ML102740327
| ML102740327 | |
| Person / Time | |
|---|---|
| Site: | Surry |
| Issue date: | 09/30/2010 |
| From: | Chris Miller Division of Reactor Safety II |
| To: | Heacock D Virginia Electric & Power Co (VEPCO) |
| References | |
| Download: ML102740327 (5) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 30, 2010 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
CONFIRMATION OF REQUESTED INITIAL OPERATOR LICENSE EXAMINATIONS FOR SURRY POWER STATION
Dear Mr. Heacock:
In a letter dated September 11, 2009, Serial # 10-417, your staff responded to Regulatory Issue Summary 2010-08 and requested we schedule initial license operator examinations for Surry Power Station. Based on your letter and following discussions with your staff, we have scheduled the requested examinations as follows:
Plant /
Station 2011 2012 Date Applicants Date Applicants Surry N/R N/R 8/13 20
- N/R - None Requested On-site validation of the examinations is typically scheduled to occur approximately three weeks before each examination. If you have a need to change the dates of your scheduled exam from that listed above, please inform us in writing of your request and the reason for the change.
Due to the large number of examinations scheduled to be administered at Region II sites, requests to change examination dates will be considered on a case-by-case basis. We will confirm any change in examination schedule with a follow-up letter.
The NRC plans to write your 2012 proposed examination. For examinations that have greater than nine applicants, each examination is scheduled for a minimum of two weeks. If the number of applicants is reduced to less than ten (10), please inform us as this will impact the examination schedule.
A supplementary letter will be sent to each stations training manager approximately 120 days prior to the initial examination. The letter will provide the training manager with the chief examiners name, an outline of examination security expectations, a list of the materials required by the NRC to conduct the examination, and it will reconfirm the examination dates and the number of candidates you have in the training program. If you have any questions concerning this information, please contact Mr. Malcolm Widmann, Chief, Operations Branch, at 404-997-4550.
VEPCO 2
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Sincerely,
/RA: Harold Christensen for/
Christopher G. Miller, Acting Director Division of Reactor Safety Docket Nos.: 50-280, 50-281 License Nos.: DPR-32, DPR-37 cc: (See page 3)
X SUNSI REVIEW COMPLETE MTW OFFICE RII:DRS RII:DRS RII:DRS SIGNATURE RA RA RA NAME PCapehart MWidmann CMiller DATE 09/ 30 /2010 09/30 /2010 09/ 30 /2010 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
VEPCO 3
cc:
Gerald T. Bischof Site Vice President Surry Power Station Virginia Electric and Power Company Electronic Mail Distribution B. L. (Sonny) Stanley Director, Nuclear Safety and Licensing Virginia Electric and Power Company Electronic Mail Distribution Lillian M. Cuoco, Esq.
Senior Counsel Dominion Resources Services, Inc.
Electronic Mail Distribution Chris L. Funderburk Director, Nuclear Licensing & Operations Support Virginia Electric and Power Company Electronic Mail Distribution Ginger L. Melton Virginia Electric and Power Company Electronic Mail Distribution Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197 Richmond, VA 23209 Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219 Senior Resident Inspector Surry Power Station U.S. Nuclear Regulatory Commission 5850 Hog Island Rd Surry, VA 23883 Michael M. Cline Director Virginia Department of Emergency Services Management Electronic Mail Distribution Tim Steed Manager of Nuclear Training Surry Power Station Virginia Electric and Power Company Electronic Mail Distribution
VEPCO 4
Letter to David A. Heacock from Christopher G. Miller dated September 30, 2010
SUBJECT:
CONFIRMATION OF REQUESTED INITIAL OPERATOR LICENSE EXAMINATIONS FOR SURRY POWER STATION Distribution:
RIDSNRRDIRS PUBLIC RidsNrrPMSurry Resource ORA, RII C. Miller H. Christensen M. Widmann P. Capehart J. Vincent G. McCoy J. McHale RIDSNRRDIRSIRIB Resource Document Control Desk - Licensing