UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 November 12, 2010 Mr. Barry Allen Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2, Mail Stop A-DB-3080 Oak Harbor, OH 43449-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION NOTIFICATION OF AN NRC SUPPLEMENTAL INSPECTION - FOLLOW-UP
Dear Mr. Allen:
During the time period of December 1 through December 3, 2010, per discussion with Mr. James Vetter, Emergency Response Manager, the NRC will conduct the onsite follow-up portion of the 95001 Supplemental Inspection at your Davis-Besse Nuclear Power Station.
In your letter dated November 10, 2010, you informed us that actions to address the identified concerns from the previous 95001 inspection had been completed, and that the site was ready for the follow-up inspection. We have confirmed with members of your Emergency Preparedness staff, that accommodations were met to support the inspection on this date.
We will contact your Emergency Preparedness staff for any documents needed prior to the inspection.
The inspection will be performed in accordance with NRC supplemental Inspection Procedure 95001, and will focus on the actions you have taken to address concerns from the previous 95001 inspection, which was performed onsite during the week of August 16, 2010.
The lead inspector for this inspection is Ms. Patricia Voss. If there are questions about the inspection, please call Ms. Patricia Voss at (630) 829-9812.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide
B. Allen Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-346 License Nos. NPF-3 cc:
Distribution via ListServ
B. Allen Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-346 License Nos. NPF-3 cc:
Distribution via ListServ DISTRIBUTION:
RidsNrrDorlLpl3-2 Resource Daniel Merzke RidsNrrPMDavisBesse Resource RidsNrrDirsIrib Resource Steven West Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak DOCUMENT NAME: G:\\DRSIII\\DRS\\Work in Progress\\DAV 111210 DRS OL 95001 Ltr of Intent.docx 9 Publicly Available 9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive To receive a copy of is document, indicate in the box: " " = Copy without attachment/enclosure "E" = Copy with attachment/encl sure "N" = No copy th C
o OFFICE RIII RIII NAME PVoss:co HPeterson DATE 11/12/10 11/12/10 OFFICIAL RECORD COPY