ML110260450
| ML110260450 | |
| Person / Time | |
|---|---|
| Site: | Sequoyah |
| Issue date: | 01/28/2011 |
| From: | Office of Nuclear Reactor Regulation |
| To: | |
| Lingam, S NRR/DORL 415-1564 | |
| Shared Package | |
| ML110280330 | List: |
| References | |
| Download: ML110260450 (15) | |
Text
Sequoyah Nuclear Plant, Unit 2 Sequoyah Nuclear Plant, Unit 2 Steam Generator Replacement Project Status and Licensing Plan 1
Licensing Plan January 26, 2011
Introduction Introduction
- Purpose
- Background
- Replacement Steam Generator (RSG) Design Features and Installation Overview
- Project Status 2
Project Status
- Licensing Plan
- Summary
Purpose Purpose
- Provide background information, RSG design and installation overview, and describe the overall licensing process that TVA will use
- Provide the NRC staff TVAs current project status and licensing plan for the Sequoyah Unit 2 (SQN 2)
Steam Generator (SG) replacement
- Describe the submittals that TVA expects to provide to the NRC 3
=
Background===
Background
- The SQN 1 steam generators were replaced in 2003
- The Watts Bar Unit 1 (WBN 1) steam generators were replaced in 2006
- The contract for SQN 2 steam generator removal g
and installation was awarded in 2009 to the Steam Generating Team (SGT)
Background (continued)
Background (continued)
- The SQN 2 replacement steam generators are like-for-like compared to the original steam generators in form, fit, and function (same as SQN 1)
- Shield Building, Steel Containment Vessel (SCV) and SG Compartment Modifications use the same methodology as SQN 1 5
RSG Design Features RSG Design Features
- Steam Generators were designed by Westinghouse, fabricated by Doosan, and SG tubes provided by Sandvik
- Same physical size as existing steam generators
- Increased tube surface area to provide additional 6
plugging margin
- Integral loose parts strainer provided for FW/AFW
- Reduced moisture content at steam nozzle exit
- Additional access hand holes for maintenance
- Snaplock Nozzle Dams provided for dose reduction
- Electro Polished Head Bowls for dose reduction
RSG Installation Overview RSG Installation Overview
- One Piece Replacement like SQN 1
- Major Activities Involve:
- Defuel Reactor
- Cut holes in Shield Building dome, SCV, and SG Compartment Roofs Remove existing SGs 7
- Remove existing SGs
- Install Replacement SGs
- Restore SG Compartments, RCS piping, SCV, and Shield Building dome
- Refuel Reactor
- Pressure Test to Demonstrate Restored Containment Integrity
Project Status Project Status
- The SQN 2 steam generators are to be replaced in the Cycle 18 (U2C18) Refueling Outage, scheduled to start October 21, 2012
- RSGs are on site (controlled storage)
- Engineering and planning for U2R17 work g
g p
g progressing on schedule
- Engineering, licensing, and installation planning for U2R18 progressing on schedule
- AREVA Accident Analyses review complete
- No new analysis required for the Unit 2 RSGs
- Currently reconciling existing calculations and analysis by mid summer 2011 8
Project Status (continued)
Project Status (continued)
- Safe Load Paths and Drop Analysis for Crane Components, Steam Generators, and Other Heavy Loads under Development
- Licensing Submittals being prepared 9
Licensing Plan Licensing Plan
- Steam Generator Component Replacement Performed via 10 CFR 50.59
- Design Changes Related to RSGs Performed via 10 CFR 50.59 10
Licensing Plan (continued)
Licensing Plan (continued)
- License Amendment Requests (LARs)
- LAR (UFSAR 3.8.3.4.8) to address the Code change used in restoration of the concrete roof of the steam generator compartments LAR (UFSAR 3 8 1) to use Bar Lock Mechanical 11
- LAR (UFSAR 3.8.1) to use Bar-Lock Mechanical Couplers instead of Cadwelds for Rebar Splicing during Shield Building Dome Restoration
- LAR to revise Steam Generator Inspections (TSTF-449)
Licensing Plan (continued)
Licensing Plan (continued)
- Relief Request
- Relief request to utilize a containment pressure test in lieu of a Containment Integrated Leak Rate Test for Post Modification Testing of restored Steel Containment Vessel
- One Time Use LARs
- One time use LAR (License Condition) for movement of loads over Essential Raw Cooling Water piping per GL 96-02
- One time use LAR for two 18 hatches in the shield building dome to allow pre-outage work in the annulus space during power 12
Licensing Plan (continued)
Licensing Plan (continued)
- Request for use of 18 hatches at power will facilitate pre-outage work in the annulus space
- Will use alternate source terms
- This is a one time change with defined times of use, limits on use, compensatory measures while in this condition, and defined expiration date p
13
Licensing Plan (continued)
Licensing Plan (continued)
- Submittal Schedule
- Relief Request for containment pressure test submitted December 22, 2010 - approval requested by October 1, 2012 One time use LAR for two 18 hatches to be submitted by 14
- One time use LAR for two 18 hatches to be submitted by May 1, 2011 - approval requested by July 1, 2012
- Three LARs to be submitted by May 1, 2011 - approval requested by October 1, 2012
- One time use LAR for movement of loads to be submitted by July 1, 2011 - approval requested by October 1, 2012
Summary Summary
- Implementing SQN/WBN Lessons Learned and Best Practices
- Based on SQN 1 Licensing/Design Basis similarities
- Plan is to provide at least 1 year NRC review time 15
- Plan is to provide at least 1 year NRC review time