Similar Documents at Salem |
---|
Category:E-Mail
MONTHYEARML24277A0812024-10-0303 October 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon Collected on 10/02/2024 ML24269A0362024-09-24024 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/24/2024 ML24248A0452024-09-0303 September 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 9/3/2024 ML24229A0422024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Implement Optimized ZIRLO Fuel Rod Cladding ML24229A0432024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Exemption from 10 CFR 50.46 and 10 CFR 50 Appendix K to Allow the Use of Optimized ZIRLO Fuel Rod Cladding ML24228A1942024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form for a Live - Atlantic Sturgeon 8/14/2024 ML24227A5092024-08-14014 August 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 8/13/2024 ML24250A0562024-07-11011 July 2024 PSEG to NMFS, Regarding Processing of Fin Clips ML24219A2472024-07-0909 July 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Shortnose Sturgeon 7/9/2024 ML24123A0522024-05-0101 May 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - One Deceased Sturgeon 4/30/2024 ML24106A0542024-04-12012 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Alive Atlantic Sturgeon 4/12/2024 ML24101A2192024-04-0909 April 2024 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 4/8/24 ML24093A1222024-04-0101 April 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - One Atlantic Sturgeon 4/1/2024 ML24075A1862024-03-14014 March 2024 NRR E-mail Capture - (External_Sender) Biological Opinion Gar 2020-02842 - PSEG Salem and Hope Creek Generating Station Annual Incidental Take Report - 2023 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML24030A8432024-01-30030 January 2024 NRR E-mail Capture - (External_Sender) 2023 PSEG Sturgeon Pit Tag Data ML24016A1612024-01-10010 January 2024 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms - Two Atlantic Sturgeon 1/9/2024 ML24002A7222023-12-29029 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - 2023 Annual Report - Inspection of the Circulating Water Intake Structure (Cwis) Trash Rack Bars ML24002A7242023-12-28028 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form - Sturgeon 12/28/2023 ML23355A2732023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) PSEG Response to Questions Associated with Supplement to Salem-Hope Creek Eab Reduction LAR ML24002A7252023-12-21021 December 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Shortnose Sturgeon 12/21/23 ML23346A0962023-12-0606 December 2023 NRR E-mail Capture - Reminder - Final Report - Completion of Required Additional Protocol (AP) Information in Accordance with the U.S. - IAEA Treaty Obligations ML23311A0792023-11-0101 November 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Atlantic Sturgeon Collected on 10/31/2023 ML23277A0482023-10-0404 October 2023 NRR E-mail Capture - 10/4/2023 Email: Acceptance Review - Hope Creek and Salem 1 and 2 - LAR to Modify Exclusion Area Boundary ML23277A0732023-09-29029 September 2023 NRR E-mail Capture - (External_Sender) 9/29/2023 Email from PSEG: Supplement to Proposed Amendment to PSEG Master Decommissioning Trust Amendment ML23226A0702023-08-11011 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Sturgeon Collected on 8/10/2023 ML23226A0732023-08-10010 August 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Submittal of Necropsy Reports Regarding Sea Turtles Collected on 06/12/2022 ML23201A0132023-07-20020 July 2023 NRR E-mail Capture - Acceptance Review - Salem 1 and 2 - Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML23172A0982023-06-21021 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/20/2022 ML23164A2062023-06-13013 June 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report - Kemps Ridley Sea Turtle Collected on 06/12/2023 ML23163A0442023-06-0606 June 2023 NRR E-mail Capture - (External_Sender) Biological Opinion GAR-2020-02842; FIN Clip Analysis Facilities ML24250A0572023-06-0606 June 2023 PSEG to NMFS, Request for Sturgeon Fin Clip Analysis Facilities ML23153A1552023-06-0202 June 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 6/1/2023 ML23151A6582023-05-31031 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/30/2023 ML23137A2632023-05-17017 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms Sturgeon 5/16/2023 ML23135A0102023-05-11011 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 5/11/2023 ML23136B2832023-05-0404 May 2023 NRR E-mail Capture - (External_Sender) PSEG Bottom Trawl Sampling - Incidental Take Report and Data Collection Form - Atlantic Sturgeon 5/3/2023 ML23122A1982023-05-0202 May 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeon 5/1/2023 ML23122A1672023-05-0202 May 2023 NRR E-mail Capture - Acceptance Review - Hope Creek and Salem 1 and 2 - Revise TS to Delete TS Section 5.5 - Meteorological Tower Location ML23117A2722023-04-17017 April 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 04/14/2023 ML23079A0032023-03-17017 March 2023 NRR E-mail Capture - Hope Creek, Salem 1 and 2 - Evacuation Time Estimate Review ML23065A0452023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Salem & Hope Creek Generating STATIONS-ANNUAL Incidental Take REPORT-STATION & REMP ML23033A0302023-02-0808 February 2023 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report Sturgeon 1/24/2023 ML23010A2882023-01-10010 January 2023 NRR E-mail Capture - (External_Sender) Salem Generating STATION-INCIDENTAL Take of Atlantic Sturgeon Collected on 01/09/2023 ML23003A2412023-01-0303 January 2023 NRR E-mail Capture - Final Nvib RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML22357A0102022-12-21021 December 2022 NRR E-mail Capture - Final Nphp RAI - Salem Unit 2 Relief Request S2-I4R-211, Fourth Inservice Inspection (ISI) Interval Limited Examinations ML23003A2402022-12-21021 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Form for Atlantic Sturgeon Collected on 12/20/2022 ML23003A2392022-12-20020 December 2022 NRR E-mail Capture - (External_Sender) Salem Generating Station - Incidental Take Report and Data Collection Forms for Atlantic Sturgeons Collected 12/19/2022 ML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22291A3702022-10-18018 October 2022 NRR E-mail Capture - Acceptance Review - Salem 2 - Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2022-LLR-0066) 2024-09-03
[Table view] |
Text
Ziev, Tracey From: Conte, Richard Sent: Wednesday, April 14, 2010 4:22 PM To: OHara, Timothy; Schroeder, Daniel Cc: Burritt, Arthur; Cline, Leonard; Wilson, Peter; Kaufman, Paul
Subject:
draft problem summary on SL 1 AFW Attachments: SL1 AFW Degradation Coating Failure.doc Tim and Dan please review. Send me corrections.
for managers, tentative cc for you use.
I C 139
Revision 0 - 4/15/10 Problem Summary:
As a result of implementation the PSEG buried pipe program, significant degradation of the No.
14 and 12 Auxiliary Feedwater Piping was identified - certain section may need to be replace based on minimum wall analysis. PSEG is developing a past and future operability review along with a finite element analysis in order to assess the structural integrity of the AFW piping including a potential design change for minimum wall thickness based on a new pressure rating.
An apparent cause is little to no coating application of this section of buried piping. An extent of condition is being developed as a part of a root cause report that will not be finalized until after the pending startup of Salem 1 -4/24/10. Unit 2 is operating and has similar piping but the difference appears to be in the use of a proper coating application based on 1994 information.
Backqround/Facts:
See attached for more details. The licensee has dug a trench along about one quarter of the southwest wall of the Unit 1 containment between the fuel handling building and the containment outer penetration building. Based on flow path, the AFW piping exits the fuel handling building and enters the outer penetration room to enter containment and feed the No.
14 and 12 Steam Generators. The piping also traverses in the fuel handling building under the fuel transfer canal from the mechanical penetration room and is surrounded by sand fill.
In the trench, PSEG is characterizing the level of degradation of the No. 14 and 12 headers based on UT information that is ASME code compliant. The licensee is also characterizing the level of degradation of piping in the fuel handling building - sand was removing exposing a portion of the AFW piping and other lines having service air and control air which also traverse the above noted trench.
Safety Sigqnificance:
AFW is safety related. AFW is also relied upon for normal startup and shutdown. In addition it is used to mitigate all internal initiating events with the exception of large and medium break LOCA's. AFW is also utilized to mitigate external initiators, such as fire and flooding If the system is capable of performing it's safety function, there is no safety significance. The licensee continues to assess the structural integrity of as-found conditions.
Licensee Next Steps:
Repair:
The licensee is still investigating the level of degradation in the yard/trench area and in the area below grade in the fuel handling building.
Based on UT measurement they need to determine extent of repair based on revised analysis for minimum wall thickness based on a new design pressure rating. They are tentatively looking at replacing 50 feet of pipe below minimum wall of .260 inches (not clear yet reduced rated pressure) without additional UT characterization. The remaining piping will have the 1 inch by 1 inch grid characterization. Where the pipes enter the outer penetration room and the FHB in this trench, the penetrations are also in need of repair.
Some repair/coating or reapplication of coating in the FHB will be needed. They are apparently relying on intact coaling on vertical section of the riser in the FHB and assuming uniform condition for the buried section in the building. A hydrostatic post repair test is to include this section of piping. This area may be a significant challenge since it is an area of wetted sand and the coating can not have any imperfections with respect to above noted assumptions.
Output Analysis:
Operability to support startup of Unit 1 Operability determination to support past operations for Unit 1.
Finite Element Analysis on ASME qualified UT information (doing a 1inch by 1 inch template review similar to that done for flow accelerated corrosion measurements.
Root Cause and extent of condition review - final documentation after startup.
Potential design change package for reduced pressure rating of system from 1950 to 1275 psi.
Extent of Conditions:
Unit 1 other headers No. 11 and 13 as well as corresponding headers in Unit 2 - Not buried, no evidence of a problem.
Unit 2 buried headers: 1994 data and records suggestion acceptable coating; and where damage occurred due to digging, it was repaired.
Other Safety Related Piping - Control Air - with one exception in the fuel handling building, the condition of coating was acceptable and appears to have been properly applied. Repair to the exception in the fuel handling building will be made, apparent due to isolated mechanical damage.
Other Safety Related Piping - Service Water Nuclear Headers - different material, concrete inner and. outer coating surrounding carbon steel Notification to State of New Jersey: Inspector was onsite observing conditions as they occurred.
NRC Staff Next Steps:
The Region added an extra week to the ISI inspection in order for the inspector to continue to follow developments.
We continue to interface internal stakeholders on a periodic basis.
An IMC 309 review was being considered. Entry conditions have not been met due to lack of evidence related to structural integrity AFW.
A review of OpE had been started - other buried pipe AFW problems have been identified back to 2000 - draft IN has been in the works since Oyster Creek issue last year.
No inquiries to date from External stakeholders.
Industry Outreach:
PSEG is interfacing with INPO OpE.
Public Outreach:
None to date
v*
Attachment 1 - Factual Development Week of 4/5/10:
Two of four AFW lines are buried on each Salem Unit. On Unit 1, approximately 150' of piping between the pumps in the Auxiliary building to SG #12 and to SG #14 are buried. Only the buried portions are in question here because they are inaccessible for inspection per the Code.
The remainder of the non-buried piping in the AFW system is included in the ISI Program and is inspected via code qualified UT. The 150' is an estimate from several prints and several of the PSEG engineers - 2 runs of 4", schedule 80, carbon steel pipe of about 150' each - total of about 300'.
Licensee was using guided wave technology for initial characterization and need to dig additional pits - turned out they needed to dig the whole area up. The inspector explained agency position that the ASME code does not recognize the Guided Wave readings and they cannot be credited for dimensions as part of a repair. The ISI Program Manager acknowledges this and understands the concern.
Engineers have alluded to visual inspections conducted in 1998 which said the coating was in good shape - however that have not been able to present those reports. Those inspections should be documented or they did not occur.
Regarding the min wall situation, not all of the limited Code UT are below calculated min wall of 0.278" (nominal is .337") for a rated pressure of 1950 psi.
PSEG had ordered replacement pipe.
Example picture