MONTHYEARML24022A2592024-01-22022 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Revise TS LCO 3.8.2 to Remove Note C-S Diesel Generator ML24016A0762024-01-16016 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2 - License Amendment Request to Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications ML23347A0642023-12-13013 December 2023 12-13-23 Email from Kimberly Green to Wells, Russell, Subject: Results of NRC SUNSI Review of Watts Bar Nuclear Plant Dual-Unit UFSAR, Amendment 5 ML23334A0932023-11-28028 November 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate During Mode 6 ML23319A1662023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant, Exemption Request Related to 10 CFR 37.11(c)(2) ML23254A2872023-09-11011 September 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Table 1.1-1 Re Number of Required Rvh Closure Bolts ML23236A2562023-08-24024 August 2023 NRR E-mail Capture - Acceptance Review Results for the Sequoyah and Watts Bar License Amendment Request to Adopt TSTF-567 (L-2023-LLA-0106) ML23191A8672023-07-10010 July 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23150A2472023-05-25025 May 2023 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23116A1492023-04-21021 April 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23075A0032023-03-13013 March 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1, 2, and 3, License Amendment Request to Revise TS 3.7.11, Required Actions A.1 and E.1 Footnotes Re Date for the Modification ML23072A0722023-03-10010 March 2023 NRR E-mail Capture - (External_Sender) State Consultation - Sequoyah Nuclear Plant, Units 1 and 2; and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23013A0382023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML23013A0362023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22356A2982022-12-22022 December 2022 Email Response to Letter, Dated November 22, 2022 Regarding Watts Bar Integrated Inspection Report ML22353A0812022-12-15015 December 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 2, Alternative Request WBN-2-ISI-01 Regarding Examination of Upper Head Injection Nozzle Dissimilar Metal Piping Butt Welds ML22348A0972022-12-14014 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML22348A0442022-12-13013 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0712022-08-15015 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 (EPID L-2022-LLA-0103) - Corrected ML22227A0262022-08-12012 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22215A2752022-08-0303 August 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-554 ML22194A8762022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-529 ML22166A4292022-06-0606 June 2022 NRR E-mail Capture - LAR to Adopt TSTF-577 ML22146A3342022-05-25025 May 2022 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Relief Requests (EPID L-2022-LLR-0045 - 0047) ML22136A0182022-05-16016 May 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, Alternative Request RP-11 and Watts Bar Nuclear Plant, Units 1 and 2, Alternative Request IST-RR-9 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML22123A1812022-05-0303 May 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-577 ML22115A1402022-04-25025 April 2022 NRR E-mail Capture - Requests for Confirmation of Information and Additional Information Regarding Watts Bar Nuclear Plant, Unit 2 Exemption Request Re 10 CFR Part 26 (L-2022-LLE-0017) ML22083A2372022-03-24024 March 2022 NRR E-mail Capture - Request for Additional Information and Confirmation of Information Related to Tva'S Request for Changes to Watts Bar Nuclear Plant, Units 1 and 2, Technical Specification 3.7.8 ML22081A2222022-03-22022 March 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 1, License Amendment Request to Revise Allowable Value for TS Table 3.3.2-1, Function 6.e(1) ML22056A3802022-02-25025 February 2022 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-02 ML22131A1902022-02-23023 February 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Unit 2, Request to Revise the Reactor Vessel Surveillance Capsule Withdrawal Schedule ML22046A0392022-02-15015 February 2022 NRR E-mail Capture - Request for Confirmation of Information Regarding the Watts Bar Nuclear Plant, Unit 2, Cycle 4 Mid-Cycle Outage Generic Letter 95-05 Final Report ML22038A1882022-02-0404 February 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Revise the TVA Radiological Emergency Plan ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22011A0382022-01-10010 January 2022 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-205-A, Rev. 3 and TSTF-563-A ML21306A2452021-11-0202 November 2021 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.7.8, Essential Raw Cooling Water (ERCW) System ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar ML21252A0912021-09-0909 September 2021 NRR E-mail Capture - Request for Comments on Proposed Issuance of Amendments to Watts Bar Nuclear Plant, Unit 2 - Revise Steam Generator Secondary Side Water Level ML21223A2592021-08-11011 August 2021 Affidavit - Prop Slides - Partially Closed Meeting with TVA Potential Watts Bar, Unit 2 Tube Locking LAR ML21221A2602021-08-0909 August 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Watts Bar, Unit 1 Tech Specs Related to Continuous Opening of the Auxiliary Building Secondary Containment Enclosure Boundary ML21215A1152021-07-26026 July 2021 NRR E-mail Capture - (External_Sender) Correction to WBN Chiller Replacement LAR ML21215A1142021-07-26026 July 2021 NRR E-mail Capture - (External_Sender) Correction to WBN Chiller Replacement LAR ML21197A0452021-07-15015 July 2021 WBN U1 Isi/Sgisi Request for Information (RFI) Letter ML21193A2422021-07-12012 July 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar Nuclear Plant, Unit 2 Technical Specifications Related to Steam Generator Inspection/Repair Program Provisions ML21189A0202021-06-29029 June 2021 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specifications 3.3.6 and 3.3.7 Re Radiation Monitor Redundant Unit of Measure 2024-01-22
[Table view] |
Text
WBN2Public Resource From: Crouch, William D [wdcrouch@tva.gov]
Sent: Wednesday, March 16, 2011 9:19 AM To: Poole, Justin; Milano, Patrick; Campbell, Stephen Cc: Adair, James G; Arent, Gordon; Beach, Charles D; Detchemendy, Thomas F; Elton, Thomas L; Freeman, Edwin E; Gillman, Marie; Glover, Christopher Edmund; Henrich, Nolan T Jr; Hilmes, Steven A; Johnson, Robert M; Jones, Dennis Michael; Knuettel, Edward Terry; Koontz, Frank A Jr; Metzler, Ernest Thomas; Olson, Peter Edwin; Riedl, Christopher John; Schlessel, Jerry V; Shea, Joe; Snyder, Laura L; Spink, Thomas E; Stephenson, Catherine L; Stockton, Rickey A; Thompson, Jeffery S; Tinley, Mary Darlene; Woods, Steven E
Subject:
Bucket List 3/16/11 Attachments: NRC PM Open Items List 3-17-11.docx William D. (Bill) Crouch (423) 3652004 WBN (256) 7777676 Cell 1
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 332 Mail Envelope Properties (B75BE6D61CDE4A468D264343045CAC4F08499A34)
Subject:
Bucket List 3/16/11 Sent Date: 3/16/2011 9:19:02 AM Received Date: 3/16/2011 9:19:12 AM From: Crouch, William D Created By: wdcrouch@tva.gov Recipients:
"Adair, James G" <jgadair0@tva.gov>
Tracking Status: None "Arent, Gordon" <garent@tva.gov>
Tracking Status: None "Beach, Charles D" <cdbeach@tva.gov>
Tracking Status: None "Detchemendy, Thomas F" <tfdetchemendy@tva.gov>
Tracking Status: None "Elton, Thomas L" <tlelton@tva.gov>
Tracking Status: None "Freeman, Edwin E" <eefreeman@tva.gov>
Tracking Status: None "Gillman, Marie" <mgillman@tva.gov>
Tracking Status: None "Glover, Christopher Edmund" <ceglove0@tva.gov>
Tracking Status: None "Henrich, Nolan T Jr" <nthenrich@tva.gov>
Tracking Status: None "Hilmes, Steven A" <sahilmes@tva.gov>
Tracking Status: None "Johnson, Robert M" <rmjohnson1@tva.gov>
Tracking Status: None "Jones, Dennis Michael" <dmjones0@tva.gov>
Tracking Status: None "Knuettel, Edward Terry" <etknuettel@tva.gov>
Tracking Status: None "Koontz, Frank A Jr" <fakoontz@tva.gov>
Tracking Status: None "Metzler, Ernest Thomas" <etmetzler@tva.gov>
Tracking Status: None "Olson, Peter Edwin" <peolson@tva.gov>
Tracking Status: None "Riedl, Christopher John" <cjriedl@tva.gov>
Tracking Status: None "Schlessel, Jerry V" <jvschlessel@tva.gov>
Tracking Status: None "Shea, Joe" <jwshea@tva.gov>
Tracking Status: None "Snyder, Laura L" <llsnyder@tva.gov>
Tracking Status: None "Spink, Thomas E" <tespink@tva.gov>
Tracking Status: None "Stephenson, Catherine L" <clstephenson@tva.gov>
Tracking Status: None "Stockton, Rickey A" <rastockton@tva.gov>
Tracking Status: None "Thompson, Jeffery S" <jsthompson@tva.gov>
Tracking Status: None "Tinley, Mary Darlene" <mdtinley@tva.gov>
Tracking Status: None "Woods, Steven E" <sewoods@tva.gov>
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Tracking Status: None "Milano, Patrick" <Patrick.Milano@nrc.gov>
Tracking Status: None "Campbell, Stephen" <Stephen.Campbell@nrc.gov>
Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 86 3/16/2011 9:19:12 AM NRC PM Open Items List 3-17-11.docx 32319 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Page 1 of 5 NRC PM Open Items List 3/17/11 (423) 751-6338 ID 657601 No. Description Status Additional Comments Resp Org/Person
- 1. Cyber Security Plan/Controls and Assess Update Cyber Security Plan IAW NEI 08-09 Rev 6 per Heinrich/Snyder Implementation CDAs/Identify NRC letter dated 5/24/10. NRC Inspection in 2011 (Bryan)
Mods 2/28/11A Provide update to change commitment for April ready for Inspection RAI Response 3/25/11 Response to 3 Generic RAIs Scope Mods 3/31/11 TI issued 5/30/11 NRC Table Top/Pilot TBD Procedures complete 9/30/11 Inspection 10/23/11
- 2. RAIs (Elton) FSAR, SSER Closed All RAI captured individually below. Licensing/Eng (Crouch)
- 3. GL 2004-02 submittal of post Unit 1 Step 1 Step 1 Report w/o test data Eng/Koontz RAIs (Beach) 9/10/10A (Bryan)
Step 2 Include test data and remainder of RAI Step 2 responses 3/4/11A
Page 2 of 5 No. Description Status Additional Comments Resp Org/Person
- 4. Instrumentation RAI List (Knuettel) Ongoing Eng/Hilmes (Smith)
- 5. Develop list of planned License 9/1/11 Review Unit 1 SER for exemptions. NRR/TVA Conditions, Exemptions and Relief (Bryan)
Requests (Crouch)
- 6. Resolve Licensing Basis Preservation 4/1/11 NRC/NRR Inspection in March Eng/Freeman Self Assessment PERs (Crouch) (Smith)
- 7. Generic Letter 2008-01 Gas 3/14/11A Provide submittal of Engineering Products with Eng/Helms Accumulation High Point Vents (Beach) commitment for final walkdown in 2011 (Bryan)
Include latest RAIs
- 8. Status on Aquatic Contention (Arent) 3/18/11 Thermal-hydraulic submittal by 2/8/11A Arent Impingement/Entrainment info by 3/18/11 (Bryan)
Last Impingement Sample the Week of 3/14-18/11 Entrainment to be completed week of 3/7-11/11
- 9. Unit Difference submittal (Stockton) 10/28/10A Bulk of Unit Differences addressed by 10/28/10 letter. Licensing 4/15/11 Need final supplement for remainder of EDCRs (Smith)
- 10. Status of GSI 199 Eastern Seismicity 3/15/11 TVA/NRR (Crouch)
- 11. Address ACRS questions - Tritium 2/24/11A Issues addressed in 2/24/11 ACRS Eng/Freeman concentration in plume from leak, WBN (Crouch) versus VC Summer weld flaw commonalities, baffle bolts status (Crouch)
- 12. Submit final REP prior to fuel load Complete NRR to determine if submittal has to occur before EP/
(Spink) Item 1 License rather than before fuel load. Detchemendy (Bryan) 5/1/11 1. Fix Section 6.0, Event 6.2 in Rev 92xx.
Item 2
- 2. Submit EPIPs 180 days prior to OL.
- 13. Complete Implementation (Hemmer) RAI Response Respond to RAI Hemmer 3/25/11 (Smith)
Implement two unit commitments.
Diesel 6/1/11 Provide updated information for tables contained in the 6/29/07 and 7/1/10 letters.
Page 3 of 5 No. Description Status Additional Comments Resp Org/Person Pump Relocation Letter did not address Phase I commitments 6/17/11 Procedures Issued 6/30/11 Inspection -
August 2011 Phase I commitments 2/11/11
- 14. Issue two Unit Offsite Dose Calculation 9/1/11 Chemistry/
Manual (Beach) Review TS Chapter 5 Woods programs also (Bryan)
- 15. Issue Unit 2 Completion Letter (Crouch) Licensing (Crouch)
- 16. Combined U1/U2 FSAR (Stockton) Licensing (Crouch)
- 17. Provide feedback on the status of NRC SSER 23 Were there any assumptions/lineups in the Unit 1 test NRR review of Integrated Safeguards Test that would make the test applicable for single unit submittal operation only? What facility changes have been made that could affect the results of the test and how do we ensure they do not affect the independence?
Provide copy of presentation to Bob Haag.
- 18. Document Control Issues for two letters 3/15/11 7/15, 10/5, 10/21 and 10/29 letters. NRC to reprint Licensing/Boyd 7/15 letter and provide to NRC Document control.
TVA/Bechtel to provide non-proprietary version of documents that can be released to the public. TVA to provide revised letter that says non-prop once prop documents removed. TVA to confirm A102 gets into ADAMS. Currently only the cover letter is available.
Contacted Kenny Nguyen, NRC Document Control.
Page 4 of 5 No. Description Status Additional Comments Resp Org/Person He has the action.
- 19. Submit final as-constructed FSAR 10/1/11 Licensing/
figures Stockton (Crouch)
- 20. Unit 1 Tech Specs Verify current Unit 1 Tech Specs are acceptable for Unit 1 Licensing two unit operation (specifically review common (Bryan) systems).
- 21. Joint Dry Run of ACRS (Feb 24) 2/22/11A ACRS presentation to provide status of each licensing TVA/NRR issue
- 22. Chapter 15.5 RAIs 12/10/10A Additional question regarding meteorology data from Wastrack RAI response 2008-2009 (Bryan) 3/25/11
- 23. Fire Protection Report Questions 3/16/11 Provide RAI responses (original plus two emails) and ENG/Hilmes regarding OMAs and Rev 40 revised FPR. (Crouch)
- 24. IST Tech Spec Change 3/18/11 TVA Corporate Licensing (Smith)
- 25. Environmental Phone call to discuss 3/18/11 Telecon held. Response in progress Environmental/
intake flow rate/velocity at IPS and Hopping SCCW in EIS versus NPDES. (Bryan)
- 26. Verify Tech Spec Setpoints match calcs 3/25/11 Eng/Hilmes (Bryan)
- 27. Letter to terminate Part 30/40 License Licensing after receipt of Part 50 License (Crouch)
- 28. SSER 22 Open Items Response 3/18/11 Partial response 3/18/11 ENG/Freeman (Bryan)
- 29. Chapter 11/12 RAIs 2/25/11A Response submitted Chem/Eng Closed (Bryan)
- 30. Tech Spec Revisions from latest T/S 3/25/11 Licensing/Elton markup (Bryan)
- 31. ASME III to XI transition Eng/Helms (Crouch)
- 32. AFW RAIs 2/25/11A Response submitted Eng/Koontz Closed (Smith)
Page 5 of 5 No. Description Status Additional Comments Resp Org/Person
- 33. Anti-Trust RAIs 2/22/11A Letter submitted Licensing/Arent Closed
- 34. Chapter 15 RAI on Dose calc basis Bechtel (Fredrick) preparing answer. Eng/Koontz (Bryan)
- 35. Chapter 9 RAI on PASS elimination 3/18/11 Licensing/REP (Smith)
- 36. FSAR Amendment A103 3/15/11A Licensing/
Stockton
- 37. Chapter 11/12 E-mail RAIs 3/18/11 Telecon Public meeting 3/22/11, Determine if impact Chem/Woods to EIS (Bryan)
- 38. Chapter 15 Transient Analysis RAIs Public Meeting Inadvertent SI, CVCS Malfunction, Overpressure, Eng/Koontz 3/15/11A Steam Line Break (Bryan)
- 39. Confirm ACRS accepted IST 3/08/11A Discussed with Ed Hackett and provided copy of Lic/Crouch presentation presentation on 3/15/11 3/18/11 Followup with Ed Hackett to confirm actions required
- 40. Boron Related RAI (e-mail) 3/16/11 Provide requested technical information Additional Eng/Koontz info requested during 3/15/11 public meeting
- 41. Turbine Integrity RAI 3/25/11 Siemens provide draft answers Eng/Koontz
- 42. Hydrology sand bag question Has the NRC accepted the use of sand bags on the Corp/Selman dams? Five RAI questions
- 43. Letter to notify NRC when Vital Area Lic/Crouch Boundary returned to original location
- 44. GDC 5 RAIs 3/17/11 Provide requested technical information Eng/Koontz
- 45. Fire Protection Public Meeting 3/29/11 Provide background on revised FPR and RAI Eng/Hilmes responses.
- 46. Large Break LOCA RAI 3/29/11 Provide requested technical information 47.
48.
49.
50.