MONTHYEARML22235A7862022-08-23023 August 2022 Acceptance Review: Exemption Request from 10 CFR 20, Appendix G, LLW Shipping Investigation Requirements ML21181A1882021-06-30030 June 2021 E-mail from S. Johnston, Holtec, to A. Snyder and F. Bower, NRC - Oyster Creek Nuclear Generating Station - Readiness Status for ISFSI Only Inspection ML21175A2092021-06-24024 June 2021 E-mail from A. Sterdis to P. Longmire - Oyster Creek Nuclear Generating Station: ISFSI-only Physical Security Plan (Stating Implementation Intent) ML21162A3602021-06-11011 June 2021 E-mail Response from the State of New Jersey Regarding the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21162A1172021-06-11011 June 2021 E-mail to HDI: Acceptance Review - FOF Exemption ML21168A0172021-06-10010 June 2021 E-mail from HDI: RAI Response ML21161A2572021-06-0707 June 2021 State Consultation: ISFSI-only Physical Security Plan (Email Response) ML21175A0712021-06-0202 June 2021 Issuance of Request for Additional Information: Oyster Creek Nuclear Generating Station. Request for Amendment to Technical Specifications ML21148A0562021-05-27027 May 2021 E-mail to State of New Jersey Informing of the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21132A3182021-05-12012 May 2021 E-Mail from V. Gubbi, DEP to Z. Cruz, NRC - Oyster Creek Nuclear Generating Station - State of New Jersey Response to the Pending Revision to the Defueled Technical Specifications to Reflect Independent Spent Fuel Storage Installation Only ML21132A0312021-05-11011 May 2021 E-mail to State of New Jersey Informing of the Pending Revision to the Physical Security Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21119A1422021-04-28028 April 2021 E-mail to State of New Jersey Informing of the Pending Revision to the Emergency Plan to Reflect Independent Spent Fuel Storage Installation Only Status ML21113A0742021-04-23023 April 2021 Acceptance Review Email - April 20, 2021 Oyster Creek Request for Exemption from 10 CFR Part 73 Requirements Due to Covid ML21099A0382021-04-0808 April 2021 Email from Z. Cruz to A. Sterdis - Request for Additional Information - HDI Request for Approval of Oyster Creek Nuclear Generating Station Independent Spent Fuel Storage Installation Facility Only Emergency Plan ML21085A4872021-03-26026 March 2021 E-mail from Z. Cruz to A. Sterdis - Acceptance Review: Oyster Creek Nuclear Generating Station - Request for Approval of Independent Spent Fuel Storage Installation Only Permanently Defueled Technical Specifications ML21064A2432021-03-0505 March 2021 Email from Z. Cruz to A. Sterdis Acceptance Review_ Oyster Creek Nuclear Generating Station - Request for Approval of Independent Spent Fuel Storage Installation Facility Only Emergency Plan and Emergency Action Level Scheme ML21064A2392021-03-0202 March 2021 E-mail from Z. Cruz to A. Sterdis Acceptance Review - Oyster Creek Nuclear Generating Station - Request for Approval of Independent Spent Fuel Storage Installation Only Physical Security Plan ML20345A1462020-12-0909 December 2020 E-mail - Response to Request for Additional Information: HDI Request for One-Time Exemption from Part 73, Appendix B FOF Requirements ML20335A3112020-11-30030 November 2020 Request for Additional Information Regarding Request for a one-time Exemption from Part 73, Appendix B Requirements for Oyster Creek Nuclear Generating Station ML20332A1472020-11-24024 November 2020 Acceptance Review: November 20 2020 Exemption Request from 10 CFR Part 73 Appendix B Requirements for Oyster Creek ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20279A5082020-10-0505 October 2020 Email to Holtec - Response to Notification of Oyster Creek Onsite Property Insurance Coverage ML20266G4032020-09-22022 September 2020 Acceptance Review Email - Request for Approval of HDI Fleet Decommissioning Quality Assurance Program, Revision 0 ML20134H8742020-05-12012 May 2020 Request for Additional Information Regarding Request for Temporary Exemption from Part 73, Appendix B Requirements ML20133J9182020-05-11011 May 2020 Acceptance Review Email - Oyster Creek Request for Exemption from Part 73 Qualification Requirements ML20120A0252020-04-22022 April 2020 NRR E-mail Capture - (External_Sender) Oyster Creek Sea Turtle Handling and Conservation Recommendation Obligations NRC-2019-0073, Response from NEIMA Local Community Advisory Board Questionnaire 10-30-2019 R Discenza2019-10-30030 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-30-2019 R Discenza ML19344C8022019-10-20020 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-20-2019 a Dressler ML19344C8002019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 W Mcmullin ML19344C7982019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 M Noto ML19344C7992019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 s Feldman ML19344C7932019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 C Bischoff ML19344C7962019-10-0909 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-09-2019 G Adams ML19344C7912019-10-0808 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-08-2019 J Branciforte ML19344C7902019-10-0808 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-08-2019 Anonymous ML19344C7892019-10-0505 October 2019 Response from NEIMA Local Community Advisory Board Questionnaire 10-05-2019 P Dressler ML19263D1222019-09-20020 September 2019 for Your Action Request for Additional Information Hdi Oyster Creek PSDAR ML19214A0452019-08-0202 August 2019 NRC to NMFS, Revised Proposed Action for Oyster Creek Endangered Species Act Section 7 Consultation ML19182A3422019-07-0101 July 2019 Transaction ML19178A0702019-06-26026 June 2019 Email to State of New Jersey - Oyster Creek - Request Comments on Proposed Amendment to Remove Reference to the Oyster Creek Cyber Security Plan and Update License Condition 2.C.(4) in the Renewed Facility License ML19196A3422019-06-20020 June 2019 Email: Courtesy Notice on the Issuance of the Oyster Creek License Transfer and Exemption (Sierra Club) ML19196A3342019-06-20020 June 2019 Email: Courtesy Notice on the Issuance of the Oyster Creek License Transfer and Exemption ML19162A2242019-06-11011 June 2019 NRC to NMFS, NRC Responses to NMFS Requests for Additional Information for Oyster Creek ESA Section 7 Consultation NRC-2018-0237, Comment from Paul Dressler of the Concerned Citizens for Lacey Coalition, Regarding the Oyster Creek Nuclear Plant License Transfer Application2019-06-0707 June 2019 Comment from Paul Dressler of the Concerned Citizens for Lacey Coalition, Regarding the Oyster Creek Nuclear Plant License Transfer Application ML19155A1182019-06-0404 June 2019 Incoming E-mail from State of New Jersey on the Oyster Creek Exemption for Reduced Insurances and Use of Decommissioning Trust Fund for Spent Fuel Management and Site Restoration ML19155A1192019-06-0404 June 2019 State of New Jersey Comments - Oyster Creek Conforming Amendment Associated with the Oyster Creek Generating Station License Transfer Application ML19154A0582019-05-31031 May 2019 E-mail Response from State of New Jersey Dated May 31, 2019, Notification-and-Request-Oyster Creek License Transfer Application L-2018-LLM-0002 ML19158A2912019-05-30030 May 2019 NRR E-mail Capture - Oyster Creek ESA Consultation: Information Requests from NMFS ML19158A2772019-05-28028 May 2019 NRR E-mail Capture - Oyster Creek ESA Consultation: Information Requests from NMFS ML19148A4392019-05-24024 May 2019 NMFS to NRC, Requests for Additional Information to Support Oyster Creek Reinitiated Section 7 Consultation 2022-08-23
[Table view] |
Text
, '
Metzger, Brian From: Frumkin, Daniel \'mu-Sent: Wednesday, May 05, 2010 3:58 PM To: Sullivan, Kenneth; Metzger, Brian Cc: Klein, Alex
Subject:
BNL Schedule to support manual actions exemption reviews
- Ken, Let us look into this.
Dan From: Sullivan, Kenneth [ks@bnl.gov] yl-)'l--
Sent: Wednesday, May 05, 2010 3:43 PM To: Metzger, Brian Cc: Frumkin, Daniel
Subject:
RE: Submitted - Oyster Creek OMA ER RAI Response Hi Brian -
Working on OC now.. .hope to have a draft TER to you next week (before the NEI meeting)
The proposed timeline may be a problem .... I'm booked for June .... supporting Paul Lain at Oconee (805 review) and Mark Salley in RES how firm is your schedule... ?
Ken From: Metzger, Brian [1]
Sent: Wednesday, May 05, 2010 3:31 PM To: Sullivan, Kenneth Cc: Frumkin, Daniel
Subject:
RE: Submitted - Oyster Creek OMA ER RAI Response
- Ken, Slipping a week on Oyster Creek is fine with us. What we propose is for you to get your draft to us sometime next week, so mid-May, followed by your Wolf Creek draft in mid-June and your Indian Point draft in mid-July.
All of the necessary documents should be publicly available in ADAMS with the exception of the Indian Point RAI responses, which we just received today. Once these are available, we will send them over as well.
Please let me know if you can support this timeline and if you have any questions.
- Regards, Brian Metzger Fire Protection Engineer, NRR/DRA/AFPB, Phone: 301-415-3972 Location: O-10G13 Mail Stop: O-10C15 [j]i I
From: Sullivan, Kenneth [2]
Sent: Wednesday, April 28, 2010 10:14 AM To: Metzger, Brian
Subject:
RE: Submitted - Oyster Creek OMA ER RAI Response Hi Brian Brian Pretty busy juggling several balls right now (payback for being out sick for nearly a month) .. so the draft OC exemption may slip a week to the 14th .... Willing to do unnatural acts If delivery by the 7th is critical.
Ken From: Metzger, Brian [3] *[QJ(. .
Sent: Monday, April 26, 2010 3:49 PM To: Sullivan, Kenneth
Subject:
RE: Submitted - Oyster Creek OMA ER RAI Response Great. Please provide us with a date for when you anticipate having a draft amendment document to us. Also, please confirm that you are still planning to have us a draft exemption for Oyster Creek during the first week of May.
- Regards, Brian Metzger Fire Protection Engineer, NRR/DRA/AFPB, Phone: 301-415-3972 Location: O-10G13 Mail Stop: O-10C15 From: Sullivan, Kenneth [4] ,QI)OL-Sent: Thursday, April 22, 2010 10:48 AM To: Frumkin, Daniel Cc: Metzger, Brian
Subject:
RE: Submitted - Oyster Creek OMA ER RAI Response Got it ... Thanks!
From: Frumkin, Daniel ,
Sent: Wednesday, April 21, 2010 12:19 PM To: Sullivan, Kenneth Cc: Metzger, Brian
Subject:
RE: Submitted - Oyster Creek OMA ER RAI Response 2
Ken attached is a 1Omeg file. Please confirm you got this.
If you can't get it, I can send you an 8.5meg file. Although the text is okay, the pictures in that file are unusable.
Dan From: Metzger, Brian Sent: Wednesday, April 21, 2010 9:12 AM To: Sullivan, Kenneth Cc: Frumkin, Daniel
Subject:
RE: Submitted - Oyster Creek OMA ER RAI Response
- Ken, Yes, that number is correct. It appears that it is not currently publicly available. I will look into it.
- Regards, Brian From: Sullivan, Kenneth [5] r-)flL-Sent: Wednesday, April 21, 2010 9:05 AM To: Metzger, Brian
Subject:
RE: Submitted - Oyster Creek OMA ER RAI Response Brian - Cant find the Wolf Creek RAI Response on Adams ... is the accession# correct? Is it publically available?
Thanks Ken From: Metzger, Brian [6] iLL Sent: Monday, April 19, 2010 11:13 AM To: Sullivan, Kenneth; Frumkin, Daniel
Subject:
RE: Submitted - Oyster Creek OMA ER RAI Response
- Ken, Wolf Creek's RAI responses can be found at ML101040250. Please let us know if you have any questions.
- Regards, Brian Metzger Fire Protection Engineer, NRR/DRA/AFPB, Phone: 301-415-3972 Location: O-10G13 Mail Stop: O-10C15 I -
3
From: Sullivan, Kenneth [7]
- Sent: Wednesday, April 07, 2010 2:22 PM To: Frumkin, Daniel Cc: Metzger, Brian
Subject:
RE: Submitted - Oyster Creek OMA ER RAI Response Dan / Brian Just returned to work yesterday after 3 weeks of sick leave (had a blood infection). As you can imagine, I'm pretty busy just answering e-mails and trying to get things back in order... I looked over the OC response .... it's pretty comprehensive (well, at least lengthy) .... Also, OC appears to have changed the request from that which was previously reviewed (e.g., based on Rev 2 of RG 1.189, they have withdrawn certain OMAs from their initial request). In addition, a detailed review of supporting information contained in five separate attachments (Attachments 2 - 6) will be required.,
(one example is the adequacy of defense-in-depth features described in Attachment 2, for fire areas that rely on the use of OMAs in lieu of III.G.2 fire protection features).
So.... Considering all of this in conjunction with my current work schedule .... I'd say a "best case estimate" for delivery of a draft technical evaluation report (i.e., draft exemption) would be four weeks from this Friday, May 7.....Having said that.. .let me know if this creates a major problem .... I can try to rearrange priorities if necessary.
Also... you mentioned that you had (or would have) an example of an approved OMA exemption for use as a "boilerplate" of the exemption report format. Ifyou have a good example please provide me a copy.... If not, I assume I should follow the guidance provided in Section 4.9.2 of LIC 103 Rev. 1 Thanks Ken Ken Sullivan Research Engineer Energy Sciences and Technology Department Brookhaven National Laboratory (631) 344-7915 mailto:ks@bnl.gov From: Frumkin, Daniel Sent: Wednesday, April 07, 2010 9:39 AM To: Sullivan, Kenneth Cc: Miller, Ed; Metzger, Brian
Subject:
FW: Submitted - Oyster Creek OMA ER RAI Response
- Ken, Here is the Oyster Creek OMA RAI Responses.
Can you provide an estimate of when you think you will have a draft exemption to Brian and I?
- Thanks, 4