1 WBN2Public Resource From:
Poole, Justin Sent:
Thursday, February 10, 2011 8:14 AM To:
Garg, Hukam; Darbali, Samir; Singh, Gursharan; Carte, Norbert Cc:
WBN2HearingFile Resource
Subject:
FW: NRC RAI Matrix Question Hukam, Since Norbert will not be able to make todays meeting, can you take a look at these and address their comments during the meeting. Thanks.
JustinC.Poole ProjectManager NRR/DORL/LPWB U.S.NuclearRegulatoryCommission (301)4152048 email:Justin.Poole@nrc.gov From: Crouch, William D [1]
Sent: Thursday, February 10, 2011 7:45 AM To: Poole, Justin; Clark, Mark Steven Cc: Hilmes, Steven A
Subject:
FW: NRC RAI Matrix Question ThebelowquestionsneedtobediscussedattodaysI&Ctelecon.ItappearsNorberthaschangedtheownershipfor someitemsfromNRCtoTVA;however,itappearstousthattheitemsarethingsNorbertwilldoduringtheupcoming audit.Sowedonotseethatwehaveanyactionontheseotherthantosupporttheaudit.Pleasemakesuretheseare discussedtodayduringthetelecon.Theremaybeanactionforusandwejustdonotunderstandwhatitis.
William D. (Bill) Crouch (423)3652004WBN (256)7777676Cell
From: Clark, Mark Steven Sent: Tuesday, February 08, 2011 11:03 AM To: Crouch, William D; Hilmes, Steven A Cc: Knuettel, Edward Terry
Subject:
NRC RAI Matrix Question Bill:
Please forward the following to Justin Poole for Norbert Carte to respond to:
Responses to the following items have been provided. The NRC reviewer has changed ownership back to TVA/WEC. We are unable to determine what action is required by TVA/WEC to close these items.
- 1. Items 043 and 244:
NNC 2/2/11: Issues with Common Q TR & SPM compliance were discussed in the weekly public
2 meetings. Westinghouse to perform Common Q TR & SPM compliance self assessment; this will be discussed in detail on the next audit.
- 2. Items 245, 246 and 251:
NNC 2/2/11: Issues with the Common Q TR & SPM were discussed in the weekly public meetings.
Westinghouse to perform Common Q TR & SPM compliance self assessment.
We think the self assessment report will be reviewed during the audit.
- 3. Item 041 NNC 2/3/11: At next audit compare & discuss:
(1) WNA-PT-00058-GEN Rev. 0 (2) WNA-PT-00138-WBT Rev. 0 (3) AP1000 STP Since there is no request to submit the results of the WEC self assessment, it appears the plan to close the preceding items will be by NRC audit. If this is the case, then we suggest the items remain NRC action items until such time as there is a request to which TVA can respond.
- Regards, Steve Steve Clark Bechtel Power Corp.
Control Systems Watts Bar 2 Completion Project Phone: 423.365.3007 e-mail: msclark0@tva.gov
Hearing Identifier:
Watts_Bar_2_Operating_LA_Public Email Number:
255 Mail Envelope Properties (19D990B45D535548840D1118C451C74D7EFF5445E6)
Subject:
FW: NRC RAI Matrix Question Sent Date:
2/10/2011 8:14:05 AM Received Date:
2/10/2011 8:14:06 AM From:
Poole, Justin Created By:
Justin.Poole@nrc.gov Recipients:
"WBN2HearingFile Resource" <WBN2HearingFile.Resource@nrc.gov>
Tracking Status: None "Garg, Hukam" <Hukam.Garg@nrc.gov>
Tracking Status: None "Darbali, Samir" <Samir.Darbali@nrc.gov>
Tracking Status: None "Singh, Gursharan" <Gursharan.Singh@nrc.gov>
Tracking Status: None "Carte, Norbert" <Norbert.Carte@nrc.gov>
Tracking Status: None Post Office:
HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 2746 2/10/2011 8:14:06 AM Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received: