From:
Miller, Ed Sent:
Tuesday, March 29, 2011 2:04 PM To:
'Kilby, Gary'
Subject:
- Gary, Emmett provided me with the following draft RAI. I am providing it to you in draft form to ensure that the question is clear. Please let me know if you have any questions. Thanks.
Ed Miller 415-2481 Draft RAI #1:
The proposed exclusion criteria for paragraph d. of TS 6.7.6.k is not consistent with the planned inspection scope (described in Section 3.2 of the technical evaluation supporting the proposed LAR) in the event that PWSCC is found at the TTS during the upcoming inspection.
The planned inspection scope is a key element supporting the proposed amendment for an interim H*. Please resolve the discrepancy or provide a revised proposal for paragraph d. which resolves the above inconsistency.