WBN2Public Resource From: Poole, Justin Sent: Friday, April 08, 2011 12:59 PM To: Epperson, Dan; Raghavan, Rags Cc: WBN2HearingFile Resource

Subject:

FW: Updated Bucket List 4/8/11 Attachments: NRC PM Open Items List 4-8-11.docx Justin C. Poole Project Manager NRR/DORL/LPWB U.S. Nuclear Regulatory Commission (301)4152048 email: Justin.Poole@nrc.gov From: Crouch, William D [1]

Sent: Friday, April 08, 2011 12:57 PM To: Poole, Justin; Milano, Patrick; Campbell, Stephen Cc: Arent, Gordon; Bryan, Robert H Jr; Smith, James D

Subject:

Updated Bucket List 4/8/11 I updated the list based on todays phone call.

William D. (Bill) Crouch (423) 3652004 WBN (256) 7777676 Cell 1

Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 301 Mail Envelope Properties (19D990B45D535548840D1118C451C74D7F6E4FC164)

Subject:

FW: Updated Bucket List 4/8/11 Sent Date: 4/8/2011 12:58:42 PM Received Date: 4/8/2011 12:58:57 PM From: Poole, Justin Created By: Justin.Poole@nrc.gov Recipients:

"WBN2HearingFile Resource" <WBN2HearingFile.Resource@nrc.gov>

Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>

Tracking Status: None "Raghavan, Rags" <Rags.Raghavan@nrc.gov>

Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 533 4/8/2011 12:58:57 PM NRC PM Open Items List 4-8-11.docx 34590 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received:

Page 1 of 6 NRC PM Open Items List 4/8/11 (423) 751-6338 ID 657601 No. Description Status Additional Comments Resp Org/Person

1. Cyber Security Plan/Controls and Assess Update Cyber Security Plan IAW NEI 08-09 Rev 6 per Heinrich/Snyder Implementation CDAs/Identify NRC letter dated 5/24/10. NRC Inspection in 2011 (Bryan)

Mods 2/28/11A Provide update to change commitment for April ready for Inspection RAI Response 4/7/11A Response to 3 Generic RAIs Scope Mods 3/31/11 TI issued 5/30/11 NRC Table Top/Pilot TBD Procedures complete 9/30/11 Inspection 10/23/11

2. RAIs (Elton) FSAR, SSER Closed All RAI captured individually below. Licensing/Eng (Crouch)
3. GL 2004-02 submittal of post Unit 1 Step 1 Step 1 Report w/o test data Eng/Koontz RAIs (Beach) 9/10/10A (Bryan)

Step 2 Include test data and remainder of RAI Step 2 responses 3/4/11A

Page 2 of 6 No. Description Status Additional Comments Resp Org/Person

4. Instrumentation RAI List (Knuettel) Ongoing Eng/Hilmes (Smith)
5. Develop list of planned License 9/1/11 Review Unit 1 SER for exemptions. NRR/TVA Conditions, Exemptions and Relief (Bryan)

Requests (Crouch)

6. Resolve Licensing Basis Preservation 4/28/11 NRC/NRR Inspection in April Eng/Freeman Self Assessment PERs (Crouch) (Smith)
7. Generic Letter 2008-01 Gas 3/14/11A Provide submittal of Engineering Products with Eng/Helms Accumulation High Point Vents (Beach) commitment for final walkdown in 2011 (Bryan)

Include latest RAIs

8. Status on Aquatic Contention (Arent) 3/29/11A Thermal-hydraulic submittal by 2/8/11A Arent Impingement/Entrainment info by 3/18/11 (Bryan)
9. Unit Difference submittal (Stockton) 10/28/10A Bulk of Unit Differences addressed by 10/28/10 letter. Licensing 4/7/11A Need final supplement for remainder of EDCRs (Smith)
10. Status of GSI 199 Eastern Seismicity 4/15/11 TVA/NRR (Crouch)
11. Address ACRS questions - Tritium 2/24/11A Issues addressed in 2/24/11 ACRS Eng/Freeman concentration in plume from leak, WBN (Crouch) versus VC Summer weld flaw commonalities, baffle bolts status (Crouch)
12. Submit final REP prior to fuel load Complete NRR to determine if submittal has to occur before EP/

(Spink) Item 1 License rather than before fuel load. Detchemendy (Bryan) 5/1/11 1. Fix Section 6.0, Event 6.2 in Rev 92xx.

Item 2

2. Submit EPIPs 180 days prior to OL.
13. Complete Implementation (Hemmer) RAI Response Respond to RAI Hemmer 3/29/11A (Smith)

Implement two unit commitments.

RAI Clarification Provide updated information for tables contained in for Fuel the 6/29/07 and 7/1/10 letters.

Question 2

Page 3 of 6 No. Description Status Additional Comments Resp Org/Person 4/22/10 Letter did not address Phase I commitments Diesel 6/1/11 Pump Relocation 6/17/11 Procedures Issued 6/30/11 Inspection -

August 2011 Phase I commitments 2/11/11

14. Issue two Unit Offsite Dose Calculation 9/1/11 Chemistry/

Manual (Beach) Review TS Chapter 5 Woods programs also (Bryan)

15. Issue Unit 2 Completion Letter (Crouch) Licensing (Crouch)
16. Combined U1/U2 FSAR (Stockton) Licensing (Crouch)
17. Provide feedback on the status of NRC SSER 23 Were there any assumptions/lineups in the Unit 1 test NRR review of Integrated Safeguards Test that would make the test applicable for single unit submittal operation only? What facility changes have been made that could affect the results of the test and how do we ensure they do not affect the independence?

Provide copy of presentation to Bob Haag.

18. Document Control Issues for two letters 4/15/11 7/15, 10/5, 10/21 and 10/29 letters. NRC to reprint Licensing/Boyd 7/15 letter and provide to NRC Document control.

TVA/Bechtel to provide non-proprietary version of

Page 4 of 6 No. Description Status Additional Comments Resp Org/Person documents that can be released to the public. TVA to provide revised letter that says non-prop once prop documents removed. TVA to confirm A102 gets into ADAMS. Currently only the cover letter is available.

Contacted Kenny Nguyen, NRC Document Control.

He has the action.

19. Submit final as-constructed FSAR 10/1/11 Licensing/

figures Stockton (Crouch)

20. Unit 1 Tech Specs 4/15/11 Verify current Unit 1 Tech Specs are acceptable for Unit 1 Licensing two unit operation (specifically review common (Bryan) systems).
21. Joint Dry Run of ACRS (Feb 24) 2/22/11A ACRS presentation to provide status of each licensing TVA/NRR issue
22. Chapter 15.5 RAIs 12/10/10A Additional question regarding meteorology data from Wastrack RAI response 2008-2009 (Bryan) 4/30/11
23. Fire Protection Report Questions 3/31/11A Justification Criteria ENG/Hilmes regarding OMA 4/29/11 Justifications (Crouch)

TBD (draft Next RAI set prior to 4/21 mtg)

24. IST Tech Spec Change 4/15/11 TVA Corporate Licensing (Smith)
25. Environmental Phone call to discuss 4/15/11 Telecon held. Response in progress Environmental/

intake flow rate/velocity at IPS and Hopping SCCW in EIS versus NPDES. (Bryan)

26. Verify Tech Spec Setpoints match calcs 8/1/11 Eng/Hilmes (Bryan)
27. Letter to terminate Part 30/40 License Licensing after receipt of Part 50 License (Crouch)
28. SSER 22 Open Items Response 4/6/11A Partial response 4/4/11 ENG/Freeman (Bryan)
29. Chapter 11/12 RAIs 2/25/11A Response submitted Chem/Eng

Page 5 of 6 No. Description Status Additional Comments Resp Org/Person Closed (Bryan)

30. Tech Spec Revisions from latest T/S 4/22/11 NRC comments due by 4/8/11 Licensing/Elton markup (Bryan)
31. ASME III to XI transition When does ISI program begin with partial plant N-3? Eng/Helms Are repairs/mods after N-5 controlled under Section III (Crouch) or Section XI?
32. AFW RAIs 2/25/11A Response submitted Eng/Koontz Closed (Smith)
33. Anti-Trust RAIs 2/22/11A Letter submitted Licensing/Arent Closed
34. Chapter 15 RAI on Dose calc basis Bechtel (Fredrick) preparing answer. Eng/Koontz (Bryan)
35. Chapter 9 RAI on PASS elimination 4/1/11A Licensing/REP (Smith)
36. FSAR Amendment A103 3/15/11A Licensing/

Stockton

37. Chapter 11/12 E-mail RAIs 4/30/11 Chem/Woods (Bryan)
38. Chapter 15 Transient Analysis RAIs Public Meeting Inadvertent SI, CVCS Malfunction, Overpressure, Eng/Koontz 3/15/11A Steam Line Break (Bryan)
39. Confirm ACRS accepted IST 3/08/11A Discussed with Ed Hackett and provided copy of Lic/Crouch presentation presentation on 3/15/11 3/18/11A Followup with Ed Hackett to confirm actions required ACRS requested a re-presentation. Added item to ACRS topics below.
40. Boron Related RAI (e-mail) 3/25/11A Provide requested technical information Additional Eng/Koontz info requested during 3/15/11 public meeting
41. Turbine Integrity RAI 3/25/11A Siemens provide draft answers Eng/Koontz
42. Hydrology sand bag question 4/15/11 Has the NRC accepted the use of sand bags on the Corp/Selman dams? Five RAI questions
43. Letter to notify NRC when Vital Area 5/31 Date for schedule Lic/Crouch Boundary returned to original location
44. GDC 5 RAIs 4/11/11 Provide requested technical information Eng/Koontz

Page 6 of 6 No. Description Status Additional Comments Resp Org/Person

45. Fire Protection/GDC 5 Public Meeting 3/29/11A Provide background on revised FPR and RAI Eng/Hilmes responses. Provide methodology of GDC 5 cooldown analysis
46. Large Break LOCA RAI 4/1/11A Provide requested technical information Koontz/WEC
47. PSA Definition of Vulnerability 4/1/11A Enis
48. Part 70 License vs Part 50 procedure 4/15/11 Determine ability to control Part 70 fuel under Unit 1 Milano question Part 50 procedures. TVA to contact Rafael regarding wording of license. Discussed issue with Rafael on 3/30/11. E-mail sent to Rafael on 3/31/11 with proposed license markup.
49. ACRS Topics Improvements, Inspection status, Refurb status, Construction Status, Japan, IST Re-Presentation, Cyber Security
50. SAMDA RAIs 05/20/11 Provide partial responses to speed up review.
51. SSER 22 Open Items Response
52. Chapter 12 RAI on Instrument Channel ENG/Hilmes Operability Tests
53. Transient Analysis issues ENG/Koontz Inadvertent SI 4/22/11 WEC/Morgan CVCS Malfunction 4/22/11 Steam line break 4/15/11