ML110550126

From kanterella
Jump to navigation Jump to search

Request for Additional Information Regarding Amendment Application for Approval of the Indian Point Cyber Security Plan
ML110550126
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 03/03/2011
From: Boska J
Plant Licensing Branch 1
To:
Entergy Nuclear Operations
Boska J, NRR/DORL/LPLI-1, 415-2901
References
TAC ME4212, TAC ME4213, TAC ME4214
Download: ML110550126 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 3, 2011 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249

SUBJECT:

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1, 2 AND 3 - REQUEST FOR ADDITIONAL INFORMATION REGARDING AMENDMENT APPLICATION FOR APPROVAL OF THE INDIAN POINT CYBER SECURITY PLAN (TAC NOS.

ME4212, ME4213, AND ME4214)

Dear Sir or Madam:

By letter dated July 8, 2010 (Agencywide Documents Access and Management System Accession No. ML101970048), as supplemented by letters dated September 23 and November 30, 2010 (ADAMS Accession Nos. ML102780434 and ML103410158, respectively),

Entergy Nuclear Operations, Inc. (the licensee) resubmitted a request to amend the Facility Operating Licenses (Nos. DPR-5, DPR-26, and DPR-64) for Indian Point Generating Unit Nos.

1, 2, and 3 (IP1, IP2, and IP3). Per the proposed license amendment, the licensee requested approval of the IP1, IP2, and IP3 Cyber Security Plan (CSP), provided a proposed CSP Implementation Schedule, and included a proposed revision to the Facility Operating License to incorporate the provisions for implementing and maintaining in effect the provisions of the approved CSP. The licensee's amendment request was based on a generic template developed by the Nuclear Energy Institute (NEI) in concert with the industry.

The Nuclear Regulatory Commission (NRC) staff is reviewing the CSP and the proposed CSP Implementation Schedule and has determined that additional information is required to complete its technical review. The specific questions are found in the enclosed request for additional information (RAI).

V. P. Operations -2 On March 2, 2011, the Entergy staff indicated that a response to the RAI would be provided by April 4, 2011.

Please contact me at (301) 415-2901 if you have any questions on this issue.

Sincerely,

~~ka~Oject a:~t riCenSing Branch 1-1 Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.50-003,50-247, and 50-286

Enclosure:

RAI cc w/encl: Distribution via Listserv

REQUEST FOR ADDITIONAL INFORMATION REGARDING APPROVAL OF THE CYBER SECURITY PLAN ENTERGY NUCLEAR OPERATIONS. INC.

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 1! 2, AND 3 DOCKET NOS. SO-003, SO-247, AND SO-286 RAI 1: Records Retention Title 10 of the Code of Federal Regulations (10 CFR) Section 73.S4(c)(2) requires licensees to design a cyber security program to ensure the capability to detect, respond to, and recover from cyber attacks. Furthermore, 10 CFR 73.S4(e)(2)(i) requires licensees to maintain a Cyber Security Plan (CSP) that describes how the licensee will maintain the capability for timely detection and response to cyber attacks. The ability for a licensee to detect and respond to cyber attacks requires accurate and complete records and is further supported by 10 CFR 73.S4(h), which states that the licensee shall retain all records and supporting technical documentation required to satisfy the requirements of 10 CFR 73.S4 as a record until the Commission terminates the license for which the records were developed, and shall maintain superseded portions of these records for at least 3 years after the record is superseded, unless otherwise specified by the Commission.

The licensee's CSP in Section 4.13 states that Critical Digital Asset (COA) audit records and audit data (e.g., operating system logs, network device logs) are retained for a period oftime that is less than what is required by 10 CFR 73.S4(h).

Explain the deviation from the 10 CFR 73.S4(h) requirement to retain records and supporting technical documentation until the Commission terminates the license (or to maintain superseded portions of these records for at least 3 years) and how that meets the requirements of 10 CFR 73.S4.

RAI 2: Implementation Schedule The regulation at 10 CFR 73.54, "Protection of digital computer and communication systems and networks," requires licensees to submit a CSP that satisfies the requirements of this section for Commission review and approval. Furthermore, each submittal must include a proposed implementation schedule and the implementation of the licensee's cyber security program must be consistent with the approved schedule. 10 CFR 73.54(a) requires licensees to provide high assurance that digital computer and communication systems and networks are adequately protected against cyber attacks, up to and including the design-basis threat (OBT). The completion of several key intermediate milestones (Items (a) through (g) below) would demonstrate progress toward meeting the requirements of 10 CFR 73.S4. The Nuclear Regulatory Commission (NRC) staff's expectation is that the key intermediate milestones will be completed in a timely manner, but no later than December 31, 2012. The key CSP implementation milestones are as follows:

Enclosure

-2 (a) Establish, train and qualify Cyber Security Assessment Team, as described in Section 3.1.2, "Cyber Security Assessment Team," of the CSP.

(b) Identify Critical Systems and CDAs, as described in Section 3.1.3, "Identification of Critical Digital Assets," of the CSP.

(c) Implement cyber security defense-in-depth architecture by installation of deterministic one-way devices, as described in Section 4.3, "Defense-In-Depth Protective Strategies" of the CSP.

(d) Implement the management, operational and technical cyber security controls that address attacks promulgated by use of portable media, portable devices, and portable equipment as described in Appendix D Section 1.19 "Access Control for Portable and Mobile Devices," of Nuclear Energy Institute (NEI) 08-09, Revision 6.

(e) Implement observation and identification of obvious cyber related tampering to existing insider mitigation rounds as described in Appendix E Section 4.3, "Personnel Performing Maintenance and Testing Activities," and Appendix E Section 10.3, "Baseline Configuration" of NEI 08-09, Revision 6.

(f) Identify, document, and implement cyber security controls to physical security target set CDAs in accordance with Section 3.1.6, "Mitigation of Vulnerabilities and Application of Cyber Security Controls," of the CSP.

(g) Ongoing monitoring and assessment activities will commence for those target set CDAs whose security controls have been implemented, as described in Section 4.4, "Ongoing Monitoring and Assessment," of the CSP.

(h) Full implementation of the CSP for all safety, security, and emergency preparedness functions.

Provide a revised CSP implementation schedule that identifies the appropriate milestones, completion dates, supporting rationale, and level of detail to allow the NRC to evaluate the licensee's proposed schedule and associated milestone dates which include the final completion date. It is the NRC's intention to develop a license condition incorporating your revised CSP implementation schedule containing the key milestone dates.

RAI 3: Scope of Systems 10 CFR 73.54(a) requires licensees to provide high assurance that digital computer and communication systems and networks are adequately protected against cyber attacks, up to and including the DBT as described in 10 CFR 73.1. In addition, 10 CFR 73.54(a)(1) states that the licensee shall protect digital computer and communication systems and networks associated with:

(i) Safety-related and important-to-safety functions;

-3 (ii) Security functions; (iii) Emergency preparedness functions, including offsite communications; and (iv) Support systems and equipment which, if compromised, would adversely impact safety, security, or emergency preparedness functions.

Subsequent to the issuance of the cyber security rule, the NRC stated that 10 CFR 73.54 should be interpreted to include structures, systems, and components (SSCs) in the balance of plant (BOP) that have a nexus to radiological health and safety (Agencywide Documents Access and Management System (ADAMS) Accession No. ML103490344, dated November 19, 2010). The SSCs in the BOP are those that could directly or indirectly affect reactivity of a nuclear power plant and could result in an unplanned reactor shutdown or transient and are, therefore, within the scope of important-to-safety functions described in 10 CFR 73.54(a){1). Furthermore, the NRC issued a letter to NEI dated January 5, 2011 (ADAMS Accession No. ML103550480) that provided licensees with additional guidance on one acceptable approach to comply with the Commission's policy determination.

Explain how the scoping of systems provided by licensee's CSP meets the requirements of 10 CFR 73.54 and the additional guidance provided by the NRC.

v. P. Operations -2 On March 2, 2011, the Entergy staff indicated that a response to the RAI would be provided by April 4, 2011.

Please contact me at (301) 415-2901 if you have any questions on this issue.

Sincerely, Ira!

John P. Boska, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.50-003, 50-247, and 50-286

Enclosure:

RAI cc w/encl: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrDorlLpl1-1 RidsNrrPMlndianPoint RidsOGCRp LPL1-1 Reading File RidsNrrLASLittle RidsAcrsAcnw_MailCTR RidsNrrDorlDpr RidsRgn1 MailCenter RidsNsirdSPlscpb R. Pascarelli, NRR/DORL C. Erlanger, NSIRIISCPB P. Pederson, NSIRIISCPB B. Singal, NRR/DORL T. Wengert, NRR/DORL ADAMS ACCESSION NO.: ML110550126 (*) No substantial change in the RAI Memo OFFICE LPL 1-1/PM LPL1-lILA NSIRIISCPB/BC* LPL 1-1/BC LPL 1-1/PM NAME JBoska I SUttle CErlanger NSalgado JBoska DATE 3/3/11 I 3/3/11 02118/11 313/11 3/3/11 OFFICIAL RECORD COpy