L-2010-259, St. Lucie, Unit 1 - Extended Power Uprate Licensing Report, Attachment 7; Summary of Regulatory Commitments

From kanterella
(Redirected from ML103560452)
Jump to navigation Jump to search
St. Lucie, Unit 1 - Extended Power Uprate Licensing Report, Attachment 7; Summary of Regulatory Commitments
ML103560452
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 12/15/2010
From:
Florida Power & Light Co
To:
Office of Nuclear Reactor Regulation
References
L-2010-259
Download: ML103560452 (3)


Text

St. Lucie Unit 1 EPUAtt. 7-1 Summary of Regulatory CommitmentsSt. Lucie Unit 1L-2010-259Docket No. 50-335Attachment 7ATTACHMENT7 LICENSE AMENDMENT REQUESTEXTENDED POWER UPRATE

SUMMARY

OF REGULATORY COMMITMENTSFLORIDA POWER AND LIGHTST. LUCIE NUCLEAR PLANT, UNIT1This coversheet plus 2pages St. Lucie Unit 1 EPUAtt. 7-2 Summary of Regulatory CommitmentsSt. Lucie Unit 1L-2010-259Docket No. 50-335Attachment 7ATTACHMENT7

SUMMARY

OF REGULATORY COMMITMENTSIntroductionThe regulatory commitments listed below are intended to maintain compliance with regulatory requirements during preparation for and upon extended power uprate (EPU) implementation. The commitments are based upon the plant changes summarized in license amendment request (LAR) Attachment5, EPU Licensing Report. These commitments will be completed prior to the final implementation of EPU.REGULATORY COMMITMENTS1.Update the Inservice Testing Program to reflect changes to plant pumps and valves under EPU conditions.2.Provide operator training to account for increased EPU power level and resultant plant changes.3.Implement modifications to provide radiation shielding for reactor auxiliary building heating, ventilation, and air conditioning (HVAC) components identified in LR Section2.3.1, Environmental Qualification of Electrical Equipment.4.Implement modification(s) to increase safety injection tank design pressure for EPU conditions described in LR Section2.8.5.6.3, Emergency Core Cooling System and Loss-of-Coolant Accidents.5.Implement modification(s) necessary to accommodate the simultaneous hot and cold leg injection requirements for EPU conditions as described in LR Section2.8.5.6.3, Emergency Core Cooling System and Loss-of-Coolant Accidents.6.Implement modification(s) to install a leading edge flow meter (LEFM) as described in LR Section2.4.4, Measurement Uncertainty Recapture Power Uprate, and update UFSAR Section13.8, Licensee-Controlled Technical Specification Requirements, to include Limiting Conditions for Operation (LCO) and Action Statements for the LEFM system.7.Implement modification(s) to the ac electrical busses as described in LR Section2.3.3, AC Onsite Power System.8.Revise the administrative controls for the main containment purge isolation valves such that they are maintained closed in MODES1, 2, 3 and4.9.Implement modification(s) to pipe supports for systems impacted by loads due to EPU conditions, as described in LR Section2.2.2.2, Balance of Plant Piping, Components, and Supports.10.Revise applicable procedures to accommodate operator actions during station blackout at EPU conditions, as described in LR Section2.11, Human Factors.11.Implement a Metamic TM insert surveillance program as described in LR Section2.8.6.2, Spent Fuel Storage, and update the UFSAR to include the program requirements.

St. Lucie Unit 1 EPUAtt. 7-3 Summary of Regulatory CommitmentsSt. Lucie Unit 1L-2010-259Docket No. 50-335Attachment 7By letter R. Anderson, Florida Power and Light (FPL) to NRC Document Control Desk, Extended Power Uprate License Amendment Request - Response to NRC Acceptance Review Questions, dated July30,2010 (ML102160343), FPL provided a list of six regulatory commitments, which are listed below. These six commitments are either completed or will no longer be required as indicated below.1.FPL commits to perform a new spent fuel pool criticality analysis to replace the existing analysis of record once the draft interim staff guidance (ISG) is formally issued. This revised analysis will be submitted as a separate license amendment request (LAR) for NRC review and approval. FPL will submit this LAR within one year of issuance of the final ISG.This commitment is completed with the new spent fuel pool criticality analyses submitted via FPL letter L-2010-259.2.Implement administrative controls to impose a 7% burnup penalty on the average burnup of any 2 X 2 array configuration allowed by current Technical Specifications. This burnup margin will offset the two issues identified by NRC and provides additional margin.This commitment will no longer be required upon NRC approval and subsequent FPL implementation of the revised technical specifications associated with the EPU.3.Implement administrative controls to maintain a spent fuel pool (SFP) boron concentration limit of 2000ppm which is above the current Technical Specification limit of 1720ppm.This commitment will no longer be required upon NRC approval and subsequent FPL implementation of the revised technical specifications associated with the EPU.4.Verify the normal position of valve V15322 (primary makeup water hose connection to the cask storage isolation) is locked closed as part of normal operator rounds in the fuel handling building.This commitment will no longer be required upon NRC approval and subsequent FPL implementation of the revised technical specifications associated with the EPU.5.Verify, as part of normal operator rounds in the fuel handling building, that there are not other sources or indications of dilution to the SFP.This commitment will no longer be required upon NRC approval and subsequent FPL implementation of the revised technical specifications associated with the EPU.6.Verify that the SFP boron concentration is 2000ppm twice every seven days.This commitment will no longer be required upon NRC approval and subsequent FPL implementation of the revised technical specifications associated with the EPU.