VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 January 25, 2011 U.S. Nuclear Regulatory Commission Serial No.: 11-026 Attention: Document Control Desk NAPS/JHL: RO Washington, D.C. 20555 Docket No.: 50-338 License No.: NPF-4 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)

NORTH ANNA POWER STATION UNIT 1 OWNER'S ACTIVITY REPORT In accordance with the requirements of American Society of Mechanical Engineers (ASME) Code Case N-532-4, enclosed is the Owner's Activity Report (Form OAR-i), for refueling outage N1 R21. This report is for the first refueling outage of the first period of the fourth inspection interval.

Should you have any questions regarding this submittal, please contact Mr. Donald R.

Taylor at (540) 894-2616.

Very truly yours, F. Mladen Director - Nuclear Station Safety and Licensing Commitments made in this letter: None Attachment A-047

cc: U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Avenue, NE, Suite 1200 Atlanta, Georgia 30303-1257 NRC Senior Resident Inspector North Anna Power Station Mr. J. E. Reasor, Jr.

Old Dominion Electric Cooperative Innsbrook Corporate Center 4201 Dominion Blvd.

Suite 300 Glen Allen, Virginia 23060 Dr. V. Sreenivas NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 0-8 G9A Rockville, MD 20852-2738 Ms. K. R. Cotton NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 0-8 G9A Rockville, MD 20852-2738 Mr. M. M. Grace Authorized Nuclear Inspector North Anna Power Station

Attachment Owner's Activity Reports for North Anna Unit 1 Refueling Outage NIR21 - First Period of the Fourth ISI Interval North Anna Power Station Virginia Electric and Power Company

FA Ac Rep- o PDominion, Report Number: N1R21 (Unit 1, 4th Interval, 1 st Period)

Plant: North Anna Power Station Unit No. 1 Commercial service date: 6/6/1978 Refueling outage no. N1 R21 (if applicable)

Current inspection interval: 4 th (May 1, 2009 - April 30, 2019)

(1Ts, 2nd, 3 rd, 4 th, other)

Current inspection period: 1s' (May 1, 2009 -April 30, 2012)

( 1 S1, 2 w', 3 ra 4 fl)

Edition and Addenda of Section XI applicable to the inspection plans: 2004 Edition Date and revision of inspection plans: February 2010. Revision 1 Edition and Addenda of Section XI applicable to repair/replacement activities, if different than the inspection Plans N/A Code Cases used: N-432-1, N-460, N-504-3, N-526, N-532-4, N-552, N-566-2, N-586-1, N-597-2, N-613-1.

N-624. N-638-1 N-641 N-651. N-658. N-661. N-663. N-683. N-696. N-706-1. N-722. and N-729-1.

(if applicable)

CERTIFICATE OF CONFORMANCE I certify that (a) the statements made in this report are correct; (b) the examinations and tests meet the Inspection Plan as required by the ASME Code,Section XI; and (c) the repair/replacement activities and evaluations supporting the completion of NiR21 conform to the requirements of Section XI.

(refueling outage number)

Signed - D n 2. Date /  ! Zo f

CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of Virginia and employed by HSB CT of Hartford, CT have inspected the items described in this Owner's Activity Report, and state that, to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section Xl.

By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the repair/replacement activities and evaluation described in this report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with thig'?spection.

conne1*y Commissions NB 9531-A-N-I-C / VA 424-R Inspector's Signerture National Board, State, Province and Endorsements Date J721zx2,0//I Form No. 729595 (Aug 2009)

Form OAR-I, 0 A a ,

Owner's Activity Report 0 *Jwy 1ý ý w ý! 611

ý,IDominion-Table I Items with Flaws or Relevant Conditions That Required Evaluation for Continued Service Examination Item Description Evaluation Description Category and Item Number Spring Hanger 1 11/2-RC- Spring hanger's cold load 105/SH-3 setting was beyond readable range. Engineering eval, F-A/ Fl.1OC CR396534, found pipe hung up until jarred loose after work on valve 1-RC-105. Support Summary # N1. F1.10.476 found acceptable.

Spring Hanger 6-CH-19/SH-29 Spring can rod found bowed.

Eval per CR396117 identified F-A/ F1.20C SAT spring can loading and minimal misalignment.

Summary # N1 .F1.20.211 Support found acceptable.

Support 14-RH-2/R-16 2 anchor bolts appeared not seated tightly to base plate.

F-A/ F1.20A Eng. Eval per CR395483 found support meeting design Summary # N1.F1.20.359 basis and bolting fully engaged.

1-RH-MOV-1720A CR395392 Code case N-522-B-P / B15.10 2 evaluation on MOV bolting, acceptable for next operating 1 -PT-48 cycle.

1-RH-MOV-1 701 CR395326 Code case N-522-B-P /B15.10 2 evaluation on MOV bolting, acceptable for next operating 1-PT-304RH cycle.

Spring Hanger 10-CC-B351 / Found outside 10% cold load SH-380 setting. CR395146 eval.

F-A / F1.30C Found within working range for all load cases. Support Summary # N1 .F1.30.601 found acceptable Pipe restraint 6-CC-397 / R- Clearances found out of 376 tolerance. CR394552 F-A / F1.30B evaluated support, found Summary # N1.F1.30.597 acceptable.

1-CH-P-2B Excessive inactive boric acid at bolting, evaluated per D-B / D2.10 CR392333, no degradation.

Acceptable for continued 1 -PT-302CH service.

Form No. 729595 (Aug 2009)

Form OAR-I, Owner's Activity Report FW;Dominion E-A IS10 ATAHMN 1 'Pg 30 of0 Table 2 Abstract of Repair/Replacement Activities Required for Continued Service Code Date Repair/Replacement Class Item Description Description of Work Completed Plan Number Repair weld/base 1 1-RC-HSS-115B metal by metal 12/18/09 2009-137 removal 2 1-BD-119 Clamp Valve and 1/26/10 2009-141 Piping Appendix IX 1 1-RC-HSS-818 Replace Snubber 10/1/10 2010-210 2 1-QS-37 Valve Bonnet Weld 10/20/10 2010-215 Repair 3 1-CC-PH-R- Replace nut and 9/30/10 2010-222 329.76A realign support clamp 2 1-RS-HSS-208A Replace Snubber 1/1/10 2010-225 3 W-PP-20.00- Window joint repair on 10/20/10 2010-130 WS-PIPE-E23- pp 02/0 21-3 151-Q3 pipe 3 1 -QS-38 Replace Bonnet 10/2/10 2010-197 Bolting 1-SW-PPA-1A1- Install new SW Spray 3 ARRAY Array and modify 5/6/10 2008-137 supports 1-SW-PPA-1 B2- Install new SW Spray 3 ARRAY Array and modify 6/1/10 2008-130 supports Form No. 729595 (Aug 2009)