ML110620662

From kanterella
Jump to navigation Jump to search
COL Hearing - FW: FPL Letter L-2011-082 Dated 02/28/2011 - Submittal of the Groundwater Model Report Revision 1
ML110620662
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 03/02/2011
From:
- No Known Affiliation
To:
NRC/NRO/DNRL/NWE1
References
+reviewedmmc1
Download: ML110620662 (138)


Text

1 PMTurkeyCOLPEm Resource From:

Franzone, Steve [Steve.Franzone@fpl.com]

Sent:

Wednesday, March 02, 2011 9:37 AM To:

Kugler, Andrew

Subject:

FW: FPL Letter L-2011-082 dated 02/28/2011 - Submittal of the Groundwater Model Report Revision 1 Attachments:

L-2011-082 dated 02-28-2011 Groundwater Report Submittal Reduced.pdf

SteveFranzone NNPLicensingManagerCOLA Ilikethedreamsofthefuturebetterthanthehistoryofthepast."ThomasJefferson 561.694.3209(office) 754.204.5996(cell)

This transmission is intended to be delivered only to the named addressee(s) and may contain information that is confidential and /or legally privileged. If this information is received by anyone other than the named addressee(s),

the recipient should immediately notify the sender by E-MAIL and by telephone (561.694.3209) and permanently delete the original and any copy, including printout of the information. In no event shall this material be read, used, copied, reproduced, stored or retained by anyone other than the named addressee(s), except with the express consent of the sender or the named addressee(s).

From: Burski, Raymond Sent: Monday, February 28, 2011 3:03 PM To: Brown, Alison; Bortone, Pilar; Burski, Raymond; David Matthews (david.matthews@nrc.gov); Fernandez, Antonio; Franzone, Steve; Hamrick, Steven; Madden, George; Maher, William; Manny M. Comar (manny.comar@nrc.gov); Orthen, Richard; 'Scott Stewart (scott.stewart@nrc.gov)'; Victor M. McCree

Subject:

FPL Letter L-2011-082 dated 02/28/2011 - Submittal of the Groundwater Model Report Revision 1

Re: Florida Power & Light Company Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 NRC June 2010 Environmental Audit Submittal of Groundwater Model Development and Analysis:

Units 6 & 7 Dewatering and Radial Collector Well Simulations, Revision 1

References:

1. FPL Letter L-2009-144 to NRC, dated June 30, 2009, Application for Combined License for Turkey Point Units 6 & 7
2. NRC Memorandum A. Kugler to R. Whited, dated September 21, 2010, Summary of the Environmental Site Audit Related to the Review of the Combined License Application for Turkey Point Units 6 and 7 Florida Power & Light Company (FPL) submitted a Combined License (COL) Application for two AP1000 pressurized water reactor units to be located at the Turkey Point site, designated Turkey Point Units 6 and 7, located in Miami-Dade County, FL on June 30, 2009 (Reference 1).

During the week of June 7, 2010, the NRC and its contractors conducted a site audit to assist their review of the Environmental Report submitted as part of the COL Application. The NRC issued the site audit summary on September 21, 2010 (Reference 2).

In discussions between FPL and the NRC during the Environmental Site Audit, FPL indicated that a revision of the groundwater model was being performed and would provide information related to several information need requests.

2 The purpose of this letter is to submit the Groundwater Model Development and Analysis, Units 6 & 7 Dewatering and Radial Collector Well Simulations, Revision 1. The report documents the development, calibration, and simulation results of a groundwater flow model of the proposed dewatering systems and radial collector well system for Turkey Point Units 6 & 7.

3 Additionally, this letter is also to inform the NRC that a revision to the groundwater model calculation (Revision

4) has been completed and a copy has been placed in the Reading Room for inspection.

The input/output files for the groundwater model will be provided by separate letter.

Ray Burski New Nuclear Plant - Licensing FPL Contractor (O) 561-694-4496 (C) 504-909-6436 Florida Power & Light Company Mail Stop NNP/JB B3318 700 Universe Blvd Juno Beach, FL 33408-0420 This transmission is intended to be delivered only to the named addressee(s) and may contain information that is confidential and/or legally privileged. If this information is received by anyone other than the named addressee(s), the recipient should immediately notify the sender by E-MAIL and by telephone (561) 694-4311 and permanently delete the original and any copy, including printout of the information. In no event shall this material be read, used, copied, reproduced, stored or retained by anyone other than the named addressee(s), except with the express consent of the sender or the named addressee(s)

Hearing Identifier:

TurkeyPoint_COL_Public Email Number:

230 Mail Envelope Properties (254F03B2E28A7E49922AF0123C7E5210575391DA34)

Subject:

FW: FPL Letter L-2011-082 dated 02/28/2011 - Submittal of the Groundwater Model Report Revision 1 Sent Date:

3/2/2011 9:36:53 AM Received Date:

3/2/2011 9:37:26 AM From:

Franzone, Steve Created By:

Steve.Franzone@fpl.com Recipients:

"Kugler, Andrew" <Andrew.Kugler@nrc.gov>

Tracking Status: None Post Office:

JBXEXVS02.fplu.fpl.com Files Size Date & Time MESSAGE 4202 3/2/2011 9:37:26 AM L-2011-082 dated 02-28-2011 Groundwater Report Submittal Reduced.pdf 3470640 Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received:

Florida Power & Light Company 700 Universe Boulevard, Juno Beach, FL 33408 L-2011-082 10 CFR 52.3 February 28, 2011 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555-0001 Re: Florida Power & Light Company Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 NRC June 2010 Environmental Audit Submittal of Groundwater Model Development and Analysis:

Units 6 & 7 Dewatering and Radial Collector Well Simulations, Revision 1

References:

1. FPL Letter L-2009-144 to NRC, dated June 30, 2009, Application for Combined License for Turkey Point Units 6 & 7
2. NRC Memorandum A. Kugler to R. Whited, dated September 21, 2010, Summary of the Environmental Site Audit Related to the Review of the Combined License Application for Turkey Point Units 6 and 7 Florida Power & Light Company (FPL) submitted a Combined License (COL)

Application for two AP1000 pressurized water reactor units to be located at the Turkey Point site, designated Turkey Point Units 6 and 7, located in Miami-Dade County, FL on June 30, 2009 (Reference 1).

During the week of June 7, 2010, the NRC and its contractors conducted a site audit to assist their review of the Environmental Report submitted as part of the COL Application. The NRC issued the site audit summary on September 21, 2010 (Reference 2).

In discussions between FPL and the NRC during the Environmental Site Audit, FPL indicated that a revision of the groundwater model was being performed and would provide information related to several information need requests.

The purpose of this letter is to submit the Groundwater Model Development and Analysis, Units 6 & 7 Dewatering and Radial Collector Well Simulations, Revision 1.

The report documents the development, calibration, and simulation results of a groundwater flow model of the proposed dewatering systems and radial collector well system for Turkey Point Units 6 & 7.

FPL Turkey Point Units 6 & 7 Project GROUNDWATER MODEL DEVELOPMENT AND ANALYSIS:

UNITS 6 & 7 DEWATERING AND RADIAL COLLECTOR WELL SIMULATIONS Revision 1 Bechtel Power Corporation February 2011 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations TABLE OF CONTENTS EXECUTIVE

SUMMARY

.....................................................................................10 1.0 OBJECTIVE & SCOPE.................................................................................12 2.0 AQUIFER DESCRIPTION & AVAILABLE DATA..........................................12 2.1 Site Overview............................................................................................12 2.2 Regional Hydrostratigraphy......................................................................12 2.3 Biscayne Aquifer.......................................................................................13 2.4 Groundwater Levels..................................................................................15 2.5 Surface Water...........................................................................................16 2.6 Recharge and Evapotranspiration............................................................18 2.7 Hydraulic Conductivity..............................................................................19 2.7.1 Pumping Tests...................................................................................19 2.7.2 Literature Values................................................................................20 2.8 Water Wells...............................................................................................20 3.0 MODEL DEVELOPMENT.............................................................................21 3.1 Conceptual Hydrogeologic Model.............................................................21 3.1.1 Summary of Changes to Model Since Previous Revision of the Report................................................................................................21 3.1.1.1 Conceptual Model.........................................................................21 3.1.1.2 Numerical Model...........................................................................22 3.1.1.3 Calibration and Validation.............................................................22 3.1.1.4 Predictive Runs............................................................................23 3.1.1.5 Sensitivity Analysis.......................................................................23 3.2 Numerical Model.......................................................................................23 3.2.1 Numerical Code.................................................................................23 3.2.2 Numerical Solver................................................................................24 3.2.3 Model Grid..........................................................................................24 3.2.4 Model Layers......................................................................................24 3.2.5 Boundary Conditions..........................................................................25 3.3 Assumptions.............................................................................................26 3.3.1 Equivalent Porous Media...................................................................26 3.3.2 Steady-State Condition......................................................................27 3.3.2.1 Pumping Tests..............................................................................27 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 2 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations 3.3.2.2 Groundwater Flow........................................................................27 3.3.3 Constant-Density................................................................................27 3.3.4 Hydrostratigraphic Units.....................................................................28 3.3.5 Boundary Conditions..........................................................................29 3.3.6 Hydraulic Conductivities.....................................................................31 3.3.7 Precipitation and Evapotranspiration.................................................31 3.3.8 Groundwater Control: Dewatering......................................................32 3.3.9 Radial Collector Wells........................................................................32 4.0 MODEL CALIBRATION................................................................................33 4.1 Calibration Measures and Statistics...........................................................33 4.2 Calibration Criteria....................................................................................35 4.3 Calibration Parameters.............................................................................35 4.4 Calibration Results....................................................................................35 4.4.1 Simulation of Pumping Tests..............................................................36 4.4.1.1 Pumping Test PW-7L..................................................................37 4.4.1.2 Pumping Test PW-1....................................................................38 4.4.1.3 Pumping Test PW-7U..................................................................39 4.4.2 Comparison to Regional Flow Regime................................................40 4.4.3 Comparison with Cooling Canal System.............................................40 4.5 Model Validation.......................................................................................41 4.6 Conclusions..............................................................................................41 5.0 CONSTRUCTION & POST-CONSTRUCTION SIMULATIONS...................41 5.1 Groundwater Control During Construction................................................42 5.2 Post-Construction Radial Collector Well Simulation.................................43 5.2.1 Origins of Water Supplying Radial Collector Wells............................45 5.2.2 Approach Velocity at Bay/Aquifer Interface........................................46 5.2.3 Sensitivity Analysis..............................................................................47

6.0 CONCLUSION

S...........................................................................................48

7.0 REFERENCES

.............................................................................................49 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 3 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations LIST OF TABLES Table 1. Station S20F Rainfall Data for February to May 2009..........................54 Table 2. Station S20F Annual Rainfall Data.......................................................55 Table 3. Extinction Depth and Maximum Evapotranspiration Rate....................56 Table 4. Regional Hydraulic Conductivity Values Based on Onsite Tests and Literature Review.....................................................................................57 Table 5. Surface Water Levels Corrected to Reference Density........................58 Table 6. Model Calibration PW-7L - Horizontal Hydraulic Conductivity.............59 Table 7. Model Calibration PW-7L - Measured Versus Simulated Drawdowns (at end of test)...............................................................................................60 Table 8. Model Calibration PW Measured Versus Simulated Drawdowns (at end of test)...............................................................................................61 Table 9. Model Calibration PW-7U - Measured Versus Simulated Drawdowns (at end of test)...............................................................................................62 Table 10. Model Calibration PW-6U - Measured Versus Simulated Drawdowns (at end of test)..........................................................................................63 Table 11. Radial Collector Wells - Origin of Water (including sensitivity analysis)

.................................................................................................................64 Table 12. Radial Collector Wells - Approach Velocity (including sensitivity analysis)...................................................................................................65 LIST OF FIGURES Figure 1. Location of Turkey Point Units 6 & 7 and Major Hydrological Features

.................................................................................................................66 Figure 2. Industrial Wastewater Facility, the L-31E Canal, and the Card Sound Canal.......................................................................................................67 Figure 3. Regional Generalized Hydrostatigraphic Column...............................68 Figure 4. Site Hydrostatigraphic Column............................................................69 Figure 5. Cross Section Location.......................................................................70 Figure 6. Hydrostratigraphic Cross Section A-A'................................................71 Figure 7. West-East Cross Section in the Vicinity of the Southern End of the Turkey Point Plant Property.....................................................................72 Figure 8. Feasibility Geological Investigation of Potential Plant Site (2006) -

Boring and Stratigraphic Cross Section Locations..................................73 Figure 9. Feasibility Geological Investigation of Potential Plant Site (2006) -

Stratigraphic Cross Section A-A'.............................................................74 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 4 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 10. Feasibility Geological Investigation of Potential Plant Site (2006) -

Stratigraphic Cross Section B-B'.............................................................75 Figure 11. Stratigraphic Cross Section from Wells Drilled for Turkey Point Peninsula Aquifer Performance Test.......................................................76 Figure 12. Turkey Point Units 6 & 7 Site Investigation Observation Well Location Plan.........................................................................................................77 Figure 13. May 1993 Biscayne Aquifer Potentiometric Surface Map.................78 Figure 14. November 1993 Biscayne Aquifer Potentiometric Surface Map.......79 Figure 15. Land Use for Southern Florida..........................................................80 Figure 16. Upper Floridan Aquifer Production Wells for Unit 5...........................81 Figure 17. Numerical Model Domain..................................................................82 Figure 18. Model Grid and Site Features for the Units 6 & 7 Power Block.........83 Figure 19. East-West Model Cross Section towards Southern End of the Turkey Point Cooling Canals...............................................................................84 Figure 20. South-North Model Cross Section along Return Canal of Turkey Point Cooling Canals........................................................................................85 Figure 21. Cooling Canals Water Balance.........................................................86 Figure 22. Extent of Freshwater Limestone and Key Largo Limestone in Model Layer 7.....................................................................................................87 Figure 23. Material Distribution in Biscayne Bay................................................88 Figure 24. Hydraulic Conductivity Anisotropy Values in the Different Formations

.................................................................................................................89 Figure 25. Plan and Cross-Section of Units 6 & 7 Excavations..........................90 Figure 26. Planned Area of Radial Collector Well Caissons Relative to Plant Site Area.........................................................................................................91 Figure 27. Model Calibration - Delineation of Hydraulic Conductivity Zones in the Key Largo Limestone.........................................................................92 Figure 28. Model Calibration - Layout of Pumping Well and Observation Well Clusters for Pumping Tests PW-7L and PW-7U......................................93 Figure 29. Grid Refinement in Vicinity of Unit 7 Reactor Footprint.....................94 Figure 30. Test Well PW-7L and Related Observation Wells.............................95 Figure 31. Test Well PW-7L: Observed Versus Calculated Drawdowns............96 Figure 32. Model Calibration - Pumping and Monitoring Wells Layout for Pumping Test PW-1.................................................................................97 Figure 33. Model Calibration - Finite Difference Grid and Well Layout for Test PW-1........................................................................................................98 Figure 34. Test Well PW-1: Observed versus Calculated Drawdowns..............99 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 5 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 35. Model Calibration - Finite Difference Grid and Well Layout for Test PW-7U...................................................................................................100 Figure 36. Test Well PW-7U: Observed versus Calculated Drawdowns..........101 Figure 37. Simulated Groundwater Contours - Model Layer 1 - Onshore Muck and Offshore Sand/Sediments and Miami Limestone...........................102 Figure 38. Simulated Groundwater Contours - Model Layer 3 - Miami Limestone..............................................................................................103 Figure 39. Simulated Groundwater Contours - Model Layer 4 - Upper Higher Flow Zone..............................................................................................104 Figure 40. Simulated Groundwater Contours - Model Layer 5 - Key Largo Limestone..............................................................................................105 Figure 41. Simulated Groundwater Contours - Model Layer 7 - Freshwater Limestone..............................................................................................106 Figure 42. Simulated Groundwater Contours - Model Layer 9 - Fort Thompson Formation...............................................................................................107 Figure 43. Simulated Groundwater Contours - Model Layer 10 - Lower Higher Flow Zone..............................................................................................108 Figure 44. Simulated Groundwater Contours - Model Layer 14 - Tamiami Formation...............................................................................................109 Figure 45. Existing Cooling Canals Water Balance - Comparison with Groundwater Model...............................................................................110 Figure 46. Model Validation - Layout of Pumping and Observation Wells for Pumping Test PW-6U............................................................................111 Figure 47. Test Well PW-6U: Observed versus Calculated Drawdowns..........112 Figure 48. Location of Units 6 & 7 Construction Dewatering Cut-Off Walls.....113 Figure 49. Location of Units 6 & 7 Construction Cut-Off Walls, Simulated Sump Pumps, and Gridlines............................................................................114 Figure 50. Cross Section of Model Setup for Units 6 & 7 Excavations.............115 Figure 51. Grouting Holes Spacing and Frequency during Proposed Grouting Method...................................................................................................116 Figure 52. Comparison of Pumping Rates under Different Grouting Scenarios

...............................................................................................................117 Figure 53. Post-Construction Recharge Zones for Units 6 & 7........................118 Figure 54. Location of Mechanically Stabilized Earth Retaining Walls around Perimeter of the Turkey Point Units 6 & 7 Plant Area (Excluding the Makeup Water Reservoir)......................................................................119 Figure 55. Location of Radial Collector Wells and Laterals, with Finite-Difference Grid and Pumping Well Locations Overlaid...........................................120 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 6 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 56. Potentiometric Surface within the Upper Higher Flow Zone during Radial Collector Well Simulations..........................................................121 Figure 57. Head Contours in Layer 1 during Radial Collector Well Simulations

...............................................................................................................122 Figure 58. Cross Section through Turkey Point Peninsula Showing Groundwater Contours Resulting from Operation of the RCW System.......................123 Figure 59. RCW Drawdown within the Top Layer............................................124 Figure 60. RCW Drawdown within the Pumped Layer (Upper Higher Flow Zone)

...............................................................................................................125 Figure 61. Origin of Flow to the RCW System (Layer 1)..................................126 Figure 62. Origin of Flow to the RCW System (Layer 2)..................................127 Figure 63. Additional Areas for RCW Approach Velocity Calculation...............128 Figure 64. Calculated Flux of Water between Layers 1 and 2 (Darcy Velocity)129 Figure 65. RCW Drawdown within the Top Layer (0.1 ft drawdown contour) -

Seasonal High and Low Water Level Biscayne Bay..............................130 Figure 66. RCW Drawdown within the Top Layer (0.1 ft drawdown contour) -

Sensitivity Case Biscayne Bay Vertical Hydraulic Conductivity.............131 Figure 67. RCW Drawdown within the Top Layer (0.1 ft drawdown contour) -

Hydraulic Conductivity of Key Largo Limestone....................................132 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 7 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations UNITS cm/s centimeters per second ft/day feet per day ft2/day feet squared per day ft/s feet per second gpm gallons per minute kg/m3 kilograms per meter cubed ABBREVIATIONS ARM Absolute Residual Mean bgs Below Ground Surface CCS Cooling Canal System COLA Combined License Application DEM Digital Elevation Model DRN Drain Package (MODFLOW) epm Equivalent Porous Media FPL Florida Power and Light GHB General-Head Boundary Package (MODFLOW)

GMG Geometric Multigrid (MODFLOW)

HFB Horizontal Flow Boundary Package (MODFLOW)

IWW Industrial Wastewater Facility Kh Horizontal Hydraulic Conductivity Kv Vertical Hydraulic Conductivity Md Mass Balance Discrepancy MNW Multi-Node Well Package (MODFLOW)

MODFLOW Modular Groundwater Flow Model MRGIS Marine Resources Geographic Information System MSE Mechanically Stabilized Earth (Retaining Wall)

NED National Elevation Dataset NAVD 88 North American Vertical Datum of 1988 NOAA National Oceanic and Atmospheric Administration NRMS Normalized Root Mean Square OCS Office of Coast Survey RCW Radial Collector Well RMS Residual Mean Squared RIV River Cell Package (MODFLOW)

SCA Site Certification Application SEE Standard Error of the Estimate FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 8 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 9 of 132 SEGS Southeastern Geological Society SFWMD South Florida Water Management District USGS United States Geological Survey WEL Well Package (MODFLOW)

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations EXECUTIVE

SUMMARY

A groundwater flow model of the Florida Power and Light (FPL) Turkey Point site has been developed for Units 6 & 7. The model is a steady-state, constant-density, three-dimensional representation of the surficial aquifer system developed using the numerical code MODFLOW 2000 developed by the U.S.

Geological Survey (USGS), as it is implemented in the user-interface software Visual MODFLOW developed by Schlumberger Water Services. The groundwater model serves two purposes. The first is to evaluate groundwater control options for construction of Units 6 & 7. The second is to simulate the feasibility of a radial collector well system to serve as a temporary source of make-up water. The original version of this report was issued in support of the Site Certification Application (SCA) completeness review. The groundwater model has been revised in response to review from the South Florida Water Management District and other state and federal agencies. Changes to the model include modifications to the conceptual model, the numerical model, the calibration and validation runs, the predictive runs, and the sensitivity analyses.

Hydrostratigraphic layer elevations were developed from geotechnical and geophysical logs for Units 6 & 7, pumping test wells in the Turkey Point Units 6 &

7 plant area and Turkey Point peninsula, pumping wells from the 1975 Turkey Point plant property Upper Floridan Aquifer study, from historical borings and well logs from the Turkey Point plant property, and from logs for wells in the Florida Geological Survey Lithologic database.

Hydraulic conductivity values were based on results from three historical pumping tests in the Biscayne Aquifer on the Turkey Point plant property, regional groundwater models that include the Turkey Point plant property within their domain, recent pumping tests at the plant area and the Turkey Point peninsula, and literature values.

The interaction between surface water and groundwater was simulated by including Biscayne Bay, the cooling canals, L-31E Canal, Card Sound Canal, Florida City Canal, and Model Land Canal (C-107) in the model. Spatially-variable groundwater recharge and evapotranspiration are considered based on land-use classification.

Calibration was approached with a multi-faceted methodology. Initially, the response to three pumping tests (PW-7L, PW-1, and PW-7U) was simulated by adjusting hydraulic conductivities of the various hydrostratigraphic units comprising the Biscayne Aquifer. The conductance values of the various head-dependent boundary conditions were also primary calibration parameters.

Following the calibration, groundwater flow directions were compared to historical data, and a qualitative comparison of calculated groundwater discharge/recharge between cooling water canals and groundwater beneath Biscayne Bay to results from pre-existing surface water modeling was performed. The groundwater model was then validated by simulating an additional pumping test (PW-6U) and comparing the modeled and observed drawdown values.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 10 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations The conclusion from model simulations of construction dewatering utilizing cut-off walls indicates that by implementing a grout blanket between the base of the excavation and the base of the cut-off walls, dewatering rates can be reduced to between 100 and 1000 gpm.

Particle tracking and water balance calculations from the proposed radial collector wells at the Turkey Point peninsula in Biscayne Bay indicate that approximately 97.8% of the water pumped from the radial collector wells originates in Biscayne Bay. A suite of sensitivity analyses addressing parameter and water level uncertainty indicate that this percentage remains similar for the tested range of variability.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 11 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations 1.0 OBJECTIVE & SCOPE The objective of this report is to document the development, calibration, and simulation results of a groundwater flow model of the proposed dewatering systems and radial collector well system for the Turkey Point Units 6 & 7 Project at the Turkey Point facility.

A three-dimensional groundwater model was used to simulate steady-state, constant-density groundwater flow in the Biscayne Aquifer to evaluate construction and post-construction activities related to the construction and operation of two new nuclear units (Units 6 & 7).

2.0 AQUIFER DESCRIPTION & AVAILABLE DATA 2.1 Site Overview Turkey Point plant property is located in Miami-Dade County, Florida, approximately 25 miles south of Miami (Figure 1) and approximately 9 miles southeast of Homestead. It is bordered on the east by Biscayne Bay, on the west by the FPL Everglades Mitigation Bank, and on the northeast by Biscayne National Park. The 5900-acre Industrial Wastewater Facility (IWW)

(approximately 2 miles wide and 5 miles long), of which 4370 acres is water (approximately 75 percent), is a predominant feature within the Turkey Point plant property (Figure 2). Just west of the IWW is the L-31E canal, which is part of the regional drainage system.

The Units 6 & 7 plant area covers an area of approximately 218 acres and is situated south of Units 1 through 5 within the IWW. The units occupy a relatively small portion of the Turkey Point plant property. The preconstruction ground surface in the Units 6 & 7 plant area is generally flat, with elevations ranging from

-2.4 to 0.8 feet NAVD 88.

Surface waters are a dominant feature of the Turkey Point plant property and surrounding region given that the plant is located between Biscayne Bay and the Everglades. A network of regional canals surround the site boundary and provides drainage for areas west of the Turkey Point plant property. The Units 6

& 7 plant area is within the IWW and is surrounded by cooling canals that return water back to the intake structures for Units 1 through 4.

2.2 Regional Hydrostratigraphy The hydrostratigraphic framework of Florida consists of a thick sequence of Cenozoic sediments that comprise three main units (Reference 1):



The surficial aquifer system (containing the Biscayne Aquifer and semi-confining Tamiami Formation).



The intermediate confining unit, referred to as the Hawthorn Group.



The Floridan aquifer system.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 12 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations In southern Florida, the surficial aquifer system consists of the Tamiami, Caloosahatchee, Fort Thompson, and Anastasia Formations; the Key Largo and Miami Limestones; and undifferentiated sediments. The thickness of the surficial aquifer system ranges from approximately 20 feet to 400 feet and is approximately 220 feet under the Units 6 & 7 plant area.

The intermediate confining unit separates the Biscayne aquifer from the underlying Floridan aquifer system. It is characterized regionally by a sequence of relatively low hydraulic conductivity, largely clayey deposits, but it can locally contain transmissive units that act as an aquifer system. The Southeastern Geological Society (SEGS) (Reference 1) define the intermediate confining unit as all rocks that lie between and collectively retard the exchange of water between the overlying surficial aquifer system and the underlying Floridan aquifer system. This unit is also referred to as the Hawthorn Group, with a thickness of approximately 900 feet in southern Florida.

Beneath the intermediate aquifer system/confining unit is the Floridan aquifer system which underlies all of Florida. The system formally consists of three hydrogeologic units: the Upper Floridan aquifer, the middle confining unit, and the Lower Floridan aquifer. The Upper Floridan aquifer is a major source of potable water in Florida, however, in the southeastern portion of the state (including Miami-Dade County) the water is brackish.

Hydrostratigraphic columns are presented in Figures 3 and 4.

2.3 Biscayne Aquifer The surficial aquifer system within the Turkey Point plant property does not contain all of the regionally identified units. Those units identified within the plant property as a result of the 1971 (Reference 2), 2008 (Reference 3), and 2009 (Reference 4) subsurface investigations are summarized as:



Muck - The surface of the site consists of approximately 2 to 6 feet of organic soils called muck. The muck is composed of recent light gray calcareous silts with varying amounts of organic content. This unit does not extend into Biscayne Bay, where exposed rock and sandy material is present in its place.



Miami Limestone - The Pleistocene Miami Limestone is a white, porous sometimes sandy, fossiliferous, oolitic limestone.



Upper Higher Flow Zone - At the boundary between the Miami Limestone and Key Largo Limestone is a laterally continuous relatively thin layer of high secondary porosity. The Upper Higher Flow Zone was defined based on a review of geophysical logs and drilling records. The primary identifier was the loss of drilling fluid identified at the boundary of the Key Largo Limestone and Miami Limestone. This observation was also coincident with an increase in the boring diameter as identified by the caliper logging.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 13 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations



Key Largo Limestone (interpreted as the Fort Thompson Formation elsewhere) - This is a coralline limestone (fossil coral reef) believed to have formed in a complex of shallow-water, shelf-margin reefs and associated deposits along a topographic break during the last interglacial period.



Freshwater Limestone - At the base of the Key Largo Limestone is a layer of dark-gray fine-grained limestone, referred to as the Freshwater Limestone. Where present, the limestone is generally two feet or more thick and often possesses a sharp color change from light to dark gray at its base marking the transition from the Key Largo Limestone to the Fort Thompson Formation. It is not laterally continuous across the Turkey Point plant property.



Fort Thompson Formation - The Pleistocene Fort Thompson Formation directly underlies the Key Largo Limestone. The Fort Thompson Formation is generally a sandy limestone with zones of uncemented sand interbeds, some vugs, and zones of moldic porosity after gastropod and/or bivalve shell molds and casts.



Lower Higher Flow Zone -At the location of Units 6 & 7, a zone of secondary porosity was evident from the drilling and geophysical logs.

This occurred at a depth of approximately 15 feet below the top of the Fort Thompson Formation and was assumed to extend across the model domain. The regional drilling conducted by the USGS (Reference 5) did not identify a laterally persistent layer but rather more isolated zones at varying depths below the Upper Higher Flow Zone. As represented in the model, the Lower Higher Flow Zone represents an aggregation of these observations and is conservative due to the fact it is modeled as laterally extensive.



Tamiami Formation - The Pliocene Tamiami Formation directly underlies the Fort Thompson Formation. The contact between the Tamiami Formation and the Fort Thompson Formation is an inferred contact picked as the bottom of the last lens of competent limestone encountered. The Tamiami Formation represents a semi-confining unit.

The most permeable portions of the Miami Limestone and Key Largo Limestone are considered to be acting as one hydrogeological unit and designated the Upper Monitoring Zone. The underlying Fort Thompson is designated the Lower Monitoring Zone.

The geology is shown in the following cross sections:



Hydrostratigraphic cross section in the vicinity of the Units 6 & 7 as shown in Figure 5 and Figure 6 (Reference 2).



Geologic cross section across in the vicinity of the Units 6 & 7 as shown in Figure 7 (Reference 6).

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 14 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations



Boring plan and stratigraphic cross sections parallel to and across Units 6

& 7 as shown in Figure 8, Figure 9, and Figure 10 (Reference 7).



Plan and geologic cross section at the Turkey Point peninsula from exploratory drilling and aquifer testing program as shown in Figure 11 (Reference 4).

The following list summarizes the stratigraphic picks for the top of each stratum identified above from geotechnical boring logs and well logs:



Stratigraphic picks from geotechnical boring logs for Units 6 & 7 (Reference 3) B-601 to B-639, B-701 to B-739, and B-802 to B-814.



Stratigraphic picks from boring logs for the 1971 site investigation (Reference 2), L-1 through L-6, and GH-1 through GH-15.



Stratigraphic picks from Upper Floridan aquifer study pumping wells (Reference 2), GB-1 and GB-2.



Geotechnical boring logs from the Feasibility Geological Investigation of Potential Plant Site (Reference 7) borings B-1000 through B-1003.



Additional water well logs available from Florida Geological Survey lithologic database (Reference 8) and the U.S. Geological Survey (USGS)

(Reference 9).



Stratigraphic picks from boring logs for the Turkey Point peninsula (Reference 4) and Units 6 & 7 pumping tests.

In 2010, 14 borings were drilled in and around the Turkey Point plant area as part of the FPL Unit 3 & 4 Uprate Conditions of Certification (Reference 5).

Biscayne aquifer monitoring well clusters were subsequently installed at each of the 14 core borings as part of a monitoring plan. The plan was developed and implemented to satisfy Conditions of Certification IX and X of the Turkey Point Units 3 & 4 Uprate Certification (Reference 10). These well clusters were not included in the stratigraphic picks used to develop the model because they were not available at the appropriate time, but downhole logs (caliper and acoustic) performed by the USGS from these borings were qualitatively assessed to confirm zones of secondary porosity.

2.4 Groundwater Levels During the 2008 subsurface investigation for Units 6 & 7, 22 groundwater monitoring locations were installed within the Units 6 & 7 plant area. Ten observation wells were installed in the Key Largo and Miami Limestone (referred to as the Upper Monitoring Unit) and ten were installed in the Lower Fort Thompson Formation (referred to as the Lower Monitoring Unit). Two piezometers were installed in the Tamiami Formation, one at each proposed reactor site. The 20 observation wells were installed as 10 well pairs, enabling FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 15 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations the determination of the vertical gradient between the upper and lower monitoring units. A description of the field activities and groundwater level data evaluation are presented in Reference 3.

Figure 12 shows the 22 monitoring locations within the Units 6 & 7 plant area.

The observation wells are named in three series, which represent the location and screened intervals as described below:



OW-600 series wells are located in the Unit 6 power block area and include U, L, and D suffix wells monitoring the Miami Limestone, the lower Fort Thompson Formation, and the upper Tamiami Formation.



OW-700 series wells are located in the Unit 7 power block area and include U, L, and D suffix wells monitoring the Miami Limestone, the lower Fort Thompson Formation, and the upper Tamiami Formation.



OW-800 series wells are located outside of the power block areas and include U and L suffix wells that monitor the Miami Limestone and the lower Fort Thompson Formation.

The U and L observation wells recorded hourly water level measurements between June 2008 and June 2010, after which point the transducers were removed and monitoring ceased. Comparison of well clusters (U and L wells) show an upward gradient during both high and low tides at all monitored locations.

Two regional historic Biscayne Aquifer potentiometric surface maps are also available. They cover the following months:



May 1993, Figure 13



November 1993, Figure 14 2.5 Surface Water Surface water features around the Turkey Point plant property are shown on Figure 2 and include the following:



Biscayne Bay - This feature is located east of Units 6 & 7 and is a shallow, subtropical lagoon along the southeastern coast of Florida.

Biscayne Bay is a fairly recent geological feature and has been modified and dredged with average depths ranging from 6 feet to 10 feet. Surface water flow into Biscayne Bay is primarily controlled by the system of canals, levees, and control structures maintained by the South Florida Water Management District (SFWMD). The National Oceanic and Atmospheric Administration (NOAA) maintains a tidal water level and meteorological data collection station (#8723214) on Virginia Key in Biscayne Bay. The station is located on a pier just to the southwest of the causeway that connects Virginia Key to Key Biscayne (Reference 11).

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 16 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Station 8723214 is the closest active station to the study area. The diurnal range, difference in height between mean higher high water and mean lower low water for the station is approximately 2.19 feet (Reference 11).



Cooling Canal System (CCS) (also referred to as the Industrial Wastewater Facility) - The cooling canals are a closed system and do not directly discharge to adjacent surface water, however, the canals are unlined and hence the water interacts with groundwater.

After cooling water passes through the Units 1 through 4 condensers and gains heat, the water is released to the northern end of the 32 westernmost canals. These westernmost canals are approximately 4 feet deep and oriented north-south. The warm water flows towards the southern end of the westernmost canals where it then flows eastward across the southern end of the canals to the seven easternmost canals. These easternmost canals provide the cooling water return, and the circulating pumps are located on the return side, in the northeastern corner of the closed loop system. The pumps in the northeastern corner maintain a head difference of four to five feet relative to the release location. This head difference is the driving force for circulation through the system. Blowdown from Unit 5 also contributes to flow in the CCS.

The head differential created by the circulating water pumps is maintained despite or in addition to the tidal fluctuations. The head differential is a maximum at the northern end of the system; the highest head is in the northern end of the westernmost canals and the lowest head is in the northern end of the easternmost canals. The release of warm water to the northern end of the cooling canals means that the water level in the westernmost canals is always higher than the water level in Biscayne Bay. The intake of return water from the easternmost canals by the circulating pumps, means that the water level in the easternmost canals is always lower than that of Biscayne Bay. At the southern end of the system, the influence of the enforced head differential is relatively lower and water levels are approximately equal to the water level in Biscayne Bay/Card Sound.

Interceptor Ditch - The Interceptor Ditch was constructed in conjunction with the cooling canals to limit inland movement of the water from the cooling canals in the upper portion of the aquifer.

This ditch is about 30 feet wide, 19 feet deep, and has a total length of approximately 29000 feet. The Interceptor Ditch is located about 1000 feet to the southeast of the L-31E canal.

Operation of the Interceptor Ditch prevents seepage from the industrial waste water facility from moving landwards towards the L-31E Canal in the upper portion of the aquifer. The Interceptor FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 17 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Ditch is operated (seasonally) only when required to maintain a seaward hydraulic gradient from L-31E.



L-31E (SFWMD Salinity Structure) - The L-31E Canal (shown in Figure

2) is a stormwater control structure and also provides a salinity barrier that is designed to help prevent saltwater from moving inland. L-31E was constructed prior to the cooling canals being built.

2.6 Recharge and Evapotranspiration The net infiltration, or groundwater recharge, accounts for the rate of net gain of the groundwater system resulting from surface infiltration. Recharge to the Biscayne Aquifer is controlled by land use, and in southern Florida the recharge occurs mainly through wetland areas. Figure 15 indicates major land use classifications used by Langevin (Reference 12) for a regional model of the Biscayne Aquifer.

Based on land use and the Turkey Point facility-related surface conditions, three recharge/evapotranspiration zones are considered for the model domain:



Surface water bodies with continuous head of water, such as Biscayne Bay, the cooling canal system, and regional canals.



Areas of wetland.



Buildings and paved areas.

Surface water bodies, buildings, and paved areas in the model are assumed to have zero recharge and zero evapotranspiration. Recharge applied to the wetland areas is determined by using monthly rainfall data from SFWMD Station S20F (Reference 13) located on canal L-31E. Historically, up to four different rainfall data recorders have been used at Station S20F. The NRG recorder (which reports rain gauge data augmented with radar-based rainfall data), is the preferred data source, but is only available for the most recent two years. The TELE (telemetry, i.e. radio network) and OMD (data received from operation/

main, with multiple sources) recorders are considered to be equally reliable secondary sources of data, for years prior to the NRG record. In years when both TELE and OMD data were available, but NRG data were not, the TELE and OMD records were averaged. Finally, the BELF (Belfort rain gauge) recorder data are used prior to 1992, before the other recorders were available. For the calibration/validation models, a value of 42.6 in/yr is used for the wetlands recharge rate. This value is calculated by summing the total rainfall data for the months during which the on-site 2009 pumping tests were conducted (February to May 2009) and then scaling the total to a year, as shown in Table 1. For the predictive runs, the long-term average rainfall for the period of record at Station S20F was used, giving a recharge rate of 46.75 in/yr, as shown in Table 2.

The evapotranspiration rate and extinction depth for the wetland areas is determined using values from Langevin (Reference 12) presented in Table 3.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 18 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations For the calibration/validation, using maximum evapotranspiration from February to May gives an evapotranspiration rate of 54.52 in/yr. For the predictive runs, maximum evapotranspiration for every month is used to calculate an evapotranspiration rate of 59.50 in/yr. For all models, the extinction depth of 0.69 m (2.26 ft) for wetlands is used (Table 3).

2.7 Hydraulic Conductivity The following sections describe the results from pumping tests and slug tests to evaluate hydraulic conductivity for the Biscayne Aquifer.

2.7.1 Pumping Tests Pumping tests performed within the footprints of Units 6 & 7 power block are summarized as follows:



PW-6U (Key Largo Limestone) - This pumping test was performed in March 2009, with the test well pumped at an average rate of 5103 gpm for eight hours. The test well is located in the footprint of the Unit 6 reactor building. The hydraulic conductivity was estimated to be 3.3 cm/s.



PW-7U (Key Largo Limestone) - This pumping test was performed in February 2009, with the test well pumped at an average rate of 4181 gpm for approximately nine hours. The test well is located in the footprint of the Unit 7 reactor building. The hydraulic conductivity was estimated to be 4.3 cm/s.



PW-6L (Fort Thompson Formation) - This pumping test was performed in March 2009, with the test well pumped at an average rate of 3342 gpm for eight hours. The test well is located in the footprint of the Unit 6 reactor building. The hydraulic conductivity was estimated to be 0.1 cm/s.



PW-7L (Fort Thompson Formation) - This pumping test was performed in March 2009, with the test well pumped at an average rate of 3403 gpm for nine hours. The test well is located in the footprint of the Unit 7 reactor building. The hydraulic conductivity was estimated to be 0.2 cm/s.

A pumping test at Turkey Point peninsula to characterize the hydrogeology for a potential radial collector system is summarized as follows (Reference 4):



PW-1 (Miami Limestone/Cemented Sand/Key Largo Limestone) -

This pumping test was performed in April and May 2009, with the test well pumped at an average rate of 7100 gpm for seven days.

The hydraulic conductivity of the test zone was estimated to be between 10.3 cm/s and 17.6 cm/s based on a reported range of transmissivity between 700000 ft2/day and 1200000 ft2/day.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 19 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations On the Turkey Point plant property, aquifer pumping tests in the Biscayne Aquifer have been performed in three test wells (Reference 2). Figure 5 shows locations of test wells GH-11B, GH-14A, and GH-14B. Pumping test results are summarized as follows:



GH-14A (Miami Limestone) - This pumping test is located to the southeast of L-31E, adjacent to the northwest portion of the cooling canal system. The test was performed in June 1971, with the test well pumped at 1386 gpm for four hours. The hydraulic conductivity was estimated to be 7.9 x 10-2 cm/s.



GH-11B (Key Largo Limestone) - This pumping test is located between Model Land Canal and L-31E. The test was performed in June 1971, with the test well pumped at 1386 gpm for four hours. The hydraulic conductivity was estimated to be 5.1 cm/s.



GH-14B (Fort Thompson Formation) - This pumping test is located to the southeast of L-31E adjacent to the northwest portion of the cooling canals. The test was performed in June 1971, with the test well pumped at 1386 gpm for two hours. The hydraulic conductivity was estimated to be 1.6 cm/s.

2.7.2 Literature Values Several investigations of the Biscayne Aquifer have provided estimates for the hydraulic conductivity of various units of the Biscayne Aquifer. All of these studies have been conducted by either the USGS or SFWMD. Presented in Table 4 is a summary of hydraulic conductivity values for the Biscayne Aquifer.

2.8 Water Wells No water supply wells are located in the Biscayne Aquifer within the plant property. Three production wells (PW-1, PW-2, and PW-4) are located in the Upper Floridan aquifer (Figure 16) and provide process water for Units 1 and 2, and process and cooling tower makeup water for Unit 5. The average production of these wells is approximately 180 million gallons per month.

The Biscayne Aquifer at Turkey Point Units 3 & 4 is also used for disposal of domestic wastewater. A single Class V, Group 3 gravity injection well is used to dispose of up to 35000 gpd of domestic wastewater at the Turkey Point Units 3 &

4 wastewater treatment plant. The well, designated IW-1, is open from 42 to 62 feet bgs and is 8-inches in diameter. Due to the low injection rate (up to 24 gpm) this well is not included in the numerical model.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 20 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations 3.0 MODEL DEVELOPMENT 3.1 Conceptual Hydrogeologic Model The Biscayne Aquifer is conceptualized as consisting of eight hydrostratigraphic units. The base of the model (bottom of the Tamiami Formation) is designated as a no-flow boundary as leakage through the confining Hawthorn Formation is assumed to be negligible.

Recharge to the Biscayne Aquifer occurs primarily in areas of wetland and along the regional series of canals. Discharge from the Biscayne Aquifer occurs to Biscayne Bay, a portion of the cooling canals, and the regional series of canals.

The cooling canals are the dominant stress at the Units 6 & 7 Site.

Evapotranspiration is also a dominant stress on the groundwater system.

The model domain was selected to minimize the impact of assumptions regarding boundary conditions at model sides. The boundaries of the model domain were placed where reasonable assumptions regarding local conditions could be made. Figure 17 shows the model domain. The model area extends several miles beyond the plant property and covers a total area of 47500 feet by 37000 feet (about 63 square miles).

The northern and southern model boundaries were extended several miles beyond the plant property, however they do not coincide with any hydrogeologic features. The eastern model boundary extends into Biscayne Bay, and the western boundary was extended beyond the L-31E canal.

3.1.1 Summary of Changes to Model Since Previous Revision of the Report Numerous changes have been made to this report since the previous revision was issued. A comprehensive listing of modifications is detailed below. The majority of these modifications have arisen from comments provided following review of the groundwater model by state and federal agencies. The intention of these changes is to provide a more robust conceptual and numerical model and to incorporate local knowledge of the Biscayne Aquifer from working practitioners. Other additions of and corrections to various site features were made as a part of the model revision and recalibration process.

3.1.1.1 Conceptual Model



Identification and incorporation of zones of higher hydraulic conductivity based on review of geological and geophysical data. These zones of higher hydraulic conductivity are associated with secondary porosity.

This has resulted in including a zone of higher hydraulic conductivity at the top of the Key Largo Limestone (average elevation of -16.4 feet) and one within the Fort Thompson Formation (average elevation of -52.4 feet).

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 21 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations



Coincident with the refinement of the geology has been a reinterpretation of the geology of Turkey Point peninsula. This reinterpretation incorporated new geophysical data and drilling information.



The muck layer present throughout Biscayne Bay has been revised based on a literature review of sediment/rock type on the floor of Biscayne Bay. This review identified sandy soils and bare rock (Miami Limestone) that had previously been represented as muck.



Incorporation of two hydraulic conductivity zones within the Key Largo Limestone based on prior information and model calibration.



Across the Turkey Point Units 6 & 7 plant area, recharge zones have been delineated to represent post-construction conditions. These updated zones are used for the radial collector well simulations.



The head drop across the circulating water pumps has been updated to the average value observed over the period of the pumping tests, as opposed to spot measurements, which provided a smaller head drop than observed.



All canal depths have been updated to reflect actual conditions.

3.1.1.2 Numerical Model



The base model used for calibration begins with all layering modifications necessary for construction and post-construction simulations.



The model layers are laterally continuous across the model domain.

Previously, surface water features had been incised into layers, resulting in lateral discontinuity between some cells.



The boundary condition used to represent Biscayne Bay has been updated from constant-head to general-head to account for resistance to flow to the bay floor.

3.1.1.3 Calibration and Validation



Three pumping tests are now used in the model calibration phase; two of these tests were conducted in the Key Largo Limestone and one in the Fort Thompson Formation. In the previous revision of the model, two tests had been simulated.



The model now includes a validation step, whereby an additional pumping test is simulated following the calibration phase.



A range for the hydraulic conductivity anisotropy value (horizontal:

vertical) of between 8:1 and 15:1 is used for the various hydrogeologic FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 22 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations units. These values were determined during calibration and constrained by literature and field observations.

3.1.1.4 Predictive Runs Construction



Construction Groundwater Control: Grouting the rock between the base of the excavation and base of the cut-off walls. Grouting simulated to estimate associated dewatering rates.

Operational



Radial Collector Well (RCW) System: Upper Higher Flow Zone and bottom of the Key Largo Limestone evaluated for placement of laterals.



RCW: Flow into the laterals distributed non-linearly along its length to reflect the increase in flow closer to the caisson.

3.1.1.5 Sensitivity Analysis Construction



Construction Groundwater Control: Sensitivity analysis of hydraulic conductivity of grout plug and its effect on seepage rates into the base of the excavations for Units 6 & 7.

Operational



RCW: Sensitivity analysis on Biscayne Bay general-head conductance to determine the origin of water to the radial collector wells and approach velocities to the bay floor.



RCW: Sensitivity analysis on Biscayne Bay seasonal high and low water level to determine the origin of water to the radial collector wells and approach velocities to the bay floor.



RCW: Sensitivity analysis on hydraulic conductivity of the Key Largo Limestone to determine the origin of water to the radial collector wells and approach velocities to the bay floor.

3.2 Numerical Model 3.2.1 Numerical Code The conceptual hydrogeologic model is developed into a three-dimensional numerical groundwater model using the code MODFLOW-2000 (Reference 14).

MODFLOW solves the three-dimensional groundwater flow equation using a FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 23 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations finite-difference method. This code is widely used in the industry since its development by the USGS (Reference 15 and Reference 16).

MODFLOW has a modular structure that allows the incorporation of additional modules and packages to solve other equations that are often needed to handle specific groundwater problems. Over the years several such modules and packages have been added to the original code. MODFLOW-2000 is major revision of the code that expands upon the modularization approach that was originally included in MODFLOW.

The modeling pre-processor Visual MODFLOW (Reference 17) is used to facilitate the development of the FPL Turkey Point Units 6 & 7 groundwater flow model. Visual MODFLOW is developed by Schlumberger Water Services.

3.2.2 Numerical Solver The geometric multigrid solver (GMG) in Visual MODFLOW produces converged solutions for the model, and is used for all simulations presented. The GMG solver uses two convergence criteria, the head change between successive outer iterations and the residual criterion, which is based on the change between successive inner iterations. The model uses the default values of 0.01 feet for the head change criterion and 0.01 feet for the residual criterion.

3.2.3 Model Grid Figure 18 shows the model grid and site features for the power block vicinity. At its finest, the model grid spacing is approximately three feet by three feet within the plant area for Units 6 & 7, and expands to 100 feet by 100 feet at the model perimeter. The grid spacing is also refined in the vicinity of the Turkey Point peninsula, to enable simulation of pumping test PW-1 and the radial collector wells. In this area, the grid spacing is reduced to 25 feet by 25 feet.

3.2.4 Model Layers The model is bounded by the ground surface and bottom of Biscayne Bay on top and the bottom of the Tamiami Formation at the model bottom. A topobathy surface referenced to NAVD 88 was developed for the ground surface topography of the FPL Turkey Point Units 6 & 7 groundwater flow model. A topobathy surface is a surface that combines land elevation and seafloor topography with a uniform vertical datum (Reference 18). Several data sources were reviewed for potential integration into the topobathy surface. The final topobathy surface was developed from the USGSs National Elevation Dataset (NED) Digital Elevation Models (DEMs) (Reference 19) and NOAAs Office of Coast Survey (OCS) harbor soundings (Reference 20). The selection of the final datasets was based primarily on which two datasets produced the smoothest shoreline transition.

Fourteen model layers are included as follows:

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 24 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations



Model Layer 1 - Onshore organic soils, referred to as Muck and Marl.

Offshore sand/sediment and Miami Limestone.



Model Layers 2/3 - Marine limestone, referred to as the Miami Limestone.



Model Layer 4 - Marine limestone, referred to as the Upper Higher Flow Zone.



Model Layer 5/6 - Marine limestone, referred to as the Key Largo Limestone (divided into two areal zones based on prior information).



Model Layer 7 - Freshwater limestone, referred to as the Freshwater Limestone, and where this is absent the Key Largo Limestone.



Model Layer 8/9 and 11/12/13 - Marine limestone, referred to as the Fort Thompson Formation.



Model Layer 10 - Marine limestone, referred to as the Lower Higher Flow Zone.



Model Layer 14 - Marine limestone or sandstone, referred to as the Tamiami Formation.

Elevations are assigned to each model cell based on the results of the interpolation of stratigraphic picks. Figure 19 and Figure 20 show cross sections of the model with relevant features highlighted.

3.2.5 Boundary Conditions The model incorporates several types of boundary conditions, including river cells, recharge cells, evapotranspiration cells, general-head cells, horizontal flow barrier cells, and no-flow cells. A brief description of boundary conditions as they are used in the model is provided below:



River Boundary - (1) Cooling Canal System, (2) L-31E, (3) C-107, (4)

Card Sound Canal, and (5) Florida City Canal: The river boundary condition allows leakage into the model or leakage out of the model based on (a) specified surface water elevation in the canal, (b) simulated groundwater elevations in adjoining grid cells, and (c) sediment conductance at the bottom and sides of the canals. River cells are employed in lieu of constant head cells to allow flexibility to adjust the conductance and hence flow to adjoining cells during calibration.



Recharge Boundary - Model Layer 1: The recharge boundary condition is applied at the ground surface (top of model layer 1) and simulates the effect of infiltration from precipitation (before evapotranspiration losses).

Recharge in the model is only applied to land surfaces (no recharge is applied to surface water features).



Evapotranspiration Boundary - Model Layer 1: The evapotranspiration boundary condition is applied at the ground surface (top of model layer 1) and simulates the effects of plant transpiration and direct evaporation by FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 25 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations removing water from the saturated groundwater regime. Evapotranspira-tion is applied only over land surfaces in the model.



General-Head Boundary (GHB):

o (1) Model Sides: General-head boundary conditions are assigned to the perimeter of all layers. The general-head boundary represents the influence of conditions beyond the model area. Flow through the onshore general-head boundaries is influenced by aquifer recharge in the Everglades area.

o (2) Biscayne Bay: General-head boundary conditions are assigned to the top of model layer 1 to represent the exchange of water between Biscayne Bay and the underlying aquifer.

The specified head in the GHB cell is based on tidal monitoring at Virginia Key. Use of the GHB condition rather than the constant head condition allows for limiting the exchange of water between Biscayne Bay and the underlying aquifer based on the properties of the sea floor sediments.



Horizontal Flow Barrier Boundary - Mechanically Stabilized Earth (MSE)

Retaining Wall and Cut-Off Walls for Units 6 & 7: The horizontal flow barrier boundary is used to simulate the effects of the excavation cut-off walls surrounding the power blocks for Units 6 & 7 for construction dewatering and also the MSE retaining wall surrounding the Units 6 & 7 plant area (excluding the makeup water reservoir). This package was developed to simulate the effects of thin, vertical, low hydraulic conductivity features that restrict the horizontal flow of groundwater.



No-Flow Boundary - Bottom of Model: The bottom of the model is designated a no-flow boundary because water levels in the Biscayne Aquifer are expected to be negligibly affected by upward leakage through the Lower Tamiami Formation and Hawthorne Group, which is several hundred feet thick and acts as a confining layer.



No-Flow Boundary - Units 6 & 7 Excavations: The excavations are designated as inactive to flow. Minor seepage will occur through the cut-off walls into the excavations but the quantities will be insignificant.

3.3 Assumptions The model development includes the assumptions described below.

3.3.1 Equivalent Porous Media Assumption: The flow regime is simulated using an equivalent porous media (epm).

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 26 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Rationale: The effects of small-scale heterogeneities become averaged when used in an analysis of this scale. Preferential higher flow zones identified at the site are relatively thin and are expected to have laminar flow; therefore, they can be represented in the model by assigning higher hydraulic conductivities to these zones using an epm approach (as opposed to conduit flow).

3.3.2 Steady-State Condition 3.3.2.1 Pumping Tests Assumption: The pumping tests can be modeled by matching the steady-state drawdown values in each observation well rather than a transient simulation matching the entire drawdown curve.

Rationale: Steady-state conditions from the pumping tests are reached after a very short period of time due to 1) the confined nature of the test zones, and 2) the high hydraulic conductivity of the test zones.

3.3.2.2 Groundwater Flow Assumption: The cooling canals are assumed to be in steady-state.

Rationale: Previous modeling of the cooling canals assumed the system was in equilibrium and hence steady state. Figure 21 presents the balance of flows as documented in a previous study. This balance assumes that the existing units are operating at capacity. This assumption is conservative for determination of origins of water to the radial collector wells.

3.3.3 Constant-Density Assumption: The flow regime is simulated with a constant-density groundwater model.

Rationale: The primary purpose of this groundwater model is to estimate quantities for excavation dewatering and to evaluate the influence of the radial collector wells. For these two localized areas of interest the pressure influences of density variation are insignificant relative to the hydraulic gradient imposed by pumping.

Assumption: Seawater is used as the reference fluid.

Rationale: For a constant density model, water levels should be normalized to a reference fluid to satisfy the steady-state, constant-density equation. Water levels in the model are normalized to a saline reference density of 1022.4 kg/m3. The hypersaline water of the cooling FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 27 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations canal system and the freshwater of the drainage canals are adjusted to seawater using the following equation:

w r

r w

w r

w r

z h

h

















Where:

hr is the head at the reference density hw is the observed head at the natural density zw is the water (canal) depth at the natural density w

 is the natural density of the water r

 is the reference density For the calibration cases where the Biscayne Bay level is -1.05 feet NAVD 88, normalized head values at locations around the cooling canals and stormwater management canals are presented in Table 5.

3.3.4 Hydrostratigraphic Units Assumption: The Freshwater Limestone is assumed to be absent if the contoured thickness is less than 1.5 ft.

Rationale: It is possible that this layer is laterally continuous and where it is not observed it is due to the method of drilling used. A more likely explanation is that due to the freshwater nature of the deposit it is not laterally continuous and the assumed distribution is a reasonable interpretation. Figure 22 shows the extent of the Freshwater Limestone in the model.

Assumption: The Upper and Lower Higher Flow Zones are assumed to be laterally continuous. The Upper Higher Flow Zone is assumed to be present on top of the Key Largo Limestone over the model domain. The Lower Higher Flow Zone is assumed to be present 15 feet below the top of the Fort Thompson Formation over the model domain.

Rationale: Review of borings logs indicates mud loss at the contact between the Miami Limestone and Key Largo Limestone. Caliper logs also indicate an enlarged boring diameter at this depth. This layer is identified across the site and designated the Upper Higher Flow Zone.

At Units 6 & 7, where the majority of borings exist, another higher flow zone is identified at approximately 15 feet below the top of the Fort Thompson Formation. Its laterally continuity across the site is not as obvious as the Upper Higher Flow Zone; however, for the purposes of this model it is assumed to be laterally extensive. Uprate monitoring borings, drilled as part of FPL Units 3 & 4 Uprate Conditions of Certification (Reference 5) in 2010 confirm these interpretations Assumption: The Upper and Lower Higher Flow Zones are assumed to have a thickness of one ft.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 28 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Rationale: A study conducted by Renken et al. (Reference 21) suggested a thickness of three feet for an aerially extensive zone of higher hydraulic conductivity. Because the transmissivity of the units needs to be preserved during calibration, selecting a smaller thickness for these units will permit a higher hydraulic conductivity, which will facilitate preferential flow and hence be conservative.

Assumption: Hydrostratigraphic units in layer 1 are assumed to be distributed as shown in Figure 23.

Rationale: Layer 1 of the model represents the hydrostratigraphic units located at ground surface on land or on the floor of Biscayne Bay.

Muck is known to be present on land (Reference 3); however, this unit does not extend into Biscayne Bay, where exposed rock and sandy material is present in its place. Hydrostratigraphic units in Biscayne Bay were assigned using the Marine Resources Geographic Information System (MRGIS) Benthic Habitats - South Florida file (Reference 22). Benthic zones designated as Continuous Seagrass were designated as sandy material in layer 1 as loose material is necessary to support seagrass. Patchy (Discontinuous) Seagrass and Hardbottom with seagrass benthic zones were designated as rock in layer 1.

3.3.5 Boundary Conditions Assumption: Upward leakage through the Hawthorn Group to the Biscayne Aquifer is assumed to be sufficiently small that it will have negligible effect on flow paths within the Biscayne Aquifer, so the bottom of the Tamiami Formation is assumed to be a no-flow boundary for this model.

Rationale: The Hawthorn Group has a relatively low hydraulic conductivity and is hundreds of feet thick in South Florida.

Assumption: The cooling canals and regional canals can be modeled by the MODFLOW River Package (RIV).

Rationale: The River Package is applicable to surface water bodies that can either contribute water to the groundwater system, or act as groundwater discharge zones, depending on the hydraulic gradient between the surface water body and the groundwater system.

Assumption: Biscayne Bay has a surface water elevation of -1.05 feet NAVD 88 in the model for the model calibration and validation phases.

Rationale: This value is the average of the monthly average surface water elevation between February 2009 and May 2009. This time period is when the pumping tests used for calibration and validation occurred.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 29 of 132 Assumption: The head difference between release and intake structures of the cooling canals is assumed to be 4.66 feet.

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Rationale: Field monitoring during the period of the pumping tests showed an average head difference of 2.33 feet between the barge canal (Biscayne Bay) and the intake basin. Because the southern end of the cooling canal system is assumed to be equal to the water level in Biscayne Bay, and the head difference assumed to be equal between the intake and release sides, the head difference across the circulating water pumps is therefore twice the difference between the barge canal and intake basin, or 4.66 feet. Additional observations to confirm the field monitoring indicate that the water level on the east or intake side of the cooling canal system is drawn down about three feet lower than the water level on the west or release side of the cooling canal system. Field observations in 2009 also provide a similar number for the head difference.

Assumption: The 4.66 feet head drop between release and intake structures of the cooling canals can be equally distributed between the south flowing cooling canals and the north flowing cooling canals. Based on the surface water elevation for Biscayne Bay, the following water levels are assigned to the intake and release sides for Units 1 through 4:

Release side of Units 1 though 4 is 1.28 feet NAVD 88.

Lake Rosetta (intake structure) is -3.38 feet NAVD 88.

Rationale: The flowpath length for the release side and return canals is approximately equal.

Assumption: Water level at the southern end of the cooling canals is assumed to be equal to the water level in Biscayne Bay/Card Sound.

Rationale: Site information indicated that at the southern end of the cooling canal system the water level is approximately equal to the water level in Biscayne Bay/Card Sound.

Assumption: A thickness of 0.1 feet of sediment is assumed to have built up in the cooling canals.

Rationale: Negligible silt build up is assumed to occur due to the scouring action of the water and the flushing as a result of tide changes and the high hydraulic conductivity of the Miami Limestone.

Assumption: Water level in:

L-31E is 0.02 feet NAVD 88.

Interceptor Ditch is -0.28 feet NAVD 88.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 30 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Westernmost release side cooling canal is 1.08 feet NAVD 88 at northern end dropping linearly to -1.05 feet NAVD 88 at the southern end.

Rationale: Water level in the interceptor ditch is maintained (by pumping) at a certain level to induce a seaward hydraulic gradient, ensuring that water from the cooling canals does not move inland in the upper portion of the aquifer. The Interceptor Ditch is operated (seasonally) only when required to maintain a seaward hydraulic gradient.

3.3.6 Hydraulic Conductivities Assumption: The anisotropy ratio is determined by calibration and limited to a value between 1:1 and 15:1 for all layers (Kh:Kv).

Rationale: Anisotropy was estimated from Figure 24, which tends to cluster between a value of 1:1 and 10:1. This figure presents the results of a USGS study by Cunningham et al. of horizontal and vertical air permeability measurements on core samples from the Biscayne Aquifer (References 23 and 24). Subsequent work by the same author (Reference 25) indicates similar anisotropy ratios. An upper limit of 15:1 was designated to allow for large-scale features not represented by the core samples.

Assumption: The hydraulic conductivity of material accumulated in the bottom of the cooling canals is assumed to be 1 x 10-5 cm/s.

Rationale: This represents a standard value for the hydraulic conductivity of silty sand (Reference 26).

3.3.7 Precipitation and Evapotranspiration Assumption: Groundwater recharge zones are separated into two zones.

Rationale: Two groundwater recharge zones are used in the model.

These zones represent 1) a recharge value of zero applied to: open water and the existing plant area that is paved and impermeable, and 2) wetlands, which have a constant recharge rate. These recharge zones are based on the land use classifications of Langevin as shown in Figure 15 (Reference 12).

Assumption: Evapotranspiration zones are the same as the groundwater recharge zones.

Rationale: Impermeable areas and open water will also have zero evapotranspiration. Wetland areas will have a constant evapotranspiration rate.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 31 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations 3.3.8 Groundwater Control: Dewatering Assumption: Figure 25 shows the location of the excavation cut-off walls for constructing Units 6 & 7 structures. The elevation of the base of the excavation is -35 feet NAVD 88 and the cut-off wall depth has been revised from -65 to -60 feet NAVD 88. The thickness of the cut-off walls is 3 feet.

Rationale: The cut-off wall depth has been raised to -60 feet NAVD 88 to avoid setting the toe within the Lower Higher Flow Zone. Borings logs at Units 6 & 7 indicate that the Lower Higher Flow Zone occurs at approximately -65 feet NAVD at this location.

Assumption: The walls are assumed to have a hydraulic conductivity of 1 x 10-8 cm/s.

Rationale: The design value for the hydraulic conductivity of the cut-off walls is 8.3 x 10-10 cm/s (Reference 27). A value of 1 x 10-8 cm/s is a conservative estimate that will provide an upper bound on the dewatering rate.

Assumption: Units 6 & 7 are excavated and dewatered sequentially.

Rationale: The construction schedule shows the power block excavations to be excavated sequentially.

Assumption: The rock between the base of the cut-off walls and base of the excavation can be grouted to a hydraulic conductivity of 1 x 10-4 cm/s.

Rationale: A value of 1 x 10-4 cm/s is an industry standard for this type of formation (Reference 28 and 29).

3.3.9 Radial Collector Wells Assumption: The three western-most radial collector wells and laterals are modeled as operational for plant operations. Figure 26 shows the general location where all four of the radial collector wells will be located.

Rationale: This simulation will provide a conservative estimate of the quantity of water originating from inland due to the proximity of the radial collector wells to land.

Assumption: Operation of the radial collector wells is simulated using the MODFLOW WEL package.

Rationale: Use of the WEL package is a documented method of simulating horizontal wells (Reference 30). Other methods within MODFLOW of simulating the radial collector wells could include the drain package (DRN) and the multi-node well package (MNW).

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 32 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Assumption: Operation of the radial collector wells is simulated as steady-state.

Rationale: The radial collector wells are intended to be operated only when the primary source of makeup water is not available. Simulating the radial collector wells on a steady-state basis provides the maximum drawdown from the wells and is therefore a conservative approach.

Assumption: The laterals are assumed to be 700 feet in length with a maximum of 300 feet of screened casing at the end of the lateral.

Rationale: A conceptual engineering study (Reference 31) provided an upper estimate of 900 ft for the length of the laterals. This value was adjusted during modeling to remain outside the boundary of the Biscayne National Park. A shorter lateral provides a more conservative estimate. It should also be noted that the layout will go through a formal design process at a later stage.

Assumption: Flow to the radial collector wells is distributed non-linearly along the laterals.

Rationale: The head difference between the water level in the lateral and outside the lateral is greatest closest to the caisson and smallest at the end of the lateral.

4.0 MODEL CALIBRATION A multi-faceted approach to calibration was taken that included the following:



Calibration to pumping tests on the Turkey Point plant property.



Verification using a pumping test on the Turkey Point plant property.



Performing a qualitative comparison of calculated groundwater flows to and from the cooling canal system with an analytical water balance (Reference 32).



Qualitatively comparing model wide groundwater flow directions with published potentiometric surface maps.



4.1 Calibration Measures and Statistics Several parameters providing different measures of the agreement between simulated and observed drawdown levels were used for the calibration of the model. These parameters are defined in terms of the calibration residuals of the drawdown defined as the difference between calculated and observed drawdown. The calibration residual, at a point i is defined as:

i R

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 33 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 34 of 132 i

(1) model obs i

i R =

X -

X Where:

is the calculated drawdown at point i; and model i

X is the observed drawdown at point i.

obs i

X The residual mean, R is a measure of the average residual value and is defined by the equation:

n i

i=1 1

R=

R n 

(2)

Where n is the number of points where calculated and observed values are compared.

The absolute residual mean (ARM),

R is a measure of the average absolute residual value and is defined as:

n i

i=1 1

R =

R n 

(3)

The Root Mean Squared (RMS) residual is defined by:

1/2 n

2 i

i=1 1

RMS=

R n








(4)

The normalized root mean squared (NRMS) is the RMS divided by the maximum difference in the observed drawdown values. It is given by the following equation:

obs obs max min RMS NRMS=

X X

(5)

A measure of the numerical convergence of each run is the discrepancy between inflows and outflows from the model domain. To satisfy the overall mass balance, this discrepancy should be zero. In practice, however, a mass balance of zero may not be possible. The aim in obtaining a converged numerical solution is to achieve a mass balance Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations discrepancy as small as possible. The numerical mass balance discrepancy, Md, is calculated using the following equation:



in out d

in out V -V M = 1 V +V 2

(6) where Vin is total flow into the model domain; and Vout is total flow out of the model domain.

The final measure of the adequacy of the calibrated model is the discrepancy between the cooling canal system inflows and outflows determined by the groundwater model and the steady-state water balance determined by the site surface water model (Reference 32). Flow values for the groundwater model are determined by assigning flow zones across the discharge and recharge sides of the cooling canal system. Fluxes into and out of these zones are then calculated and compared with the water balance. In a successful calibration, the mass balance discrepancy between the two models will be as small as possible.

4.2 Calibration Criteria The following criteria for calibration measures and statistics were used for model calibration:



Root mean squared residual (RMS) < 1 ft;



Normalized root mean squared residual (NRMS) < 10 percent;



Absolute residual mean (ARM) < 1 ft;



Numerical mass balance discrepancy (Md) < 0.1 percent;



Physical mass balance in the cooling canal system within an order of magnitude of the water balance from the surface water model.

4.3 Calibration Parameters The primary calibration parameters were the hydraulic conductivity, and also the conductance for head dependent boundary conditions (cooling canals, regional canals, Biscayne Bay and model sides). These parameters were varied to achieve satisfactory agreement between simulated and observed pumping test drawdowns, regional flow directions, and flow magnitudes.

4.4 Calibration Results The original intent was to utilize the steady-state drawdown values from pumping tests PW-7L and PW-1 as the calibration data set and then validate the model using an additional pumping test from the suite conducted in the vicinity of the FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 35 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations proposed Units 6 & 7 power blocks. Following calibration to the two tests, the validation case was run (pumping test PW-7U) and the results demonstrated that the model could not replicate the drawdown values observed at the end of this test. As a result, the validation data set subsequently became part of the calibration data set and an additional pumping test (PW-6U) was used for model validation. As the model was able to adequately replicate the drawdown values from the PW-6U pumping test, model validation was achieved.

4.4.1 Simulation of Pumping Tests Parameter estimation was performed using manual optimization, whereby model parameters were changed on a trial-and-error basis until a satisfactory match was observed between observed and modeled drawdowns. The procedure used to calibrate the model to the drawdown data was to run the model to steady state with no wells operating for an assumed set of model parameters. Following this run, the steady-state head at each of the monitoring well locations was noted and used as the initial head for the simulation with the pumps operating. Following the execution of the model with the pumping well operating, the model drawdown at each well was calculated by subtracting the final head from the starting head values. This model-determined drawdown was then compared to the observed drawdown to calculate calibration statistics. Model parameters were then adjusted to match the observed drawdown values, and the process described above was then repeated. In addition to adjusting the hydraulic conductivity of the hydrogeologic units, the conductance of the general-head boundaries was also adjusted to represent changes in the properties of the layers, thereby tying the conductance of all general-head boundary cells to the hydraulic conductivity of the layer that the boundary cell is contained within.

Initially, the model was calibrated to two pumping tests: PW-7L and PW-1.

During the calibration process, the hydraulic conductivity of all layers was allowed to vary within a predefined range, which was determined from the literature and site hydrogeologic parameters given in Table 4. Following adequate calibration to these two tests, pumping test PW-7U was simulated with the parameters determined from the prior utilization. This simulation provided a poor match to test PW-7U, and as a result a series of forward runs were conducted where the hydraulic conductivity of the Key Largo Limestone was varied to improve the match. Following an adequate match to PW-7U, it was observed that PW-1 was unacceptably degraded. It was then concluded that a satisfactory match to both the PW-7U and PW-1 drawdown data could not be achieved by treating the hydraulic conductivity of the Key Largo Limestone as a homogeneous property.

The final phase in calibrating involved holding constant parameters below the Freshwater Limestone from the first optimization and further optimizing to the two tests conducted in the Key Largo Limestone. In order to achieve satisfactory calibration, it was necessary to introduce two hydraulic conductivity zones within the Key Largo Limestone, which were delineated based on two pieces of prior information. The first piece of prior information was an observation from the 2010 drilling program that the upper portion of the Fort Thompson Formation FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 36 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations (synonymous here with the Key Largo Limestone) exhibited heterogeneity across the model domain. The second was from the type-curve analysis of pumping tests conducted at the nuclear island (the Units 6 & 7 containment building, shield building, and auxiliary building) and at the Turkey Point peninsula; the tests at the nuclear island consistently demonstrated a lower hydraulic conductivity than the one conducted at the Turkey Point peninsula. The zones were established by drawing a line between PW-1 on the Turkey Point peninsula and the nuclear island, bisecting the line, and then extending another line perpendicular from this point until it intersected the boundaries of the model domain. The two zones are displayed in Figure 27. The strategy behind this approach was to fix the dominant parameters controlling test PW-7L, hence trying to maintain an optimal calibration and then only allowing parameters above the Freshwater Limestone to vary, which provide primary control on the tests in the Key Largo Limestone. It was important to check this final phase of calibration by simulating all tests separately to ensure that well interference from simulating multiple tests at the same time did not affect the results. In addition, following each round of optimization, the starting heads were updated, and the conductance value for each general head boundary cell was updated to reflect the new hydraulic conductivity value in the direction of flow. These steps were necessary because the optimization runs only updated the hydraulic conductivity of the model layers. The final hydraulic conductivity values determined from the model calibration are presented in Table 6 and fall within the limits defined by the literature and site review of hydrogeologic parameters.

4.4.1.1 Pumping Test PW-7L Calibration to pumping test PW-7L results was performed by simulating the steady-state response to pumping from the Fort Thompson Formation within the footprint of the proposed reactor building for Unit 7. This test was one of four conducted in the first quarter of 2009 to assess the feasibility of construction dewatering. Two tests were conducted within the footprint of each of the reactor buildings for Units 6 & 7, one in the Key Largo Limestone (U or upper test zone),

and one in the Fort Thompson Formation (L or lower test zone). The layout of the test (test well and monitoring wells) for this phase of calibration is shown in Figure 28. The notation used for the observation well naming is as follows:

CX-#$ where:

X = Reactor building (6 or 7)

  1. = Number indicating well position 1= approximately 10 feet east of upper zone test well 2= approximately 10 feet north of upper zone test well 3= approximately 25 feet north of upper zone test well 4= approximately 40 feet north of upper zone test well 5= approximately 10 feet east of lower zone test well FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 37 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations

$ = Alphabetic character designating the well monitoring zone A= Miami Limestone B= Freshwater Limestone C= Tamiami Formation D= Key Largo Limestone E= Fort Thompson Formation The constant rate test of well PW-7L was conducted in March 2009, with an average discharge rate of 3403 gpm for nine hours.

The rationale for selecting test well PW-7L is:



The hydrogeological units overlying the Fort Thompson formation and within the footprint of the excavation will be contained by a cut-off wall with the implication that the deeper zone tests are more relevant.



The PW-7L pumping test data were considered more complete than the PW-6L data.

The refined grid in the area of Unit 7 is presented in Figure 29 along with a close-up showing the test and observation wells in Figure 30. The model interpolates the numerical results calculated at the grid nodes to the input locations of the observation wells. Because water levels in the Fort Thompson Formation stabilized within ten minutes of turning on the pump, the test was simulated by matching the drawdown values at the end of the test only. The rationale for this is that the test had reached steady-state and hence a transient simulation was not necessary.

Results of the pumping test simulation are tabulated in Table 7. This shows simulated and measured drawdown values in each of the monitoring wells that were instrumented. The drawdown response was well matched.

A plot of observed versus simulated drawdown is presented in Figure 31 for all monitored layers. The normalized root mean square for all layers is 7.9%, which is considered acceptable for this model and is within the calibration criteria established in Section 4.2.

4.4.1.2 Pumping Test PW-1 An exploratory drilling and aquifer testing program was performed on the Turkey Point peninsula to assess the hydraulic properties of the Biscayne Aquifer (Reference 4). The aim of the program was to provide data to help determine whether a radial collector well system could be implemented at this location to meet the water-supply requirements for Units 6 & 7.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 38 of 132 The pumping well, PW-1 was open across the Key Largo Limestone. Five monitoring wells were installed at radial distances of between 75 feet and 2070 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations feet of the pumping well. Monitoring wells at all radial distances are screened in the Key Largo Limestone to monitor water levels in the test zone. In the case of the closest monitoring well, the zones immediately above (Miami Limestone) and below (Fort Thompson Formation) the test zone are also monitored. The layout of the test (test well and monitoring wells) is shown in Figure 32. The constant rate test of well PW-1 was conducted in April and May of 2009, with an average discharge rate of 7100 gpm for seven days.

The finite-difference grid in the area of the Turkey Point peninsula and the wells (pumping and observation) is presented in Figure 33. Results of the pumping test simulation are tabulated in Table 8. This shows simulated and measured drawdown values in each of the monitoring wells that were instrumented. The drawdown response was well matched.

A plot of observed versus simulated drawdown is presented in Figure 34 for all monitored layers. The normalized root mean square for all layers is 5.3%, which is considered acceptable for this model and is within the calibration criteria established in Section 4.2.

4.4.1.3 Pumping Test PW-7U Calibration to pumping test PW-7U results was performed by simulating the steady-state response to pumping from the Key Largo Limestone within the footprint of the proposed reactor building for Unit 7. The layout of the test (test well and monitoring wells) for this phase of calibration is shown in Figure 28 and follows the same notation as test PW-7L described in Section 4.4.1.1.

The constant rate test of well PW-7U was conducted in March 2009, with an average discharge rate of 4181 gpm for just under nine hours. As shown in Figure 28, observation wells were constructed in all geologic units of the Biscayne Aquifer to monitor the water level response to pumping.

PW-7U was selected as part of the calibration data following its unsuccessful use to validate the model after calibration to PW-7L and PW-1 alone. The grid refinement presented for PW-7L also covers the same area for PW-7U and is presented in Figure 29 along with a close-up showing the test and observation wells in Figure 35.

Because water levels in the Key Largo Limestone stabilized within ten minutes of initiating pumping, the test was simulated by matching the drawdown values at the end of the test only. The rationale for this is that the test had reached steady-state and hence a transient simulation was not necessary.

Results of the pumping test simulation are tabulated in Table 9, which shows simulated and measured drawdown values in each of the monitoring wells that were instrumented. The drawdown response was well matched with the exception of monitoring well C7-1D, which shows greater drawdown compared to C7-2D, both of which are equidistant from the test well. The difference in drawdown between the observation wells could suggest localized heterogeneity FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 39 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations and/or well construction issues or instrument malfunction. Review of the well construction information and both the raw data and processed data files did not indicate any obvious well construction or data collection issues that would cause the difference in drawdown. The difference in drawdown between these two wells is likely attributable to small-scale heterogeneities that are not captured in the model. A plot of observed versus simulated drawdown is presented in Figure 36 for all monitored layers.

The normalized root mean square for all layers is 11.3%. Although the NRMS is marginally outside the criterion established in Section 4.2, the RMS, ARM, and Md are all within limits. This result is considered adequate because the model is also calibrated to two other pumping tests, compared to the regional flow regime, and additionally calibrated to a water balance for the cooling canal system.

4.4.2 Comparison to Regional Flow Regime For matching of regional flow direction and patterns, simulated groundwater contours and levels were compared to potentiometric surface maps for the Biscayne Aquifer from May and November 1993 (Figure 13 and Figure 14).

The intention of this is to qualitatively capture the overall flow paths and direction.

Figure 37 through Figure 44 show the simulated heads for each of the hydrostratigraphic units, indicating a predominant flow direction from west to east, which is in agreement with Figure 13 and Figure 14. Flows are more complex in the vicinity of the cooling canals due to the exchange of water between the canals and groundwater. These nuances are not captured in the larger flow picture shown in Figure 13 and Figure 14.

4.4.3 Comparison with Cooling Canal System The interaction of groundwater with the surface water comprising the cooling canal system was assessed by comparing model results against estimates obtained from an independent water balance model on a steady-state basis. The water balance model for the cooling canal system is displayed schematically in Figure 21 (Reference 33). The model accounts for flow from the release side of the cooling canals downward to the groundwater beneath the canal system and flow from underneath Biscayne Bay inward and upward to the return canals.

This figure has been updated to include the simulated flow rates from the groundwater model and is shown in Figure 45. The area outlined in blue shows that part of the surface water model that is replicated in the current groundwater model. The top figure for each parameter (net blowdown and net makeup) represents that from the surface water model while the lower figure is the calculated value from the groundwater model. Values for comparison were determined from the groundwater model by assigning flow zones across the release and return sides of the cooling canal system. Fluxes into and out of these zones were then calculated for comparison with the water balance. A comparison of the values indicates that the groundwater model shows up to 31 percent higher cooling canal system makeup and blowdown values than the FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 40 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations surface water. This is considered an acceptable match given that the cooling canal system water balance is a simple analytical model.

4.5 Model Validation The PW-6U test, conducted in the Key Largo Limestone at the location of the proposed site of the Unit 6 power block, was used for model validation. The test and monitoring well layout is depicted in Figure 46 and uses the same numbering system as described in Section 4.4.1.1.

The constant rate test of well PW-6U used an average discharge rate of 5103 gpm for eight hours. As shown in Figure 46, observation wells were constructed in all geologic units of the Biscayne Aquifer to monitor the water level response to pumping.

Results of the pumping test simulation are tabulated in Table 10. This shows simulated and measured drawdown values in each of the monitoring wells that were instrumented. The drawdown response was well matched.

A plot of observed versus simulated drawdown is presented in Figure 47 for all monitored layers. Although the NRMS of 11.4% is marginally outside the criterion established in Section 4.2, the RMS, ARM, and Md are all within limits.

These results are considered acceptable for model validation, considering that PW-6U data are completely independent.

4.6 Conclusions The model is considered to be calibrated based on the following observations:



Calibration to pumping tests at PW-7L, PW-1, and PW-7U indicate a good match between observed and modeled drawdown values.



Matching of regional flow patterns.



Comparison with an independent cooling canal system water model shows similar flow exchanges between the cooling canals and the groundwater beneath them.



Validation of the model to pumping test PW-6U indicates a good match between observed and modeled drawdown values.



Hydraulic conductivity values obtained by model calibration are within the range of values reported in the literature.

5.0 CONSTRUCTION & POST-CONSTRUCTION SIMULATIONS Predictive simulations are used for two purposes: evaluating groundwater control options during construction of Units 6 & 7, and operation of the radial collector well system and its influence of the existing groundwater regime.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 41 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations A concrete cut-off wall for construction groundwater dewatering control will be installed around the excavations for Units 6 & 7. It is estimated that the cut-off wall will extend to an elevation of -60 feet NAVD 88 with the base of the excavation at an elevation of -35 feet NAVD 88. The top of the cut-off wall will extend up to an elevation of 2 feet NAVD 88. In addition, the rock between the base of the excavation and the base of the cut-off walls will be grouted. The purpose of modeling the construction dewatering is to estimate discharge rates required to maintain the water table below the base of the excavation.

Radial collector wells will be installed on Turkey Point peninsula in order to provide backup cooling tower makeup water for the proposed AP1000 units at Units 6 & 7 when the primary supply of makeup water is not available. These simulations are performed to determine the origins of water that supply the RCW system, using MODPATH (Reference 34) and ZoneBudget (Reference 35).

5.1 Groundwater Control During Construction Groundwater flow simulations for dewatering of the power block excavations were performed with the calibrated base model. For these simulations, the muck is left in place in the model. It is likely that during earthworks, the muck will be stripped and replaced with backfill to provide a stable working platform. This simplification is expected to have no impact on the dewatering rates.

Several refinements were made to the base model to represent the excavations:



The interior of the excavation (ground surface to -35 feet NAVD 88) was defined as inactive to flow.



The Horizontal Flow Boundary (HFB) package (Reference 36) was used to simulate the cut-off walls from the base of the excavation down to an elevation of -60 feet NAVD 88.



Constant head cells were added to the layer below the excavation to represent the sump pumps in the base of the excavation used to maintain dry working conditions. The constant head level was set to -35 feet NAVD 88 (the floor of the excavation), and pumping rates were calculated from the simulated inflows to the constant head cells. The grid elevations of the cells immediately below the base of the excavation were adjusted to provide a uniform, thin layer within which the constant head cells could be placed.



A new hydraulic conductivity zone was added from the base of the excavation to the base of the cut-off walls to simulate grouting.



The water level in Biscayne Bay was set to the long-term average of -0.81 feet NAVD 88.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 42 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations



Water levels in the cooling canal system, L-31E Canal, Card Sound Canal, and the Model Land Canal (C-107) were adjusted based on the long-term average Biscayne Bay water level.

Figure 48 shows the outline of the excavations while Figure 49 illustrates the implementation of the excavation in the model. Figure 49 shows the model grid, excavation walls, and interior dewatering wells. A cross section through the model illustrating the depth of the excavation and cut-off walls is presented in Figure 50 The two excavations were dewatered sequentially to represent the construction schedule. For each unit, the model was run to steady-state, starting with previously derived steady-state heads under no pumping conditions.

ZoneBudget was used along with the simulation to determine the quantity of water being extracted from the interior dewatering wells.

To aid in construction-related groundwater control, a grout plug will be formed between the bottom of the excavation and the bottom of the cut-off wall. The rationale behind this methodology is to reduce the hydraulic conductivity by injecting grout into a pattern of holes within the excavation between the bottom of the excavation and the bottom of the cut-off wall. By reducing the hydraulic conductivity of the rock, lower discharge rates are achieved, such that sump pumps in the floor of the excavation rather than active dewatering wells can be used to keep the excavation dry.

Figure 51 shows the proposed methodology whereby grout is injected in a series of Primary borings until refusal is achieved. Subsequent borings are then drilled in between the borings of the prior step. Three series of borings are possible after the Primary set: a Secondary, Tertiary, and Quarternary set.

Each set is drilled and grout injected until refusal occurs. Quarternary borings may not be required at all locations; only where excessive seepage is observed as the excavation progresses.

In the base case, a hydraulic conductivity of 1 x 10-4 cm/s is used for the grouted formations. Discharge rates obtained from this model yield a value of 140 and 136 gpm each for Unit 6 and Unit 7 respectively. A series of runs evaluating different values for the hydraulic conductivity of the grout plug were performed to determine a feasible range of discharge rates that may be achievable with grouting. In addition to the run described above, values of 1 x 10-3 cm/s, 1 x 10-5 cm/s, and 1 x 10-6 cm/s were simulated. The results are displayed graphically in Figure 52.

5.2 Post-Construction Radial Collector Well Simulation Groundwater flow simulations for the radial collector wells were performed with the calibrated base model. Several refinements were made to the represent the conditions at the site post-construction:

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 43 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations



Cut-off walls installed during construction (and represented in dewatering simulations) are left in place;



Concrete fill added within the cut-off walls between an elevation of -35 feet NAVD 88 (base of excavation) and -16 feet NAVD 88 with a hydraulic conductivity of 1 x 10-8 cm/s;



Concrete mud mat for reactor building added within cut-off walls between

-16 feet NAVD 88 and -14 feet NAVD 88 with a hydraulic conductivity of 1 x 10-8 cm/s;



Reactor building included as inactive to flow;



Redefined new zones of recharge at the Units 6 & 7 plant area as represented in Figure 53. The values of recharge for grass and backfill of 2 in/yr and 10 in/yr respectively were selected to represent the land surface and also the relatively lower recharge expected compared to the wetlands which dominates a large majority of the model area;



Backfill added between reactor building and cut-off walls with a hydraulic conductivity of 0.01 cm/s;



Muck removed from area in immediate vicinity of reactor buildings (shown in upper half of Figure 25) and replaced with backfill (hydraulic conductivity of 0.01 cm/s);



The water level in Biscayne Bay was set to the long-term average of -0.81 feet NAVD 88;



Recharge and evaportranspiration set to long-term average values;



Water levels in the cooling canal system were shifted to account for the change in Biscayne Bay water level;



Mechanically Stabilized Earth (MSE) retaining walls, as shown in Figure 54 installed around perimeter of the Turkey Point Units 6 & 7 plant area (excluding the makeup water reservoir) down to 0 feet NAVD 88. The MSE retaining wall is also shown as implemented in the numerical model in Figure 53, which details recharge zones at the Turkey Point Units 6 & 7 plant area.

To simulate the radial collector wells and laterals, other changes were made to the model:



Four pumping wells were placed on the last 300 feet of each lateral to represent the screened intervals. Flows were distributed along the laterals based on head loss calculations. The flows are as follows: 872 gpm at the end, 881 gpm at 100 feet from the end, 909 gpm at 200 feet FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 44 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations from the end, and 956 gpm at 300 feet from the end of the lateral. Total flows are 3618 gpm per lateral or 28944 gpm per radial collector well (8 laterals per radial collector well x 3618 gpm per lateral).



Three of the four radial collector wells are operational, resulting in a total system pumping rate of 86832 gpm (3 radial collector wells x 28944 gpm per radial collector well). To provide a conservative estimate of the source of water from inland areas to the radial collector wells, the three wells closest to the shore were modeled as operational.



Zones were defined around the model domain to estimate the volume of water coming from land or Biscayne Bay.



The radial collector wells are pumped from the Upper Higher Flow Zone.

An alternate scenario was also modeled in which the radial collector wells are pumped from the Key Largo Limestone.



The top of the cut-off walls was truncated at the boundary of the Miami Limestone and muck (approximate elevation -4 feet NAVD 88). The actual elevation will be 2 feet NAVD 88, however this simplification is expected to have no affect on the RCW calculations of approach velocity and origin of flow to the RCW.

Figure 55 shows the modeled location of the radial collector wells on the Turkey Point peninsula with the finite-difference grid overlaid and also the location of the pumping wells (light blue) representing the screened portion of the laterals.

Figure 56 shows the potentiometric surface after model execution in the Upper Higher Flow Zone. Figure 57 shows the head contours in layer 1. Figure 58 is a section across the most centrally located radial collector well showing groundwater contours for all modeled layers. Figure 59 and Figure 60 show the drawdown in the vicinity of the Turkey Point peninsula in layer 1 and the Upper Higher Flow Zone (pumped zone) respectively. In the alternate case where the radial collector wells are instead placed in the Key Largo Limestone, the water table, groundwater contours, and drawdown plots are virtually identical to those produced when the radial collector wells are pumped from the Upper Higher Flow Zone.

5.2.1 Origins of Water Supplying Radial Collector Wells To determine the origins of water supplying the radial collector wells a multi-step process is followed. The first step is to place a particle in each boundary condition cell representing a source of water (River, General-Head, and Recharge). Particles are not placed in other cells because the model is steady-state and therefore all water discharging from the RCWs has to originate from a boundary condition. MODPATH is then run in forward tracking mode and the endpoint file reviewed to identify only those particles that end up in the pumping cells representing the RCWs. Once those particles have been identified their starting locations are set up as a separate zone within ZoneBudget for tracking purposes. Following execution of ZoneBudget, the separate fluxes from each of FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 45 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations the boundaries (River, General-Head, and Recharge minus Evapotranspiration) are summed and compared to the discharge from the RCW system as a check.

For both the base case with the laterals in the Upper Higher Flow Zone and the alternate case with the laterals in the Key Largo Limestone, 99.9% of the expected flow to the RCW system is accounted for by the ZoneBudget boundary fluxes. The results presenting the origins of the water to the RCW are presented in Table 11 and broken down into two main components. The first of these is flow from Biscayne Bay, which includes vertical flow down through the Bay floor and lateral flow from the sides of the model in the Bay. The second component is flow from inland, which is further broken down into water originating from the CCS, and that originating from recharge by precipitation.

Figure 61 and Figure 62 present the output for layers 1 and 2 for the base case where the laterals are placed in the Upper Higher Flow Zone. The blue colored clusters on these figures show the starting location of particles that ultimately discharge to the RCW. In the alternate case where the radial collector wells are pumped from the Key Largo Limestone, the flow distribution is the same as the base case, as is shown in Table 11.

The cumulative impacts of the radial collector wells were examined by comparing the difference in flow into the model across the western and northwestern boundary when the radial collector wells are operating at steady-state, versus the steady-state case when no wells are running. Eastward flow is defined as the flow across the western boundary and the flow across the northern boundary from the western edge of the model to L-31E. Flow quantities were determined using ZoneBudget. In both cases, 14 gpm of additional flow into the model domain is induced across the model boundaries as compared to the case with no pumps operating.

5.2.2 Approach Velocity at Bay/Aquifer Interface Three separate approach velocities through the floor of Biscayne Bay were calculated while simulating the operation of the radial collector wells. Using the Biscayne Bay capture zone identified in Figure 61 and the additional zones identified in Figure 63, three values for the approach velocity were calculated representing the following:

1. Average approach velocity for entire control volume (blue in NE corner of Figure 61);
2. Average approach velocity for immediate area defined by the radial collector wells (green in Figure 63); and
3. Average approach velocity for the laterals (colored zones along laterals in Figure 63).

The volumetric flow rate for each of these zones was calculated using ZoneBudget and then divided by the area of the zone to calculate an approach FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 46 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations velocity. The following values were obtained for the three zones for the base case with the radial collector wells pumping from the Upper Higher Flow Zone:



Entire RCW Catchment:

3.3 x 10-5 cm/s (1.1 x 10-6 ft/s)



Immediate RCW Area:

5.2 x 10-4 cm/s (1.7 x 10-5 ft/s)



Average of all RCW Laterals:

6.2 x 10-4 cm/s (2.0 x 10-5 ft/s)

To further illustrate these results, a plot of the Darcy velocities in the top layer of the model showing the spatial variation in approach velocity (ft/day) through the floor of Biscayne Bay is given in Figure 64. Irregularities in the contours of the Darcy velocity are related to the hydraulic conductivity distribution for layer 1 (Figure 23). When the radial collector wells are instead located in the Key Largo Limestone, the approach velocities are only slightly different compared to the base case (see Table 12).

5.2.3 Sensitivity Analysis A suite of sensitivity analyses was performed on the radial collector well simulations to address parameter and water level uncertainty. The radial collector wells pump from the Upper Higher Flow Zone in all sensitivity runs.

Two sensitivity runs were performed to address the uncertainty in Biscayne Bay water levels. These runs considered that Biscayne Bay water levels vary seasonally. One case was run with Biscayne Bay set at the seasonal high water level, and another case was run with Biscayne Bay set at the seasonal low level.

The seasonal extreme values were determined by taking the highest and lowest monthly mean sea level measurements at NOAAs tidal water level and meteorological data collection station (#8723214) on Virginia Key in Biscayne Bay. The seasonal low level of Biscayne Bay is -1.40 feet NAVD 88 while the seasonal high level of Biscayne Bay is 0.09 feet NAVD 88 (Reference 11). Using the equation given in Section 3.3.3, water levels in the cooling canals, L-31E Canal, Card Sound Canal, and Model Land Canal (C-107) were adjusted based on the water level in Biscayne Bay. The areal extent of the GHB cells representing Biscayne Bay was not adjusted for this sensitivity analysis. Results of the seasonal water level runs indicate that either increasing or decreasing the Biscayne Bay water level has no effect on the approach velocities for the RCW.

Increasing the Biscayne Bay water level slightly increases the percent contribution to the radial collector wells from Biscayne Bay, while lowering the Biscayne Bay water level slightly decreases the percent contribution to the radial collector wells. Changing the Biscayne Bay level induces an additional flow into the model domain of 12 gpm for the high water level case and 15 gpm for the low water level case when compared to the case with no pumps operating.

Two additional sensitivity runs were performed to assess the impact of the anisotropy ratio in Biscayne Bay on the radial collector well simulations. In the base model, an anisotropy ratio of 15:1 (Kh:Kv) is used. In the sensitivity runs, the vertical hydraulic conductivity (Kv) is either doubled or halved, producing FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 47 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations anisotropy ratios of 30:1 and 7.5:1, respectively. This change is only made offshore to the first three layers of the model, which represent the Miami Limestone (and a small area of sediment in layer one) Results of the anisotropy sensitivity runs indicate that for the RCW laterals and the immediate RCW area, the approach velocities increase as the Kv increases, and decrease as the Kv decreases. Doubling the Kv slightly increases the percent contribution to the radial collector wells from Biscayne Bay, while halving the Kv slightly decreases the percent contribution to the radial collector wells. Changing the anisotropy ratio in Biscayne Bay induces an additional flow into the model domain of 4 gpm for the double Kv case and 42 gpm for the half Kv case, when compared to the case with no pumps operating.

A final set of sensitivity runs were performed to evaluate the impact of the hydraulic conductivity of the Key Largo Limestone on the radial collector well simulations. The reason for this additional suite is because the Key Largo Limestone is divided into two zones of hydraulic conductivity based on prior information. These zones were defined to improve the calibration and these sensitivity runs are intended to determine if the difference in hydraulic conductivity between the zones results in any change in the induced flow across the western boundary. The results indicate that an additional 6 gpm of flow is induced across the model boundaries when the horizontal hydraulic conductivity is 5.9 cm/s and 20 gpm when the horizontal hydraulic conductivity is 10 cm/s when compared to the case with no pumps operating.

A compilation of the results for the base case and sensitivity cases can be found in Table 11 for the origin of water to the radial collector wells and Table 12 for the approach velocities of each zone. As was done with the base case, a comparison of the RCW discharge was made with the ZoneBudget boundary fluxes as a check. For these sensitivity cases, between 99.7% and 100.2% of the expected flow to the RCW system is accounted for by the ZoneBudget boundary fluxes. For both the base case with the laterals in the Upper Higher Flow Zone and the alternate case with the laterals in the Key Largo Limestone, 99.9% of the expected flow to the RCW system is accounted for by the ZoneBudget boundary fluxes. In addition to the tabulated summary a graphical representation of the sensitivity of these parameters to the 0.1 ft drawdown contour is presented in Figures 65, 66, and 67 for the aforementioned cases.

6.0 CONCLUSION

S A steady-state, constant-density, three-dimensional model was developed to simulate groundwater flow under present conditions at the Turkey Point Units 6 &

7 Site. The model was developed and calibrated using available historic data and data collected in support of the Combined License Application (COLA) and Site Certification Application (SCA).

The calibrated model was used to simulate construction dewatering for Units 6 &

7 reactor buildings. Calculated pumping rates to enable dry working conditions are 140 gpm and 136 gpm for Units 6 & 7 respectively, when each unit is constructed separately. These simulations for groundwater control involve FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 48 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations injecting grout between the bottom of the excavation and the bottom of the cut-off wall and using sump pumps in the base of the excavation to remove seepage through the grout plug into the excavation.

The model was also used to determine the origin of water supplying the radial collector wells by a combination of particle tracking and evaluating flows through different parts of the model. These simulations indicate that approximately 97.8% of the pumped water will originate from Biscayne Bay while the remainder will originate from inland.

7.0 REFERENCES

1.

Southeastern Geological Society (SEGS), 1986. Hydrogeological Units of Florida, Special Publication 28, Ad Hoc Committee on Florida Hydrostratigraphic Unit Definition.

2.

Dames & Moore, 1971, Geohydrologic Conditions Related to the Construction of Cooling Ponds, Florida Power & Light Company, Steam Generating Station, Turkey Point, Florida, Prepared for Brown and Root, Inc.

3.

MACTEC Engineering and Consulting, 2008. Final Data Report -

Geotechnical Exploration and Testing: Turkey Point COL Project Florida City, Florida, Rev. 2, October 6, 2008.

4.

HDR Engineering Inc., 2009. Turkey Point Exploratory Drilling and Aquifer Performance Test Program. August 19, 2009.

5.

JLA Geosciences Inc., 2010. Geology and Hydrogeology Report for Turkey Point Plant Groundwater, Surface Water & Ecological Monitoring Plan.

6.

Dames & Moore, 1975, Florida Aquifer Water Supply Investigation, Turkey Point Area, Dade County, Fl. Prepared for Florida Power & Light Company.

7.

Enercon Services, Inc. and William Lettis & Associates, Inc. (WLA), 2006.

Feasibility Geological Investigation of Potential New Nuclear Plant Site:

FPL Turkey Point Facility. Submitted to: Florida Power and Light.

8.

Florida Geological Survey, 2008. Lithologic Database. Available at:

http://www.dep.state.fl.us/geology/gisdatamaps/litholog.htm, accessed September 6th, 2008.

9.

United States Geological Survey (USGS), 2006. Groundwater Characterization and Assessment of Contaminants in Marine Areas of Biscayne National Park.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 49 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations

10.

Florida Power and Light (FPL), 2009. FPL Turkey Point Power Plant Groundwater, Surface Water, and Ecological Monitoring Plan. Exhibit B.

October 2009. Available at http://publicfiles.dep.state.fl.us/siting/Outgoing/FPL_Turkey_Point/Units_6

_7/Completeness/Plant_Associated_Facilities/2nd_round_Completeness/

FPL_Response_Part_A_Information/Attachments/2nd%20Round%20Atta chments/101409%20Final%20Turkey%20Point%20Monitoring%20Plan.p df, accessed November 10, 2010.

11.

NOAA, 2010. Tides & Currents Virginia Key, FL #8723214 web page (NOAA). Available at:

http://tidesandcurrents.noaa.gov/station_info.shtml?stn=8723214%20Virgi nia%20Key,%20FL, accessed October 13, 2010.

12.

Langevin, C.D., 2001. Simulation of Ground-Water Discharge to Biscayne Bay, Southeastern Florida, U.S. Geological Survey Water-Resources Investigations Report 00-4251.

13.

South Florida Water Management District (SFWMD), 2010. South Florida Water Management District DBHYDRO database query, Station S20F, available at:

http://www.sfwmd.gov/dbhydroplsql/show_dbkey_info.date_selection?v_j s_flag=Y&v_db_request_id=2802506&v_parameter_string=&v_dbkey=05 816%2FVN225%2FK8666%2F16692&v_frequency=&v_sdate=19680522

&v_edate=20101025, accessed October 14, 2010.

14.

Harbaugh, Arlen W., Edward R. Banta, Mary C. Hill, and Michael G.

McDonald, 2000. MODFLOW-2000, The U.S. Geological Survey Modular Ground-Water Model - User Guide to Modularization Concepts and the Ground-Water Flow Process, U.S. Geological Survey Open-File Report 00-92. Available at http://pubs.er.usgs.gov/usgspubs/ofr/ofr200092, accessed September 30, 2008.

15.

McDonald, Michael G., and Arlen W. Harbaugh, 1984. A Modular Three-Dimensional Finite-Difference Ground-Water Flow Model. U.S.

Geological Survey Open-File Report 83-875, 528 p. Available at http://pubs.er.usgs.gov/usgspubs/ofr/ofr83875, accessed September. 29, 2008.

16.

McDonald, Michael G., and Arlen W. Harbaugh, 1988. Chapter A1 - A Modular Three-Dimensional Finite-Difference Ground-Water Flow Model.

Techniques of Water-Resources Investigations of the U.S. Geological Survey, Book 6, Modeling Techniques. Available at http://pubs.er.usgs.gov/usgspubs/twri/twri06A1, accessed Sep. 29, 2008.

17.

Schlumberger Water Services, 2009. Visual MODFLOW Professional v.2009, Users Manual.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 50 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations

18.

NOAA, 2008. NOAA Coastal Services Center. Topographic and bathymetric data considerations: datums, datum conversion techniques and data integration, Part II: A Roadmap to a Seamless Topobathy Surface, National Oceanic and Atmospheric Administration (NOAA),

Technical Report NOAA/CSC/20718-PUB.

19.

NOAA, 2010. VDatum - Online Users Guide, available at http://vdatum.noaa.gov/docs/usersguide.html, accessed October 13, 2010.

20.

NOAA, 2010. FME SpatialDirect, Office of Coast Survey (OCS) Harbor Sounding, available at http://ocs-spatial.ncd.noaa.gov/SpatialDirect/translationServlet?SSFunction=prepar eFetch, accessed May 13, 2010.

21.

Renken, R., Cunningham, K., Shapiro, A., Harvey, R., Zygnerski, M.,

Metge, D., and Wacker, M., 2008. Pathogen and chemical transport in the karst limestone of the Biscayne aquifer: 1. Revised conceptualization of groundwater flow, Water Resources Reasearch, Vol. 44.

22.

Fish and Wildlife Research Institute (FWRI), 2010. Marine Resources Geographic Information System (MRGIS) GIS Data, Benthic Habitats -

South Florida. Available at:

http://ocean.floridamarine.org/mrgis_ims/Description_Layers_Marine.htm, accessed June 25, 2010.

23.

Cunningham, K.J., Carlson, J.L., Wingard, G.L., Robinson, E., and Wacker, M.A., 2004. Characterization of Aquifer Heterogeneity Using Cyclostratigraphy and Geophysical Methods in the Upper Part of the Karstic Biscayne Aquifer, Southeastern Florida, Water-Resources Investigations Report 03-4208, U.S. Geological Survey, 2004.

24.

Cunningham, K.J., Wacker, M.A., Robinson, E., Dixon, J.F., and Wingard, G.L., 2006. A Cyclostratigraphic and Borehole-Geophysical Approach to the Development of a Three-Dimensional Conceptual Hydrogeologic Model of the Karstic Biscayne Aquifer, SE Florida. U.S.G.S. Scientific Investigations Report 2005-5235.

25.

Cunningham, K.J., Sukop, M.C., Huang, H., Alvarez, P.F., Curran, H.A.,

Renken, R.A., and Dixon, J.F., 2009. Prominence of ichnologically influenced macroporosity in the karst Biscayne aquifer: Stratiform "super-K" zone. Geological Society of America Bulletin, v. 121, no. 1/2, p. 164-180.

26.

Fetter, C.W., 1994. Applied Hydrogeology. 3rd Edition, Prentice Hall.

27.

Rice, R.W. and Walton, T.C., October 2006 Design Factors Affecting the Flow of Water through Below-Ground Concrete Vaults, Journal of Environmental Engineering, v, 132, no. 10, pp 1346-1354.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 51 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations

28.

Warner, J., 2004. Practical Handbook of Grouting: soil, rock, and structures. John Wiley and Sons, 700 p.

29.

Weaver, K.D. and Bruce, D.A., 2007. Dam Foundation Grouting, Revised and Expanded Edition, American Society of Civil Engineers, Subsection 14.2.1 Permeability Criteria.

30.

Gamble, B.F. and Stowe, S.M., 2008. Approaches to Modeling Collector Wells and Horizontal Wells with MODFLOW. MODFLOW and More 2008: Groundwater and Public Policy. Conference proceedings, pp 489-493.

31.

HDR Engineering Inc., 2009. Conceptual Engineering Report - March 2009 FPL Turkey Point Units 6 & 7.

32.

Golder Associates, Inc., 2008. Cooling Pond Modeling Report.

33.

Golder Associates, Inc., 2008. Final Report on Florida Power & Light Company. Turkey Point New Nuclear Project Cooling Canal Data and Analysis Report.

34.

Pollock, D.W., 1994. Users Guide for MODPATH/MODPATH-PLOT, Version 3: A particle tracking post-processing package for MODFLOW, the U. S. Geological Survey finite-difference ground-water flow model:

U.S. Geological Survey Open-File Report 94-464.

http://water.usgs.gov/software/MODPATH/code/doc/ofr94464.pdf Accessed 1/31/2011.

35.

Harbaugh, A.W., 1990. A computer program for calculating subregional water budgets using results from the U.S. Geological Survey modular three-dimensional ground-water flow model: U.S. Geological Survey Open-File Report 90-392, p. 46.

36.

Hsieh, Paul and Freckleton, John, 1993. Documentation of Computer Program to Simulate Horizontal-Flow Barriers Using the United States Geological Surveys Modular Three-Dimensional Finite-Difference Ground-Water Flow Model. U.S. Geological Survey Open-File Report 92-477, 528 p. Available at http://water.usgs.gov/nrp/gwsoftware/modflow2005/ofr92_477_HFB.pdf,

accessed May 27, 2009.

37.

Krupa, A.J. and M.T. Mullen, 2005. Literature Review And Assessment Of Geologic Logs To Determine The Extent Of A Dense Limestone Layer In The Upper Portion Of The Biscayne Aquifer In The Pennsuco Wetlands, Miami-Dade County, Florida.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 52 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations

38.

Sonenshein, R.S., 2001. Methods to Quantify Seepage Beneath Levee 30, Miami-Dade County, Florida, U.S. Geological Survey Water-Resources Investigations Report 01-4074.

39.

Merritt, M.L., 1996. Simulation of the Water-Table Altitude in the Biscayne Aquifer, Southern Dade County, Florida, Water Years 1945-89, U.S. Geological Survey Water-Supply Paper 2458.

40.

Swain, E.D., Howie, B., and Dixon, J. 1996. Description and Field Analysis of a Coupled Ground-Water/Surface-Water Flow Model (MODFLOW/BRANCH) with Modifications for Structures and Wetlands in Southern Dade County, Florida: U.S. Geological Survey Water-Resources Investigations Report 1996-4118, 71 p.

41.

Fish, J.E. and M. Stewart, 1991. Hydrogeology of the Surficial Aquifer System, Dade County, Florida, U.S. Geological Survey Water-Resources Investigations Report 90-1408.

42.

Florida Power & Light, 2009. Turkey Point Units 6 & 7 Final Safety Analysis Report, Combined Operating and Licensing Application.

43.

Reese, R., and Richardson, E., 2008. Synthesis of the Hydrogeologic Framework of the Floridan Aquifer System and Delineation of a Major Avon Park Permeable Zone in Central and Southern Florida, Scientific Investigations Report 2007-5207, U.S. Geological Survey.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 53 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Table 1.

Station S20F Rainfall Data for February to May 2009 Month Days VN225 Feb 28 0.34 Mar 31 3.72 Apr 30 0.27 May 31 9.63 Total 120 13.96 Rounded to nearest tenth 14.0 Scaled to Year 42.6 in/yr Total Precipitation (inches) 2009 Source: Based on Reference 13 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 54 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 55 of 132 Table 2.

Station S20F Annual Rainfall Data 1969 67.52 BELF 67.52 1970 40.67 BELF 40.67 1971 32.16 BELF 32.16 1972 54.38 BELF 54.38 1973 40.60 BELF 40.60 1974 35.48 BELF 35.48 1975 43.08 BELF 43.08 1976 43.68 BELF 43.68 1977 43.89 BELF 43.89 1978 38.06 BELF 38.06 1979 33.89 BELF 33.89 1980 41.17 BELF 41.17 1981 45.46 BELF 45.46 1982 46.19 BELF 46.19 1983 59.62 BELF 59.62 1984 36.92 BELF 36.92 1985 37.37 BELF 37.37 1986 38.75 BELF 38.75 1987 41.54 BELF 41.54 1988 73.31 BELF 73.31 1989 46.84 BELF 46.84 1990 39.89 BELF 39.89 1991 40.41 BELF 40.41 1992 46.26 60.38 OMD 60.38 1993 38.59 36.18 OMD 36.18 1994 55.10 60.06 OMD 60.06 1995 74.75 86.11 OMD 86.11 1996 49.55 49.56 OMD 49.56 1997 53.25 49.98 OMD 49.98 1998 48.01 57.41 64.32 OMD/TELE 60.87 1999 36.46 44.62 44.90 OMD/TELE 44.76 2000 38.87 41.23 41.64 OMD/TELE 41.44 2001 57.35 47.41 47.66 OMD/TELE 47.54 2002 48.91 48.48 OMD/TELE 48.70 2003 43.75 43.48 OMD/TELE 43.62 2004 32.60 32.90 OMD/TELE 32.75 2005 47.91 44.98 OMD/TELE 46.45 2006 44.54 44.97 OMD/TELE 44.76 2007 51.14 51.42 OMD/TELE 51.28 2008 44.11 45.47 45.61 NRG 45.61 2009 44.89 44.00 45.86 NRG 45.86 Average 46.75 in/yr Water Year Combined Series (inches)

Recorder Selected Precipitation (inches)

BELF 5618 OMD 16692 TELE K866 NRG VN225 Source: Based on Reference 13 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Table 3.

Extinction Depth and Maximum Evapotranspiration Rate Land-use category Urban Agriculture Rangeland Upland forests Water Wetlands Barren land Transportation January February March April May June - October November December Maximum evapotranspiration rate (cm/d) 0.20 0.28 0.36 0.43 0.46 0.53 0.30 0.28 0.5 Extinction depth (m) 0.3 0.43 0.61 0.7 0.183 0.69 0.15 0.3 0.2 0

0 0

Runoff coefficient 0.5 0.5

0.2 Source

Based on Reference 12 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 56 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Table 4.

Regional Hydraulic Conductivity Values Based on Onsite Tests and Literature Review HG Unit Kh min Kh max Kv min Kv max Kh min Ref Kh max Ref Kv min Ref Kv max Ref Offshore Sediment Onshore Muck 2.5E-04 2.5E-04 3.5E-05 37 1.8E-02 38 3.5E-04 12 1.8E-03 38 Miami Limestone 7.9E-02 7.9E-02 5.0E-03 8.0E-03 3.5E-05 37 1.1E+01 39 3.5E-02 38 1.1E+00 40 Upper Higher Flow Zone Key Largo 3.3E+00 1.8E+01 1.1E+00 38 3.5E+01 41 1.1E-01 38 Freshwater Limestone 7.0E-05 3.0E-03 3.5E-05 37 3.5E-04 38 3.5E-05 38 3.0E-03 37 Lower Higher Flow Zone Fort Thompson 1.0E-01 1.6E+00 1.8E-01 39 1.1E+01 39 1.8E-02 40 1.1E+00 40 Tamiami Formation 3.0E-02 4.0E-01 3.5E-05 40 7.1E-01 41 3.5E-06 40 7.1E-03 38 Literature Review FPL Onsite Tests Note: Italicized values indicate instances where only one hydraulic conductivity value was available and thus the maximum and minimum values are equal.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 57 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Table 5.

Surface Water Levels Corrected to Reference Density Surface Water Feature Location Base of Canal (ft NAVD 88)

Canal Stage (ft NAVD 88)

Water Type Water Density (kg/m 3)

Reference Head (ft NAVD 88)

Interceptor Ditch CHD of -0.28

-19.2

-0.28 FW 996.70

-0.76 Interceptor Ditch Start of variable H

-19.2

-0.18 FW 996.70

-0.66 Interceptor Ditch End of variable H

-19.2

-1.05 FW 996.70

-1.51 L-31E All

-22.8 0.02 FW 996.70

-0.55 Southern Portion of Grand Canal Outside the CCS All

-21.2

-1.05 SALINE 1022.40

-1.05 C-106 All

-14

-1.05 SALINE 1022.40

-1.05 E-W Release Canal H = 1.28

-21.2 1.28 CCS 1048.00 1.84 E-W Release Canal H = 1.08

-21.2 1.08 CCS 1048.00 1.64 N-S Shallow Canal H = 1.08

-3.02 1.08 CCS 1048.00 1.18 N-S Shallow Canal H = -1.05

-3.02

-1.05 CCS 1048.00

-1.00 E-W Collector All

-21.2

-1.05 CCS 1048.00

-0.55 Grand Canal Top

-21.2

-3.18 CCS 1048.00

-2.73 Grand Canal Bottom

-21.2

-1.05 CCS 1048.00

-0.55 E. Return Canal Top

-19.2

-3.18 CCS 1048.00

-2.78 E. Return Canal Bottom

-19.2

-1.05 CCS 1048.00

-0.60 Island SW

-21.2

-3.18 CCS 1048.00

-2.73 Island NE

-21.2

-3.28 CCS 1048.00

-2.83 Intake Basin NE Island

-21.2

-3.28 CCS 1048.00

-2.83 Intake Basin Pumps

-21.2

-3.38 CCS 1048.00

-2.93 FW - Freshwater CCS - Hypersaline FW 

996.7 kg/m 3

Ref  (Bisc. Bay) 1022.4 kg/m 3

CCS 

1048.0 kg/m 3

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 58 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Table 6.

Model Calibration PW-7L - Horizontal Hydraulic Conductivity HG Unit Kh Kv Anisotropy Ratio Offshore Sediment 3.53E-02 2.4E-03 15:1 Onshore Muck 4.4E-03 4.4E-04 10:1 Miami Limestone 8.8E-02 5.9E-03 15:1 Upper Higher Flow Zone 3.0E+01 3.7E+00 8:1 Key Largo SW 5.9E+00 7.4E-01 8:1 Key Largo NE 1.0E+01 1.3E+00 8:1 Freshwater Limestone 3.4E-05 2.3E-06 15:1 Lower Higher Flow Zone 1.7E+00 1.7E-01 10:1 Fort Thompson 3.3E-01 3.3E-02 10:1 Tamiami Formation 2.8E-04 2.8E-05 10:1 Hydraulic Conductivity (cm/s)

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 59 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Table 7.

Model Calibration PW-7L - Measured Versus Simulated Drawdowns (at end of test)

Well HG Unit Easting Northing Observed Calculated Ri (Obs-Calc) lRil lRil2 C7-2A Miami Limestone 875822.2 396944.9 0.31 0.48

-0.18 0.18 0.03 C7-2C Tamiami Formation 875822.2 396944.9 1.54 1.19 0.35 0.35 0.12 C7-2D Key Largo Limestone 875817.3 396944.9 0.34 0.49

-0.15 0.15 0.02 C7-2E Fort Thompson Formation 875817.3 396944.9 3.56 4.44

-0.87 0.87 0.76 C7-3A Miami Limestone 875822.4 396960.2 0.32 0.48

-0.16 0.16 0.03 C7-3C Tamiami Formation 875822.4 396960.2 2.91 1.21 1.70 1.70 2.89 C7-3D Key Largo Limestone 875817.2 396959.9 0.35 0.49

-0.14 0.14 0.02 C7-3E Fort Thompson Formation 875817.2 396959.9 4.96 6.10

-1.15 1.15 1.32 C7-4A Miami Limestone 875822.3 396975.2 0.32 0.48

-0.16 0.16 0.03 C7-4C Tamiami Formation 875822.3 396975.2 2.03 1.22 0.81 0.81 0.66 C7-4E Fort Thompson Formation 875817.3 396974.3 11.40 9.37 2.03 2.03 4.13 C7-5A Miami Limestone 875829.5 396984.1 0.32 0.48

-0.16 0.16 0.02 C7-5D Key Largo Limestone 875828.1 396989.3 0.38 0.48

-0.10 0.10 0.01 C7-5E Fort Thompson Formation 875828.1 396989.3 12.61 10.85 1.77 1.77 3.12 PW-7 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 60 of 132 L

Fort Thompson Formation 875819.4 396985.1 Difference 12.30 10.37 Number 14 14 Maximum 12.61 10.85 Total 9.72 13.16 Minimum 0.31 0.48 ARM 0.69 RMS 0.97 NRMS (%)

7.9 Md (%)

0.00 DRAWDOWN (ft)

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Table 8.

Model Calibration PW Measured Versus Simulated Drawdowns (at end of test)

Well HG Unit Easting Northing Observed Calculated Ri (Obs-Calc) lRil lRil2 MW-1A Miami Limestone 880083.2 401545.1 0.78 0.74 0.04 0.04 0.00 MW-1B Key Lar FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 61 of 132 go Limestone 880083.2 401545.1 0.71 0.78

-0.07 0.07 0.00 MW-1D Fort Thompson Formation 880083.2 401545.1 0.63 0.63 0.00 0.00 0.00 MW-2B Key Largo Limestone 880967.2 402023.5 0.19 0.17 0.02 0.02 0.00 MW-3B Key Largo Limestone 878292.6 401339.6 0.08 0.07 0.01 0.01 0.00 MW-4B Key Largo Limestone 878331.1 400609.9 0.09 0.06 0.03 0.03 0.00 PW-1 Key Largo Limestone 880146.6 401595.4 Difference 0.70 0.72 Number 6

6 Maximum 0.78 0.78 Total 0.18 0.01 Minimum 0.08 0.06 ARM 0.03 RMS 0.04 NRMS (%)

5.3 Md (%)

0.00 DRAWDOWN (ft)

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Table 9.

Model Calibration PW-7U - Measured Versus Simulated Drawdowns (at end of test)

Well HG Unit Easting Northing Observed Calculated Ri (Obs-Calc) lRil lRil2 C7-1A Miami Limestone 875829.5 396932.8 0.88 1.03

-0.15 0.15 0.02 C7-1C Tamiami Formation 875829.5 396932.8 0.42 0.52

-0.10 0.10 0.01 C7-1D Key Largo Limestone 875829.6 396937.7 2.07 1.50 0.57 0.57 0.33 C7-1E Fort Thompson Formation 875829.6 396937.7 0.50 0.62

-0.12 0.12 0.01 C7-2A Miami Limestone 875822.2 396944.9 0.89 1.04

-0.15 0.15 0.02 C7-2C Tamiami Formation 875822.2 396944.9 0.42 0.52

-0.10 0.10 0.01 C7-2D Key Largo Limestone 875817.3 396944.9 1.48 1.55

-0.07 0.07 0.01 C7-2E Fort Thompson Formation 875817.3 396944.9 0.54 0.62

-0.08 0.08 0.01 C7-3A Miami Limestone 875822.4 396960.2 0.75 1.02

-0.27 0.27 0.07 C7-3C Tamiami Formation 875822.4 396960.2 0.35 0.52

-0.17 0.17 0.03 C7-3D Key Largo Limestone 875817.2 396959.9 1.27 1.30

-0.03 0.03 0.00 C7-3E Fort Thompson Formation 875817.2 396959.9 0.42 0.61

-0.19 0.19 0.04 C7-4A Miami Limestone 875822.3 396975.2 0.82 1.00

-0.18 0.18 0.03 C7-4C Tamiami Formation 875822.3 396975.2 0.44 0.52

-0.08 0.08 0.01 C7-4D Key Largo Limestone 875817.3 396974.3 1.13 1.18

-0.06 0.06 0.00 C7-4E Fort Thompson Formation 875817.3 396974.3 0.52 0.61

-0.09 0.09 0.01 PW-7U Key Lar FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 62 of 132 go Limestone 875819.3 396935.3 Difference 1.72 1.03 Number 16 16 Maximum 2.07 1.55 Total 2.41 0.60 Minimum 0.35 0.52 ARM 0.15 RMS 0.19 NRMS (%)

11.3 Md (%)

0.00 DRAWDOWN (ft)

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Table 10.

Model Calibration PW-6U - Measured Versus Simulated Drawdowns (at end of test)

Well HG Unit Easting Northing Observed Calculated Ri (Obs-Calc) lRil lRil2 C6-1A Miami Limestone 876678.1 396935.4 1.46 1.37 0.08 0.08 0.01 C6-1C Tamiami Formation 876678.1 396935.4 0.53 0.53 0.01 0.01 0.00 C6-1D Key Largo Limestone 876677.9 396940.4 1.66 1.86

-0.20 0.20 0.04 C6-1E Fort Thompson Formation 876677.9 396940.4 0.57 0.58

-0.01 0.01 0.00 C6-2A Miami Limestone 876670.8 396947.3 1.34 1.39

-0.05 0.05 0.00 C6-2C Tamiami Formation 876670.8 396947.3 0.53 0.53 0.00 0.00 0.00 C6-2D Key Largo Limestone 876665.5 396947.4 2.08 1.95 0.13 0.13 0.02 C6-2E Fort Thompson Formation 876665.5 396947.4 0.58 0.58 0.00 0.00 0.00 C6-3A Miami Limestone 876670.5 396962.6 1.09 1.36

-0.27 0.27 0.07 C6-3C Tamiami Formation 876670.5 396962.6 0.51 0.53

-0.01 0.01 0.00 C6-3D Key Largo Limestone 876665.7 396962.5 1.30 1.60

-0.30 0.30 0.09 C6-3E Fort Thompson Formation 876665.7 396962.5 0.50 0.58

-0.07 0.07 0.01 C6-4A Miami Limestone 876670.9 396978.1 0.98 1.30

-0.32 0.32 0.10 C6-4C Tamiami Formation 876670.9 396978.1 0.56 0.52 0.04 0.04 0.00 C6-4D Key Largo Limestone 876666.0 396977.9 1.01 1.43

-0.42 0.42 0.17 C6-4E Fort Thompson Formation 876666.0 396977.9 0.52 0.57

-0.05 0.05 0.00 PW-6U Key Lar FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 63 of 132 go Limestone 876668.7 396938.0 Difference 1.58 1.43 Number 16 16 Maximum 2.08 1.95 Total 1.96 0.51 Minimum 0.50 0.52 ARM 0.12 RMS 0.18 NRMS (%)

11.4 Md (%)

0.00 DRAWDOWN (ft)

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 64 of 132 Table 11.

Radial Collector Wells - Origin of Water (including sensitivity analysis)

Zone RCW in Upper High Flow Zone (Base case)

RCW in Key Largo Limestone Seasonal High Water Level Seasonal Low Water Level Double Vertical Hyd. Cond.

Half Vertical Hyd. Cond.

Key Largo All Lower K (Blue)

Key Largo All Higher K (Red)

Biscayne Bay 97.8%

97.8%

98.1%

97.6%

99.2%

95.3%

97.4%

98.5%

Flow from Inland 2.2%

2.2%

1.9%

2.4%

0.8%

4.7%

2.6%

1.5%

- Via Cooling Canal System 1.9%

1.9%

1.8%

2.0%

0.7%

3.2%

2.2%

1.3%

- Precipitation Recharge 0.3%

0.3%

0.1%

0.4%

0.1%

1.5%

0.4%

0.2%

Percent Contribution to Radial Collector Wells Note:

The top two rows contribute to the total flow and sum to 100%. The bottom two rows are components of inland flow.

(Blue) and (Red) in final two columns refer to the Key Largo hydraulic conductivity distribution shown in Figure 27.

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Table 12.

Radial Collector Wells - Approach Velocity (including sensitivity analysis)

Zone RCW in Upper High Flow Zone (Base case)

RCW in Key Largo Limestone Seasonal High Water Level Seasonal Low Water Level Double Vertical Hyd.

Cond.

Half Vertical Hyd. Cond.

Key Largo All Lower K (Blue)

Key Largo All Higher K (Red)

Entire RCW Catchment 3.3E-05 3.3E-05 3.2E-05 3.3E-05 3.9E-05 2.9E-05 3.2E-05 3.5E-05 Immediate RCW Area 5.2E-04 5.2E-04 5.2E-04 5.2E-04 5.3E-04 5.0E-04 5.2E-04 5.2E-04 Average of all RCW Laterals 6.2E-04 6.1E-04 6.2E-04 6.2E-04 9.2E-04 4.0E-04 6.1E-04 7.7E-04 Approach Velocity (cm/s)

Note: (Blue) and (Red) in final two columns refer to the Key Largo hydraulic conductivity distribution shown in Figure 27.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 65 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 1. Location of Turkey Point Units 6 & 7 and Major Hydrological Features Source: Reference 42.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 66 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 2. Industrial Wastewater Facility, the L-31E Canal, and the Card Sound Canal Source: Reference 42 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 67 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 3. Regional Generalized Hydrostatigraphic Column Source: Reference 42 (modified from Reference 43)

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 68 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 4. Site Hydrostatigraphic Column Color represents similar composition (carbonate, clastics, and organics).

Source: Reference 42.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 69 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 70 of 132 Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 70 of 132 Figure 5. Cross Section Location Source: Adapted from Reference 2 Note: Best available scan from original document Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 6. Hydrostratigraphic Cross Section A-A' Source: Reference 2 Note: Best available scan from original document FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 71 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 7. West-East Cross Section in the Vicinity of the Southern End of the Turkey Point Plant Property Source: Reference 6 Note: Best available scan from original document FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 72 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 8. Feasibility Geological Investigation of Potential Plant Site (2006) -

Boring and Stratigraphic Cross Section Locations Source: Reference 7 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 73 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 9. Feasibility Geological Investigation of Potential Plant Site (2006) - Stratigraphic Cross Section A-A' Source: Reference 7 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 74 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 75 of 132 Figure 10. Feasibility Geological Investigation of Potential Plant Site (2006) - Stratigraphic Cross Section B-B' Source: Reference 7 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 11. Stratigraphic Cross Section from Wells Drilled for Turkey Point Peninsula Aquifer Performance Test Source: Reference 4 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 76 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 12. Turkey Point Units 6 & 7 Site Investigation Observation Well Location Plan Source: Reference 42 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 77 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 13. May 1993 Biscayne Aquifer Potentiometric Surface Map FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 78 of 132 Source: Reference 42 (modified from Reference 12)

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 14. November 1993 Biscayne Aquifer Potentiometric Surface Map FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 79 of 132 Source: Reference 42 (modified from Reference 12)

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 80 of 132 Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 80 of 132 Figure 15. Land Use for Southern Florida Source: Reference 12 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 16. Upper Floridan Aquifer Production Wells for Unit 5 Source: Reference 42 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 81 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 17. Numerical Model Domain Note: Model domain identified by extents of axes, not extents of image. White portions on right side are where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 82 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 18. Model Grid and Site Features for the Units 6 & 7 Power Block FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 83 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 19. East-West Model Cross Section towards Southern End of the Turkey Point Cooling Canals Note: Section along Row 420, vertical exaggeration 50:1 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 84 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 20. South-North Model Cross Section along Return Canal of Turkey Point Cooling Canals Note: Section along Column 280, vertical exaggeration 50:1.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 85 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 86 of 132 Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 86 of 132 Figure 21. Cooling Canals Water Balance Note: Units in acre-ft/month Source: Reference 33 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 22. Extent of Freshwater Limestone and Key Largo Limestone in Model Layer 7 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 87 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 23. Material Distribution in Biscayne Bay Note: Blue = Muck. Green = Miami Limestone. Grey = Offshore Sediment.

N Note: Blue = Muck. Green = Miami Limestone. Grey = Offshore Sediment.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 88 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 89 of 132 Figure 24. Hydraulic Conductivity Anisotropy Values in the Different Formations

).

Source: Reference 42 (data from Reference 23 & 24 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 25. Plan and Cross-Section of Units 6 & 7 Excavations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 90 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 26. Planned Area of Radial Collector Well Caissons Relative to Plant Site Area Source: Reference 42 FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 91 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 27. Model Calibration - Delineation of Hydraulic Conductivity Zones in the Key Largo Limestone Legend: Dark Red = Key Largo Limestone Southwest. Blue = Key Largo Limestone Northeast.

Green Lines = SFWMD Canals.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 92 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 93 of 132 Figure 28. Model Calibration - Layout of Pumping Well and Observation Well Clusters for Pumping Tests PW-7L and PW-7U Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 29. Grid Refinement in Vicinity of Unit 7 Reactor Footprint Note: Black lines represent Unit 7 reactor building and associated structures.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 94 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 30. Test Well PW-7L and Related Observation Wells Note: Red symbol = pumping well. Green symbol = observation well. Black line represents eastern edge of Unit 7 reactor building.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 95 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 31. Test Well PW-7L: Observed Versus Calculated Drawdowns FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 96 of 132 0

2 4

6 8

10 12 14 0

2 4

6 8

10 12 14 Calculated Drawdown (ft)

Observed Drawdown (ft)

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 32. Model Calibration - Pumping and Monitoring Wells Layout for Pumping Test PW-1 N

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 97 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 98 of 132 Note: Blue line = shoreline and radial collector well arms. Red line = CCS outline. Red symbol = pumping well. Green symbol = observation well.

Figure 33. Model Calibration - Finite Difference Grid and Well Layout for Test PW-1 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 34. Test Well PW-1: Observed versus Calculated Drawdowns FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 99 of 132 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 Calculated Drawdown (ft)

Observed Drawdown (ft)

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 35. Model Calibration - Finite Difference Grid and Well Layout for Test PW-7U Note: Red symbol = pumping well. Green symbol = observation well.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 100 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 101 of 132 Figure 36. Test Well PW-7U: Observed versus Calculated Drawdowns 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4 Calculated Drawdown (ft)

Observed Drawdown (ft)

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 37. Simulated Groundwater Contours - Model Layer 1 - Onshore Muck and Offshore Sand/Sediments and Miami Limestone Legend: Contour interval is 0.2 feet (NAVD 88).

Note: Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 102 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 38. Simulated Groundwater Contours - Model Layer 3 - Miami Limestone Legend: Contour interval is 0.2 feet (NAVD 88)

Note: Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 103 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 39. Simulated Groundwater Contours - Model Layer 4 - Upper Higher Flow Zone Legend: Contour interval is 0.2 feet (NAVD 88)

Note: Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 104 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 40. Simulated Groundwater Contours - Model Layer 5 - Key Largo Limestone Legend: Contour interval is 0.2 feet (NAVD 88)

Note: Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 105 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 41. Simulated Groundwater Contours - Model Layer 7 - Freshwater Limestone Legend: Contour interval is 0.2 feet (NAVD 88)

Note: Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 106 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 42. Simulated Groundwater Contours - Model Layer 9 - Fort Thompson Formation Legend: Contour interval is 0.2 feet (NAVD 88)

Note: Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 107 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 43. Simulated Groundwater Contours - Model Layer 10 - Lower Higher Flow Zone Legend: Contour interval is 0.2 feet (NAVD 88)

Note: Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 108 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 109 of 132 Figure 44. Simulated Groundwater Contours - Model Layer 14 - Tamiami Formation Legend: Contour interval is 0.2 feet (NAVD 88)

Note: Light yellow portion in top right is where aerial imagery is not available.

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 45. Existing Cooling Canals Water Balance - Comparison with Groundwater Model Units 1-4 Cooling Canals Groundwater Under Biscayne Bay Unit 5

Upper Floridan Miami-Dade City Water 1,312 2,313 3,027 (131%)

3,351 3,622 (108%)

Evaporation 3,815 Precipitation 2,304 Net Blowdown Net Makeup 28 Evaporation 603 Cooling Water Blowdown &

Recycled Wastewater 737 Area represented by groundwater flow model Note: Values in acre-ft/month.

Top value is plant at full capacity from surface water model (Reference 33), lower value is from groundwater model at average plant conditions. Value in parentheses is percentage difference between surface water model and groundwater model.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 110 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 46. Model Validation - Layout of Pumping and Observation Wells for Pumping Test PW-6U FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 111 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 47. Test Well PW-6U: Observed versus Calculated Drawdowns 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 Calculated Drawdown (ft)

Observed Drawdown (ft)

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 112 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 48. Location of Units 6 & 7 Construction Dewatering Cut-Off Walls Legend: Blue lines represent cut-off walls.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 113 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 49. Location of Units 6 & 7 Construction Cut-Off Walls, Simulated Sump Pumps, and Gridlines Legend: Blue lines represent reactor building and associated structures. Khaki cells represent implementation of MODFLOWs HFB flow package in model to represent cut-off walls. Red cells represent sump pumps (inside cut-off walls).

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 114 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 115 of 132 Figure 50. Cross Section of Model Setup for Units 6 & 7 Excavations Note: Cut-off walls extended to top of model domain for illustration only Section Across Row 218. Vertical Exaggeration 5:1 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 51. Grouting Holes Spacing and Frequency during Proposed Grouting Method FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 116 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 52. Comparison of Pumping Rates under Different Grouting Scenarios FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 117 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 118 of 132 Figure 53. Post-Construction Recharge Zones for Units 6 & 7 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 54. Location of Mechanically Stabilized Earth Retaining Walls around Perimeter of the Turkey Point Units 6 & 7 Plant Area (Excluding the Makeup Water Reservoir)

Note: Mechanically stabilized earth retaining walls highlighted in red.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 119 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 55. Location of Radial Collector Wells and Laterals, with Finite-Difference Grid and Pumping Well Locations Overlaid FPL Turkey Point Units 6 & 7 Project Single Lateral Redundant Well Turkey Point Peninsula Caisson Note: Dark red lines = radial collector well arms. Dark red symbol = pumping well node..

Rev. 001 Page 120 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 56. Potentiometric Surface within the Upper Higher Flow Zone during Radial Collector Well Simulations Legend: Blue lines are equipotentials in 0.5 feet increments.

Note: the Upper Higher Flow Zone is above the Key Largo Limestone and is the zone from which the RCW system is pumped. Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 121 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 57. Head Contours in Layer 1 during Radial Collector Well Simulations Legend: Blue lines are equipotentials in 1 foot increments.

Note: Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 122 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 123 of 132 Figure 58. Cross Section through Turkey Point Peninsula Showing Groundwater Contours Resulting from Operation of the RCW System Legend: Blue lines are equipotentials in 1 foot increments.

ion = 20:1 Note: Section Across Row 120, Vertical Exaggerat Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 59. RCW Drawdown within the Top Layer Note: Thin red line = 0.1, 0.5, 1.0, 2.0, and 3.0 foot drawdown contours. Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 124 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 60. RCW Drawdown within the Pumped Layer (Upper Higher Flow Zone)

Note: Thin red line = 0.1, 0.5, 1.0, 2.0, and 3.0 foot drawdown contours. Light yellow portion in top right is where aerial imagery is not available. Approximate elevation of Upper Higher Flow Zone underneath Turkey Point Peninsula is -22 ft NAVD 88..

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 125 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 61. Origin of Flow to the RCW System (Layer 1)

Note: Blue areas show origins of water contributing to RCW system.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 126 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 127 of 132 Figure 62. Origin of Flow to the RCW System (Layer 2)

Note: Blue areas show origins of water contributing to RCW system.

Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 63. Additional Areas for RCW Approach Velocity Calculation FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 128 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 64. Calculated Flux of Water between Layers 1 and 2 (Darcy Velocity)

Notes:

Units in ft/day. Light yellow portion in top right is where aerial imagery is not available.

FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 129 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 65. RCW Drawdown within the Top Layer (0.1 ft drawdown contour) -

Seasonal High and Low Water Level Biscayne Bay FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 130 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations Figure 66. RCW Drawdown within the Top Layer (0.1 ft drawdown contour) -

Sensitivity Case Biscayne Bay Vertical Hydraulic Conductivity FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 131 of 132 Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure

Groundwater Model Development and Analysis: Units 6 & 7 Dewatering and Radial Collector Well Simulations FPL Turkey Point Units 6 & 7 Project Rev. 001 Page 132 of 132 Figure 67. RCW Drawdown within the Top Layer (0.1 ft drawdown contour) -

Hydraulic Conductivity of Key Largo Limestone Proposed Turkey Point Units 6 and 7 Docket Nos.52-040 and 52-041 L-2011-082 Enclosure