SOUTHERN CALIFORNIA
~
EDISON An EDISON INTERNATIONAL Company March 30, 2011 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Richard J. St. Onge Director Nuclear Regulatory Affairs 10 CFR 50.54
Subject:
Docket Nos. 50-206, 50-361 and 50-362 Nuclear Property Insurance San Onofre Nuclear Generating Station Units 1, 2, and 3
Dear Sir or Madam:
This letter is the report required by 10 CFR 50.54(w)(3). The following Nuclear Property and Decontamination Liability Insurance will be in effect for the San Onofre Nuclear Generating Station on the April 1, 2011 policy renewal date:
Policy (Amount)
Primary Property and Decontamination Liability Insurance Policy
($500 million)
Decontamination Liability, Decommissioning Liability and Excess Property Insurance Policy
($2,250 million)
Source Nuclear Electric Insurance Limited (NEIL Primary)
Nuclear Electric Insurance Limited (NEIL II)
All policies providing coverage mentioned above comply with 10 CFR 50.54(w),
including provisions for the insurance proceeds to be prioritized for dedicated reactor stabilization/safety and then for decontamination of the site.
P.O. Box 128 San Clemente, CA 92674
Document Control Desk March 30, 2011 There are no commitments contained in this letter.
If you have any questions or require additional information, please contact Ms. Linda Conklin at 949-368-9443.
Sincerely, cc:
E. E. Collins, Regional Administrator, NRC Region IV J. E. Whitten, Region IV, San Onofre Unit 1 R. Hall, NRC Project Manager, San Onofre Units 2 and 3 J. C. Shepherd, NRC Project Manager, San Onofre Unit 1 G. G. Warnick, NRC Senior Resident Inspector, San Onofre Units 2 and 3