)] (2-1)

Where:

Keq = the equivalent whole body dose factor weighted by historical radionuclide distribution in releases in mrem/yr per pCi/m3 .

Ki = the whole body dose factor due to gamma emissions for each identified noble gas radionuclide i, in mrem/yr per ltCi/m 3 from Table 3-3.

fi = the fraction of noble gas radionuclide i in the total noble gas radionuclide mix.

The equivalent skin dose factor is calculated as follows:

(L + l.lM)eq = Zi[(Li + 1.1Mi)(fi)] (2-2)

Where:

(L+I.lM)eq = the equivalent skin dose factor due to beta and gamma emissions from all noble gases released, weighted by the historical radionuclide distribution in releases in mrem/yr per ýtCi/m 3.

Li = the skin dose factor due to the beta emissions for each identified noble gas radionuclide i, in mrem/yr per [tCi/m 3 from Table 3-3.

Mi the air dose factor due to gamma emissions for each identified noble gas radionuclide i, in mrad/yr per [LCi/m 3 from Table 3-3.

f. = the fraction of noble gas radionuclide i in the total noble gas radionuclide mix.

1.1 = unit conversion constant of 1.1 mrem/mrad converts air dose to skin dose.

13 ODCM Rev. 25

2.1.2.2 Site Release Rate Limit (QsITE)

The release rates corresponding to 80% of the whole body (QwB) and skin (QSK) dose rate limits are calculated using the equivalent dose factors defined in Section 2.1.2.1.

The site release rate limit (QsITE) is the lower of QWB or QSK, thus assuring that the more restrictive dose rate limit will not be exceeded.

The QSITE is established as follows:

QSITEWB (DwB)(0' 8 ) (2-3)

(Keq)(X/Q)sITE Where:

QSITEWB = the site release rate, in ltCi/sec, that would deliver a dose rate 80% of the whole body dose rate limit, DWB.

DWB = whole body dose rate limit of 500 mrem/yr.

Keq = equivalent whole body dose factor, in mrem/yr per iCi/m 3 weighted by the historical radionuclide distribution.

(X/Q)SITE = 8.91E-06, the highest calculated annual average dispersion parameter, in sec/m 3 , at the Site Boundary for any of the 3 units, from Table 3-2.

0.8 = administrative factor to compensate for any unexpected variability in the radionuclide mix and to ensure that Site Boundary dose rate limits will not be exceeded.

(DsK)(0' 8 ) (2-4)

~SITE,SK =(L + 1.1M)eq(X/Q)SITE Where:

QSITE,SK = the site release rate limit, in IICi/sec, that would deliver a dose rate 80% of the skin dose rate limit, DSK.

DSK = skin dose rate limit of 3000 mrem/yr.

(L+I.IM)eq = equivalent skin dose factor, in mremn/yr per [tCi/m 3 , weighted by the radionuclide distribution.

(X/Q)SITE = 8.91E-06, the highest calculated annual average dispersion parameter, in sec/m 3 , at the Site Boundary for any of the three units, from Table 3-2.

0.8 = administrative factor to compensate for any unexpected variability in the radionuclide mix and to ensure that Site Boundary dose rate limits will not be exceeded.

After determination of the QSITE whole body and skin dose rates (equations 2-3 and 2-4, respectively), the most conservative result will be used as QSITE, the site release rate limit.

14 ODCM Rev. 25

2.1.2.3 Unit Release Rate Limits (QUNIT)

Typically QSITE will be divided equally among operating units. If operational history dictates a,larger fraction of the QSITE be assigned to a specific unit then a weighted average of each unit's contribution to the QSITE will be utilized to determine the QUNIT.

QUNIT = (fUNIT) (QSITE) (2-5)

Where:

QUNIT = unit release rate limit, in LtCi/sec.

fUNIT = the fraction (< 1) of noble gas historically released from a specific operating unit to the total of all noble gas released from the site.

QSITE = the site release rate limit, in ýLCi/sec determined in Section 2.1.2.2.

2.1.2.4 Setpoint Determination To comply with the requirements in Section 2.1, the alarm/trip setpoints can now be established using the unit release rate limit (QUNIT) to ensure that the noble gas releases do not exceed the dose rate limits.

To allow for multiple sources of releases from different or common release points, the effluent monitor setpoint includes an administrative factor which allocates a percentage of the unit release rate limit to each of the release sources. Monitor setpoints will also be adjusted in accordance with Nuclear Administrative and Technical Manual procedures to account for monitor-specific characteristics.

Monitors RU-143 and RU-145 The alarm/trip setpoint for Monitors RU-143 and RU-145 is calculated as follows:

Monitor (QUNIT)(a)

Setpoint (472)(Flow Rate) (2-6)

Where:

Monitor Setpoint = the setpoint for the effluent monitor, in [tCi/cc, which provides a safe margin of assurance that the allowable dose rate limits will not be exceeded.

QUNIT = unit release rate limit, in ltCi/sec, as determined in Section 2.1.2.3.

Flow Rate = the flow rate, in cfm, from flow rate monitors or the fan design flow rate for the release source under consideration.

472 = conversion factor, cubic centimeter/second per cubic feet/minute.

a = fraction of QUNIT allocated for a specific release point. The sum of these administrative values shall be less than or equal to one.

15 ODCM Rev. 25

Monitor RU-12 The alarm/trip setpoint for Monitor RU-12, the Waste Gas Decay Tank Monitor, is calculated as follows:

Monitor [(QUNIT)(a)(0. 9 ) - (H)(PF)(472)] (2-7) setpoint (Flow Rate)(472)

Where:

Monitor Setpoint = the setpoint for the monitor, in [tCi/cc at STP, which provides a safe margin of assurance that the allowable dose rate limits will not be exceeded.

QUNIT = unit release rate limit, in ltCi/sec, as determined in Section 2.1.2.3.

Flow Rate = flow rate, in cfm at STP at which the tank will be released.

PF = the current process flow of the plant vent in CFM.

H = the current plant vent monitor concentration in [tCi/cc.

a = fraction of QUNIT allocated for a specific release point. This administrative value should be equal to or less than the administrative value used for the Plant Vent.

0.9 = an administrative value to account for potential increases in activity from other contributors to the same release point.

472 = conversion factor, cubic centimeter/second per cubic feet/minute.

If there is no release associated with this monitor, the monitor setpoint should be established as close as practical to background to prevent spurious alarms, and yet assure an alarm should an inadvertent release occur.

2.1.2.5 Monitor Calibration The Radiation Level Conversion Factor (RLF) for each monitor is entered into the Radiation Monitoring System Database and may change whenever the monitor is calibrated. Calibration is performed in accordance with Nuclear Administrative and Technical Manual procedures.

16 ODCM Rev. 25

3.0 GASEOUS AND LIQUID EFFLUENT DOSE RATES

3.1 Requirements

Gaseous Effluents The dose rate due to radioactive materials released in gaseous effluents from the site (see Figure 6-4 and Figure 6-5) shall be limited to the following:

a. For noble gases: Less than or equal to 500 mrems/yr to the total body and less than or equal to 3000 mrems/yr to the skin, and ,
b. For 1-131 and 1-133, for tritium, and for all radionuclides in particulate form with half-lives greater than 8 days: Less than or equal to 1500 mrems/yr to any organ.

Applicability: At all times.

Action:

With the dose rate(s) exceeding the above limits, immediately decrease the release rate to within the above limits(s).

3.1.1 Surveillance Requirements

a. The dose rate due to noble gases in gaseous effluents shall be determined to be within the above limits in accordance with the methods contained in Section 3.1.2.
b. The dose rate due to 1-131, 1-133, tritium and all radionuclides in particulate form with half-lives greater than 8 days in gaseous effluents shall be determined to be within the above limits in accordance with the methods contained in Section 3.1.2 by obtaining representative samples and performing analyses in accordance with the sampling and analysis program specified in Table 3-1.

17 ODCM Rev. 25

3.1.2 Implementation of the Requirements Noble Gases Noble gas activity monitor setpoints are established at release rates which permit corrective action to be taken before exceeding the 10 CFR 20 annual dose limits as described in Section 2.0. The requirements for sampling and analysis of continuous and batch effluent releases are given in Table 3-1. The methods for sampling and analysis of continuous and batch effluent releases are given in the Nuclear Administrative and Technical Manual procedures. The dose rate in unrestricted areas shall be determined using the following equations.

For whole body dose rate:

DWB = Zi[(Ki)(X/Q)SITE(Qi)] (3-1)

For skin dose rate:

DSK = Z,[(Li + l.lMX)(X/Q)SITE(Qi)] (3-2)

Where:

Ki = the whole body dose factor due to gamma emissions for each identified noble gas radionuclide i, in mrem/yr per ýtCi/m 3 from Table' 3-3.

Qi = the release rate of radionuclide i, in pCi/sec.

(X/Q)SITE = 8.91E-06, the highest calculated annual average dispersion parameter, in sec/m 3, for any of the three units, from Table 3-2.

DWB = the annual whole body dose rate (mrem/yr.).

Li = the skin dose factor due to the beta emissions for each identified noble gas radionuclide i, in mrem/yr per [tCi/m 3 from Table 3-3.

Mi = the air dose factor due to gamma emissions for each identified noble gas radionuclide i, in mrad/yr per liCi/m 3 from Table 3-3.

DSK = the annual skin dose rate (mrem/yr).

1.1 = unit conversion constant of 1.1 mrem/mrad converts air dose to skin dose.

18 ODCM Rev. 25

1-131. 1-133, tritium and radionuclides in particulate form with half-lives greater than 8 days The methods for sampling and analysis of continuous and batch releases for 1-131, 1-133, tritium and radionuclides in particulate form with half-lives greater than 8 days, are given in the applicable Nuclear Administrative and Technical Manual procedures. Additional monthly and quarterly analyses shall be performed in accordance with Table 3-1. The total organ dose rate in unrestricted areas shall be determined by the following equation:

Do = Zi[(Pi)(X/Q)sITE(Qi)] (3-3)

Where:

Pi = the dose factor, in mrem/yr per gCi/m 3, for radionuclide i, for the inhalation pathway, from Table 3-4.

(X/Q)SITE = 8.91E-06, the highest calculated annual average dispersion parameter, in sec/m 3 , at the Site Boundary, for any of the three units, Qi = the release rate of radionuclide i, in ýLCi/sec Do = the total organ dose rate (mrem/yr).

19 ODCM Rev. 25

TABLE 3-1 RADIOACTIVE GASEOUS WASTE SAMPLING AND ANALYSIS PROGRAM MINIMUM LOWER LIMIT SAMPLING ANALYSIS TYPE OF OF DETECTION GASEOUS RELEASE TYPE FREQUENCY FREQUENCY ACTIVITY ANALYSIS (LLD) (l.Ci/ml)a A. Waste Gas Storage P P Principal Gamma 1.OE-04 Each Tank Grab Each Tank Emittersg Sample B. Containment Purge P P Principal Gamma 1.OE-04 Each Purgeb'c Each Purgeb'c Emittersg Grab Sample H-3 IOE-06 C. 1. DELETED Mb'e Mb Principal Gamma 1.OE-04

2. Plant Vent Grab Sample Emittersg
3. Fuel Bldg. Exhaust H-3 1.0E-06 Continuousf 4 /M' 1-131 1.OE-12 Charcoal Sample 1-133 1.OE-10 Continuousf 4/Md Principal Gamma .OE-1 1 Particulate Emittersg Sample (1- 131, Others)

Continuousf M Gross Alpha 1.OE- 11 Composite Particulate Sample Continuousf Q Sr-89, Sr-90 L.OE-I I Composite Particulate Sample D. All Radwaste Types as Noble Gas Noble Gases Gross Beta 1.OE-06 listed in A., B., and C., Monitor or Gamma above.

20 ODCM Rev. 25

Table 3-1 (Continued)

TABLE NOTATION a The LLD is the smallest concentration of radioactive material in a sample that will yield a net count (above system background) that will be detected with 95% probability with only 5% probability of falsely concluding that a blank observation represents a real signal.

For a particular measurement system (which may include radiochemical separation):

4.66 sb LLD = 4 E

  • V
  • 2.22E6
  • Y
  • exp(-X*At)

Where:

LLD is the a priori lower limit of detection as defined above (as pCi per unit mass or volume). Current literature defines the LLD as the detection capability for the instrumentation only and the MDC minimum detectable concentration, as the detection capability for a given instrument, procedure and type of sample.

sb is the standard deviation of the background counting rate or of the counting rate of a blank sample as appropriate (as counts per minute),

E is the counting efficiency (as counts per transformation),

V is the sample size (in units of mass or volume),.

2.22E6 is the number of transformations per minute per microcurie,.

Y is the fractional radiochemical yield (when applicable),

Xkis the radioactive decay constant for the particular radionuclide, and At is the elapsed time between the midpoint of sample collection and time of counting (for plant effluents, not environmental samples).

The value of sb used in the calculation of the LLD for a detection system shall be based on the actual observed variance of the background counting rate or of the counting rate of the blank samples (as appropriate) rather than on an unverified theoretically predicted variance. In calculating the LLD for a radionuclide determined by gamma-ray spectrometry the background should include the typical contributions of other radionuclides normally present in the samples. Typical values of E, V, Y, and At should be used in the calculation.

It should be recognized that the LLD is defined as an a priori (before the fact) limit representing the capability of a measurement system and not as an a posteriori (after the fact) limit for a particular measurement.

21 ODCM Rev. 25

Table 3-1 (Continued)

TABLE NOTATION b Analyses shall also be performed following SHUTDOWN, STARTUP, or a THERMAL POWER change exceeding 15% of the RATED THERMAL POWER within a 1-hour period if 1) analysis shows that the DOSE EQUIVALENT 1-131 concentration in the primary coolant has increased more than a factor of 3; and 2) the noble gas activity monitor on the plant vent shows that effluent activity has increased by more than a factor of 3. If the associated noble gas vent monitor is inoperable, samples must be obtained as soon as possible. Analyses shall be performed within a four-hour period. This requirement does not apply to the Fuel Building Exhaust.

c Sampling and analyses shall also be performed at least once per 31 days when purging time exceeds 30 days continuous.

d Samples shall be changed at least 4 times a month and analyses shall be completed within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> after changing (or after removal from sampler). When samples collected for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> are analyzed, the corresponding LLDs may be increased by a factor of 10.

e Tritium grab samples shall be taken at least monthly from the ventilation exhaust from the spent fuel pool area, whenever spent fuel is in the spent fuel pool.

f The ratio of the sample flow rate to the sampled stream flow rate shall be known for the time period covered by each dose or dose rate calculation made in accordance with Requirements 3.1, 4.1 and 4.2 of the ODCM.

g The principal gamma emitters for which the LLD specification applies include 'the following radionuclides: Kr-87, Kr-88, Xe-133, Xe-133m, Xe-135, and Xe-138 for gaseous emissions and Mn-54, Fe-59, Co-58, Co-60, Zn-65, Mo-99, Cs-134, Cs-137, Ce-141 and Ce-144 for particulate emissions. This list does not mean that only these nuclides are to be detected and reported. Other peaks which are measurable and identifiable, together with the above nuclides shall also be identified and reported in the Annual Radioactive Effluent Release Report..

22 ODCM Rev. 25

TABLE 3-2 DISPERSION AND DEPOSITION PARAMETERS FOR LONG TERM RELEASES AT THE SITE BOUNDARY UNIT 1 UNIT 2 UNIT 3 DISTANCE X/Q D/Q DISTANCE X/Q 3 D/Q DISTANCE X/Q 3 D/Q DIRECTION (METERS) (SEC/m 3) (m" 2) (METERS) (SEC/m ) (m2 ) (METERS) (SEC/m ) (m-2)

N 1037 4.93E-06 9.24E-09 1318 3.85E-06 6.17E-09 1661 3.54E-06 4.86E-09 NNE 1057 4.14E-06 1.19E 1342 3.18E-06 7.93E-09 1693 2.86E-06 6.23E-09 NE 2206 2.84E-06 6.84E-09 2545 2.42E-06 5.34E-09 2756 2.21 E-06 4.65E-09 ENE 1967 2.5 1E-06 4.43E-09 2206 2.22E-06 3.64E-09 2337 2.08E-06 3.30E-09 E 1927 2.56E-06 3.24E-09 2163 2.27E-06 2.66E-09 2290 2.14E-06 2.4 1E-09 ESE 1967 2.61 E-06 2.46E-09 2067 2.32E-06 2.11E-09 2023 2.37E-06 2. 1OE-09 SE 2049 3.56E-06 2.36E-09 2101 3.47E-06 2.26E-09 2256 3.24E-06 2.OOE-09 SSE 2730 3.80E-06 1.58E-09 3026 3.43E-06 1.32E-09 2786 3.72E-06 1.52E-09 S 3006 5.07E-06 1.78E-09 2699 5.16E-06 1.97E-09 2346 5.90E-06 2.5 1E-09 SSW 2258 6.52E-06 3.20E-09 1836 7.90E-06 4.56E-09 1607 8.91E-06 5.73E-09 SW 1487 7.47E-06 5.65E-09 1208 7.72E-06 6.88E-09 1057 8.68E-06 8.61E-09 WSW 1251 4.52E-06 5.93E-09 1014 5.55E-06 8.44E-09 889 5.34E-06 8.83E-09 W 1225 4.73E-06 9.49E-09 993 5.86E-06 1.34E-08 871 6.72E-06 1.67E-08 WNW 1244 3.76E-06 6.76E-09 1010 4.67E-06 9.60E-09 885 5.37E-06 1.19E-08 NW 1254 3.43E-06 5.87E-09 1191 3.62E-06 6.40E-09 1045 4.17E-06 7.98E-09 NNW 1069 3.70E-06 7.26E-09 1342 2.85E-06 4.87E-09 1561 2.93E-06 4.58E-09 0

Reference:

Distances are from the PVNGS ER-OL, Table 2.3-33. Dispersion and Deposition parameters are from a September, 1985, calculation by NUS Corporation based on 9 years of meteorological data; NUS Corporation letter NUS-ANPP-1386, dated October 4, 1985.

TABLE 3-3 DOSE FACTORS FOR NOBLE GASES AND DAUGHTERS Whole Body Skin Gamma Air Dose Factor Dose Factor Dose Factor Beta Air Dose Ki Li Mi Factor Ni 3 3 mrad-m 3 3 mrem-m mrem-m mrad-m Radionuclide yr-ptCi yr-ptCi yr-jtCi yr-pCi Kr-83m 7.56E-02 1.93E+01 2.88E+02 Kr-85m 1.17E+03 1.46E+03 1.23E+03 1.97E+03 Kr-85 1.61E+01 1.34E+03 i.72E+01 1.95E+03 Kr-87 5.92E+03 9.73E+03 6.17E+03 1.03E+04 Kr-88 1.47E+04 2.37E+03 1.52E+04 2.93E+03 Kr-89 1.66E+04 1.01E+04 1.73E+04 1.06E+04 Kr-90 1.56E+04 7.29E+03 1.63E+04 7.83E+03 Xe-131m 9.15E+01 4.76E+02 1.56E+02 1.11 E+03 Xe-133m 2.5 1E+02 9.94E+02 3.27E+02 1.48E+03 Xe- 133 2.94E+02 3.06E+02 3.53E+02 1.05E+03 Xe- 135m 3.12E+03 7.11E+02 3.36E+03 7.39E+02 Xe-135 1.81E+03 1.86E+03 1.92E+03 2.46E+03 Xe-137 1.42E+03 1.22E+04 1.511E+03 1.27E+04 Xe-138 8.83E+03 4.13E+03 9.21 E+03 4.75E+03 Ar-41 8.84E+03 2.69E+03 9.30E+03 3.28E+03

Reference:

Regulatory Guide 1.109, Table B- 1.

24 ODCM Rev. 25

TABLE 3-4 Pi VALUES FOR THE INHALATION PATHWAY (mrem/yr/tCi/m3)

NUCLIDE Age Group Organ Pi H-3 TEEN LIVER 1.27E+03 CR-51 TEEN LUNG 2.1OE+04 MN-54 TEEN LUNG 1.98E+06 FE-59 TEEN LUNG 1.53E+06 CO-58 TEEN LUNG 1.34E+06 CO-60 TEEN LUNG 8.72E+06 ZN-65 TEEN LUNG 1.24E+06 SR-89 TEEN LUNG 2.42E+06 SR-90 TEEN BONE 1.08E+08 ZR-95 TEEN LUNG 2.69E+06 SB- 124 TEEN LUNG 3.85E+06 1-131 CHILD THYROID 1.62E+07 1-133 CHILD THYROID 3.85E+06 CS-134 TEEN LIVER 1.13E+06 CS-137 CHILD BONE 9.07E+05 BA- 140 TEEN LUNG 2.03E+06 CE- 141 TEEN LUNG 6.14E+05 CE- 144 TEEN LUNG 1.34E+07 25 ODCM Rev. 25

3.2 Requirements

Secondary System Liquid Waste Discharges To Onsite Evaporation Ponds or Circulating Water System - Concentration The concentration of radioactive material discharged from secondary system liquid waste to the circulating water system shall be limited to:

5.0E-07 ltCi/ml for the principal gamma emitters (except Ce-144) 3.0E-06 ýtCi/ml for Ce-144 1.0E-06 RCi/ml for 1-131 1.0E-03 ltCi/ml for H-3 The concentration of radioactive material discharged from secondary system liquid waste to the onsite evaporation ponds shall be limited to:

2.0E-06 pCi/ml for Cs-134 2.0E-06 [tCi/ml for Cs-137 The concentrations specified in 10 CFR Part 20.1001-20.2402, Appendix B, Table 2, Column 2, for all other isotopes Applicability: At all times.

Action:

When any secondary system liquid waste discharge pathway concentration determined in accordance with the surveillance requirements given below exceeds the above Requirements, divert that discharge pathway to the liquid radwaste system without delay or terminate the discharge.

3.2.1 Surveillance Requirements

a. Secondary system liquid wastes shall be sampled and analyzed according to the sampling and analysis program of Table 3-5.

3.2.2 Implementation of the Requirements This requirement is implemented by Nuclear Administrative and Technical Manual procedures.

26 ODCM Rev. 25

TABLE 3-5 RADIOACTIVE LIQUID WASTE SAMPLING AND ANALYSIS PROGRAM Lower Limit Of Detection Secondary System Liquid Release Sampling & Type Of (LLD)a Pathway Destination Analysis Frequency Notes Activity Analysis (10Ci/ml)

I. Chemical Waste Neutralizer Retention Tank P Each Batch Principal Gamma Emittersc 5.OE-07 Tank (CWNT)b liquid radwaste N. A. 1-131 1.OE-06 H-3 1.OE-05

2. Steam Generator Blowdown circ. water P Each Batch 1 Principal Gamma Emittersc 5.OE-07 Low TDS Sumpb CWNT N. A. 1-131 1.OE-06 H-3 .OE-05
3. Condensate
a. Condensate Polishing Low circ. water P Each Batch 3 Principal Gamma Emittersc 5.OE-07 TDS Sumpb CWNT N. A. 1-131 1.OE-06 H-3 1.OE-05
b. Initial Backwash (low TDS sump) to P Each Discharge Principal Gamma Emittersc 5.OE-07 circ. water 1-131 1.OE-06 (low TDS sump) to N. A. H-3 1.0E-05 CWNT
c. Pre-service rinse effluent Retention Tank P Each Discharge 2 Principal Gamma Emittersc 5.OE-07 through SC-N-V069 1-131 1.OE-06 condenser through N. A. H-3 1.OE-05 SC-N-UV232
d. Overboard condensate circ water through P Each Discharge Principal Gamma Emittersc 5.OE-07 CD-N-V 194 1-131 1.OE-06 Retention Tank P Each Discharge 2 H-3 1.OE-05 through SC-N-V079.

0 4. Turbine Building Sump' Retention Tank D Grab Sample 3 Principal Gamma Emittersc 5.OE-07

(-I CWNT N.A. 1-131 L.OE-06 H-3 1.OE-05

TABLE 3-5 RADIOACTIVE LIQUID WASTE SAMPLING AND ANALYSIS PROGRAM Lower Limit Of Detection Secondary System Liquid Release Sampling & Type Of (LLD)a Pathway Destination Analysis Frequency Notes Activity Analysis (ltCi/ml)

5. North & South Condenser Area Retention Tank D Grab Sample 3 Principal Gamma Emittersc 5.OE-07 Sumpsd CWNT N. A. 1-131 L.OE-06 H-3 1.OE-05
6. Steam Generator Blowdown to Retention Tank P Each Discharge 2 Principal Gamma Emittersc 5.OE-07 Retention Tank through SC-N-V064 1-131 1.OE-06 1H-3 1.OE-05
7. Retention Tank to Evaporation evaporation pond P Each Batch Principal Gamma Emitters' 5.OE-07 Pond 1-131 1.OE-06 H-3 1.OE-05 IN)

I Sampling and analysis are required only when concentration for chemical waste neutralizer tank or steam generator activity exceeds the requirement 2 RU-200 shall be demonstrated OPERABLE by performance of the CHANNEL CHECK, SOURCE CHECK, CHANNEL CALIBRATION, and CHANNEL FUNCTIONAL TEST at the frequencies shown in Table 3-6. The Alarm/Trip setpoints for RU-200 are set to ensure that the concentrations in the Retention Tanks do not exceed the Requirement 3 Sampling and analysis are required only when concentration for chemical waste neutralizer tank or condensate activity exceeds the requirement (I)

Table 3-5 (Continued)

TABLE NOTATION a The LLD is defined as the smallest concentration of radioactive material in a sample that will yield a net count, above system background, that will be detected with 95% probability with only 5% probability of falsely concluding that a blank observation represents a "real" signal.

For a particular measurement system which may include radiochemical separation:

LLD -4.66 sb E

  • V
  • 2.22E6
  • Y
  • exp(-XAt)

Where:

LLD is the "a priori" lower limit of detection as defined above as microcuries per unit mass or volume, sb is the standard deviation of the background counting rate or of the counting rate of a blank sample as appropriate as counts per minute, E is the counting efficiency as counts per disintegration, V is the sample size in units of mass or volume, 2.22E6 is the number of disintegrations per minute per microcurie, Y is the fractional radiochemical yield when applicable, X is the radioactive decay constant for the particular radionuclide, and At is the elapsed time between midpoint of sample collection and time of counting.

Typical values of E, V, Y, and At should be used in the calculation.

It should be recognized that the LLD is defined as an a priori (before the fact) limit representing the capability of a measurement system and not as an a posteriori (after the fact) limit for a particular measurement.

b A batch release is the discharge of liquid wastes of a discrete volume. Prior to sampling for analyses, each batch shall be isolated, and then thoroughly mixed to assure representative sampling.

c The principal gamma emitters for which the LLD specification applies include the following radionuclides: Mn-54, Fe-59, Co-58, Co-60, Zn-65, Mo-99, Cs-134, Cs-137, and Ce-141. Ce-144 shall also be measured, but with an LLD of 3.OE-06. This list does not mean that only these nuclides are to be considered. Other gamma peaks that are identifiable, together with those of the above nuclides, shall also be analyzed and reported in the Annual Radioactive Effluent Release Report.

d A continuous release is the discharge of liquid wastes of a nondiscrete volume, e.g., from a volume of a system that has an input flow during the continuous release 29 ODCM Rev. 25

TABLE 3-6 RADIOACTIVE LIQUID EFFLUENT MONITORING INSTRUMENTATION Channel Mode in which Channel Source Channel Functional Surveillance is Instrument Check Check Calibration Test Required RU-200 P N. A. R Q See Table 3-7 TABLE 3-7 RADIOACTIVE LIQUID EFFLUENT MONITORING INSTRUMENTATION SURVEILLANCE REQUIREMENTS Mode in which Surveillance Secondary System Liquid Release Pathway is Required Action if RU-200 is inoperable Obtain grab sample at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and analyze in accordance Pre-service rinse to Retention Tanks At All Times with section 3.2 Obtain grab sample at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and analyses in accordance Condensate overboard to Retention Tanks 1-4 with section 3.2 Modes 1-4: Suspend the release Steam Generator Blowdown/Drain to Retention At All Times Modes 5,6 & defueled: Obtain grab Tanks sample at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and analyze in accordance with sec-tion 3.2 30 ODCM Rev. 25

4.0 GASEOUS & LIQUID EFFLUENTS - DOSE

4.1 Requirements

Noble Gases The air dose due to noble gases released in gaseous effluents, from each reactor unit to areas at and beyond the SITE BOUNDARY (see Figure 6-4 and Figure 6-5) shall be limited to the following:

a. During any calendar quarter: Less than or equal to 5 mrads for gamma radiation and less than or equal to 10 mrads for beta radiation and,
b. During any calendar year: Less than or equal to 10 mrads for gamma radiation and less than or equal to 20 mrads for beta radiation.

Applicability: At all times.

Action:

With the calculated air dose from radioactive noble gases in gaseous effluents exceeding any of the above limits, prepare and submit to the Commission within 30 days, a Special Report that identifies the cause(s) for exceeding the limit(s) and defines the corrective actions that have been taken to reduce the releases and the proposed corrective actions to be taken to assure that subsequent releases will be in compliance with the above limits.

4.1.1 Surveillance Requirements

a. Cumulative dose contributions for the current calendar quarter and current calendar year for noble gases shall be determined in accordance with the methodology contained in Section 4.1.2 at least once per 31 days..

31 ODCM Rev. 25

4.1.2 Implementation of the Requirement: Noble Gas The air dose in unrestricted areas beyond the site boundary due to noble gases released in gaseous effluents from each unit during any specified time period shall be determined by the following equations:

For gamma radiation:

D 7, = (3.17E-08) 1i [(Mi) (X/Q)UNIT(Qi)] (4-1)

For beta radiation:

D Pu = (3.17E-08) 1i [(Ni) (X/Q)UNIT(Qi)] (4-2)

Where:

Mi" = the air dose factor due to gamma emissions for each identified noble gas radionuclide i, in mrad/yr per ICi/m3 from Table 3-3.

Ni- the air dose factor due to beta emissions for each identified noble gas radionuclide i, in mrad/yr per .tCi/m3 from Table 3-3.

(X/Q)UNIT = the highest calculated annual average dispersion parameter, in sec/m 3 , at the site boundary for the particular Unit, from Table 3-2. Optionally, the highest value may be used for any Unit calculation.

=7.47E-06 from Unit I

=7.90E-06 from Unit 2

=8.91E-06 from Unit 3 D 7u = the total gamma air dose, for the particular unit, in mrad, due to noble gases released in gaseous effluents for a specified time period at the SITE BOUNDARY.

D P. = the total beta air dose, for the particular unit, in mrad, due to noble gases released in gaseous effluents for a specified time period at the SITE BOUNDARY.

Q= the integrated release, from the particular unit, in ltCi, of each identified noble gas radionuclide i, in gaseous effluents for a specified time period.

3.17E-08 = the inverse of seconds in a year (yr/sec).

The cumulative gamma air dose and beta air dose for a quarterly or annual evaluation shall be based on the calculated dose contribution from each specified time period occurring during the reporting time period.

32 ODCM Rev. 25

4.2 Requirement

Iodine-131, Iodine-133, Tritium, and. All Radionuclides in Particulate Form With Half-Lives Greater Than 8 Days The dose to a MEMBER OF THE PUBLIC from iodine-131, iodine-133, tritium, and all radionuclides in particulate form with half-lives greater than 8 days in gaseous effluents released, from each reactor unit, to areas at and beyond the SITE BOUNDARY (see Figure 6-4 and Figure 6-

5) shall be limited to the following:
a. During any calendar quarter: Less than or equal to 7.5 mrems to any organ and,
b. During any calendar year: Less than or equal to 15 mrems to any organ.

Applicability: At all times.

Action:

With the calculated dose from the release of iodine-131, iodine-133, tritium, and radionuclides in particulate form with half-lives greater than 8 days, in gaseous effluents exceeding any of the above limits, prepare and submit to the Commission within 30 days, a Special Report that identifies the cause(s) for exceeding the limit and defines the corrective actions that have been taken to reduce the releases and the proposed corrective actions to be taken to assure that subsequent releases will be in compliance with the above limits.

4.2.1 Surveillance Requirements

a. Cumulative dose contributions for the current calendar quarter and current calendar year for iodine-131, iodine-133, tritium, and radionuclides in particulate form with half-lives greater than 8 days shall be determined in accordance with the methodology and parameters contained in Section 4.2.2 at least once per 31 days.

33 ODCM Rev. 25

4.2.2 Implementation of the Requirement The organ dose to an individual from 1-131, 1-133, tritium, and all radionuclides in particulate form, with half-lives greater than eight days, in gaseous effluents released to unrestricted areas from each reactor unit is calculated using the following expressions:

Dou = (3.17E-08) 1i [-k (Rik Wk) (Qi)] (4-3)

Where:

Dou the total accumulated organ dose from gaseous effluents for a particular unit, to a MEMBER OF THE PUBLIC, in mrem, at the SITE BOUNDARY or at the controlling location.

Qi = the quantity of radionuclide i, in 1iCi, released in gaseous effluents from a particular unit.

Rik = the dose factor for each identified radionuclide i, for pathway k (for the inhalation pathway in mrem/yr per ýiCi/m 3 and for the food and ground plane pathways in m2 - mrem/yr per jLCi/sec, except H-3, which has units of mrem/yr per jiCi/m 3) at the controlling location. The Rik's for each age group are given in Tables 4-1 through 4-15.

3.17E-08 = the inverse of seconds per year (yr/sec).

Wk = the highest, annual average dispersion or deposition parameter for the particular Unit, used for estimating the dose at the site boundary or to a MEMBER OF THE PUBLIC at the controlling location for the particular Unit. Optionally, the highest value may be used for any Unit calculation.

= (X/Q)UNIT, in sec/m 3 for the inhalation pathway and for all tritium calculations, for organ dose at the site boundary, from Table 3-2.

=7.47E-06 from Unit I

=7.90E-06 from Unit 2

=8.91E-06 from Unit 3

= (X/Q)UNIT, in sec/m 3 for the inhalation pathway and for all tritium calculations, for organ dose at the controlling location, from Table 4-16, 4-17 or 4-18.

=2.92E-06 from Unit 1

=2.19E-06 from Unit 2

=2.31E-06 from Unit 3 (D/Q)UNIT, in m-2 , for the food and ground plane pathways, for organ dose at the site boundary, from Table 3-2.

=1.19E-08 from Unit I

=1.34E-08 from Unit 2

=1.67E-08 from Unit 3 34 ODCM Rev. 25

= (D/Q)UNIT, in m-2 , for the food and ground plane pathways, for organ dose at the controlling location, from Table 4-16, 4-17, or 4-18.

=3.25E-09 from Unit I

=3.88E-10 from Unit 2

=4.21E-10 from Unit 3 Residences, vegetable gardens and milk animals located within 5 miles of the site will be identified during the annual land use census. The controlling pathway and location will be identified and will be used for all MEMBER OF THE PUBLIC dose evaluations.

The Ri values were calculated in accordance with the methodologies in NUREG-0133. The following site specific information was used to calculate Ri:

Value The length of the grazing season for milk animals (fs).

Ref. ER-OL, Section 2.1.3.4.3 0.75 The length of the grazing season for meat animals (Q.

Ref. ER-OL, Section 2.1.3.4.4 0.25 The fraction of daily feed derived from pasture while on pasture for milk animals (fp).

Ref. ER-OL, Section 2.1.3.4.3 0.35 The fraction of daily feed derived from pasture while on pasture for meat animals (fp).

Ref. ER-OL, Section 2.1.3.4.3 0.05 The fraction of year vegetables are grown, (fl) approximation.

Ref. ER-OL, Section 2.1.3.4, Table 2.1-8. 0.667 The annual absolute humidity (g/m 3), H, Ref. UFSAR, Table 2.3-16 6 35 ODCM Rev. 25

4.3 Requirements

Gaseous Radwaste Treatment The GASEOUS RADWASTE SYSTEM and the VENTILATION EXHAUST TREATMENT SYSTEM shall be used to reduce radioactive materials in gaseous waste prior to their discharge when the projected gaseous effluent air doses due to gaseous effluent releases, from each reactor unit, from the site (see Figure 6-4 and Figure 6-5) when averaged over 31 days, would exceed 0.2 mrad for gamma radiation and 0.4 mrad for beta radiation. The VENTILATION EXHAUST TREATMENT SYSTEM shall be used to reduce radioactive materials in gaseous waste prior to their discharge when the projected doses due to gaseous effluent releases, from each reactor unit, to areas at and beyond the SITE BOUNDARY (see Figure 6-4 and Figure 6-5) when averaged over 31 days would exceed 0.3 mrem to any organ of a MEMBER OF THE PUBLIC.

Applicability: At all times:

Action:

With radioactive gaseous waste being discharged without treatment and in excess of the above limits, prepare and submit to the Commission within 30 days, a Special Report which includes the following information:

a. Identification of the inoperable equipment or subsystems and the reason for inoperability,
b. Action(s) taken to restore the inoperable equipment to OPERABLE status, and
c. Summary description of action(s) taken to prevent a recurrence.

4.3.1 Surveillance Requirements

a. Doses due to gaseous releases from the site shall be projected at least once per 31 days, in accordance with the methodology and parameters in Section 4.3.2.

36 ODCM Rev. 25

4.3.2 Implementation of the Requirement Where possible, consideration for expected operational evolutions (i.e., outages, etc.) should be taken in the dose projections.

Dose Projection - Noble Gases The air dose, in mrads is determined using the methodology described in Section 4.1.2 of this manual. This information is used to determine an air dose projection for the next 31 days using the following equations:

For gamma radiation:

31day7 = D7+/- CD . (4-4)

For beta radiation:

31 day = DP D13+CDP (4-5)

Where:

Dy = the total gamma air dose in mrads at the site boundary due to noble gases released in gaseous effluents for the previous 31 days.

DP = the total beta air dose in mrads at the site boundary due to noble gases released in gaseous effluents for the previous 31 days.

CDy = any current or projected change in gamma air dose, in mrads, due to noble gases released in gaseous effluents, which could have a significant impact on 31 dayy.

CDP3 = any current or projected change in beta air dose, in mrads, due to noble gases released in gaseous effluents, which could have a significant impact on 31 day P3.

When performing the 31 day dose projection using the Gaseous Radioactive Effluent Tracking System (GRETS), Dy and DP3 will include the dose from any release permits that fall within the selected 31 day time period. As a result, the actual dose projection will often be based on the accumulated dose for a time period greater than 31 days.

37 ODCM Rev. 25

Dose Projection 131. 1-133. tritium, and all radionuclides in particulate form with half-lives greater than eight days The organ dose, in mrem, is determined using the methodology described in Section 4.2.2 of this manual. This information is used to determine an organ dose projection for the next 31 days using the following equation:

31day = D++/- CD, (4-6)

Where:

Do = the total organ dose due to 1-131, 1-133, tritium, and all radionuclides in particulate form with half-lives greater than eight days in morem, released in gaseous effluents for the previous 31 days.

CDo = any current or projected change in organ dose, in mrem, which could have a significant impact on 31 day0 .

When performing the 31 day dose projection using the Gaseous Radioactive Effluent Tracking System (GRETS), D, will include the dose from any release permits that fall within the selected 31 day time period. As a result, the actual dose projection will often be based on the accumulated dose for a time period greater than 31 days.

38 ODCM Rev. 25

TABLE 4-1 Ri DOSE CONVERSION FACTORS FOR THE GROUND PLANE PATHWAY NUCLIDE T. BODY SKIN H-3 O.OOE+00 0.OOE+00 CR-51 4;66E+06 5.5 1E+06 MN-54 1.39E+09 1.63E+09 FE-59 2.73E+08 3.21E+08 CO-58 3.79E+08 4.44E+08 CO-60 2.15E+10 2.53E+10 ZN-65 7.47E+08 8.59E+08 SR-89 2.16E+04 2.5 1E+04 SR-90 0.OOE+00 0.OOE+00 ZR-95 2.45E+08 2.84E+08 SB-124 5.98E+08 6.90E+08 1-131 1.72E+07 2.09E+07 1-133 2.45E+06 2.98E+06 CS-134 6.86E+09 8.OOE+09 CS-137 1.03E+10 1.20E+10 BA- 140 2.05E+07 2.35E+07 CE- 141 1.37E+07 1.54E+07 CE- 144 6.95E+07. 8.04E+07 39 ODCM Rev. 25

TABLE 4-2 Ri DOSE CONVERSION FACTORS FOR THE VEGETATION PATHWAY - ADULT RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 O.OOE+00 2.87E+03 2.87E+03 2.87E+03 2.87E+03 2. 87E+03 2.87E+03 CR-51 0.OOE+00 0.OOE+00 4.OOE+04 2.39E÷04 8.82E+03 5.3 1E+04 1.01E+07 MN-54 0.OOE+00 2.97E+08 5.66E+07 0.OOE+00 8.83E+07 O.OOE+00 9.09E+08 FE-59 1.14E+08 2.68E+08 1.03E+08 0.OOE+00 0.OOE+00 7.49E+07 8.93E+08 CO-58 0.OOE+00 2.84E+07 6.38E+07 O.OOE+00 0.OOE+00 0.OOE+00 5.76E+08 CO-60 0.OOE+00 1.59E+08 3.51 E+08 0.OOE+00 0.OOE+00 0.OOE+00 2.99E+09 ZN-65 3.OOE+08 9.56E+08 4.32E+08 0.OOE÷00 6.39E+08 0.OOEO00 6.02E+08 SR-89 9.08E+09 0.OOE+00 2.61E+08 O.OOE+00 O.OOE+00 0.OOE+00 1.46E+09 SR-90 5.76E+11 0.OOE+00 1.41E+ll O.OOE+00 0.OOE+00 O.OOE+00 1.67E+10 ZR-95 1.08E+06 3.47E+05 2.35E+05 0.OOE+O0 5.45E+05 O.OOE+00 1.1 OE+09 SB- 124 9.53E+07 1.80E+06 3.78E+07 2.3 1E+05 O.OOE+00 7 .42E+07 2.7 1E+09 1-131 5.49E+07 7.85E+07 4.50E+07 2.57E+10 1.35E+08 0.OOE+00 2.07E+07 1-133 1.39E+06 2.42E+06 7.38E+05 .3.56E+08 4.22E+06 O.OOE+00 2.17E+06 CS- 134 4.44E+09 1.06E+ 10 8.64E+09 0.OOE+00 3.42E+09 1.13E+09 1.85E+08 CS-137 6.06E+09 8.29E+09 5.43E+09 O.OOE+00 2.8 1E+09 9.36E+08 1.60E+08 BA- 140 9.43E+07 1.19E+05 6.18E+06 0.OOE+00 4.03E+04 6.78E+04 1.94E+08 CE-141 1.73E+05 1.17E+05 1.33E+04 O.OOE÷00 5.44E+04 0.OOE÷00 4,48E+08 CE-144 3.12E+07 1.30E+07 1.67E+06 0.OOE+00 7.73E+06 0.OOE+O0 1.05E+10 40 ODCM Rev. 25

TABLE 4-3 Ri DOSE CONVERSION FACTORS FOR THE VEGETATION PATHWAY - TEEN RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 0.OOE+00 3.36E+03 3.36E+03 3.3 6E+03 3.36E+03 3.36E+03 3.36E+03 CR-51 0.00E+00 0.00E+00 5.60E+04 3.11 E+04 1.23E+04 7.99E+04 9.41E+06 MN-54 0.00E+00 4.41 E+08 8.74E+07 0.OOE+00 1.31E+08 0.00E+00 9.04E+08 FE-59 1.69E+08 3.94E+08 1.52E+08 0.OOE+00 0.00E+00 1.24E+08 9.3 1E+08 CO-58 0.OOE+00 4.16E+07 9.59E+07 0.OOE+00 0.00E+00 0.OOE+00 5.74E+08 CO-60 0.00E+00 2.42E+08 5.45E+08 0.00E+00 0.00E+00 0.OOE+00 3.15E+09 ZN-65 4.11E+08 1.43E+09 6.65E+08 0.00E+00 9.12E+08 0.00E+00 6.04E+08 SR-89 1.43E+10 O.OOE+00 4.10E+08 0.00E+00 0.00E+00 0.00E+00 1.70E+09 SR-90 7.30E+1 1 0.OOE+00 1.80E+11 0.OOE+00 0.00E+00 0.OOE+00 2.05E+10 ZR-95 1.64E+06 5.17E+05 3.56E+05 O.OOE+00 7.60E+05 0.00E+00 1.19E+09 SB-124 1.47E+08 2.70E+06 5.73E+07 3.33E+05 0.00E+00 1.28E+08 2.96E+09 1-131 5.29E+07 7.41E+07 3.98E+07 2.16E+ 10 1.28E+08 0.OOE+00 1.47E+07 1-133 1.29E+06 2.19E+06 6.68E+05 3.06E+08 3.84E+06 0.00E+00 1.66E+06 CS- 134 6.90E+09 1.62E+10 7.53E+09 0.00E+00 5.16E+09 1.97E+09 2.02E+08 CS-137 9.86E+09 1.31E+10 4.57E+09 0.OOE+00 4.46E+09 1.73E+09 1.87E+08 BA-140 1.07E+08 1.3 1E+05 6.88E+06 0.00E+00 4.44E+04 8.80E+04 1.65E+08 CE-141 2.61E+05 1.74E+05 2.OOE+04 0.00E+00 8.19E+04 0.00E+00 4.98E+08 CE- 144 5.11E+07 2.12E+07 2.75E+06 0.00E+00 1.26E+07 0.OOE+00 1.29E+110 41 ODCM Rev. 25

TABLE 4-4 Ri DOSE CONVERSION FACTORS FOR THE VEGETATION PATHWAY - CHILD RECEPTOR NUCLIDES BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 0.OOE+O0 5.23E+03 5.23E+03 ,5.23E+03 5.23E+03 5.23E+03 5.23E+03 CR-51 0.OOE+00 0.OOE+00 1.08E+05 6.02E+04 1.64E+04 1.1OE+05 5.75E+06 MN-54 0.OOE+00 6.49E+08 1.73E+08 0.OOE+00 I1.82E+08 0.OOE+00 5.45E+08 FE-59 3.79E+08 6.13E+08 3.05E+08 0.OOE+00 0.OOE+00 1.78E+08 6.38E+08 CO-58 0.OOE+00 6.21E+07 1.90E+08 0.OOE+00 0.OOE+00 0.OOE+00 3.62E+08 CO-60 0.OOE+0O 3.70E+08 1.09E+09 0.OOE+/-0O 0.OOE+00 0.OOE+00 2.05E+09 ZN-65 7.93E+08 2.11E+09 1.31 E+09 0.OOE+/-00 1.33E+09 0.OOE+00 3.71 E+08 SR-89 3.44E+ 10 0.OOE+00 9.83E+08 0.OOE+00 0.OOE+00 0.OOE+00 1.33E+09 SR-90 1.22E+12 0.OOE+00 3.09E+1 I O.OOE+00 0.OOE+00 0.OOE+00 1.64E+10 ZR-95 3.72E+06 8.17E+05 7.27E+05 0.OOE+00 1. 17E+06 0.OOE+00 8.52E+08 SB- 124 3.38E+08 4.39E+06 1.19E+08 7.47E+05 0.OOE+00 1.88E+08 2.12E+09 1-131 9.95E+07 1.00E+08 5:68E+07 3.31 E+10 1.64E+08 0.OOE+00 8.90E+06 1-133 *2.36E406 2.91E+06 '1.IOE+06 5.41 E+08 4.85E+06 0.OOE+00 1.17E+06 CS- 134 1.57E+10 2.57E+10 5.43E+09 0,00E+00 7.98E+09 2.86E+09 .1.39E+08 CS-137 2.34E+10 2.24E+10 3.31 E+09 0.OOE+O0 7.3 1IE+09 2.63E+09 1.40E+08 BA-140 2.20E+08 1.93E+05 1.28E+07 0.OOE+00 6.27E+04 1.15E+05 1.11E+08 CE-141 6.15E+05 3.07E+05 4.55E+04 0.OOE+00 1.34E+05 0.OOE+00 3.83E+08 CE- 144 1.24E+08 3.89E+07 6.62E+06 0.OOE+00 2.15E+07 0.OOE+00 1.01E+10 42 ODCM Rev. 25

TABLE 4-5 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MEAT PATHWAY - ADULT RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 O.OOE+00 4.33E+02 4.33E+02 4.33E+02 4.33E+02 4.33E+02 4.33E+02 CR-51 O.OOE+00 O.OOE+00 3.44E+02 2.06E+02 7.58E+01 4.57E+02 8.65E+04 MN-54 O.OOE+00 2.71 E+06 5.18E+05 O.OOE+00 8.08E+05 O.OOE+00 8.31E+06 FE-59 2.60E+07 6.1 lE+07 2.34E+07 O.OOE+00 O.OOE+00 1.71E+07 2.04E+08 CO-58 O.OOE+00 2.84E+06 6.36E+06 O.OOE+00 O.OOE+00 O.OOE+00 5.75E+07 CO-60 O.OOE+00 2.61E+07 5.76E+07 O.OOE+00 O.OOE+00 O.OOE+00 4.90E+08 ZN-65 9.97E+07 3.17E+08 1.43E+08 O.OOE+00 2.12E+08 O.OOE+00 2.OOE+08 SR-89 3.41E+07 O.OOE+00 9.79E+05 O.OOE+00 O.OOE+00 O.OOE+00 5.47E+06 SR-90 4.43E+09 O.OOE-00 1.09E+09 O.OOE+00 O.OOE+00 O.OOE+00 1.28E+08 ZR-95 2.68E+05 8.58E+04 5.8 1E+04 O.OOE+00 1.35E+05 O.OOE+00 2.72E+08 SB-124 2.67E+06 5.05E+04 1.06E+06 6.48E+03 O.OOE+00 2.08E+06 7.59E+07 1-131 1.36E+05 1.94E+05 1.11E+05 6.37E+07 3.33E+05 O.OOE+00 5.13E+04 1-133 4.56E-03 7.94E-03 2.42E-03 l. 17E+00 1.39E-02 O.OOE+00 7.14E-03 CS- 134 2.17E+08 5.17E+08 4.23E+08 O.OOE+00 1.67E+08 5.56E+07 9.05E+06 CS-137 '3.11 E+08 4.25E+08 2.78E+08 O.OOE+00 1.44E+08 4.79E+07 8.22E+06 BA-140 4.35E+05 5.46E+02 2.85E+04 O.OOE+00 1.86E+02 3.13E+02 8.95E+05 CE-141 8.87E+02 6.OOE+02 6.80E+01 O.OOE+00 2.79E+02 O.OOE+00 2.29E+06 CE-144 4.23E+05 1.77E+05 2.27E+04 O.OOE+00 1.05E+05 O.OOE+00 1.43E+08 43 ODCM Rev. 25

TABLE 4-6 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MEAT PATHWAY - TEEN RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 O.OOE+00 2.58E+02 2.58E+02 2.58E+02 2.58E+02 2.58E+02 2.58E+02 CR-51 0.OOE+00 0.OOE+00 2.75E+02 1.53E+02 6.03E+01 3.93E+02 4.62E+04 MN-54 0.OOE+00 2.07E+06 4.1 1E+05 0.OOE+00 6.18E+05 0.OOE+00 4.25E+06 FE-59 2.08E+07 4.85E+07 1.87E+07 0.OOE+00 0.OOE÷00 1.53E+07 1.15E+08 CO-58 0.00E+00 2.19E+06 5.04E+06 0.OOE+00 0.OOE+00 0.OOE+00 3.02E+07 CO-60 0.OOE+00 2.03E+07 4.56E+07 0.OOE+00 0.OOE+00 0.OOE+00 2.64E+08 ZN-65 7.01E+07 2.43E+08 1.14E+08 0.OOE+00 1.56E+08 0.OOE+00 1.03E+08 SR-89 2.88E+07 0.OOE+00 8.24E+05 0.OOE+00 0.OOE+00 0.OOE+00 3.43E+06 SR-90 2.87E+09 0.OOE+00 7.08E+08 0.OOE+00 0.OOE+00 0.OOE+00 8.05E+07 ZR-95 2.14E+05 6.76E+04 4.65E+04 0.OOE+00 9.93E+04 0.OOE+00 1.56E+08 SB-124 2.18E+06 4.02E+04 8.52E+05 4.95E+03 0.OOE+00 1.91 E+06 4.40E+07 1-131 1.13E+05 1.58E+05 8.49E+04 4.61 E+07 2.72E+05 0.OOE+00 3.13E+04 1-133 3.82E-03 6.48E-03 1.98E-03 9.04E-01 1. 14E-02 0.OOE+00 4.90E-03 CS-134 1.73E+08 4.07E+08 1.89E+08 0.OOE+00 1.29E+08 4.94E+07 5.06E+06 CS-137 2.58E+08 3.43E+08 1.20E+08 0.OOE+00 1. 17E+08 4.54E+07 4.88E+06 BA- 140 3.59E+05 4.40E+02 2.3 1E+04 0.OOE+00 1.49E+02 2.96E+02 5.54E+05 CE-141 7.45E+02 4.97E+02 5.71E+01 0.OOE+00 2.34E+02 0.OOE+00 1.42E+06 CE- 144 3.56E+05 1.47E+05 1.91E+04 0.OOE+00 8.,80E+04 0.OOE+00 8.96E+07 44 ODCM Rev. 25

TABLE 4-7 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MEAT PATHWAY - CHILD RECEPTOR NUCLIDES BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 O.OOE+00 3.12E+02 3.12E+02 3.12E+02 3.12E+02 3.12E+02 3.12E+02 CR-51 O.OOE+00 O.OOE+00 4.29E+02 2.38E+02 6.5 1E+O1 4.35E+02 2.28E+04 MN-54 O.OOE+00 2.37E+06 6.3 1E+05 O.OOE+00 6.64E+05 O.OOE+00 1.99E+06 FE-59 3.68E+07 5.96E+07 .2.97E+07 O.OOE+00 O.OOE+00 1.73E+07 6.20E+07 CO-58 O.OOE+00 2.55E+06 7.82E+06 O.OOE+00 O.OOE+00 O.OOE+00 1.49E+07 CO-60 O.OOE+00 2.40E+07 7.09E+07 O.OOE+00 O.OOE+00 O.OOE+00 1.33E+08 ZN-65 1.05E+08 2.80E+08 1.74E+08 O.OOE+00 1.77E+08 O.OOE+00 4.92E+07 SR-89 5.45E+07 O.OOE+00 1.56E+06 O.OOE+00 O.OOE+00 O.OOE+00 2.11E+06 SR-90 3.70E+09 O.OOE+00 9.39E+08 O.OOE+00 O.OOE+00 O.OOE+00 4.99E+07 ZR-95 3.81E+05 8.36E+04 7.45E+04 O.OOE+00 1.20E+05 O.OOE+00 8.73E+07 SB- 124 3.95E+06 5.12E+04 1.38E+06 8.72E+03 O.OOE+00 2.19E+06 2.47E+07 1-131 2.09E+05 2.11E+05 1.20E+05 6.96E+07 3.46E+05 O.OOE+00 1.87E+04 1-133 7.09E-03 8.77E-03 3.32E-03 1.63E+00 1.46E-02 O.OOE+00 3.53E-03 CS- 134 3.05E+08 5.OOE+08 1.06E+08 O.OOE+00 1.55E+08 5.56E+07 2.70E+06 CS-137 4.75E+08 4.55E+08 6.71E+07 O.OOE+00 1.48E+08 5.33E+07 2.85E+06 BA-140 6.63E+05 5.81E+02 3.87E+04 O.OOE+00 1.89E+02 3.46E+02 3.36E+05 CE- 141 1.40E+03 6.99E+02 1.04E+02 O.OOE+00 3.07E+02 O.OOE+00 8.72E+05 CE- 144 6.72E+05 2.11 E+05 3.58E+04 O.OOE+00 1.17E+05 O.OOE+00 5.49E+07 45 ODCM Rev. 25

TABLE 4-8 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MILK PATHWAY - ADULT RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 0.OOE+00 1.02E+03 1.02E+03 1.02E+03 1.02E+03 1.02E+03 1.02E+03 CR-51 0.OOE+00 0.OOE+00 8.28E+03 4.95E+03 1.82E+03 1.1 E+04 2.08E+06 MN-54 0.OOE+00 3.99E+06 7.6 1E+05 O.OOE+00 1.19E+06 0.OOE+00 1.22E+07 FE-59 9.69E+06 2.28E+07 8.73E+06 0.OOE+O0 0.OOE+00 6.36E+06 7.59E+07 CO-58 0.OOE+00 1.74E+06 3.90E+06 O.OOE+00 0.00E+00 0.OOE+00 3.53E+07 CO-60 0.OOE+00 8.41E+06 1.85E+07 0.OOE+00 0.OOE+00 0.OOE+00 1.58E+08 ZN-65 6.34E+08 2.02E+09 9.12E+08 0.0E+00 1.35E+09 O.OOE+00 1.27E+09 SR-89 4.90E+08 0.OOE+00 1.41E+07 O.OOE+00 0.OOE+00 0.OOE+00 7.86E+07 SR-90 2.43E+10 0.OOE+00 5.96E+09 0.00E+00 0.OOE+00 0.OOE÷00 7.02E+08 ZR-95 3.39E+02 1.09E+02 7.37E+01 0.OOE+00 1.71E+02 0.OOE+00 3.45E+05 SB- 124 9.11E+06 , .72E+05 3.61E+06 2.2 1E+04 0.OOE+00 7.09E+06 2.59E+08 1-131 7.77E+07 1.11E+08 6.37E+07 3.64E+ 10 1.91E+08 0.OOE+00 2.93E+07 1-133 1.02E+06 1.77E+06 5.39E+05 2.60E+08 3.08E+06 0.OOE+00 1.59E+06 CS- 134 2.83E+09 6.73E+09 5.50E+09 0.OOE+00 2.18E+09 7.23E+08 1.18E+08 CS-137 3.83E+09 5.24E+09 3.43E+09 0.OOE+00 1.78E+09 5.9 1E+08 1.01E+08 BA-140 7.11 E+06 8.93E+03 4.66E+05 0.OOE+00 3.04E+03 5.11 E+03 1.46E+07 CE-141 8.73E+03 5.90E+03 6.70E+02 0,00E+00 2.74E+03 0.OOE+00 2.26E+07 CE- 144 1.01E+06 4.21E+05 5.4 1E+04 0.OOE+00 2.50E+05 0.OOE+00 3.41E+08 46 ODCM Rev. 25

TABLE 4-9 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MILK PATHWAY - TEEN RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 0.OOE+00 1.33E+03 1.33E+03 1.33E+03 1.33E+03 1.33E+03 1.33E+03 CR-51 0.OOE+00 0.OOE+00 1.45E+04 8.03E+03 3.17E+03 2.06E+04 2.43E+06 MN-54 0.OOE+00 6.64E+06 1.32E+06 0.OOE÷00 1.98E+06 0.OOE+00 1.36E+07 FE-59 1.69E+07 3.95E+07 1.52E+07 0.OOE+00 0.OOE+00 1.24E+07 9.33E+07 CO-58 0.OOE+00 2.93E+06 6.76E+06 0.OOE+00 O.OOE+00 0.OOE+00 4.04E+07 CO-60 0.OOE+00 1.42E+07 3.21E+07 0.OOE+00 O.OOE+00 O.OOE+00 1.86E+08 ZN-65 9.74E+08 3.38E+09 1.58E+09 0.OOE+00 2.17E+09 0.OOE+00 1.43E+09 SR-89 9.03E+08 O.OOE+00 2.59E+07 0.OOE+00 0.OOE+00 O.OOE+00 1.08E+08 SR-90 3.43E+10 O.OOE+00 8.48E+09 0.OOE+00 0.OOE+00 O.OOE+00 9.64E+08 ZR-95 5.94E+02 1.87E+02 1.29E+02 O.OOE+00 2.75E+02 0.OOE+00 4.32E+05 SB-124 1.62E+07 2.99E+05 6.34E+06 3.69E+04 0.OOE+00 1.42E+07 3.27E+08 1-131 1.41E+08 1.98E+08 1.06E+08 5.76E+10 3.40E+08 0.OOE+00 3.91E+07 1-133 1.86E+06 3.15E+06 9.60E+05 4.39E+08 5.52E+06 0.OOE+00 2.38E+06 CS- 134 4.91E+09 1.16E+10 5.36E+09 O.OOE+00 3.67E+09 1.40E+09 1.44E+08 CS- 137 6.95E+09 9.24E+09 3.22E+09 0.OOE+00 3.15E+09 1.22E+09 1.32E+08 BA- 140 1.28E+07 1.57E+04 8.27E+05 0.OOE+00 5.33E+03 1.06E+04 1.98E+07 CE-141 1.60E+04 1.07E+04 1.23E+03 0.OOE+O0 5.03E+03 0.OOE+00 3.06E+07 CE-144 1.86E+06 7.68E+05 9.97E+04 0.OOE+00 4.59E+05 0.OOE+00 4.67E+08 47 ODCM Rev. 25

TABLE 4-10 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MILK PATHWAY - CHILD RECEPTOR NUCLIDES BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 O.OOE+00 2.09E+03 2.09E+03 2.09E+03 2.09E+03 2.09E+03 2.09E+03 CR-51 O.OOE+00 O.OOE+00 2.95E+04 1.64E+04 4.47E+03 2.99E+04 1.56E+06 MN-54 O.OOE+00 9.94E+06 2.65E+06 O.OOE+00 2.79E+06 O.OOE+00 8.34E+06 FE-59 3.92E+07 6.35E+07 3.16E+07 O0.0E+00 O.OOE+00 1.84E+07 6.61E+07 CO-58 O.OOE+00 4.48E+06 1.37E+07 0.00E+00 O.OOE+00 O.OOE+00 2.61E+07 CO-60 O.OOE+00 2.21E+07 6.52E+07 O.OOE+00 O.OOE+00 O.OOE+00 1.23E+08 ZN-65 1.91E+09 5.09E+09 3.17E+09 O.OOE+00 3.21E+09 O.OOE+00 8.95E+08 SR-89 2.23E+09 O.OOE+00 6.38E+07 O.OOE+00 O.OOE+00 O.OOE+00 8.65E+07 SR-90 5.80E+ 10 O.OOE+00 1.47E+10 O.OOE+00 O.OOE+00 O.OOE+00 7.81E+08 ZR-95 1.38E+03 3.03E+02 2.70E+02 O.OOE+00 4.34E+02 O.OOE+00 3..16E+05 SB-124 3.84E+07 4.99E+05 1.35E+07 8.49E+04 O.00E+00 2.13E+07 2.41E+08 1-131 3.42E+08 3.44E+08 1.96E+08 1.14E+l1 5.65E+08 O.OOE+00 3.06E+07 1-133 4.51E+06 5.57E+06 2.11E+06 1.04E+09 9.29E+06 O.OOE+00 2.25E+06 CSA134 1.13E+10 1.86E+10 3.92E+09 O.OOE+00 5.76E+09 2.07E+09 1.00E+08 CS-137 1.67E+10 1.60E+10 2.36E+09 O.OOE+00 5.22E+09 -1.88E+09 1.00E+08 BA-140 3.1OE+07 2.71E+04 1.81E+06 O.OOE+00 8.83E+03 1.62E+04 1.57E+07 CE-141 3.94E+04 1.97E+04 2.92E+03 O.OOE+00 8.62E+03 O.OOE+00 2.45E+07 CE-144 4.57E+06 1.43E+06 2.44E+05 O.OOE+00 7.94E+05 O.OOE+00 3.74E+08 48 ODCM Rev. 25

TABLE 4-11 Ri DOSE CONVERSION FACTORS FOR THE GRASS-COW-MILK PATHWAY - INFANT RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 O.OOE+00 3,18E+03 3.18E+03 3.18E+03 3.18E+03 3,18E+03 3.18E+03 CR-51 0.OOE+00 0.OOE+00 4.67E+04 3.05E+04 6.66E+03 5.93E+04 1.36E+06 MN-54 0.OOE+00 .1.85E+07 4,19E+06 0.OOE+00 4.1OE+06 0.OOE+00 6.79E+06 FE-59 7.32E+07 1.28E+08 5.04E+07 O.OOE+00 O.OOE+00 3.78E+07 6.11E+07 CO-58 0.OOE+00 8.96E+06 2.23E+07 0.OOE+00 0.OOE+00 O.OOE+00 2..23E+07 CO-60 O.OOE+00 4.52E+07 1.07E+08 0.OOE+00 0.OOE+00 0.OOE+00 1.07E+08 ZN-65 2.57E+09 8.81E+09 4.06E+09 0.OOE+00 4.27E+09 0.OOE+00 7.44E+09 SR-89 4.25E+09 O.OOE+00 1.22E+08 0.OOE+00 0.OOE+00 O.OOE+00 8.74E+07 SR-90 6.31E+10 0.OOE+00 1.61E+10 0.OOE+00 0.OOE+00 O.OOE+00 7.88E+08 ZR-95 2.45E+03 5.97E+02 4.23E+02 0.OOE+00 6.43E+02 0.OOE+00 2.97E+05 SB-124 7.4 1E+07 1.09E+06 2.30E+07 1.97E+05 0.OOE+00 .4.64E+07 2.29E+08 1-131 7.14E+08 8.42E+08 3.70E+08 2.77E+1 1 9.83E+08 0.OOE+00 3.OOE+07 1-133 9.52E+06 1.39E+07 4.06E+06 2.52E+09 1.63E+07 0.OOE+00 2.35E+06 CS- 134 1.82E+10 3.40E+10 3.44E+09 0.OOE+00 8.76E+09 3.59E+09 9.24E+07 CS- 137 2.67E+10 3.13E+10 2.22E+09 0.OOE+00 8.39E+09 3.40E+09 9.78E+07 BA-140 6.37E+07 6.37E+04 3.28E+06 0.OOE+00 1.51 E+04 3.91 E+04 1.57E+07 CE-141 7.81 E+04 4.77E+04 5.61E+03 0.OOE+00 1.47E+04 0.OOE+00 2.46E+07 CE-144 , 6.55E+06 2.68E+06 *3.67E+05 0.OOE+00 1.08E+06 0.OOE+00 3.76E+08 49 ODCM Rev. 25

TABLE 4-12 Ri DOSE CONVERSION FACTORS FOR THE INHALATION PATHWAY - ADULT RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 0.OOE+00 1.26E+03 1.26E+03 1.26E+03 1.26E+03 1.26E+03 1.26E+03 CR-51 0.OOE+00 0.OOE+00 1.00E+02 5.95E+01 2.28E+01 1.44E+04 3.32E+03 MN-54 0.OOE+00 3.96E+04 6.30E+03 0.OOE+O0 9. 84E+03 1.40E+06 7.74E+04 FE-59 1.18E+04 2.78E+04 1.06E+04 0.OOE+00 0.OOE+00 1.02E+06 1.88E+05 CO-58 0.OOE+00 1.58E+03 2.07E+03 O.OOE+00 0.OOE+00 9.28E+05 1.06E+05 CO-60 O.OOE+00 1.15E+04 1.48E+04 O.OOE+00 0.OOE+00 5.97E+06 2.85E+05 ZN-65 3.24E+04 1.03E+05 4.66E+04 0.OOE+00 6,90E+04 8.64E+05 5.34E+04 SR-89 3.04E+05 0.OOE+00 8.72E+03 0.OOE+00 0.OOE+00 1.40E+06 3.50E+05 SR-90 9.92E+07 0.OOE+00 6.1OE+06 0.OOE÷00 0.OOE+00 .9.60E+06 7.22E+05 ZR-95 1.07E+05 3.44E+04 2.33E+04 0.OOE+O0 5.42E+04 1.77E+06 1.50E+05 SB- 124 3.12E+04 5.89E+02 1.24E+04 7.55E+01 0.OOE+O0 2.48E+06 4.06E+05 1-131 2.52E+04 3.58E+04 2.05E+04 1.19E+07 6.13E+04 0.OOE+00 6.28E+03 1-133 8.64E+03 1.48E+04 4.52E+03 2.15E+06 2.58E+04 0.OOE+00 8.88E+03 CS-134 3.73E+05 8.48E+05 7.28E+05 0.OOE+00 2.87E+05 9.76E+04 1.04E+04 CS-137 4.78E+05 6.21E+05 4.28E+05 0.OOE+00 2.22E+05 7.52E+04 8.40E+03 BA-140 3.90E+04 4.90E+01 2.57E+03 0.OOE+00 .1.67E+01 1.27E+06 2.18E+05 CE- 141 1.99E+04 1.35E+04 .1.53E+03 0.OOE+00 6.26E+03 3.62E+05 1.20E+05 CE-144 3.43E+06 1.43E+06 1.84E+05 0.OOE+00 8.48E+05 7.78E+06 8.16E+05 50 ODCM Rev. 25

TABLE 4-13 Ri DOSE CONVERSION FACTORS FOR THE INHALATION PATHWAY - TEEN RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI.

H-3 O.OOE+00 1.27E+03 1.27E+03 1.27E+03 1.27E+03 1.27E+03 1.27E+03 CR-51 O.OOE+00 0.OOE+00 1.35E+02 7.50OE+01I 3.07E+01 2. 1OE+04 3.OOE+03 MN-54 0.OOE+00 5.1 1E+04 8.40E+03 O.OOE+O0 1.27E+04 1.98E+06 6.68E+04 FE-59 1.59E+04 3.70E+04 1.43E+04 0.OOE+00 0.OOE+00 1.53E+06 1.78E+05 CO-58 0.OOE+00 2.07E+03 2.78E+03 O.OOE+00 0.OOE+00 1.34E+06 9.52E+04 CO-60 0.OOE+00 1.51 E+04 1.98E+04 0.OOE+00 0.OOE+00 8.72E+06 2.59E+05 ZN-65 3.86E+04 1.34E+05 6.24E+04 0.OOE+00 8.64E+04 1.24E+06 4.66E+04 SR-89 4.34E+05 0.OOE+00 1.25E+04 0.OOE+00 0.OOE+00 2.42E+06 3.7 1E+05 SR-90 1.08E+08 0.OOE+00 6.68E+06 0.OOE+00 0.OOE+00 1.65E+07 7.65E+05 ZR-95 1.46E+05 4.58E+04 3.15E+04 0.OOE+00 6.74E+04 2.69E+06 1.49E+05 SB- 124 4.30E+04 7.94E+02 1.68E+04 9.76E+01 O.OOE+00 3.85E+06 3.98E+05 1-131 3.54E+04 4.91E+04 2.64E+04 1.46E+07 8.40E+04 0.00E+00 6.49E+03 1-133 1.22E+04 2.05E+04 6.22E+03 2.92E+06 3.59E+04 O.OOE+00 1.03E+04 CS- 134 *1.46E+05 5.02E+05 1.13E+06 5.49E+05 0.OOE+O0 3.75E+05 9.76E+03 CS-137 6.70E+05 8.48E+05 3.11E+05 0.OOE+00 3.04E+05 1.21E+05 8.48E+03 BA-140 5.47E+04 6.70E+01 3.52E+03 0.OOE+00 2.28E+0l 2.03E+06 2.29E+05 CE-141 2.84E+04 1.90E+04 2..17E+03 O.OOE+00 8.88E+03 6.14E+05 1.26E+05 CE- 144 4.89E+06 2.02E+06 2.62E+05 O.OOE+00 1.21E+06 1.34E+07 8.64E+05 51 ODCM Rev. 25

TABLE 4-14 Ri DOSE CONVERSION FACTORS FOR THE INHALATION PATHWAY - CHILD RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 0.OOE+00 1.12E+03 1.12E+03 1.12E+03 1.12E+03 1.12E+03 1.12E+03 CR-51 0.OOE+00 0.OOE+00 1.54E+02 8.55E+0 1 2.43E+01 1.70E+04 1.08E+03 MN-54 O.OOE+00 4.29E+04 9.5 1E+03 O.OOE+OO 1.00E+04 1.58E+06 2.29E+04 FE-59 2.07E+04 3.34E+04 1.67E+04 0.OOE+00 O.OOE+00 1.27E+06 7.07E+04 CO-58 0.OOE+00 1.77E+03 3.16E+03 0.OOE+00 0.OOE+00 1.11 E+06 3.44E+04 CO-60 0.OOE+00 1.3 1E+04 2.26E+04 0.OOE+00 0.OOE+00 7.07E+06 9.62E+04 ZN-65 4.26E+04 1.13E+05 7.03E+04 0.OOE+00 7.14E+04 9.95E+05 1.63E+04 SR-89 5.99E+05 0.OOE+00 11.72E+04 0.OOE+00 0.OOE+00 2.16E+06 1.67E+05 SR-90 1.01E+08 O.OOE+00 6.44E+06 0.OOE+00 0.OOE+00 1.48E+07 3.43E+05 ZR-95 1.90E+05 4.18E+04 3.70E+04 O.OOE+/-00 5.96E+04 2.23E+06 6.11E+04 SB-124 5.74E+04 7.40E+02 2.OOE+04 1.26E+02 0.OOE+00 3.24E+06 1.64E+05 1-131 4.8 1E+04 4.81E+04 2.73E+04 1.62E+07 7.88E+04 0.OOE+00 2.84E+03 1-133 1.66E+04 2.03E+04 7.70E+03 3.85E+06 3.38E+04 0.OOE+00 5.48E+03 CS-134 6.5 1E+05 1.01E+06 2.25E+05 0.OOE+00 3.30E+05 1.21E+05 3.85E+03 CS-137 9.07E+05 8.25E+05 1.28E+05 0.OOE+O0 2.82E+05 1.04E+05 3.62E+03 BA-140 7.40E+04 6.48E+01 4.33E+03 O.OOE+00 2.1 1E+01 1.74E+06 1.02E+05 CE-141 3.92E+04 1.95E+04 2.90E+03 0.OOE+O0 8.55E+03 5.44E+05 5.66E+04 CE-144 6.77E+06 ,2.12E+06 3.61E+05 0.OOE+00 1.17E+06 1.20E+07 3.89E+05 52 ODCM Rev. 25

TABLE 4-15 Ri DOSE CONVERSION FACTORS FOR THE INHALATION PATHWAY - INFANT RECEPTOR NUCLIDE BONE LIVER T.BODY THYROID KIDNEY LUNG GI-LLI H-3 0.OOE+00 6.47E+02 6.47E+02 6.47E+02 6.47E+02 6.47E+02 6.47E+02 CR-51 0.OOE+00 0.OOE+00 8.95E+01 5.75E+01 1.32E+01 1.28E+04 3.57E+02 MN-54 0.OOE+00 2.53E+04 4.98E+03 0.OOE+00 4.98E+03 1.00E+06 7.06E+03 FE-59 1.36E+04 2.35E+04 9.48E+03 0.OOE+0O 0.OOE+00 1.02E+06 2.48E+04 CO-58 0.OOE+00 1.22E+03 1.82E+03 O.OOE+O0 0.OOE+00 7.77E+05 1.11 E+04 CO-60 0.OOE+00 8.02E+03 1.18E+04 0.OOE+00 0.OOE+00 4.5 1E+06 3.19E+04 ZN-65 1.93E+04 6.26E+04 3.11E+04 O.OOE+00 3.25E+04 6.47E+05 5.14E+04 SR-89 3.98E+05 0.OOE+00 1.14E+04 0.OOE+O0 0.OOE+00 2.03E+06 6.40E+04 SR-90 4.09E+07 0.OOE+00 2.59E+06 0.OOE÷00 0.OOE+00 1.12E+07 1.31 E+05 ZR-95 1.15E+05 2.79E+04 2.03E+04 0.OOE+00 3.11 E+04 1.75E+06 2.17E+04 SB- 124 3.79E+04 5.56E+02 1.20E+04 1.0 IE+02 0.OOE+00 2.65E+06 5.9 1E+04 1-131 3.79E+04 4.44E+04 1.96E+04 1.48E+07 5.18E+04 0.OOE+00 1.06E+03 1-133 1.32E+04 1.92E+04 5.60E+03 3.56E+06 2.24E+04 O.OOE+00 2.16E'+03 CS- 134 3.96E+05 7.03E+05 7.45E+04 O.OOE+00 1.90E+05 7.97E+04 1.33E+03 CS-137 5.49E+05 6.12E+05 4.55E+04 0.OOE+O0 1.72E+05 7.13E+04 1.33E+03 BA- 140 5.60E+04 5.60E+01 2.90E+03 0.OOE+00 1.34E+01 1.60E+06 3.84E+04 CE-141 2.77E+04 1.67E+04 1':99E+03 O.OOE+00 5.25E+03 5.17E+05 2.16E+04 CE-144 3.19E+06 1.21E+06 1.76E+05 0.OOE+00 5.38E+05 9.84E+06 1.48E+05 53 ODCM Rev. 25

TABLE 4-16 PALO VERDE NUCLEAR GENERATING STATION DISPERSION AND DEPOSITION PARAMETERS FOR LONG TERM RELEASES AT THE NEAREST PATHWAY LOCATIONS CENTERED ON UNIT 1 X/Q RESIDENCE(b) D/Q X/Q GARDEN(b) D/Q X/Q MILK(b) D/Q DIRECTION (Sec/m 3) Dist. Miles (M" 2) (Sec/m 3) Dist. Miles (m"2) (Sec/m 3) Dist. Miles (M" 2)

N 2.92E-06 1.4 3.25E-09 2.92E-06 1.4 3.25E-09 7.03E-07 (a) 3.48E-10 NNE 1.81E-06 1.8 2.88E-09 4.70E-07 (a) 4.04E- 10 4.70E-07 (a) 4.04E-10 NE 1.95E-06 1.9 3.85E-09 1.76E-06 2.1 3.29E-09 5.77E-07 (a) 6.51E-10 ENE 1.03E-06 2.7 1.08E-09 1.03E-06 2.7 1.08E-09 3.86E-07 (a) 2.86E-10 E 9.39E-07 2.8 6.68E-10 3.7 1E-07 (a) 1.87E-10 3.7 1E-07 (a) 1.87E-10 ESE 6.37E-07 3.7 2.84E-10 4. 12E-07 4.6 1.60E-10 4.12E-07 4.6 1.60E- 10 goat SE 8.83E-07 4.1 2.61E-10 8.83E-07 4.1 2.61E-10 5.84E-07 (a) 1.52E-10 SSE 1.27E-06 4.7 2.61E-10 1.09E-06 (a) 2.15E-10 1.09E-06 (a) 2.15E-10 S 2.58E-06 4.6 4.85E-10 2.09E-06 5.2 3.59E-10. 2.13E-06 5.1 3.71E-10 cow SSW 3.26E-06 3.5 8.26E-10 2.28E-06 (a) 4.53E-10 2.28E-06 (a) 4.53E-10 SW 2.80E-06 2.9 9.10E-10 1.58E-06 (a) 3.56E-10 1.58E-06 (a) 3.56E-10 WSW 1.95E-06 2.6 1.09E-09 8.55E-07 (a) 3.18E-10 8.55E-07 (a) 3.18E-10 W 7.54E-07 (a) 4.44E- 10 7.54E-07 (a) 4.44E- 10 7.54E-07 (a) 4.44E- 10 WNW 6.03E-07 (a) 3.25E-10 6.03E-07 (a) 3.25E-10 6.03E-07 (a) 3.25E-10 NW 8.24E-07 3.8 5.25E-10 7.55E-07 4.1 4.61E-10 6.02E-07 (a) 3.27E-10 NNW 1.46E-06 2.0 1.47E-09 5.20E-07 (a) 3.04E- 10 5.20E-07 (a) 3.04E- 10 0 (a) 5-mile value used since there is no pathway located within the sector up to five miles.

r-J (b) Controlling locations are discussed in Appendix A.

References:

1984 Land Use Census (letter ANPM-2122 I-JRM/LEB). NUS Corporation letters NUS-ANPP- 1385 and NUS-ANPP- 1386.

(3'

TABLE 4-17 PALO VERDE NUCLEAR GENERATING STATION DISPERSION AND DEPOSITION PARAMETERS FOR LONG TERM RELEASES AT THE NEAREST PATHWAY LOCATIONS CENTERED ON UNIT 2 X/Q RESIDENCE(b) D/Q X/Q GARDEN(b) D/Q X/Q MILK(b) D/Q DIRECTION (Sec/m 3) Dist. Miles (m"2) (Sec/m 3) Dist. Miles (Mr2 ) (Sec/mr3) Dist. Miles (M"2 )

N 2.73E-06 1.5 2.92E-09 2.39E-06 1.7 2.35E-09 7.03E-07 (a) 3.48E-10 NNE 2.20E-06 1.5 3.87E-09. 2.20E-06 1.5 3.87E-09 4.70E-07 (a) 4.04E-10 NE 1.85E-06 2.0 3.55E-09 1.57E-06 2.3 2.78E-09 5.77E-07 (a) 6.51E-10 ENE 1.03E-06 2.7 1.08E-09 1.03E-06 2.7 1.08E-09 3.86E-07 (a) 2.86E-10 ES 8.80E-07 3.0 6.06E-10 3.7 1E-07 (a) 1.87E-10 3.71E-07 (a) 1.87E-10 ESE 6.25E-07 3.7 2.76E- 10 3.96E-07 4.7 1.51E-10 3.96E-07 4.7 1.51E- 10 goat SE 9.06E-07 4.0 2.72E-10 9.06E-07 4.0 2.72E-10 5.84E-07 (a) 1.52E-10 SSE 1.34E-06 4.5 2.81E-10 1.09E-06 (a) 2.15E-10 1.09E-06 (a) 2.15E-10 S 2.63E-06 4.5 5.01E-10 2.19E-06 5.0 3.88E-10 2.19E-06 5.0 3.88E-10 cow SSW 3.48E-06 3.2 9.19E- 10 2.28E-06 (a) 4.53E-10 2.28E-06 (a) 4.53E-10 SW 2.93E-06 2.7 9.75E-10 1.58E-06 (a) 3.56E-10 1.58E-06 (a) 3.56E-10 wSw 2.01E:06 2.5 1.16E-09 8.55E-07 (a) 3.18E-10 8.55E-07 (a) 3.18E-10 w

7.54E-07 (a) 4.44E- 10 7.54E-07 (a) 4.44E-10 7.54E-07 (a) 4.44E-10 WNW 6.03E-07 (a) 3.25E-10 6.03E-07 (a) 3.25E-10 6.03E-07 (a) 3.25E-10 NW 7.84E-07 4.0 4.88E-10 7.84E-07 4.0 4.88E-10 6.02E-07 (a) 3.27E-10 NNW 1.46E-06 2.0 1.47E-09 5.20E-07 5.0 3.04E- 10 5.20E-07 (a) 3.04E- 10 0 (a) 5-mile value used since there is no pathway located within the sector up to five miles.

(b) Controlling locations are discussed in Appendix A.

References:

1984 Land Use Census (letter ANPM-2122 I-JRM/LEB). NUS Corporation letters NUS-ANPP-1385 and NUS-ANPP-1386.

TABLE 4-18 PALO VERDE NUCLEAR GENERATING STATION DISPERSION AND DEPOSITION PARAMETERS FOR LONG TERM RELEASES AT THE NEAREST PATHWAY LOCATIONS CENTERED ON UNIT 3 X/Q RESIDENCE(b) D/Q X/Q GARDEN(b) D/Q X/Q MILK(b) D/Q DIRECTION (Sec/m 3) Dist. Miles (m"2) (Sec/m 3) Dist. Miles (M"2 ) (Sec/m 3) Dist. Miles (M" 2)

N 2.58E-06 1.8 2.47E-09 2.42E-06 1.9 2.22E-09 7.03E-07 (a) 3.48E-10 NNE 1.85E-06 1.7 2.97E-09 1.85E-06 1.7 2.97E-09 4.70E-07 (a) 4.04E-10 NE 1.66E-06 2.2 3.00E-09 1.48E-06 2.4 2.54E-09 5.77E-07 (a) 6.51E-10 ENE 8.75E-07 2.9 8.86E-10 8.75E-07 2.9 8.86E-10 3.86E-07 (a) 2.86E-10 E 8.90E-07 3.0 6.17E-10 4.06E-07 4.6 2.15E-10 4.25E-07 4.5 2.31E-10 goat ESE 6.37E-07 3.7 2.84E-10 5.80E-07 4.0 2.46E- 10 3.73E-07 (a) 1.37E-10 SE 5.84E-07 (a) 1.52E-10 5.84E-07 (a) 1.52E-10 5.84E-07 (a) 1.52E-10 SSE 1.36E-06 4.4 2.88E-10 1.09E-06 (a) 2.15E-10 1.09E-06 (a) 2.15E-10 S. 2.65E-06 4.2 5.25E-10 2.25E-06 4.9 4.06E-10 2.31E-06 4.8 4.21E-10 cow SSW 3.64E-06 3.1 9.82E-10 2.28E-06 (a) 4.53E-10 2.28E-06 (a) 4.53E-10 SW 3.19E-06 2.5 1.11 E-09 1.58E-06 (a) 3.56E-10 1.58E-06 (a) 3.56E-10 WSW 2.12E-06 2.4 1.26E-09 8.55E-07 (a) 3.18E-10 8.55E-07 (a) 3.18E-10 W 7.54E-07 (a) 4.44E- 10 7.54E-07 (a) 4.44E- 10 7.54E- 10 (a) 4.44E- 10 WNW 6.03E-07 (a) 3.25E-10 6.03E-07 (a) 3.25E-10 6.03E-07 (a) 3.25E-10 NW 6.83E-07 4.3 4.05E-10 6.82E-07 4.3 4.05E-10 6.02E-07 (a) 3.27E-10 NNW 1.34E-06 2.2 1.26E-09 5.16E-07 5.0 3.01E-10 5.20E-07 (a) 3.04E- 10 0 (a) 5-mile value used since there is no pathway located within the sector up to five miles.

0' (b) Controlling locations are discussed in Appendix A.

References:

1984 Land Use Census (letter ANPM-21221-JRM/LEB). NUS Corporation letters NUS-ANPP-1385 and NUS-ANPP-1386.

4.4 Requirements

Liquid Effluents The dose or dose commitment to a MEMBER OF THE PUBLIC from radioactive materials in liquid effluents released, from each reactor unit, to areas at and beyond the SITE BOUNDARY (See Figure 6-4 and Figure 6-5) shall be limited:

a. During any calendar quarter to less than or equal to 1.5 mrems to the total body and to less than or equal to 5 mrems to any organ, and
b. During any calendar year to less than or equal to 3 mrems to the total body and to less than or equal to 10 mrems to any organ.

Applicability: At all times.

Action:

With the calculated dose from the release of radioactive materials in liquid effluents exceeding any of the above limits, prepare and submit to the Commission within 30 days, a Special Report that identifies the cause(s) for exceeding the limit(s) and defines the corrective actions that have been taken to reduce the releases and the proposed corrective actions to be taken to assure that subsequent releases will be in compliance with the above limits.

4.4.1 Surveillance Requirements Cumulative dose contributions from liquid effluents for the current calendar quarter and the current calendar year shall be determined in accordance with the methodology and parameters in the ODCM at least once per 31 days.

4.4.2 Implementation of the Requirements This Requirement does not require implementation guidance. There are no offsite liquid effluent releases.

57 ODCM Rev. 25

5.0 TOTAL DOSE AND DOSE TO PUBLIC ONSITE

5.1 Requirement

Total Dose The annual (calendar year) dose or dose commitment to any MEMBER OF THE PUBLIC due to releases of radioactivity and to direct radiation from uranium fuel cycle sources shall be limited to less than or equal to 25 mrems to the total body or any organ, except the thyroid, which shall be limited to less than or equal to 75 mrems.

Applicability: At all times.

Action:

With the calculated doses from the release of radioactive materials in liquid and gaseous effluents exceeding twice the limits of Section 4.4a, 4.4b, 4.1a, 4.1b, 4.2a or 4.2b calculations shall be made including direct radiation contributions from the reactor units (including outside storage tanks, etc.) to determine whether the above limits of Section 5.1 have been exceeded. If such is the case, prepare and submit to the Commission within 30 days, a Special Report that defines the corrective action to be taken to reduce subsequent releases to prevent recurrence of exceeding the above limits and includes the schedule for achieving conformance with the above limits. This Special Report, as defined in 10 CFR 20.2203(a)(4), shall include an analysis that estimates the radiation exposure (dose) to a MEMBER OF THE PUBLIC from uranium fuel cycle sources, including all effluent pathways and direct radiation, for the calendar year that includes the release(s) covered by this report.

It shall also describe levels of radiation and concentrations of radioactive material involved, and the cause of the exposure levels or concentrations. If the estimated dose(s) exceeds the above limits, and if the release condition resulting in violation of 40 CFR Part 190 has not already been corrected, the Special Report shall include a request for a variance in accordance with the provisions of 40 CFR Part 190. Submittal of the report within 30 days is considered a timely request, and a variance is granted until staff action on the request is complete.

5.1.1 Surveillance Requirements

a. Cumulative dose contributions from the gaseous effluents shall be determined in accordance with the surveillance requirements of Section 4.4.1, 4.1.1 and 4.2.1 and in accordance with the methodology and parameters contained in Section 5.1.2.
b. Cumulative dose contributions from direct radiation from the reactor units and from radwaste storage tanks shall be determined in accordance with the methodology and parameters in Section 5.1.2. This requirement is applicable only under conditions set forth in Section 5.1, Action.

5.1.2 Implementation of the Requirement Since all other uranium fuel cycle sources are greater than 20 miles away, only the PVNGS site need be considered.

The total dose to any MEMBER OF THE PUBLIC will be determined based on a sum of the doses from all three units' releases and doses from direct radiation from PVNGS.

58 ODCM Rev. 25

This dose evaluation is performed annually and submitted with the Annual Radioactive Effluent Release Report to assure compliance with 40 CFR Part 190, Environmental Radiation Protection Standards for Nuclear Power Operation. NUREG-0543, Methods for Demonstrating LWR Compliance With the EPA Uranium Fuel Cycle Standard (40 CFR Part 190), February 1980, provides a discussion on compliance with 40 CFR Part 190 in relation to the Radiological Environmental Technical Specifications for sites of up to four nuclear power reactors. The NUREG concludes that as long as a nuclear plant site operates at a level below the 10 CFR Part 50, Appendix I reporting requirements, and there is no significant source of direct radiation from the site; no extra analysis is required to demonstrate compliance with 40 CFR Part 190. As a result, this dose evaluation will also be performed whenever calculated doses associated with effluent releases exceed twice the limits of Section 4.4a, 4.4b, 4.1a, 4.1b, 4.2a or 4.2b.

Dose Contribution from Liquid and Gaseous Effluents The annual whole body dose accumulated by a MEMBER OF THE PUBLIC for the noble gases released in gaseous effluents is determined by using the following equation:

DWB = (3.17E-08) Y-i [(Ki) (X/Q)UNIT (Qi)] (5-1)

Where:

Ki = the whole body dose factor due to gamma emissions for each identified noble gas radionuclide i, in mrem/yr per gCi/m 3 from Table 3-3.

Qi = the integrated release of radionuclide i, in ýtCi for the previous calendar year.

(X/Q)UNIT = the highest calculated annual average, dispersion parameter, in sec/m 3, for a particular unit, at the controlling location, from Table 4-16, 4-17, or 4-18, or concurrent meteorological data if available.

=2.92E-06 from Unit I

=2.19E-06 from Unit 2

=2.31E-06 from Unit 3 DWB the annual whole body dose in mrem to a MEMBER OF THE PUBLIC at the controlling location due to noble gases released in gaseous effluents.

3.17E-08 = the inverse of seconds in a year (yr/sec);

59 ODCM Rev. 25

The annual dose to any organ accumulated by a MEMBER OF THE PUBLIC for iodine-131, iodine-133, tritium and all radionuclides in particulate form with half-lives greater than 8 days released in gaseous effluents is determined by using the following equation:

Do = (3.17E-08) 1i [--k(RikWk) (Qi)] (5-2)

Where:

Do= the total annual organ dose from gaseous effluents to a MEMBER OF THE PUBLIC, in mrem, at the controlling location.

Qi = the integrated release of radionuclide i, in WCi, for the previous calendar year.

Rik = the dose factor for each identified radionuclide i, for pathway k (for the inhalation pathway in mrem/yr per WCi/m3 and for the food and ground plane pathways in m2-mrem/yr per WCi/sec) at the controlling location. The Rik's for each age group are given in Tables 4-1 through 4-15.

WK = the highest annual average dispersion or deposition parameter for the particular unit, used for estimating the total annual organ dose to a MEMBER OF THE PUBLIC at the controlling location for the particular unit.

= (X/Q)UNIT, in sec/m 3 for the inhalation pathway and for all tritium calculations, for organ dose at the controlling location, from Table 4-16, 4-17, or 4-18, or concurrent meteorological data if available.

=2.92E-06 from Unit 1

=2.19E-06 from Unit 2

=2.31E-06 from Unit 3

=(D/Q)uNIT, in m-2, for the food and ground plane pathways, for organ dose at the controlling location, from Table 4-16, 4-17, or 4-18, or concurrent meteorological data if available.

=3.25E-09 from Unit 1

=3.88E-10 from Unit 2

=4.21E-10 from Unit 3 3.17E-08 = the inverse of seconds in a year (yr/sec).

60 ODCM Rev. 25

Dose Due to Direct Radiation The component of dose to a MEMBER OF THE PUBLIC due to direct radiation will be evaluated by first determining the direct radiation dose at the site boundary in each sector, and then extrapolating the site boundary dose to the controlling location by the inverse square law of distance.

Dose from Radioactive Liquid and Gaseous Effluents to MEMBERS OF THE PUBLIC due to their activities within the SITE BOUNDARY.

These activities have been determined to be limited to the vicinity of the Energy Information Center (EIC) located inside the SITE BOUNDARY. An assumption was made that no MEMBER OF THE PUBLIC would spend more than eight hours per year at this location.

However this calculation has been historically performed assuming an occupancy factor of one (implying continuous occupancy over the entire year).

A X/Q, determined for the Energy Information Center, will be used for this assessment.

Equations 5-1 and 5-2 in Section 5.1.2 should be used for this assessment.

61 ODCM Rev. 25

6.0 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM (REMP)

6.1 Requirement

REMP The radiological environmental monitoring program shall be conducted as specified in Table 6-1, based on locations determined using data from the pre-operational monitoring period; and/or the operational monitoring period indicating a need to make changes in the program.

Applicability: At all times.

Action:

a. With the radiological environmental monitoring program not being conducted as specified in Table 6-1, prepare and submit to the Commission, in the Annual Radiological Environmental Operating Report, as required by Section 7.2, a description of the reasons for not conducting the program as required and the plans for preventing a recurrence.
b. With the level of radioactivity as the result of plant effluents in an environmental sampling medium at a specified location exceeding the reporting levels of Table 6-2 when averaged over any calendar quarter, prepare and submit to the Commission within 30 days, a Special Report that identifies the cause(s) for exceeding the limit(s) and defines the corrective actions to be taken to reduce radioactive effluents so that the potential annual dose* to A MEMBER OF THE PUBLIC is less than the calendar year limits of Section 4.4, 4.1 and 4.2. When more than one of the radionuclides in Table 6-2 are detected in the sampling medium, this report shall be submitted if:

concentration (1) + concentration (2) +... 1.0 reporting level (1) reporting level (2)

When radionuclides other than those in Table 6-2 are detected and are the result of plant effluents, this report shall be submitted if the potential annual dose* to a MEMBER OF THE PUBLIC is equal to or greater than the calendar year limits of Section 4.4, 4.1 and 4.2. This report is not required if the measured level of radioactivity was not the result of plant effluents; however, in such an event, the condition shall be reported and described in the Annual Radiological Environmental Operating Report.

c. With milk or fresh leafy vegetable samples unavailable from one or more of the sample locations required by Table 6-1, identify locations for obtaining replacement samples and add them to the Radiological Environmental Monitoring Program within 30 days. The specific locations from which samples were unavailable may then be deleted from the monitoring program.
  • The methodology and parameters used to estimate the potential annual dose to a MEMBER OF THE PUBLIC shall be indicated in this report.

62 ODCM Rev. 25

6.1.1 Surveillance Requirements

a. The radiological environmental monitoring samples shall be collected pursuant to Table 6-1 from the specific locations given in Table 6-4 and Figure 6-1 and Figure 6-2 and shall be analyzed pursuant to the requirements of Table 6-1, and the detection capabilities required by Table 6-3.

6.1.2 Implementation of the Requirements The results of the radiological environmental monitoring program are intended to supplement the results of the radiological effluent monitoring program by verifying that the measurable concentrations of radioactive materials and levels of radiation are not higher than expected based on the effluent measurements and modeling of the environmental exposure pathways, Thus the specified environmental monitoring program provides measurements of radiation and of radioactive materials in those exposure pathways and for those radionuclides which lead to the highest potential radiation exposures to individuals resulting from station operation.

This requirement is implemented by Nuclear Administrative and Technical Manual procedures.

63 ODCM Rev. 25

TABLE 6-1 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM Exposure Pathway Number of Representative Samples Sampling and Type and Frequency and/or Sample and Sample Locationsa Collection Frequencya of Analysisd Airborne Samples from 5 locations: 4 samples Continuous sampling Gross beta weeklyc, at or near the SITE BOUNDARIES collected weekly, or 1-131 weekly; gamma Radioiodine and (#14A, 15, 29, 40) including 3 more frequently if isotopic analysis of particulates different sectors of the highest required by dust composite (by calculated annual average ground loading, location) quarterly.

level D/Q.*

I sample (#40) from areas of special interest, which is from the vicinity of a community having the highest calculated annual average D/Q.

I sample (#6A) from a control location 15-30 km (9-18 mi) distant and in the least prevalent wind direction.e Direct radiationb Forty (40) routine monitoring Quarterly Gamma dose stations (#5-40, #42, #44, #46, #50) quarterly.

either with two or more dosimeters or with one instrument for measuring and recording dose rate continuously, placed as follows:

An inner ring of stations, one in each meteorological sector in the general area of the site boundary (16 locations);

An outer ring of stations, one in each meteorological sector in the 6-8 km (4-5 mi) range from the site (16 locations); and The balance of the stations (8 locations) to be placed in special interest areas such as population centers, nearby residences, schools, and in one or two areas to serve as control stations.

  • D/Q refers to average annual relative ground deposition rate.

64 ODCM Rev. 25

TABLE 6-1 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM Exposure Pathway Number of Representative Samples Sampling and Type and Frequency and/or Sample and Sample Locationsa Collection Frequencya of Analysisd Waterborne Surface 85 acre Water storage reservoir (#60) Quarterly grab sample Tritium and gamma 45 acre Water storage reservoir (#61) isotopic analysis Evaporation pond #1 (#59) quarterly.

Evaporation pond #2 (#63)

Evaporation pond #3 (#64)

Ground 2 onsite wellsf (#57, #58) Quarterly grab sample Tritium and gamma isotopic analysis quarterly.

Drinking (well) 3 wells from surrounding residences Composite sample of 1-131 analysis on each

(#46, #48, #49) that would be weekly grab samples composite when the affected by its discharge. over 2-week period dose calculated for when 1-131 analysis is the consumption of performed, monthly the water is greater composite of weekly than 1 mrem per grab samples otherwise year.g Composite for gross beta and gamma isotopic analyses monthlyl Composite for tritium analysis quarterly.

Ingestion Samples from milking animals in Semimonthly for Gamma isotopic and 3 locations within 5 km (3 mi) distant animals on pasture; 1-131 analysis Milk (#51, #52) having the highest dose otherwise, monthly. semimonthly when potential. If there are none, I sample animals are on pasture from milking animals in each of three or monthly at other areas between 5 and 8 km (3-5 mi) times.

distant where doses are calculated to be greater than 1 mrem per year.g One sample from milking animals at a control location 15 to 30 km (9-18 mi) distant (#53) and in the least prevalent wind direction.e 65 ODCM Rev. 25

TABLE 6-1 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM Exposure Pathway Number of Representative Samples Sampling and Type and Frequency and/or Sample and Sample Locationsa Collection Frequencya of Analysisd Food Products

  • 2 samples (#47) of 3 types of broad Monthly during Gamma isotopic leaf vegetation (as available) from growing season. analysis.

locations identified per the criteria of Section 6.2b. of this manual.

I control sample (#62) of 3 types of Monthly during Gamma isotopic broad leaf vegetation (as available) growing season, analysis.

grown 15 to 30 km (9-18 mi) distant in the least prevalent wind direction.e

  • When broad leaf vegetation samples are not available, reports from 4 existing supplemental airborne radioiodine sample locations will be substituted.

66 ODCM Rev. 25

TABLE 6-1 (Continued)

TABLE NOTATION a The number, media, frequency, and location of sampling may vary from site to site. It is recognized that, at times, it may not be possible or practical to obtain samples of the media of choice at the most desired location or time. In these instances suitable alternative media and locations may be chosen for the particular pathway in question. Actual locations (distance and direction) from the site shall be provided in Table 6-4 and Figure 6-1 or Figure 6-2 in the ODCM. Refer to Regulatory Guide 4.1, "Programs for Monitoring Radioactivity in the Environs of Nuclear Power Plants."

b Regulatory Guide 4.13 provides guidance for thermoluminescence dosimetry (TLD) systems used for environmental monitoring. One or more instruments, such as a pressurized ion chamber, for measuring and recording dose rate continuously may be used in place of, or in addition to, integrating dosimeters.

For the purposes of this table, a thermoluminescent dosimeter may be considered to be one phosphor, and two or more phosphors in a packet may be considered as two or more dosimeters. Film badges should not be used for measuring direct radiation.

c Particulate sample filters shall be analyzed for gross beta 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or more after sampling to allow for radon and thoron daughter decay. If gross beta activity in air or water is greater than 10 times the yearly mean of control samples for any medium, gamma isotopic analysis should be performed on the individual samples.

d Gamma isotopic analysis means the identification and quantification of gamma-emitting radionuclides that may be attributable to the effluents from the facility.

e The purpose of this sample is to obtain background information. If it is not practical to establish control locations in accordance with the wind direction and distance criteria, other sites that provide valid background data may be substituted.

f Groundwater samples should be taken when this source is tapped for drinking or irrigation purposes in areas where the hydraulic gradient or recharge properties are suitable for contamination.

g The dose shall be calculated for the maximum organ and age group, using the methodology and parameters in the ODCM.

67 ODCM Rev. 25

TABLE 6-2 REPORTING LEVELS FOR RADIOACTIVITY CONCENTRATIONS IN ENVIRONMENTAL SAMPLES Airborne Particulate Fresh Milk Food Products Analysis Water (pCi/I) or Gas (pCi/mr3) (pCi/I) (pCi/kg, wet)

H-3 20,000

  • Mn-54 1,000 Fe-59 400 Co-58 1,000 Co-60 300 Zn-65 300 Zr-Nb-95 400 1-131 2** 0.9 3 100 Cs-134 30 10 60 1,000 Cs-137 50 20 70 2,000 Ba-La-140 200 300 For drinking water samples. This is a 40 CFR 141 value. If no drinking water pathway exists, a value of 30,000 pCi/l may be used.
    • If no drinking water pathway exists, a reporting level of 20 pCi/1 may be used.

68 ODCM Rev. 25

TABLE 6-3 a

DETECTION CAPABILITIES FOR ENVIRONMENTAL ANALYSIS Lower Limit of Detection (LLD)b Airborne Particulate Fresh Milk Food Products Analysis Water (pCi/l) or Gas (pCi/ml3) -(pCi/l) (pCi/kg, wet)

Gross Beta 4 0.01 H-3 2000*

Mn-54 15 Fe-59 30 Co-58, -60 15 Zn-65 30 Zr-95 30 Nb-95 15 1-131 1** 0.07 1 60 Cs-134 15 0.05 15 60 Cs-137 18 0.06 18 80 Ba-140 60 60 La-140 15 15 NOTE: This list does not mean that only these nuclides are to be detected and reported. Other peaks that are measurable and identifiable, together with the above nuclides, shall also be identified and reported.

  • If no drinking water pathway exists, a value of 3000 pCi/I may be used.
    • If no drinking water pathway exists, a value of 15 pCi/1 may be used.

69 ODCM Rev. 25

Table 6-3 (Continued)

TABLE NOTATION a Guidance for detection capabilities for thermoluminescent dosimeters used for environmental measurements is given in Regulatory Guide 4.13.

b Table 6-3 indicates acceptable detection capabilities for radioactive materials in environmental samples.

These detection capabilities are tabulated in terms of the lower limits of detection (LLDs). The LLD is defined, for purposes of this guide, as the smallest concentration of radioactive material in a sample that will yield a net count (above system background) that will be detected with 95% probability with only 5% probability of falsely concluding that a blank observation represents a "real" signal.

For a particular measurement system (which may include radiochemical separation):

LLD =466Sb E

  • V
  • 2.22
  • Y* exp(-kAt)

Where:

LLD is the a priori lower limit of detection as defined above (as pCi per unit mass or volume),

Sb is the standard deviation of the background counting rate or of the counting rate of a blank sample as appropriate (as counts per minute),

E is the counting efficiency (as counts per disintegration),

V is the sample size (in units of mass or volume),

2.22 is the number of disintegrations per minute per picocurie, Y is the fractional radiochemical yield (when applicable),

k is the radioactive decay constant for the particular radionuclide, and At for environmental samples is the elapsed time between sample collection (or end of the sample collection period) and time of counting.

In calculating the LLD for a radionuclide determined by gamma-ray spectrometry the background should include the typical contributions of other radionuclides normally present in the samples (e.g.,

potassium-40 in milk samples). Typical values of E, V, Y, and At should be used in the calculation.

It should be recognized that the LLD is defined as an a priori (before the fact) limit representing the capability of a measurement system and not as an a posteriori (after the fact) limit for a particular measurement. Analyses shall be performed in such a manner that the stated LLDs will be achieved under routine conditions. Occasionally background fluctuations, unavoidable small sample sizes, the presence of interfering nuclides, or other uncontrollable circumstances may render these LLDs unachievable. In such cases, the contributing factors shall be identified and described in the Annual Radiological Environmental Operating Report.

70 ODCM Rev. 25

6.2 Requirement

Land Use Census A land use census shall be conducted and shall identify within a distance of 8 km (5 miles) the location in each of the 16 meteorological sectors of the nearest milk animal, the nearest residence and the nearest garden* of greater than 50 m2 (500 ft2 ) producing broad leaf vegetation.

Applicability: At all times.

Action:

a. With a land use census identifying a location(s) that yields a calculated dose or dose commitment greater than the values currently being calculated in Section 4.2.1, identify the new location(s) in the next Annual Radioactive Effluent Release Report, pursuant to Section 7.1.
b. With a land use census identifying a location(s) that yields a calculated dose or dose commitment (via the same exposure pathway) 20% greater than at a location from which samples are currently being obtained in accordance with Section 6.1, add the new location(s) to the radiological environmental monitoring program within 30 days. The sampling location(s), excluding the control station location, having the lowest calculated dose or dose commitment(s), via the same exposure pathway, may then be deleted from the monitoring program.

6.2.1 Surveillance Requirements

a. The land use census shall be conducted during the growing season annually using that information that will provide the best results, such as by a door-to-door survey, aerial survey, or by consulting local agriculture authorities. The results of the land use census shall be included in the Annual Radiological Environmental. Operating Report pursuant to Section 7.2.

6.2.2 Implementation of the Requirements, The above Requirement is implemented by Nuclear Administrative and Technical Manual procedures.

Broad Leaf vegetation sampling of at least three different kinds of vegetation may be performed at the SITE BOUNDARY in each of two different direction sectors with the highest predicted D/Qs in lieu of the garden census. Specifications for broad leaf vegetation sampling in Table 6-1 shall be followed, including analysis of control samples.

71 ODCM Rev. 25

6.3 Requirement

Interlaboratory Comparison Program Analyses shall be performed on radioactive materials supplied as part of an Interlaboratory Comparison Program that correspond to samples required by Table 6-1, as applicable.

Applicability: At all times.

Action:

a. With analyses not being performed as required above, report the corrective actions taken to prevent a recurrence to the Commission in the Annual Radiological Environmental Operating Report pursuant to Section 7.2.

6.3.1 Surveillance Requirements

a. A summary of the results obtained as part of the above required Interlaboratory Comparison Program and in accordance with the methodology and parameters in this manual shall be included in the Annual Radiological Environmental Operating Report pursuant to Section 7.2.

6.3.2 Implementation of the Requirements PVNGS laboratories or contract laboratories which perform analyses for the Radiological Environmental Monitoring Program (REMP) participate in an Interlaboratory Comparison Program. The participation includes all of the determinations (sample medium-radionuclide combinations) that are included in the monitoring program.

If deviation from specified limits is identified an investigation is made to determine the reason for the deviation and corrective actions are taken as necessary. The results of all analyses made under this program are included in the Annual Radiological Environmental Operating Report.

72 ODCM Rev. 25

TABLE 6-4 RADIOLOGICAL ENVIRONMENTAL MONITORING SAMPLE COLLECTION LOCATIONS LOCATION SAMPLE NOTE DESIGNATION SITE SAMPLE TYPE (d) (a) LOCATION DESCRIPTION (c) 1 TLD SUP E30 Goodyear 2 TLD SUP ENE24 Scott-Libby School 3 TLD SUP E21 Liberty School 4 TLD SUP E16 Buckeye 4 Air SUP E16 Same as TLD 5 TLD (b) SP ESE 1I Palo Verde School 6 TLD (b) Control SSE31 APS Gila Bend substation 6A Air (b) Control SSE13 Old US 80 7 TLD (b) SP SE7 Old US 80 and Arlington School Rd.

7A Air SUP ESE3 Arlington School 8 TLD (b) OR SSE4 Southern Pacific Pipeline Rd.

9 TLD (b) OR S5 Southern Pacific Pipeline Rd.

10 TLD (b) OR SE5 355th Ave. and Elliot Rd.

11 TLD (b) OR ESE5 339th Ave. and Dobbins Rd.

12 TLD (b) OR E5 339th Ave. and Buckeye-Salome Rd.

13 TLD (b) IR NI N site boundary 14 TLD (b) IR NNE2 NNE site boundary 14A Air (b) NNE2 371st Ave. and Buckeye-Salome Rd.

15 TLD (b) IR NE2 NE site boundary, WRF access road 15 Air (b) NE2 Same as TLD.

16 TLD (b) IR ENE2 ENE site boundary 17 TLD (b) IR E2 E site boundary 17A Air SUP E3 351st Ave.

18 TLD (b) IR ESE2 ESE site boundary 19 TLD (b) IR SE2 SE site boundary 20 TLD (b) IR SSE2 SSE site boundary 73 ODCM Rev. 25

TABLE 6-4 RADIOLOGICAL ENVIRONMENTAL MONITORING SAMPLE COLLECTION LOCATIONS LOCATION SAMPLE NOTE DESIGNATION SITE SAMPLE TYPE (d) (a) LOCATION DESCRIPTION (c) 21 TLD (b) IR S3 S site boundary 21 Air SUP S3 Same as TLD 22 TLD (b) IR SSW3 SSW site boundary 23 TLD (b) OR W5 N of Elliot Rd 24 TLD (b) OR SW4 N of Elliot Rd.

25 TLD (b) OR WSW5 N of Elliot Rd.

26 TLD (b) OR SSW4 Duke Property 27 TLD (b) IR SWi SW site boundary 28 TLD (b) IR WSW1 WSW site boundary 29 TLD (b) IR W1 W site boundary 29 Air (b) W1 Same as TLD 30 TLD (b) IR WNWl WNW.site boundary 31 TLD (b) IR NW1 NW site boundary 32 TLD (b) IR NNW1 NNW site boundary 33 TLD (b) OR NW4 S of Buckeye Rd.

34 TLD (b) OR NNW5 395th Ave. and Van Buren St.

35 TLD (b) SP NNW8 Tonopah 35 Air SUP NNW8 Same as TLD 36 TLD (b) OR N5 Wintersburg Rd. and Van Buren St.

37 TLD (b) OR NNE5 363rd Ave. and Van Buren St.

38 TLD (b) OR NE5 355th Ave. and Buckeye Rd.

39 TLD (b) OR ENE5 343rd Ave. N of Broadway Rd.

40 TLD (b) SP N2 Wintersburg 40 Air (b) N2 Same as TLD 41 TLD SUP ESE3 Arlington School 42 TLD (b) SP N8 Ruth Fisher School 43 TLD SUP NE5 Winters Well School 74 ODCM Rev. 25

TABLE 6-4 RADIOLOGICAL ENVIRONMENTAL MONITORING SAMPLE COLLECTION LOCATIONS LOCATION SAMPLE NOTE DESIGNATION SITE SAMPLE TYPE (d) (a) LOCATION DESCRIPTION (c) 44 TLD (b) Control ENE35 El Mirage SUP Transit 45 TLD Control ONSITE Central lab, lead pig 46 TLD (b) SP ENE30 Litchfield Park School 46 Water (b) WD NNW8 Local residence 47 TLD SUP E35 Littleton School 47 Vegetation (b) N3 Local residence 48 TLD SUP E24 Jackrabbit Trail 48 Water (b) WD SWi Local residence 49 TLD SUP ENE11 Palo Verde Rd.

49 Water (b) WD N2 Local residence 50 TLD (b) OR WNW5 S of Buckeye-Salome Rd.

51 Milk (b) NNE3 Local residence (goats) 52 Milk (b) ENE3 Local residence (goats) 53 Milk (b) Control NE30 Local residence (goats) 54 Milk SUP NNE4 Local residence (goats)

WD 55 Water SUP SW3 Local residence 57 Ground Water (b) WG onsite Well 27ddc 58 Ground Water (b) WG onsite Well 34abb 59 Surface Water (b) WS onsite Evaporation Pond #1 60 Surface Water (b) WS onsite 85 acre Water storage reservoir 61 Surface Water (b) WS onsite 45 acre Water storage reservoir 62 Vegetation (b) Control ENE26 Commercial produce company 63 Surface Water (b) WS onsite Evaporation Pond #2 64 Surface Water (b) WS onsite Evaporation Pond #3 75 ODCM Rev. 25

NOTES: (a) Distance and direction are relative to the Unit 2 containment, rounded to the nearest mile.

(b) These samples fulfill the requirements of the ODCM, Table 6-1.

(c) Refer to Figure 6-1 and Figure 6-2 for relative locations of sample sites.

(d) IR - inner ring OR - outer ring SP - school or population center WS - waterborne surface WG - waterborne ground WD - waterborne drinking SUP -designated supplemental sampling location 76 ODCM Rev. 25

,Ia~t" HASSAYAMPA RIVER 11.25° 348.75.

ADOTHWY' DIVISION MAINADT Y.1.ARD VP 95 TONOPAH 33.75*

326.25* LOSMELOA SUBSTATION MP95 SNlIN SCHOOLPO I .1 "P NE L, TO.O A (AOT)d RUTHFISHER T j SCHOOL MP H T4"W SAOM.C L,.

ENCANTO OtTO 5' 303.75',

UP 105 ,*

MCO.OL LRD COHURHOUSEAHS TRUCK STOPM HO TAC MI1CROWAVE

"-* ~ INERB S 40A ,

I<.. SAM

]

LO';,o

  • 0I~

ýY,ý ý. 917" "WE'LS L WNEo

' RELAYTOWER

.............. BUCKEYE

A38T MUNICIPAL AIRPO 'RT HOPEVILL E SSADDLE MOUNTAIN PALOVERDEHILLS 4N

_ROAIfAD *6HO H I -

IHOMOWAY HOSE T4T iSAT

__2 MIT SOUTHERN OS-3 D i 7 "17 o

10 9 8 7 6 " i 4 2 "HAT AVE ALOVERDE.' -* .L

"'::*, z -- G~ENTERTATIN*919 H-I)

DEVERO

    • " I& 2 27 " - - - T-- BIE 0

DOBBINS RD I LA U.2'PALO 208.70 SOS K~ AULIES OS C AlT tOA 1 IHST O

\ .AN- _....oE .I.. HAENRD T 24T LLArIigon.S*CO*Oqite *--V.."OLUA E SCHOOL Hwyeo :1 I "'. Valy IPowerPl-nt ' J*B'-kff. PALOIVERDE 30..

P er PISTjl P04r PIAY) , NARRAMO E RD HORD" TAHJ ARLIN,,TO. j1

.""* it- GILARIE

  • 12:

236.25*" 3.75'

@ ý0

'Z

~ N ~DESERTHOSEHRD 21.75

0) '

'.GILLESPIE DAM S12SA7 SS° GILARIVER KEY TO MAP Figure 6-1 Sample Site cJ School I; Radiological Environmental A Air Airstrip +

V Vegetation Monitoring Program Sample Sites W Water 0 - 10 Miles T TLD M Milk 77 ODCM Rev. 25

5 Iles NE LiVLETON SCHOOL 00 ESE itf" SE 25 miles 10 miles 0 20 miles 30 miles 35 miles KEY TO MAP Figure 6-2 Sample Site () School Radiological Environmental A Air Airstrip [ Monitoring Program Sample Sites (0 Ailes V Vegetation SSE 10 - 35 Miles L/t W Water T TLD y M Milk

Figure 6-3 Radiological Environmental Monitoring Program Sample Sites 35 - 75 Miles DELETED 79 ODCM Rev. 25

Figure 6-4 Site Exclusion Area Boundary DELETED Refer to UFSAR Figure 2.1-4 80 ODCM Rev. 25

Manual Palo Verde Nuclear Generating Station Offsite Dose Offsite Calculation Manual Dose Calculation Palo Verde Nuclear Generating Station Fuel Building Main Steam Plant Vent / Operations Exhaust Support Condenser Vacuum Turbine Support k Containment Fuel Buildinn Structure Combined Exhaust Building Building A Control Diesel Gei Auxiliary Radwaste Building Building Building Building 0 Elevation of Exhaust Point .Figure 6-5 Above Grade Gaseous Effluent r 7 IEXHAUST POINTS KEY PLAN Plant Vent/Condenser Vacuum 145' I I L I Fuel Building 109'-9" Release Points CD

Figure 6-6 Low Population Zone DELETED Refer to UFSAR Figure 2.1-15 82 ODCM Rev. 25

7.0 RADIOLOGICAL REPORTS

7.1 Requirement

Annual Radioactive Effluent Release Report Routine Annual Radioactive Effluent Release Reports covering the operation of the units during the previous calendar year shall be submitted in accordance with Technical Specification 5.6.3..'

The Annual Radioactive Effluent Release Reports shall include a summary of the quantities of radioactive liquid and gaseous effluents and solid waste released from the unit as outlined in Regulatory Guide 1.21, "Measuring, Evaluating, and Reporting Radioactivity in Solid Wastes and Releases of Radioactive Materials in Liquid and Gaseous Effluents from Light-Water-Cooled Nuclear Power Plants," Revision 1, June 1974, with data summarized on a quarterly basis following the format of Appendix B thereof.

The Annual Radioactive Effluent Release Report shall include an annual summary of hourly meteorological data collected over the previous year. This annual summary may be either in the form of an hour-by-hour listing on magnetic tape of wind speed, wind direction, atmospheric stability, and precipitation (if measured), or in the form of joint frequency distributions of wind speed, wind direction, and atmospheric stability**. This same report shall include an assessment of the radiation doses due to the radioactive liquid and gaseous effluents released from the unit or~station during the previous calendar year. This same report shall also include an .assessment of the radiation doses from radioactive liquid and gaseous effluents to MEMBERS OF THE PUBLIC due to their activities inside the SITE BOUNDARY (Figure 6-4) during the report period. All assumptions .used in making these assessments, i.e., specific activity, exposure time and location, shall be included in these reports. The meteorological conditions concurrent with the time of release of radioactive materials in gaseous effluents, as determined by sampling frequency and measurement, shall be used for determining the gaseous pathway doses. The assessment of radiation doses shall be performed in accordance with the methodology and parameters in the ODCM.

The Annual Radioactive Effluent Release Report shall also include an assessment of radiation doses to the likely most exposed MEMBER OF THE PUBLIC from reactor releases and other nearby uranium fuel cycle sources, including doses from primary effluent pathways and direct radiation, for the previous- calendar year to show conformance with 40 CFR Part 190, Environmental Radiation Protection Standards for Nuclear Power Operation. Acceptable methods for calculating the dose contributions are given Section 5.0 and Regulatory Guide 1.109 Rev. 1, October 1977.

The Annual Radioactive Effluent Release Report shall also include information required by the Technical Requirements Manual, Section 5.0.600.1.

A single submittal may be made for a multiple unit station. The submittal should combine those sections that are common to all units at the station; however, for units with separate radwaste systems, the submittal shall specify the releases of radioactive material from each unit.

    • In lieu of submission with the Annual Radioactive Effluent Release Report, the licensee has the option of retaining this summary of required meteorological data on site in a file that shall be provided to the NRC upon request.

83 ODCM Rev. 25

The Annual Radioactive Effluent Release Reports shall include the following information for each class of solid waste (as defined by 10 CFR Part 61) shipped offsite during the report period:

a. Container volume,
b. Total curie quantity (specify whether determined by measurement or estimate),

C. Principal radionuclides (specify whether determined by measurement or estimate),

d. Source of waste and processing employed (e.g., dewatered spent resin, compacted dry waste, evaporator bottoms),
e. Type of container (e.g., LSA, Type A, Type B, Large Quantity), and fL Solidification agent or absorbent (e.g., cement, urea formaldehyde).

The Annual Radioactive Effluent Release Reports shall include a list and description of unplanned releases from' th site to UNRESTRICTED AREAS of radioactive materials in gaseous and liquid effluents made during the reporting period.

Changes to the ODCM shall be submitted in the form of a complete, legible copy as part of or concurrent with the Annual Radioactive Effluent Release Report for the period of the report in which any change in the ODCM was made. Changes made to the Process Control Program shall be submitted with the Annual Radioactive Effluent Release Report for the period of the report in which any change in the Process Control Program was made.

84 ODCM Rev. 25

7.2 Requirement

Annual Radiological Environmental Operating Report

The Annual Radiological Environmental Operating Reports shall include summaries, interpretations, and an analysis of trends of the results of the radiological environmental surveillance activities for the report period, including a comparison with preoperational studies, with operational controls as appropriate, and with previous environmental surveillance reports, and an assessment of the observed impacts of the plant operation on the environment. The reports shall also include the results of land use censuses required by Section 6.2.

The Annual Radiological Environmental Operating Reports shall include the results of analysis of all radiological environmental samples and of all environmental radiation measurements taken during the period pursuant to the locations specified in Table 6-4 and Figure 6-1 and Figure 6-2 as well as summarized and tabulated results of these analyses and measurements in the format of the table in the Radiological Assessment Branch Technical Position, Revision 1, November 1979. In the event that some individual results are not available for inclusion with the report, the report shall be submitted noting and explaining the reasons for the missing results. The missing data shall be submitted as soon as possible in a supplementary report.

The reports shall also include the following: a summary description of the radiological environmental monitoring program; at least two legible maps** covering all sampling locations keyed to a table giving distances and directions from the centerline of one reactor; the results of licensee participation in the Interlaboratory Comparison Program, required by Section 6.3; discussion of all deviations from the sampling schedule of, Table 6-1; and discussion, of all analyses in which the LLD required by Table 6-3 was not achievable.

  • A single submittal may be made for a multiple unit station.
    • One map shall cover stations near the SITE BOUNDARY; a second shall include the more distant stations.

85 ODCM Rev. 25

APPENDIX A DETERMINATION OF CONTROLLING LOCATION The controlling location is the location of the MEMBER OF THE PUBLIC who receives the highest doses.

The determination of a controlling location for implementation of IOCFR50 for radioiodines and particulates is known to be a function of:

(1) Isotopic release rates (2) Meteorology (3) Exposure pathway (4) Receptor's age The incorporation of these parameters into Equation 5-2 results in the respective equations at the controlling location. The isotopic release rates are based upon the source terms calculated using the PVNGS Environmental Report, Operating License Stage, Table 3.5,-12, without carbon.

All of the locations and exposure pathways, identified in the 1984 Land Use Census, have been evaluated. These include cow milk ingestion, goat milk ingestion, vegetable ingestion, inhalation, and ground plane exposure. An infant is assumed to be present at all milk pathway locations. A child is assumed to be present at all vegetable garden locations. The ground plane exposure pathway is only considered to be present where an infant is not present. Naturally, inhalation is present everywhere an individual is present.

For the determination of the controlling locations, the highest X/Q and D/Q values, based on the 9 year meteorological data base, for the vegetable garden, cow milk, and goat-milk pathways', are selected for each unit. The receptor organ doses have been calculated at each of these locations. Based upon these calculations, it is determined that the controlling receptor pathway is a function of unit location. For Unit 1, the controlling receptor is a garden-child pathway; for releases from Unit 2 and Unit 3 the controlling receptor is a cow milk-infant pathway. These determinations are based upon Table 4-16, 4-17, or 4-18, which, in turn, is based upon the 1984 Land Use Census. Locations of the nearest residences, gardens and milk animals, as determined in the 1984 Land Use Census, are given in Table 4-16, 4-17, and 4-18.

86 ODCM Rev. 25

APPENDIX B BASES FOR REQUIREMENTS B-2.1 RADIOACTIVE GASEOUS EFFLUENT MONITORING INSTRUMENTATION The radioactive gaseous effluent instrumentation is provided to monitor and control, as applicable, the releases of radioactive materials in gaseous effluents during actual or potential releases of gaseous effluents. The alarm/trip setpoints for these instruments shall be calculated and adjusted in accordance with the methodology and parameters in the ODCM to ensure that the alarm/trip will occur prior to exceeding the limits of 10 CFR Part 20. The OPERABILITY and use of this instrumentation is consistent with the requirements of General Design Criteria 60, 63, 64 of Appendix A to 10 CFR PART 50.

There are two separate radioactive gaseous effluent monitoring systems: the low range effluent monitors for normal plant radioactive gaseous effluents and the high range effluent monitors for post-accident plant radioactive gaseous effluents. The low range monitors operate at all times until the concentration of radioactivity in the effluent becomes too high during post-accident conditions. The high range monitors only operate when the concentration of radioactivity in the effluent is above the setpoint in the low range monitors.

B-3.1 GASEOUS EFFLUENT - DOSE RATE This requirement provides reasonable assurance that radioactive material discharged in gaseous effluents will not result in the exposure of a MEMBER OF THE PUBLIC in an UNRESTRICTED AREA, either at or beyond the SITE BOUNDARY, in excess of the design objectives of Appendix I to 10 CFR part 50. This requirement is provided to ensure that gas.eous effluents from all units on the site will be appropriately controlled. It provides operational flexibility for releasing gaseous effluents to satisfy the Section II.A and II.C design objectives of Appendix I to 10 CFR part 50. For MEMBERS OF THE PUBLIC who may at times be within the SITE BOUNDARY,. the occupancy of that MEMBER OF THE PUBLIC will usually be sufficiently low to compensate for any increase in the atmospheric diffusion factor above that for the SITE BOUNDARY. Examples of calculations for such MEMBERS OF THE PUBLIC, with the appropriate occupancy factors, shall be given in the ODCM.

The specified release rate limits restrict, at all times, the.corresponding gamma and beta dose rates above background to a MEMBER OF THE PUBLIC at or beyond the SITE BOUNDARY to less than or equal to 500 mrems/year to the total body or to less than or equal to 3000 mrems/year to the skin.

These release rate limits also restrict, at all times, the corresponding thyroid dose rate above background to a child via the inhalation pathway to less than or equal to 1500 mrems/year. This requirement does not affect the requirement to comply with the annual limitations of 10 CFR 20.1301(a).

This requirement applies to the release of radioactive materials in gaseous effluents from all reactor units at the site.

The required detection capabilities for radioactive materials ingaseous waste samples are ,tabulated in terms of the lower limits of detection (LLD). Detailed discussion of the LLD and other detection limits can be found in Currie, L. A., "Lower Limit of Detection: Definition and Elaboration of a Proposed Position for Radiological Effluent and Environmental Measurements," NUREG/CR-4007 (September 1984), and in the HASL Procedures Manual, HASL-300 (revised annually).

87 ODCM Rev. 25

B-3.2 SECONDARY SYSTEM LIQUID WASTE DISCHARGE TO ONSITE EVAPORATION PONDS - CONCENTRATION This requirement is provided to ensure that the annual total effective dose equivalent to individual members of the public from the licensed operation does not exceed the requirements of 10 CFR Part 20, due to the accumulated activity in the evaporation ponds from the secondary system discharges.

Restricting the concentrations of the secondary liquid wastes discharged to the onsite evaporation ponds will restrict the quantity of radioactive material that can accumulate in the ponds. This, in turn, provides assurance that in the event of an uncontrolled release of the pond's contents to an UNRESTRICTED AREA, the resulting total effective dose equivalent to individual members of the public at the nearest exclusion area boundary will not exceed the requirements of 10 CFR Part 20.

This requirement applies to the secondary system liquid waste discharges of radioactive materials from all reactor units to the onsite evaporation ponds.

The required detection capabilities for radioactive materials in gaseous waste samples are tabulated in terms of the lower limits of detection (LLD). Detailed discussion of the LLD and other detection limits can be found in Currie, L. A., "Lower Limit of Detection: Definition and Elaboration of a Proposed Position for Radiological Effluent and Environmental Measurements," NUREG/CR-4007 (September 1984), and in the HASL Procedures Manual, HASL-300 (revised annually).

B-4.1 GASEOUSEFFLUENT - DOSE, Noble Gases This requirement is provided to implement Sections II.B, III.A and IV.A of Appendix I, 10 CFR Part 50. This requirement implements the guides'set forth in Section II.B of Appendix I. The ACTION statements provide the required operating flexibility and at the same time implement the guides set forth in Section IV.A of Appendix I to assure that the releases of radioactive material in gaseous effluents to UNRESTRICTED AREAS will be kept "as low as is reasonably achievable." The surveillance requirements implement the requirements in Section III.A of Appendix I that conformance with the guides of Appendix I be shown by calculational procedures based on models and data such that the actual exposure of a MEMBER OF THE PUBLIC through appropriate pathways is unlikely to be substantially underestimated. The dose calculation methodology and parameters established in the ODCM for calculating the doses due to the actual release rates of radioactive noble gases in gaseous effluents are consistent with the methodology provided in Regulatory Guide 1.109, "Calculation of Annual Doses to Man from Routine Releases of Reactor Effluents for the Purpose of Evaluating Compliance with 10 CFR 'Part 50, Appendix I," Revision 1, October 1977 and Regulatory Guide 1.111, "Methods for Estimating Atmospheric Transport and Dispersion of Gaseous Effluents in Routine Releases from Light-Water Cooled Reactors," Revision 1, July 1977. The ODCM equations provided for determining the air doses at and beyond the SITE BOUNDARY are based upon the historical average atmospheric conditions.

This requirement applies to the release of radioactive materials in gaseous effluents from each reactor unit at the site.

88 ODCM Rev. 25

B-4.2 GASEOUS EFFLUENT - DOSE - Iodine-131, Iodine-133, Tritium, and All Radionuclides in Particulate Form With Half-Lives Greater Than 8 Days This requirement is provided to implement the requirements of Sections II.C, III.A, IV.A of Appendix 1, 10 CFR Part 50. This requirement is the guide set forth in Section II.C of Appendix I. The ACTION statements provide the required operating flexibility and at the same time implement the guides set forth in Section IV.A of Appendix I to assure that the releases of radioactive materials in gaseous effluents to UNRESTRICTED AREAS will be kept "as low as is reasonably achievable." The ODCM calculational methods specified in the surveillance requirements implement the requirements in Section III.A of Appendix.1 that conformance with the guides, of Appendix I be shown by calculational procedures based on models and data, such that the actual exposure of a MEMBER OF THE PUBLIC through appropriate pathways is unlikely to be substantially underestimated. The ODCM calculational methodology and parameters for calculating the doses due to the actual release rates of the subject materials are consistent with the methodology provided in Regulatory Guide 1.109, "Calculation of Annual Doses to Man from Routine Releases of Reactor Effluents for the Purpose of Evaluating Compliance with 10 CFR Part 50, Appendix I," Revision 1, October 1977 and Regulatory Guide 1.111, "Methods for Estimating Atmospheric Transport and Dispersion of Gaseous Effluents in Routine Releases for Light-Water-Cooled Reactors," Revision 1, July 1977. These equations also provide for determining the actual doses based upon the historical average atmospheric conditions. The release rate specifications for iodine-131, iodine-133, tritium, and radionuclides in particulate form with half-lives greater than 8 days are dependent upon the existing radionuclide pathways to man, in the areas at and beyond the SITE BOUNDARY. The pathways that were examined in the development of these calculations were: (1) individual inhalation of airborne radionuclides, .(2) deposition of radionuclides onto green leafy vegetation with subsequent consumption by man, (3) deposition onto grassy areas where milk animals and meat-producing animals graze with consumption of the milk and meat by man, and (4) deposition on the ground with subsequent exposure of man.

This requirement applies to the release of radioactive materials in gaseous effluents from each reactor unit at the site.

B-4.3 GASEOUS RADWASTE TREATMENT The OPERABILITY of the GASEOUS RADWASTE SYSTEM and the VENTILATION- EXHAUST TREATMENT SYSTEM ensures that the systems will be available for use whenever gaseous 'effluents require treatment prior to release to the environment.- The requirement that the appropriate portions of these systems be used, when specified, provides reasonable assurance that.the releases of radioactive materials in gaseous effluents will be kept "as low as reasonably achievable.'-' This requirement implements the requirements of 10 CFR 50.36a, General Design Criterion 60 of Appendix A to 10 CFR Part 50, and the design objectives given in Section II.D of Appendix Ito 10 CFR Part 50. The specified limits governing the use of appropriate portions of the systems were specified as a suitable fraction of the dose design objectives set forth in Sections II.B and II.C of Appendix I, 10 CFR Part 50, for gaseous effluents.

This requirement applies to the release of radioactive materials in gaseous effluents from each reactor unit at the site.

The minimum analysis frequency of 4/M (i.e., at least 4 times per month at intervals no greater than 9 days and a minimum of 48 times a year) is used for certain radioactive gaseous waste sampling in Table 3-1. This will eliminate taking double samples when quarterly and weekly samples are required at the same time.

89 ODCM Rev. 25

B-4.4 SECONDARY SYSTEM LIQUID WASTE DISCHARGE TO ONSITE EVAPORATION PONDS - DOSE This requirement is provided to implement the requirements of Sections II.A, III.A and IV.A of Appendix I, 10 CFR Part 50. This requirement implements the guides set forth in Section II.A of Appendix I. The ACTION statements provide the required operating flexibility and at the same time implement the guides set forth in Section IV.A of Appendix I to assure that the releases of radioactive material in liquid effluents to UNRESTRICTED AREAS will be kept "as low as is reasonably achievable." Also, for fresh water sites with drinking water supplies that can be potentially affected by plant operations, there is reasonable assurance that the operation of the facility will not result in radionuclide concentrations in the finished drinking water that are in excess of the requirements of 40 CFR Part 141. The dose calculation methodology and parameters in the ODCM implement the requirements in Section III.A of Appendix I that conformance with the guides of Appendix I be shown by calculational procedures based on models and data, such that the actual exposure of a MEMBER OF THE PUBLIC through appropriate pathways is unlikely to be substantially underestimated. The equations specified in the ODCM for calculating the doses due to the actual release rates of radioactive materials in liquid effluents are consistent with the methodology provided in Regulatory Guide 1.109, "Calculation of Annual Doses to Man from Routine Releases of Reactor Effluents for the Purpose of Evaluating Compliance with 10 CFR Part 50, Appendix I," Revision 1, October 1977 and Regulatory Guide 1.113, "Estimating Aquatic Dispersion of Effluents from Accidental and Routine Reactor Releases for the Purpose of Implementing Appendix I," April 1977.

This requirement applies to the release of liquid effluents.from each reactor at the site. For units with shared radwaste treatment systems, the liquid effluents from the shared system are proportioned among the units sharing that system.

B-5.1 TOTAL DOSE AND DOSE TO PUBLIC ONSITE This requirement is provided to meet the dose limitations of 40 CFR Part 190 that have been incorporated into 10 CFR 20.1301(d). The requirement specifies the preparation and submittal of a Special Report whenever the calculated doses due to releases of radioactivity and to radiation from uranium fuel cycle sources exceed 25 mrems to the whole body or any organ, except the thyroid, which shall be limited to less than or equal to 75 mrems. Even if a site was to contain up to four reactors, it is

'highly unlikely that the resultant dose to a MEMBER OF THE PUBLIC will exceed the dose limits of 40 CFR Part 190 if the individual 'reactors remain within twice the. dose design objectives of Appendix I"and if direct, radiation doses from the reactor units (including outside storage tanks, etc.)

are kept small. The Special Report will describe a course of action that should result in the limitation of the annual dose' to a MEMBER OF THE PUBLIC to within the 40 CFR Part 190 limits. For the purposes of the Special Report, it may be assumed that the dose commitment to the MEMBER OF THE PUBLIC from other uranium fuel cycle sources is negligible, with the exception that dose contributions from other nuclear fuel cycle facilities at the same site or within a radius of 8 km must be considered. If the dose to any MEMBER OF THE PUBLIC is estimated to exceed the requirements of 40 CFR Part 190, submittal of the Special Report within 30 days with a request for a variance (provided the release conditions resulting in violation of 40 CFR Part 190 have not already been corrected), in accordance with the provisions of 40 CFR Part 190.11 and 10 CFR Part 20.2203(a)(4), is considered to be a timely request and fulfills the requirements of 40 CFR Part 190 until NRC staff action is completed. The variance only relates to the limits of 40 CFR Part.190, and does not apply in any way to other requirements for dose limitation of 10 CFR Part 20, as addressed in Section 3.2 and 3.1 of the ODCM. An individual is not considered a MEMBER OF THE PUBLIC during any period in which he/she is engaged in carrying out any operation that is part of the nuclear fuel cycle. Demonstration of compliance with the limits of 40 CFR Part 190 or with the design objectives of Appendix I to 10 CFR Part 50 will be considered to demonstrate compliance with the 0.1 rem limit of 10 CFR 20.1301.

90 ODCM Rev. 25

B-6.1 RADIOLOGICAL ENVIRONMENTAL MONITORING PROGRAM (REMP)

The Radiological Environmental Monitoring Program required by this requirement provides representative measurements of radiation and of radioactive materials in those exposure pathways and for those radionuclides that lead to the highest potential radiation exposures of MEMBERS OF THE PUBLIC resulting from the station operation. This monitoring program implementsSection IV.B.2 of Appendix I to 10 CFR Part 50 and thereby supplements the radiological effluent monitoring program by verifying that the measurable concentrations of radioactive materials and levels of radiation are not higher than expected on the basis of the effluent measurements and the modeling of the environmental exposure pathways. Guidance for this monitoring program is provided by the Radiological Assessment Branch Technical Position on Environmental Monitoring. The initially specified monitoring program will be effective for at least the first 3 years of commercial operation. Following this period, program changes may be initiated based on operational experience.

The required detection capabilities for environmental sample analyses are tabulated in terms of the lower limits of detection (LLD). The LLDs required by Table 6-3 are considered optimum for routine environmental measurements in industrial laboratories. It should be recognized that the LLD is defined as an a (before the fact) limit representing the capability of a measurement system and not as an a posteriori (after the fact) limit for a particular measurement.

Detailed discussion of the LLD and other detection limits can be found in Currie, L. A., "Lower Limit of Detection: Definition and Elaboration of a Proposed. Position for Radiological Effluent and Environmental Measurements," NUREG/CR-4007 (September 1984), and in the HASL Procedures Manual, HASL-300 (revised annually).

B-6.2 LAND USE CENSUS This requirement is provided to ensure that changes in the use of areas at and beyond the SITE BOUNDARY are identified and that modifications to the radiological environmental monitoring program are made if required by the results of this census. The best information from the door-to-door survey, from aerial survey or from consulting with local agricultural authorities shall be used. This census satisfies the requirements of Section IV.B.3 of Appendix I to 10 CFR Part 50. Restricting the census to gardens of greater than 50 m2 provides assurance that significant exposure pathways via leafy vegetables will be identified and monitored since a garden of this size is the minimum required to produce the quantity (26 kg/year) of leafy vegetables assumed in Regulatory Guide 1.109 for consumption by a child. To determine this minimum garden size, the following assumptions were made: (1) 20% of the garden was. used for growing broad leaf vegetation (i.e., similar to lettuce and cabbage), and (2) a vegetation yield of 2 kg/mi. 2 B-6.3 INTERLABORATORY COMPARISON PROGRAM The requirement for participation in an Interlaboratory Comparison Program is provided to ensure that independent checks on the precision and accuracy of the measurements of radioactive material in environmental sample matrices are performed as, part of. the quality assurance program for environmental monitoring in order to demonstrate that the results are valid for the purposes of Section IV.B.2 of Appendix I to 10 CFR Part 50..

91 ODCM Rev. 25

APPENDIX C DEFINITIONS Note:

The following definitions were derived from the Palo Verde Nuclear Generating Station Technical Specifications. These selected definitions support those portions of the Technical Specifications which were transferred to the ODCM and have been incorporated into the Requirements sections of the ODCM.

Definitions:

The defined terms of this section appear in capitalized type and are applicable throughout the Requirements sections of this ODCM.

ACTION ACTION shall be that part of a requirement which prescribes remedial measures required under designated conditions.

CHANNEL CALIBRATION See the Technical Specification definition.

CHANNEL CHECK See the Technical Specification definition.

CHANNEL FUNCTIONAL TEST See the Technical Specification definition:

DOSE EQUIVALENT 1-131 See the Technical Specification definition.

FREQUENCY NOTATION The FREQUENCY NOTATION specified for the performance of Surveillance Requirements shall correspond to the intervals defined in Table C-1.

GASEOUS RADWASTE SYSTEM A GASEOUS RADWASTE SYSTEM shall be any system designed and installed to reduce radioactive gaseous effluents by collecting primary coolant system offgases from the primary system and providing for delay or holdup for the purpose of reducing the total radioactivity prior to release. to the environment.

MEMBER(S) OF THE PUBLIC MEMBER(S) OF THE PUBLIC shall include all persons who are not occupationally associated with the plant.

This category does not include employees of the licensee, its contractors, or vendors. Also excluded from this category are persons who enter the site to service equipment or to make deliveries. This category does include persons who use portions of the site for recreational, occupational, or other purposes not associated with the plant.

92 ODCM Rev. 25

APPENDIX C DEFINITIONS (Continued)

OPERABLE-OPERABILITY A system" subsystem, train, component or device shall be OPERABLE or have OPERABILITY when it is capable of performing its specified function(s), and when all necessary attendant instrumentation, controls, electrical power, cooling or seal water, lubrication or other auxiliary equipment that are required for the system, subsystem, train, component or device to perform its function(s) are also capable of performing their related support function(s).

MODE See the Technical Specification definition.

PROCESS CONTROL PROGRAM The PROCESS CONTROL PROGRAM shall contain the current formulas, sampling, analyses, test, and determinations to be made to ensure that processing and packaging of solid radioactive wastes based on demonstrated processing of actual or simulated wet solid wastes will be accomplished in such a way as to assure compliance with 10 CFR Parts 20, 61, and 71, State regulations, burial ground requirements, and other requirements governing the disposal of solid radioactive waste.

PURGE-PURGING PURGE or PURGING shall be the controlled process of discharging air or gas from a confinement to maintain temperature, pressure, humidity, concentration, or other operating condition, in such a manner that replacement air or gas is required to purify the confinement.

RATED THERMAL POWER See the Technical Specification definition.

SITE BOUNDARY The SITE BOUNDARY shall be that line beyond which the land is neither owned, nor leased, nor otherwise controlled by the licensee.

SOLIDIFICATION SOLIDIFICATION shall be the conversion of radioactive wastes from liquid systems to a homogeneous (uniformly distributed), monolithic, immobilized solid with definite volume and shape, bounded by a stable surface of distinct outline on all sides (free-standing).

SOURCE CHECK A SOURCE CHECK shall be the qualitative assessment of channel response when the channel sensor is exposed to a source of increased radioactivity.

THERMAL POWER THERMAL POWER shall be the total reactor core heat transfer rate to the reactor coolant.

93 ODCM Rev. 25

APPENDIX C DEFINITIONS (Continued)

UNRESTRICTED AREA An UNRESTRICTED AREA shall be any area at or beyond the SITE BOUNDARY. access to which is not controlled by the licensee for the purposes of protection, of individuals from exposure to radiation and radioactive materials, or any area within the SITE BOUNDARY used for.residential quarters or for industrial, commercial, institutional, and/or recreational purposes.

VENTILATION EXHAUST TREATMENT SYSTEM A VENTILATION EXHAUST TREATMENT SYSTEM shall be any system designed and installed to reduce gaseous radioiodine or radioactive material in particulate form in effluents by passing ventilation or vent exhaust gases through charcoal adsorbers and/or HEPA filters for the purpose of removing iodines or particulates from the gaseous exhaust stream prior to the release to the environment. Such a system is not considered to have any effect on noble gas effluents. Engineered Safety Feature (ESF) atmospheric cleanup systems are not considered to be VENTILATION EXHAUST TREATMENT SYSTEM components.

VENTING VENTING shall be the controlled process of discharging air or gas from.a confinement to maintain temperature, pressure, humidity, concentration, or other operating condition, in such a manner that replacement air or gas is not provided or required during VENTING. Vent, used in system names, does not imply a VENTING process.

94 ODCM Rev. 25

TABLE C-1 FREQUENCY NOTATION NOTATION FREQUENCY S At least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

D At least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

w At least once per 7 days.

At least 4 times per month at intervals no greater than 4/M 9 days and a.minimum of 48 times per year.

M At least once per 31 days.

Q At least once per 92 days.

SA At least once per 184 days.

ANNUALLY At least once per 365 days R At least once per 18 months.

P Completed prior to each release.

S/U -Prior to reactor startup.

N.A. Not Applicable.

95 ODCM Rev. 25

APPENDIX D REFERENCES 1 Title 10, Code of Federal Regulations, Part 20, "Standards for Protection Against Radiation."

2 Title 10, Code of Federal Regulations, Part 50, "Domestic Licensing of Production and Utilization Facilities."

3 Title 40, Code of Federal Regulations, Part 190, Environmental Radiation Protection Standards for Nuclear Power Operations."

4 Federal Register, Vol. 58, No. 245, Thursday, December 23, 1993, Notices, pages 68170-68179.

5 Regulatory Guide 1.21, "Measuring, Evaluating, and Reporting Radioactivity in Solid Wastes and Releases of Radioactive Materials in Liquid and Gaseous Effluents from Light-Water-Cooled Nuclear Power Plants," Revision 1, June 1974.

6 Regulatory Guide 1.109, "Calculation of Annual Doses to Man from Routine Releases of Reactor Effluents for the Purpose of Evaluating Compliance with 10 CFR Part 50, Appendix I,"

Revision 1, October 1977.

7 Regulatory Guide 1.111, "Methods for Estimating Atmospheric Transport and Dispersion of Gaseous Effluents in Routine Releases from Light-Water Cooled Reactors," Revision 1, July 1977.

8 Regulatory Guide 4.1, "Programs for Monitoring Radioactivity in the Environs of Nuclear Power Plants," Revision 1, April 1975.

9 NUREG-0133, Preparation of Radiological Effluent Technical Specifications For Nuclear Power Plants, Oct. 1978.

10 NUREG 0841, "Final Environmental Statement Related to the Operation of Palo Verde Nuclear Generating Station, Units 1,2, and 3", Section 5.9.1.4, February, 1982.

11 NUREG-1301, "Offsite Dose Calculation Manual Guidance: Standard Radiological Effluent Controls for Pressurized Water Reactor", Arpil 1991.

12 Environmental Report Operating License Stage, Palo Verde Nuclear Generating Station, December 1981.

13 PVNGS Updated Final Safety Analysis Report 14 Calculation 13-NC-ZY-252, "Annual Average Dose from Normal Operation Liquid Discharge from the Evaporation Pond", Rev 0.

15 Calculation 13-NC-ZY-253, "Annual Average Dose from Normal Operation Airborne Direct and Sky Shine from the Evaporation Pond", Rev 0.

16 Calculation 13-NC-ZY-254, "Radiation Dose Due to an Evaporation Pond Dike Failure During a Seismic Event", Rev. 0.

96 ODCM Rev. 25