ML110810752
| ML110810752 | |
| Person / Time | |
|---|---|
| Site: | Millstone |
| Issue date: | 03/22/2011 |
| From: | John Hughey Plant Licensing Branch 1 |
| To: | Bartron W, Craft W Dominion |
| Hughey J, NRR/DORL, 301-415-3204 | |
| Shared Package | |
| ml110811170 | List: |
| References | |
| RR-04-04, FOIA/PA-2011-0115 | |
| Download: ML110810752 (3) | |
Text
From:
Hughey, John Sent:
Tuesday, March 22, 2011 1:25 PM To:
'William D Bartron'; 'Wanda D Craft' Cc:
Sanders, Carleen
Subject:
RE: DRAFT MPS2 RR-04-04 RAIs Attachments:
DRAFT MPS2 RAI's RR-04-04.docx Afternoon, Attached are the Draft RAI's for Millstone 2 relief request RR-04-04 requesting alternative pressure testing criteria for three different Component Groups of Class 1 piping segments for the fourth 10-year inspection interval. They are being sent to you to ensure that the questions are understandable, the regulatory basis for the questions is clear, and to determine if the information was previously docketed.
Please inform me by COB on Friday, 3-25-2011, if DNC desires to have a teleconference regarding the attached draft RAIs. If I dont hear from you by COB on 3-25-2011, then I will issue the RAIs with a response due date of April 29, 2011.
- Thanks, John John Hughey Peach Bottom Project Manager NRR / Division of Operating Reactor Licensing Phone: 301-415-3204 e-mail: John.Hughey@nrc.gov