MONTHYEARIR 05000443/20240032024-10-30030 October 2024 Integrated Inspection Report 05000443/2024003 ML24303A0352024-10-29029 October 2024 Operator Licensing Examination Approval IR 05000443/20244022024-10-17017 October 2024 Material Control and Accounting Program Inspection Report 05000443/2024402 (Cover Letter Only) L-2024-159, Core Operating Limits Report for Reload Cycle 242024-10-15015 October 2024 Core Operating Limits Report for Reload Cycle 24 ML24254A2552024-09-25025 September 2024 Alternative Request No. 4A-01 for the Fourth 10-Year Inservice Inspection Interval L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24239A5382024-09-20020 September 2024 Issuance of Amendment No. 175 One-Time Allowable Outage Time Extension to the Technical Specification 3.8.1.1, A.C. Sources – Operating, Limiting Condition for Operation L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000443/20240052024-08-29029 August 2024 Updated Inspection Plan for Seabrook Station (Report 05000443/2024005) ML24232A1142024-08-21021 August 2024 Correction to Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves L-2024-141, Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit2024-08-15015 August 2024 Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Be L-2024-137, Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent .2024-08-12012 August 2024 Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent . IR 05000443/20240022024-08-0606 August 2024 Integrated Inspection Report 05000443/2024002 and Independent Spent Fuel Storage Installation Inspection Report 07200063/2024001 L-2024-127, Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent2024-08-0505 August 2024 Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite.2024-07-16016 July 2024 Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite. ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update L-2024-098, Preparation and Scheduling of Operator Licensing Examinations2024-06-12012 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-084, Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-05-30030 May 2024 Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld IR 05000443/20240102024-05-29029 May 2024 Biennial Problem Identification and Resolution Inspection Report 05000443/2024010 IR 05000443/20240112024-05-24024 May 2024 Age-Related Degradation Inspection Report 05000443/2024011 IR 05000443/20240012024-05-13013 May 2024 Integrated Inspection Report 05000443/2024001 L-2024-061, NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distribut2024-05-10010 May 2024 NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distributio ML24046A0512024-05-0707 May 2024 Issuance of Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-078, 2023 Annual Radioactive Effluent Release Report2024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report L-2024-077, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000443/20245012024-04-22022 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000443/2024501 L-2024-058, Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources2024-04-19019 April 2024 Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources SBK-L-24030, 2023 Annual Environmental Operating Report2024-04-12012 April 2024 2023 Annual Environmental Operating Report L-2024-011, and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications ML24067A2622024-03-0808 March 2024 Issuance of Amendment No. 173 Revise Technical Specification 3/4.8.1 to Allow Replacement of Reserve Auxiliary Transformer (Emergency Circumstances) L-2024-038, to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0808 March 2024 to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-037, to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0606 March 2024 to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-035, Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0505 March 2024 Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24065A2522024-03-0505 March 2024 Notice of Enforcement Discretion for Seabrook Station, Unit No. 1 (EPID: L-2024-033) L-2024-032, Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0404 March 2024 Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-033, Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B2024-03-0404 March 2024 Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B L-2024-019, Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-02-28028 February 2024 Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld IR 05000443/20230062024-02-28028 February 2024 Annual Assessment Letter for Seabrook Station (Report 05000443/2023006) L-2024-016, Radiological Emergency Plan (Ssrep), Revision 822024-02-13013 February 2024 Radiological Emergency Plan (Ssrep), Revision 82 IR 05000443/20230042024-02-12012 February 2024 Integrated Inspection Report 05000443/2023004 ML24009A1152024-01-29029 January 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24022A0652024-01-22022 January 2024 Senior Reactor and Reactor Operator Initial License Examinations L-2024-003, NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report2024-01-11011 January 2024 NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report 2024-09-25
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 10, 2011 Mr. Paul Freeman Site Vice President clo Michael O'Keefe Seabrook Station NextEra Energy Seabrook, LLC P.O. Box 300 New Hampshire, NH 03874
SUBJECT:
SEABROOK STATION, UNIT NO.1 - UPCOMING STEAM GENERATOR TUBE INSERVICE INSPECTION (TAC NO. ME5715)
Dear Mr. Freeman:
Inservice inspections of steam generator (SG) tubes playa vital role in assuring SG tube integrity. Based on my discussion with Mr. Gary Kilby on February 17, 2011, a telephone conference call has been tentatively arranged for April 15, 2011, with members of your staff to discuss the ongoing results of the SG tube inspections to be conducted during the upcoming refueling outage for Seabrook Station, Unit No.1. This call will occur after the majority of the tubes have been inspected, but before the SG inspection activities have been completed.
Enclosed is a list of discussion points to facilitate this call.
The Nuclear Regulatory Commission (NRC) staff will document a summary of the conference call, including any material that you provide to the NRC staff in support of the call.
Should you have any questions, please contact me at (301) 415-1420.
G. Edward Miller, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosure:
As stated cc w/encl: Distribution via Listserv
STEAM GENERATOR TUBE INSPECTION DISCUSSION POINTS The following discussion points have been prepared to facilitate the conference call arranged with the licensee to discuss the results of the steam generator (SG) tube inspections to be conducted during the upcoming spring 2011 refueling outage at Seabrook Station, Unit No. 1 (Seabrook). This conference call is scheduled to occur towards the end of the planned SG tube inspections, but before the inspections and repairs are completed. The NRC staff notes that the spring 2011 inspection is limited to 3 inches from the top of the tubesheet and is being performed in response to a single indication of outside diameter stress corrosion cracking identified in this area during the last inspection.
The NRC staff plans to document a summary of the conference call as well as any material that is provided in support of the call.
- 1. By letter dated January 27, 2011, NextEra Energy Seabrook, LLC submitted license amendment request (LAR) 10-06 for Seabrook (Agencywide Documents Access and Management System Accession No. ML110330202). LAR 10-06 requests a one-time implementation of alternate repair criteria for the SGs. As described in the LAR, the amendment is only needed if primary water stress-corrosion cracking is identified during the limited inspection of the SGs. Depending upon the need for the amendment, a discussion of inspection results to support the LAR would be expected.
- 2. Discuss any trends in the amount of primary-to-secondary leakage observed during the recently completed cycle.
- 3. Discuss whether any secondary side pressure tests were performed during the outage and the associated results.
- 4. Discuss any exceptions taken to the industry guidelines.
- 5. For each SG, provide a description of the inspections performed including the areas examined and the probes used (e.g., dents/dings, sleeves, expansion-transition, U-bends with a rotating probe), the scope of the inspection (e.g., 100 percent of dents/dings greater than 5 volts and a 20% sample between 2 and 5 volts), and the expansion criteria.
- 6. For each area examined (e.g., tube supports, dent/dings, sleeves, etc.), provide a summary of the number of indications identified to date for each degradation mode (e.g., number of circumferential primary water stress-corrosion cracking (PWSCC) indications at the expansion transition). For the most significant indications in each area, provide an estimate of the severity of the indication (e.g., provide the voltage, depth, and length of the indication). In particular, address whether tube integrity (structural and accident-induced leakage integrity) was maintained during the previous operating cycle.
In addition, discuss whether any location exhibited a degradation mode that had not previously been observed at this location at this unit (e.g., observed circumferential PWSCC at the expansion transition for the first time at this unit).
- 7. Describe repair/plugging plans.
Enclosure
- 2
- 8. Describe in-situ pressure test and tube pull plans and results (as applicable and if available).
- 9. Discuss the following regarding loose parts:
- what inspections are performed to detect loose parts;
- a description of any loose parts detected and their location within the SG (including the source or nature of the loose part, if known);
- if the loose parts were removed from the SG; and
- indications of tube damage associated with the loose parts.
- 10. Discuss the scope and results of any secondary side inspection and maintenance activities (e.g., in-bundle visual inspections, feed-ring inspections, sludge lancing, assessing deposit loading, etc.).
- 11. Discuss any unexpected or unusual results.
- 12. Provide the schedule for SG-related activities during the remainder of the current outage.
March 10, 2011 Mr. Paul Freeman Site Vice President clo Michael O'Keefe Seabrook Station NextEra Energy Seabrook, LLC P.O. Box 300 New Hampshire, NH 03874
SUBJECT:
SEABROOK STATION, UNIT NO.1 - UPCOMING STEAM GENERATOR TUBE INSERVICE INSPECTION (TAC NO. ME5715)
Dear Mr. Freeman:
Inservice inspections of steam generator (SG) tubes playa vital role in assuring SG tube integrity. Based on my discussion with Mr. Gary Kilby on February 17, 2011, a telephone conference call has been arranged for April 15, 2011, with members of your staff to discuss the ongoing results of the SG tube inspections to be conducted during the upcoming refueling outage for Seabrook Station, Unit NO.1. This call will occur after the majority of the tubes have been inspected, but before the SG inspection activities have been completed. Enclosed is a list of discussion points to facilitate this call.
The Nuclear Regulatory Commission (NRC) staff will document a summary of the conference call, including any material that you provide to the NRC staff in support of the call.
Should you have any questions, please contact me at (301) 415-1420.
Sincerely, Ira!
G. Edward Miller, Project Manager Plant licensing Branch 1-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosure:
As stated cc wlencl: Distribution via listserv DISTRIBUTION:
Public RidsOgcRp Resource KKarwoski, NRR LPL1-2 RlF RidsRgn1 MailCenter Resource EMurphy, NRR RidsNrrDorlLpl1-2 Resource RidsAcrsAcnw_MailCTR Resource AJohnson, NRR RidsNrrLAABaxter Resource RidsNrrDciCsgb Resource AObodoako, NRR RidsNrrPMSeabrook Resource WRaymond, RI Accession No.: ML110480846 OFFICE
=======r===========F==========T==========9
-2/PM NRRlLPL 1-2/BC NAME RTa lor HChernoff DATE 3/9/11 3/8/11 3/10/11 OFFICIAL RECORD COpy