DIABLO CANYON POWER PLANT PROCESS PROTECTION SYSTEM REPLACEMENT Third Phase 0 Meeting February 3, 2011 Scott B. Patterson Pacific Gas & Electric Co.
Avila Beach, CA sbp1@pge.com 805-545-4082 Ken Schrader Pacific Gas & Electric Co.
Avila Beach, CA kjse@pge.com 11 j
@pg 805-545-4328 John Hefler Altran Solutions Corp.
San Francisco, CA jhefler@altransolutions.com 415-543-6111 Ted Quinn Altran Solutions Corp.
San Francisco, CA tedquinn@cox.net 415-543-6111 Greg Clarkson Altran Solutions Corp.
San Francisco, CA gretg@rockcreektech.com 415-543-6111
Agenda Introduction ISG-06 Update Project Plan and Schedule LAR Discussion 2
Technical Topics Factory Acceptance Test Questions (NRC Staff)
Closing Comments/Adjourn
ISG 6 Update NRC Status PG&E Progress ISG 6 Matrix - Vendor and PG&E documents ISG 6 d C b R
i t (NRC) 3 ISG 6 and Cyber Requirements (NRC)
NRC Status ISG 6 Revision was issued on 1/19/2011 Vendor Topical Report Review Tricon v10 ALS 4
ALS Forecast for approval dates Diversity Defense-in-Depth Approval Status
PG&E Progress Completed Conceptual Design Document Completed Revision 2 of the Functional Requirement and Interface Requirement Specifications 5
Specifications Including the Logic Diagrams and IO List Project Plan is near complete SQAP is near complete Contracts to vendors for ISG 6 Phase 1 documents
Phase 1 Documentation to be Submitted 6
Phase 2 Submitted and Available for Audit 7
Phase 3 Available for Inspection 8
- Diablo Canyon is responsible to ensure compliance with the applicable cyber security regulations and guidance during all life cycle phases of the plant upgrade following 10 CFR 73 54 Regulatory Guide 1 152 Rev 2 99 CFR 73.54, Regulatory Guide 1.152 Rev. 2 and ISG-01.
- Applicable to:
- Vendor equipment software development
- Diablo Canyon responsible departments
Cyber Security Summary
- Diablo Canyon will comply fully with the applicable guidance on cyber security both for the vendor design program (offsite) and the onsite installation, testing and later 10 10 g
phases as called for in NRC Reg. Guide 1.152, ISG-01 and the applicable Regulations.
- Discuss interface to cyber security program
Project Plan and Schedule Project Scope Replacement PPS Concept Milestone Schedule Lif l
D t Fl Lifecycle Document Flow 11
Project Scope 12
Replacement PPS Concept (ALS Provides Diverse Front-End Isolation and Actuation)
Containment Pressure (4-20 mA)
RCS Flow (4-20 mA)
PZR Pressure (4-20 mA)
I II NR Temperatures (4-20 mA)
Trips to SSPS (Discrete)
TRICON Trips (To SSPS)
(Discrete)
RNASA RNASB (Discrete)
Class I Analog Outputs (4-20 mA)
Neutron Flux Inputs (0-10 VDC)
Process Inputs (4-20 mA)
N Cl I
Class I Analog Outputs (4-20 mA)
I Note: SSPS & AMSAC are original equipment; not being replaced.
I I
WR Temperatures (4-20 mA)
I I
II II Communication Links (Fiberoptic)
PZR Pressure (DTTA)
(4-20 mA)
Process Inputs PPC Data Link C
Workstation I
Channel(s) in Bypass (Discrete)
AMSAC (4-20 mA)
Protection Set Trouble (Discrete)
Protection Set Failure (Discrete)
MAS MAS DTTA RTD Failure (Discrete)
MAS Data Link 13 Protection Set Trouble (Discrete)
Protection Set Failure (Discrete)
Channel(s) in Bypass (Discrete)
DTTA RTD Failure (Discrete)
MAS (4-20 mA)
TRICON REMOTE CHASSIS Data Link PPC MAINTENANCE TERMINAL WORKSTATION (Class II)
B Workstation Non Class I Analog Outputs B
C ALS TRICON RNARA RNARB (Discrete)
HMI S/G Feedflow (4-20 mA)
(DFWCS)
Data Link Data Link Data Link Process Inputs (4-20 mA)
II I
II II Data Link (4 20 mA)
Process Control (4-20 mA)
Non Class I Analog Outputs (4-20 mA)
ALS - Advanced Logic System DFWCS - Digital Feedwater Control System DTTA - Delta T/Taverage (Thermal Trips)
HMI - Human Machine Interface PPC - Plant Process Computer PZR - Pressurizer RNARA/RNARB - Auxiliary Relay Cabinets RTD - Resistance Temperature Detector RCS - Reactor Cooling System SSPS - Solid State Protection System WR - Wide Range
Project Milestone Schedule 1/1/2011 4/30/2014 4/1/2011 7/1/2011 10/1/2011 1/1/2012 4/1/2012 7/1/2012 10/1/2012 1/1/2013 4/1/2013 7/1/2013 10/1/2013 1/1/2014 4/1/2014 DCPP PPS Replacement Project 3/31/2011 Tricon SER Issued 8/1/2011 ALS Topical Report Issued 12/10/2012 Vendor FATs Complete 5/24/2013 DCPP PPS SER Issued 2/15/2014 PPS Installation 3/1/2013 Design Package Issued 2/24/2012 Vendor Phase 2 Items Complete Provided to PG&E 3/23/2012 Phase 2 Items Provided to NRC 7/15/2011 LAR Submitted to NRC 14 1/1/2011 8/1/2011 2/1/2011 3/1/2011 4/1/2011 5/1/2011 6/1/2011 7/1/2011 LAR Submittal 6/1/2011 Vendor Phase 1 Items Complete Provided to PG&E 6/15/2011 LAR w/Phase 1 Items Complete by PG&E Team Provided to Licensing for Final Review 2/3/2011 Phase 0 Meeting w/NRC 7/15/2011 LAR Submitted to NRC
Lifecycle Document Flow FRS IRS SyRS SAD SyDS HAD SRS (CLB Spec)
SRS SDD SDS HDS HDS CDD Requirements Definition Design Requirements Definition Concept (PG&E)
ALS IOM Concept (PG&E)
Glossary:
CDD Conceptual Design Document FRS Functional Requirements Specification IRS Interface Requirements Specification SAD Software Architecture Requirements HAD Hardware Architecture Requirements SyRS System Requirements Specification SyDS System Design Specification SRS Software Requirements Specification HRS Hardware Requirements Specification HDS Hardware Design Specification SDD Software Design Description SDS Software Design Specification FAT Factory Acceptance Test 15 HDS HDS FAT FAT RTM RTM SVVR SVVR SAT RTM SyVVR Design Test SAT Site Acceptance Test DVT Design Verification Testing RTM Requirements Traceability Matrix SVVR Software Verification & Validation Report SyVVR System Verification & Validation Report Test Installation/Checkout
LAR Discussion Format of LAR - with two vendors, how should the LAR be structured?
LAR Submittal as a Tier 1 for Tricon and ALS with NRC acceptance tied to both vendor topical l
16 approval Confirm review schedule NRC Resources - who and when will they be available for our review Submittal of High Level Documents first before the LAR for review
Technical Topics NRC's evaluation of ALS diversity approach -
Risks? Challenges?
Maintenance Workstation Software (non-safety) -
What review will the NRC do and what level of documentation is expected M i t W
k t ti i SIL 1 17 Maintenance Workstation is SIL 1 Time Base Verification - can this be justified without periodic measurement of time base based on how it works (e.g. self-diagnostics)
Use of simple digital components like isolators, signal conditioners with respect to diversity and CCF's RPS/ESFAS Application Software QA
Factory Acceptance Test (FAT)
Site Acceptance Test (SAT)
Two Separate FATs before SER Each vendor will perform an FAT How much time does the NRC need after the submittal of the FAT report to issue the SER?
18 Integrated SAT after SER SAT to verify equipment after shipment and testing of any external interfaces at the Project Integration and Test (PIT) facility Design Verification Test (DVT) before being placed in service
Questions NRC Staff PG&E Westinghouse I
19 Invensys
Closing Comments/Adjourn 20